CN104682383B - Method and system for adjusting open loop point by remote automatic bus transfer devices - Google Patents

Method and system for adjusting open loop point by remote automatic bus transfer devices Download PDF

Info

Publication number
CN104682383B
CN104682383B CN201510050954.8A CN201510050954A CN104682383B CN 104682383 B CN104682383 B CN 104682383B CN 201510050954 A CN201510050954 A CN 201510050954A CN 104682383 B CN104682383 B CN 104682383B
Authority
CN
China
Prior art keywords
substation
open loop
power
loop point
subsystem
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510050954.8A
Other languages
Chinese (zh)
Other versions
CN104682383A (en
Inventor
魏存良
陈文娟
陈锦昌
黄翠莲
黄海坤
陈兴华
廖晓明
吴国炳
朱力方
李继房
邹练辉
张达洄
曾招辉
甘斌
魏煌
丘演峰
熊志宏
曹德发
邬奇林
陈增雄
林志杭
廖明
李舒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd
Original Assignee
Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd, Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd filed Critical Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority to CN201510050954.8A priority Critical patent/CN104682383B/en
Publication of CN104682383A publication Critical patent/CN104682383A/en
Application granted granted Critical
Publication of CN104682383B publication Critical patent/CN104682383B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/007Arrangements for selectively connecting the load or loads to one or several among a plurality of power lines or power sources
    • H02J3/0073Arrangements for selectively connecting the load or loads to one or several among a plurality of power lines or power sources for providing alternative feeding paths between load and source when the main path fails, e.g. transformers, busbars
    • H02J13/0013
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations

Abstract

The invention provides a method and a system for adjusting an open loop point by remote automatic bus transfer devices. The method comprises the steps of detecting the real-time power of a main supply path by the remote automatic bus transfer device of a substation of a first transformer substation; judging whether the main supply path is overloaded or not according to the relationship between the real-time power and the limited power of the main supply path; if the main supply path is overloaded, sending the overload information and the overload power of the main supply path into the substation of the transformer substation at an open loop point by the remote automatic bus transfer device of the substation of the first transformer substation; comparing the overload power, the home station power and the limit load power of a spare supply path by the remote automatic bus transfer device of the substation of the transformer substation at the open loop point; if the overload power is smaller than the home station power and the home station power is smaller than the limit load power of the spare supply path, controlling the remote automatic bus transfer device of the substation of the transformer substation at the open loop point to close a switch of the spare supply path at the open loop point; after the set time of closing the switch of the spare supply path at the open loop point is delayed, opening a switch of the original main supply path of the substation of the transformer substation at the open loop point to form a new open loop point.

Description

The open loop point method of adjustment of remote automatic bus transfer equipment and system
Technical field
The present invention relates to technical field of electric power, the open loop point method of adjustment of more particularly to a kind of remote automatic bus transfer equipment and System.
Background technology
In Operation of Electric Systems, it is that solution 110kV electrical networks can by the power supply of the multiple substation operations of the statements based on collusion of power supply all the way By property, by a kind of system powered by the statements based on collusion transformer station automatic closing that 110kV remote automatic bus transfer equipments are constituted, Neng Goutong The method that isolated fault step by step realizes that statements based on collusion transformer station automatic closing is powered is crossed, realizes statements based on collusion electrical network in main power supply failure When maximum magnitude ground recover decompression transformer station and powered by stand-by power supply.In statements based on collusion electrical network, as main power supply typically only has All the way, if supplied substation load increases simultaneously, main confession circuit is easy to overload, if now divided ring point is adjusted not in time It is whole, easily cause main confession line tripping or equipment fault, have a strong impact on the power supply reliability of statements based on collusion electrical network.
The content of the invention
Based on this, it is necessary to for above-mentioned technical problem, there is provided a kind of open loop point method of adjustment of remote automatic bus transfer equipment And system.
