CN104695476A - Strengthening method and structure of ramp retaining walls for grading decomposition - Google Patents

Strengthening method and structure of ramp retaining walls for grading decomposition Download PDF

Info

Publication number
CN104695476A
CN104695476A CN201310640320.9A CN201310640320A CN104695476A CN 104695476 A CN104695476 A CN 104695476A CN 201310640320 A CN201310640320 A CN 201310640320A CN 104695476 A CN104695476 A CN 104695476A
Authority
CN
China
Prior art keywords
ramp
retaining wall
height
reinforcing bar
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310640320.9A
Other languages
Chinese (zh)
Inventor
宋泽恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN201310640320.9A priority Critical patent/CN104695476A/en
Publication of CN104695476A publication Critical patent/CN104695476A/en
Pending legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a strengthening method and a strengthening structure of ramp retaining walls for grading decomposition. According to the method, a ramp is divided into two sections, the existing retaining wall structure is adopted on the low section of the ramp, and the retaining walls on two sides of the high section of the ramp are pulled and fixed by reinforcing steel bar haul nets. Reinforced concrete cantilever type retaining walls on the section, higher than 8 m, of the ramp are changed into reinforcement retaining walls, the bearing capacity of the retaining walls is greatly improved, and the stability and the safety reliability of the section, higher than 8 m, of the ramp are ensured. The foundation bearing capacity of the strengthening structure can completely satisfy the requirement of the electrolytic aluminium grading decomposition ramp, the investment is saved, the construction period is shortened, the stress of the structure is clear and reasonable, the potential safety hazard is avoided, and the safety of the structure is guaranteed.