A kind of open loop point method of adjustment of remote automatic bus transfer equipment, comprises the steps:
The realtime power of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment;According to described real-time With the relation of the power limitation of main confession route, power judges whether the main confession route transships;
If the main confession route overload, by the remote automatic bus transfer equipment of the first subsystem in substation by its main confession route Overload messages and overload power are sent to the subsystem in substation at open loop point;
Overload power, our station power and available circuit are limited by the remote automatic bus transfer equipment of the subsystem in substation of open loop point Carry power to compare, judge whether to meet the overload power less than our station power and the our station power is limited less than available circuit Carry power;
If the overload power is less than our station power and the our station power is less than available circuit limit for tonnage power, open loop is controlled The remote automatic bus transfer equipment of the subsystem in substation at point closes the available line switching of open loop point;
After the setting time delay of the available line switching of the open loop point that closes, the original of the subsystem in substation at tripping open loop point is main For line switching, a new open loop point is formed.
A kind of open loop point adjustment system of remote automatic bus transfer equipment, including:
Detection module, for the real-time work(of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment Rate;Judge whether the main confession route transships according to relation of the realtime power with the power limitation of main confession route;
Sending module, if transshipping for the main confession route, by the remote automatic bus transfer equipment of the first subsystem in substation The overload messages and overload power of its main confession route are sent to into the subsystem in substation at open loop point;
Judge module, for the subsystem in substation by open loop point remote automatic bus transfer equipment by overload power, our station work( Rate and available circuit limit for tonnage power compare, and judge whether that meeting the overload power is less than our station power and the our station power Less than available circuit limit for tonnage power;
Control module, if for the overload power is less than our station power and the our station power is less than available circuit limit for tonnage Power, the remote automatic bus transfer equipment for controlling the subsystem in substation at open loop point close the available line switching of open loop point;
Form module, for after the setting time delay of the available line switching of the open loop point that closes, the change at tripping open loop point The former main confession line switching of power station substation, forms a new open loop point.
The open loop point method of adjustment of above-mentioned remote automatic bus transfer equipment and system, by the main confession for judging the first subsystem in substation Whether route transships, and the overload messages and overload power of its main confession route are sent to the power transformation at open loop point according to judged result Substation, and the remote automatic bus transfer equipment using the subsystem in substation at open loop point compares overload power, our station power and available The relation of circuit limit for tonnage power, further carries out the adjustment of open loop point, can improve statements based on collusion with the point of the open loop in adjust automatically electrical network The power supply reliability of electrical network.
Description of the drawings
Open loop point method of adjustment flow charts of the Fig. 1 for the remote automatic bus transfer equipment of one embodiment;
Subsystem in substation JA(junction ambient) schematic diagrams of the Fig. 2 for one embodiment;
Open loop point adjustment system structure diagrams of the Fig. 3 for the remote automatic bus transfer equipment of one embodiment.
Specific embodiment
The open loop point method of adjustment of remote automatic bus transfer equipment to the present invention and being embodied as system below in conjunction with the accompanying drawings Mode is described in detail.
With reference to Fig. 1, Fig. 1 show the open loop point method of adjustment flow chart of the remote automatic bus transfer equipment of one embodiment, bag Include following steps:
S10, detects the realtime power of its main confession route by the first subsystem in substation remote automatic bus transfer equipment;According to described With the relation of the power limitation of main confession route, realtime power judges whether the main confession route transships;
In above-mentioned steps S10, can be by judging that realtime power and the magnitude relationship of the power limitation of main confession route enter one Whether the disconnected main confession route of step transships.
S20, if main confession route overload, by the remote automatic bus transfer equipment of the first subsystem in substation by its Zhu Gong road The overload messages and overload power of line are sent to the subsystem in substation at open loop point;
In above-mentioned steps S20, after above-mentioned main confession route overload, easily cause main confession line tripping or equipment fault, seriously Affect the power supply reliability of statements based on collusion electrical network, it is therefore desirable to the open loop point of in time adjustment statements based on collusion electrical network, make the above-mentioned main confession route will not There is the situation of long term overloading.
S30, by open loop point subsystem in substation remote automatic bus transfer equipment by overload power, our station power and available line Road limit for tonnage power compares, and judges whether to meet the overload power less than our station power and the our station power is less than available line Road limit for tonnage power;
S40, if the overload power is less than our station power and the our station power is less than available circuit limit for tonnage power, control The remote automatic bus transfer equipment of the subsystem in substation at open loop point closes the available line switching of open loop point;
S50, after the setting time delay of the available line switching of the open loop point that closes, the subsystem in substation at tripping open loop point Former main confession line switching, forms a new open loop point.
The open loop point method of adjustment of the remote automatic bus transfer equipment that the present embodiment is provided, by judging the first subsystem in substation Whether main confession route transships, and the overload messages and overload power of its main confession route is sent at open loop point according to judged result Subsystem in substation, and using the subsystem in substation at open loop point remote automatic bus transfer equipment compare overload power, our station power and The relation of available circuit limit for tonnage power, further carries out the adjustment of open loop point, can be improved with the point of the open loop in adjust automatically electrical network The power supply reliability of statements based on collusion electrical network.
In one embodiment, above-mentioned steps S10 can include:
The realtime power of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment;According to described real-time With the relation of the power limitation of main confession route, power judges whether the main confession route transships;
If the realtime power judges the main confession circuit overload of the substation more than the power limitation of main confession route.
In one embodiment, above-mentioned steps S20 can include:
If the main confession route overload, the remote automatic bus transfer equipment of the first subsystem in substation is by the mistake of its main confession route Information carrying ceases and overload power is sent to the subsystem in substation at open loop point;If first subsystem in substation is located at open loop point, Overload messages and overload power are no longer forwarded then.
In the present embodiment, if first subsystem in substation is located at open loop point, the first subsystem in substation is stated then to open Subsystem in substation at circling point, without the need for again the overload messages and overload power of its main confession route are sent at other open loop points Subsystem in substation.
In one embodiment, above-mentioned steps S40 can include:
The remote automatic bus transfer equipment of the subsystem in substation at open loop point is by overload power, our station power and available circuit limit for tonnage Power compares, and overload power is designated as Pg, the our station power of the subsystem in substation at open loop point is designated as Pz, available circuit limit for tonnage Power is designated as PxIf, Pg< Pz< Px, then the remote automatic bus transfer equipment for controlling the subsystem in substation at open loop point closes at open loop point Subsystem in substation open loop point switch;
If Pg< PxBut Pg> Pz, then the overload messages and overload power are sent to and transformer station's at open loop point The station internal power of the subsystem in substation is designated as P by the subsystem in substation at the non-open loop website of adjacent first that standz+1, with such Push away, if n-th website that open loop website is started at, then its station internal power is designated as into Pz+n, when n-th subsystem in substation receives When the overload messages and overload power of the main confession route of one subsystem in substation, then the remote automatic bus transfer equipment of the substation is by Pg、 Pz+n、PxRelatively, meet Pg< Pz+n< PxWhen, then n-th subsystem in substation is set to into the subsystem in substation at open loop point, and is controlled The remote automatic bus transfer equipment of the subsystem in substation at open loop point processed closes the switch of the subsystem in substation open loop point at open loop point.
In one embodiment, above-mentioned steps S50 can include:
After the available line switching of the open loop point that closes, through setting time delay, the subsystem in substation at control open loop point Remote automatic bus transfer equipment sends confirmation to former open loop point substation, and the remote automatic bus transfer equipment of former open loop point substation receives confirmation Close the available line switching of our station afterwards, while send feedback information is to the subsystem in substation at open loop point, the change at open loop point Power station substation receives feedback information, and tripping this station owner supplies line switching, forms a new open loop point.