Description

The reinforcement means of a kind of decomposition ramp retaining wall and structure
Technical field
the present invention relates to reinforcement means and the structure of a kind of decomposition ramp retaining wall, belong to the reinforcing technique field in electrolytic aluminium decomposition ramp.
Background technology
in the technological process of electrolytic aluminium decomposition, needing to build a length is 300 meters, and width is 42 meters, and the gradient is the ramp of 3%, and ramp least significant end is concordant with natural ground, and peak height is 9 meters.Both sides, ramp are provided with retaining wall, fill and lead up compacting between retaining wall by backfill.Existing retaining wall is steel concrete cantilever structure, when this structure is not too high in ramp, substantially can meet the lateral pressure that backfill applies.But along with the continuous rising in ramp, the lateral pressure that backfill is applied to inside retaining wall is also increasing.When ramp is higher, as still adopted existing steel concrete cantilevered soil-baffling structure, the construction period is longer, invests larger.Therefore need to find in addition a kind of method that ramp retaining wall is reinforced and structure, to guarantee the safety in ramp.
Summary of the invention
the object of the invention is to, reinforcement means and the structure of a kind of decomposition ramp retaining wall is provided, to guarantee stability and the safety in electrolytic aluminium decomposition ramp.
technical scheme of the present invention:
a reinforcement means for decomposition ramp retaining wall, the method is that ramp is divided into two sections, and ramp height still adopts existing retaining wall structure compared with end section; By reinforcing bar drawknot net, the retaining wall drawknot of both sides is fixed between the retaining wall of height upper sector both sides, ramp.
in preceding method, described ramp punishes into two sections height 8 meters; Height is lower than when 8 meters being ramp height comparatively end section, and height is higher than when 8 meters being ramp height upper sector.
in preceding method, reinforced concrete foundation is provided with bottom the retaining wall of described ramp height upper sector, tension rib is embedded with inside retaining wall, between the retaining wall of both sides, backfill construction is carried out in layering, one deck reinforcing bar drawknot net is laid between every layer, reinforcing bar drawknot net welds with the tension rib be embedded in inside retaining wall, is routed to concordant with the retaining wall of both sides always; Then one reinforced concrete circle beam is built at retaining wall top.
in preceding method, when backfill construction is carried out in described layering, every layer of backfill should roll compacting, and compacting degree is more than or equal to 93%; The spacing of reinforcing bar drawknot net is not more than 0.4 meter.
according to the decomposition ramp used soil-baffling structure that preceding method is formed, described ramp with height 8 meters of for boundary, be provided with multistory reinforced drawknot net between the retaining wall of ramp height higher than 8 meters of section both sides, reinforcing bar drawknot net both sides are welded with the tension rib be embedded in retaining wall; Backfill is provided with between multistory reinforced drawknot net.
in aforementioned soil-baffling structure, the interlamellar spacing of described reinforcing bar drawknot net is 0.4 meter.
in aforementioned soil-baffling structure, be provided with reinforced concrete foundation bottom described retaining wall, reinforced concrete foundation is the strip of cross section 1000 × 400mm.
in aforementioned soil-baffling structure, described retaining wall top is provided with C25 reinforced concrete circle beam.
compared with prior art, the present invention makes ramp height into reinforced soil retaining wall higher than the steel concrete cantilever retaining wall of 8 meters of sections, not only can meet the requirement of bearing capacity of foundation soil, and can also investment reduction and reduction of erection time.When carrying out backfill construction, lay one deck backfill, paving one deck reinforcing bar drawknot net, lay one deck reinforcing bar drawknot net every 0.4, reinforcing bar drawknot net welds with the tension rib in retaining wall, can reduction of erection time greatly.The present invention substantially increases the bearing capacity of retaining wall, ensure that ramp height is higher than the stability of 8 meters of sections and security reliability.Bearing capacity of foundation soil of the present invention can meet the requirement in electrolytic aluminium decomposition ramp completely, has saved investment, has shortened the construction period; Structure stress is clear and definite, reasonable, avoids potential safety hazard, ensures the safety of structure.
Accompanying drawing explanation
fig. 1 is structural representation of the present invention;
fig. 2 be in Fig. 1 ramp height higher than the partial enlarged drawing of 8 meters of sections;
fig. 3 is the longitudinal sectional drawing at retaining wall place in Fig. 2.
being labeled as in accompanying drawing: 1-retaining wall, 2-reinforcing bar drawknot net, 3-tension rib, 4-backfill, 5-reinforced concrete foundation, 6-C25 reinforced concrete circle beam.
Detailed description of the invention
below in conjunction with accompanying drawing, the present invention is described in further detail, but not as any limitation of the invention.
a reinforcement means for decomposition ramp retaining wall, as Figure 1-3.The method is that ramp is divided into two sections, and ramp height still adopts existing retaining wall structure compared with end section; By reinforcing bar drawknot net, the retaining wall drawknot of both sides is fixed between the retaining wall of height upper sector both sides, ramp.Ramp punishes into two sections height 8 meters; Height is lower than when 8 meters being ramp height comparatively end section, and height is higher than when 8 meters being ramp height upper sector.Reinforced concrete foundation is provided with bottom the retaining wall of ramp height upper sector, tension rib is embedded with inside retaining wall, between the retaining wall of both sides, backfill construction is carried out in layering, one deck reinforcing bar drawknot net is laid between every layer, reinforcing bar drawknot net welds with the tension rib be embedded in inside retaining wall, is routed to concordant with the retaining wall of both sides always; Then one reinforced concrete circle beam is built at retaining wall top.When backfill construction is carried out in layering, every layer of backfill should roll compacting, and compacting degree is more than or equal to 93%; The spacing of reinforcing bar drawknot net is not more than 0.4 meter.
according to the decomposition ramp used soil-baffling structure that preceding method is formed, as Figure 1-3.Described ramp is with height 8 meters of for boundary, and be provided with multistory reinforced drawknot net 2 between the retaining wall 1 of ramp height higher than 8 meters of section both sides, reinforcing bar drawknot net both sides are welded with the tension rib 3 be embedded in retaining wall; Backfill 4 is provided with between multistory reinforced drawknot net.The interlamellar spacing of reinforcing bar drawknot net is 0.4 meter.Be provided with reinforced concrete foundation 5 bottom retaining wall, reinforced concrete foundation is the strip of cross section 1000 × 400mm.Retaining wall top is provided with C25 reinforced concrete circle beam 6.
Embodiment
fig. 1 is the schematic diagram in ramp used in the technological process of electrolytic aluminium decomposition, and length is 300 meters, and width is 42 meters, and the gradient is 3%, and ramp least significant end is concordant with natural ground, and peak height is 9 meters.Both sides, ramp are provided with retaining wall, fill and lead up compacting between retaining wall by backfill.Fig. 2 is the structural representation of ramp height higher than 8 meters of sections, as seen from Figure 2, this example stops up between cob wall 1 two to arrange reinforcing bar drawknot net 2, when carrying out backfill 4 and constructing, lay one deck backfill 4, paving one deck reinforcing bar drawknot net 2, lay one deck reinforcing bar drawknot net every 0.4, reinforcing bar drawknot net 2 both sides are welded with the tension rib 3 in retaining wall 1.Be provided with reinforced concrete foundation 5 bottom retaining wall, reinforced concrete foundation is the strip of cross section 1000 × 400mm.Retaining wall top is provided with C25 reinforced concrete circle beam 6.When backfill construction is carried out in layering, every layer of backfill should roll compacting, and compacting degree is more than or equal to 93%.