In one embodiment, for the information according to each subsystem in substation point, calculate Setting delay value, can specifically include:
As shown in Fig. 2 subsystem in substation C can be open loop point station, when the device of subsystem in substation A determines its main confession line When passing by load, overload power is Pg, then subsystem in substation A is by overload messages and overload power PgSubsystem in substation B is sent to, is become Power station substation B is by above-mentioned overload messages and overload power PgSend the subsystem in substation C at open loop point;Transformer station at open loop point The remote automatic bus transfer equipment of substation C is by overload power Pg, this subsystem in substation power PzAnd available circuit limit for tonnage power PxCompare Compared with working as Pg< Pz< PxWhen, then the main confession line side of the subsystem in substation C of new open loop point selection at open loop point.If Pg< Px But Pg> PzWhen, then the subsystem in substation C at open loop point sends out overload messages and overload power PgSubsystem in substation B is given, its station internal strength Rate can be designated as Pz+1, when subsystem in substation B receives the sent out overload messages of subsystem in substation C at open loop point and overload power Pg When, then the subsystem in substation remote automatic bus transfer equipment is by Pg、Pz+1、PxRelatively, meet Pg< Pz+1< PxWhen, then open loop point selection In the main confession line side of subsystem in substation B.Now subsystem in substation B sends the information for being selected as new open loop point to former open loop point The remote automatic bus transfer equipment of the subsystem in substation C at place, the subsystem in substation C at open loop point closes the available line switching of our station, Overload messages and overload power P are sent out simultaneouslygTo the subsystem in substation B at new open loop point, subsystem in substation B receives overload messages And overload power PgAfter setting time delay, this station owner of tripping supplies line switching afterwards, forms a new open loop point.
By that analogy, if n-th website starting at of the subsystem in substation C at open loop point, then be identified as being designated as Pz+n, when When n-th subsystem in substation receives the information that the subsystem in substation C at open loop point sends, then a distant place for the subsystem in substation is standby certainly Device is thrown by Pg、Pz+n、PxRelatively, meet Pg< Pz+n< PxWhen, then open loop point can be selected in the main confession line side of our station.
For the quantity of statements based on collusion subsystem in substation is more than 4 or selects in other any one transformer stations as statements based on collusion side The open loop point of formula, can be adjusted by the open loop of above-mentioned remote automatic bus transfer equipment point method of adjustment.
With reference to Fig. 3, Fig. 3 show the open loop point adjustment system structure of the remote automatic bus transfer equipment of one embodiment and illustrates Figure, including:
Detection module 10, for the real-time work(of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment Rate;Judge whether the main confession route transships according to relation of the realtime power with the power limitation of main confession route;
Sending module 20, if transshipping for the main confession route, is filled by the remote spare power source automatic transfer of the first subsystem in substation Put and the overload messages and overload power of its main confession route are sent to into the subsystem in substation at open loop point;
Judge module 30, for the subsystem in substation by open loop point remote automatic bus transfer equipment by overload power, our station Power and available circuit limit for tonnage power compare, and judge whether that meeting the overload power is less than our station power and the our station work( Rate is less than available circuit limit for tonnage power;
Control module 40, if for the overload power is less than our station power and the our station power is limited less than available circuit Power is carried, the remote automatic bus transfer equipment for controlling the subsystem in substation at open loop point closes the available line switching of open loop point;
Module 50 is formed, for after the setting time delay of the available line switching of the open loop point that closes, at tripping open loop point The former main confession line switching of subsystem in substation, forms a new open loop point.
In one embodiment, above-mentioned detection module 10 can be further used for:
The realtime power of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment;According to described real-time With the relation of the power limitation of main confession route, power judges whether the main confession route transships;
If the realtime power judges the main confession circuit overload of the substation more than the power limitation of main confession route.
In one embodiment, above-mentioned sending module 20 can be further used for:
If the main confession route overload, the remote automatic bus transfer equipment of the first subsystem in substation is by the mistake of its main confession route Information carrying ceases and overload power is sent to the subsystem in substation at open loop point;If first subsystem in substation is located at open loop point, Overload messages and overload power are no longer forwarded then.
In one embodiment, above-mentioned control module 40 can be further used for:
The remote automatic bus transfer equipment of the subsystem in substation at open loop point is by overload power, our station power and available circuit limit for tonnage Power compares, and overload power is designated as Pg, the our station power of the subsystem in substation at open loop point is designated as Pz, available circuit limit for tonnage Power is designated as PxIf, Pg< Pz< Px, then the remote automatic bus transfer equipment for controlling the subsystem in substation at open loop point closes at open loop point Subsystem in substation open loop point switch;
If Pg< PxBut Pg> Pz, then the overload messages and overload power are sent to and transformer station's at open loop point The station internal power of the subsystem in substation is designated as P by the subsystem in substation at the non-open loop website of adjacent first that standz+1, with such Push away, if n-th website that open loop website is started at, then its station internal power is designated as into Pz+n, when n-th subsystem in substation receives When the overload messages and overload power of the main confession route of one subsystem in substation, then the remote automatic bus transfer equipment of the substation is by Pg、 Pz+n、PxRelatively, meet Pg< Pz+n< PxWhen, then n-th subsystem in substation is set to into the subsystem in substation at open loop point, and is controlled The remote automatic bus transfer equipment of the subsystem in substation at open loop point processed closes the switch of the subsystem in substation open loop point at open loop point.
In one embodiment, above-mentioned formation module 50 can be further used for:
After the available line switching of the open loop point that closes, through setting time delay, the subsystem in substation at control open loop point Remote automatic bus transfer equipment sends confirmation to former open loop point substation, and the remote automatic bus transfer equipment of former open loop point substation receives confirmation Close the available line switching of our station afterwards, while send feedback information is to the subsystem in substation at open loop point, the change at open loop point Power station substation receives feedback information, and tripping this station owner supplies line switching, forms a new open loop point.
The open loop point adjustment system of the remote automatic bus transfer equipment of the present invention and the open loop of the remote automatic bus transfer equipment of the present invention Point method of adjustment is corresponded, in the technical characteristic that the embodiment of the open loop point method of adjustment of above-mentioned remote automatic bus transfer equipment is illustrated And its advantage is hereby give notice that suitable for the embodiment of the open loop point adjustment system of remote automatic bus transfer equipment.
Embodiment described above only expresses the several embodiments of the present invention, and its description is more concrete and detailed, but and Therefore the restriction to the scope of the claims of the present invention can not be interpreted as.It should be pointed out that for one of ordinary skill in the art For, without departing from the inventive concept of the premise, some deformations and improvement can also be made, these belong to the guarantor of the present invention Shield scope.Therefore, the protection domain of patent of the present invention should be defined by claims.

Claims (8)

1. the open loop point method of adjustment of a kind of remote automatic bus transfer equipment, it is characterised in that comprise the steps:
The realtime power of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment;According to the realtime power Judge whether the main confession route transships with the relation of the power limitation of main confession route;
If the main confession route overload, by the remote automatic bus transfer equipment of the first subsystem in substation by the overload of its main confession route Information and overload power are sent to the subsystem in substation at open loop point;
By open loop point subsystem in substation remote automatic bus transfer equipment by overload power, our station power and available circuit limit for tonnage work( Rate compares, and judges whether to meet the overload power less than our station power and the our station power is less than available circuit limit for tonnage work( Rate;
If the overload power is less than our station power and the our station power is less than available circuit limit for tonnage power, at control open loop point The remote automatic bus transfer equipment of subsystem in substation close the available line switching of open loop point;If the overload power is less than this Power and the our station power stand less than available circuit limit for tonnage power, the remote spare power source automatic transfer of the subsystem in substation at open loop point is controlled Device close the subsystem in substation open loop point at open loop point switch the step of include:
The remote automatic bus transfer equipment of the subsystem in substation at open loop point is by overload power, our station power and available circuit limit for tonnage power Compare, overload power is designated as into Pg, the our station power of the subsystem in substation at open loop point is designated as Pz, available circuit limit for tonnage power It is designated as PxIf, Pg< Pz< Px, then the remote automatic bus transfer equipment for controlling the subsystem in substation at open loop point closes the change at open loop point The switch of power station substation open loop point;
If Pg< PxBut Pg> Pz, then the overload messages and overload power are sent to adjacent with the subsystem in substation at open loop point First non-open loop website at subsystem in substation, the station internal power of the subsystem in substation is designated as into Pz+1, by that analogy, if It is n-th website that open loop website is started at, then its station internal power is designated as into Pz+n, when n-th subsystem in substation receives the first power transformation When the overload messages and overload power of the main confession route of substation, then the remote automatic bus transfer equipment of the substation is by Pg、Pz+n、PxThan Compared with meeting Pg< Pz+n< PxWhen, then n-th subsystem in substation is set to into the subsystem in substation at open loop point, and controls open loop point The remote automatic bus transfer equipment of the subsystem in substation at place closes the switch of the subsystem in substation open loop point at open loop point;
After the setting time delay of the available line switching of the open loop point that closes, the former main confession line of the subsystem in substation at tripping open loop point Way switch, forms a new open loop point.