Claims (8)

1. a decomposition reinforcement means for ramp retaining wall, is characterized in that: the method is that ramp is divided into two sections, and ramp height still adopts existing retaining wall structure compared with end section; By reinforcing bar drawknot net, the retaining wall drawknot of both sides is fixed between the retaining wall of height upper sector both sides, ramp.
2. method according to claim 1, is characterized in that: described ramp punishes into two sections height 8 meters; Height is lower than when 8 meters being ramp height comparatively end section, and height is higher than when 8 meters being ramp height upper sector.
3. method according to claim 2, it is characterized in that: bottom the retaining wall of described ramp height upper sector, be provided with reinforced concrete foundation, tension rib is embedded with inside retaining wall, between the retaining wall of both sides, backfill construction is carried out in layering, one deck reinforcing bar drawknot net is laid between every layer, reinforcing bar drawknot net welds with the tension rib be embedded in inside retaining wall, is routed to concordant with the retaining wall of both sides always; Then one reinforced concrete circle beam is built at retaining wall top.
4. method according to claim 3, is characterized in that: when backfill construction is carried out in described layering, every layer of backfill should roll compacting, and compacting degree is more than or equal to 93%; The spacing of reinforcing bar drawknot net is not more than 0.4 meter.
5. the decomposition ramp used soil-baffling structure that either method is formed according to claim 1-4, it is characterized in that: described ramp with height 8 meters of for boundary, be provided with multistory reinforced drawknot net (2) between the retaining wall (1) of ramp height higher than 8 meters of section both sides, reinforcing bar drawknot net (2) both sides are welded with the tension rib (3) be embedded in retaining wall (1); Backfill (4) is provided with between multistory reinforced drawknot net (2).
6. soil-baffling structure according to claim 5, is characterized in that: the interlamellar spacing of described reinforcing bar drawknot net (2) is 0.4 meter.
7. soil-baffling structure according to claim 5, is characterized in that: described retaining wall (1) bottom is provided with reinforced concrete foundation (5), the strip that reinforced concrete foundation (5) is cross section 1000 × 400mm.
8. soil-baffling structure according to claim 5, is characterized in that: described retaining wall (1) top is provided with C25 reinforced concrete circle beam (6).
CN201310640320.9A 2013-12-04 2013-12-04 Strengthening method and structure of ramp retaining walls for grading decomposition Pending CN104695476A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310640320.9A CN104695476A (en) 2013-12-04 2013-12-04 Strengthening method and structure of ramp retaining walls for grading decomposition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310640320.9A CN104695476A (en) 2013-12-04 2013-12-04 Strengthening method and structure of ramp retaining walls for grading decomposition

Publications (1)

Publication Number Publication Date
CN104695476A true CN104695476A (en) 2015-06-10

Family

ID=53342991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310640320.9A Pending CN104695476A (en) 2013-12-04 2013-12-04 Strengthening method and structure of ramp retaining walls for grading decomposition

Country Status (1)

Country Link
CN (1) CN104695476A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4643618A (en) * 1985-02-11 1987-02-17 Hilfiker Pipe Co. Soil reinforced cantilever wall
CN1490468A (en) * 2003-08-29 2004-04-21 中国地质大学(武汉) Inter-anchored thin retaining wall
KR20040072586A (en) * 2004-07-23 2004-08-18 박성언 Reinforced earth construction method for tree-planting and stabilization of slope, making use of front and underground geo-grids
KR20070073434A (en) * 2006-01-05 2007-07-10 박성언 Environment green wall
CN201321618Y (en) * 2008-12-23 2009-10-07 中铁二院工程集团有限责任公司 Cantilever retaining wall reinforcing compound structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4643618A (en) * 1985-02-11 1987-02-17 Hilfiker Pipe Co. Soil reinforced cantilever wall
CN1490468A (en) * 2003-08-29 2004-04-21 中国地质大学(武汉) Inter-anchored thin retaining wall
KR20040072586A (en) * 2004-07-23 2004-08-18 박성언 Reinforced earth construction method for tree-planting and stabilization of slope, making use of front and underground geo-grids
KR20070073434A (en) * 2006-01-05 2007-07-10 박성언 Environment green wall
CN201321618Y (en) * 2008-12-23 2009-10-07 中铁二院工程集团有限责任公司 Cantilever retaining wall reinforcing compound structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴彬彬等: "加筋土路肩挡土墙施工工艺", 《西铁科技》 *

Similar Documents

Publication Publication Date Title
CN103952986B (en) A kind of off-load formula rigid culvert structure
CN203923924U (en) No. 0 section bracket prepressing device
CN104294769B (en) A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement
CN202787271U (en) Stacked inner supporting structure for foundation pit supporting
CN203782684U (en) Anti-skid pile provided with crossbeam
CN202969393U (en) Ribbing load reduction structure of road high hill culvert
CN203113352U (en) Pre-stressed beam for retaining and protection of foundation pit
CN105696546A (en) Low-consumption underground diaphragm wall and construction method thereof
CN203614107U (en) Composite retaining structure for horsehead
CN103244129B (en) Construction method for three-dimensional intersection concave-convex fulcrums
CN103161169A (en) Prestressed girder for foundation pit supporting
CN103334778A (en) Construction technology of step temporary support and partial double side walls
CN104594297A (en) Double-deck concrete faced rock-fill dam and construction method thereof
CN204097889U (en) A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement
CN204151798U (en) A kind of steel reinforced concrete anti-slide pile structure
CN110953005B (en) Large-deep-buried high-stress coal bunker supporting structure and construction method thereof
CN203035204U (en) Large-section tunnel second lining grouping formwork trolley
CN103397668B (en) The regulation method of each sections uneven settlement of foundation of a kind of railway tunnels
CN204311457U (en) A kind of Metro station excavation excavation construction composite retaining structure system
CN103233447B (en) High concrete face rockfill dam seismic strengthening structure and construction method thereof
CN203361163U (en) Prestress steel support used for controlling differential displacement inside and outside foundation ditch enclosure wall
CN102852150B (en) Superposed inner support structure for foundation pit support
CN104695476A (en) Strengthening method and structure of ramp retaining walls for grading decomposition
CN104846856B (en) Horizontal inclined independent bent frame column pushing correction method
CN211227885U (en) Rock foundation existing high-speed railway dyke force balance side width structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150610