2. the open loop point method of adjustment of remote automatic bus transfer equipment according to claim 1, it is characterised in that described to pass through One subsystem in substation remote automatic bus transfer equipment detects the realtime power of its main confession route;According to the realtime power and main confession route The relation of power limitation judge that the step of whether main confession route transships includes:
The realtime power of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment;According to the realtime power Judge whether the main confession route transships with the relation of the power limitation of main confession route;
If the realtime power judges the main confession circuit overload of the substation more than the power limitation of main confession route.
3. the open loop point method of adjustment of remote automatic bus transfer equipment according to claim 1, it is characterised in that if described The overload messages and overload power of its main confession route are sent out by main confession route overload, the remote automatic bus transfer equipment of the first subsystem in substation The step of giving the subsystem in substation at open loop point includes:
If the main confession route overload, the remote automatic bus transfer equipment of the first subsystem in substation is by the mistake information carrying of its main confession route Breath and overload power are sent to the subsystem in substation at open loop point;If first subsystem in substation is located at open loop point, no Overload messages and overload power are forwarded again.
4. the open loop point method of adjustment of remote automatic bus transfer equipment according to claim 1, it is characterised in that in setting time delay The former main confession line switching of the subsystem in substation at tripping open loop point afterwards, includes the step of form a new open loop point:
After the available line switching of the open loop point that closes, through setting time delay, a distant place for the subsystem in substation at open loop point is controlled Backup auto-activating device sends confirmation to former open loop point substation, and the remote automatic bus transfer equipment of former open loop point substation is closed after receiving confirmation The available line switching of upper our station, while send feedback information is to the subsystem in substation at open loop point, the transformer station at open loop point Substation receives feedback information, and tripping this station owner supplies line switching, forms a new open loop point.
5. a kind of open loop point of remote automatic bus transfer equipment adjusts system, it is characterised in that include:
Detection module, for the realtime power of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment;Root Judge whether the main confession route transships according to relation of the realtime power with the power limitation of main confession route;
Sending module, if transshipping for the main confession route, by the remote automatic bus transfer equipment of the first subsystem in substation by its The overload messages and overload power of main confession route are sent to the subsystem in substation at open loop point;
Judge module, for the subsystem in substation by open loop point remote automatic bus transfer equipment by overload power, our station power and Available circuit limit for tonnage power compares, and judges whether to meet the overload power less than our station power and the our station power is less than Available circuit limit for tonnage power;
Control module, if for the overload power is less than our station power and the our station power is less than available circuit limit for tonnage work( Rate, the remote automatic bus transfer equipment for controlling the subsystem in substation at open loop point are closed the available line switching of open loop point;The control Module is further used for:
The remote automatic bus transfer equipment of the subsystem in substation at open loop point is by overload power, our station power and available circuit limit for tonnage power Compare, overload power is designated as into Pg, the our station power of the subsystem in substation at open loop point is designated as Pz, available circuit limit for tonnage power It is designated as PxIf, Pg< Pz< Px, then the remote automatic bus transfer equipment for controlling the subsystem in substation at open loop point closes the change at open loop point The switch of power station substation open loop point;
If Pg< PxBut Pg> Pz, then the overload messages and overload power are sent to adjacent with the subsystem in substation at open loop point First non-open loop website at subsystem in substation, the station internal power of the subsystem in substation is designated as into Pz+1, by that analogy, if It is n-th website that open loop website is started at, then its station internal power is designated as into Pz+n, when n-th subsystem in substation receives the first power transformation When the overload messages and overload power of the main confession route of substation, then the remote automatic bus transfer equipment of the substation is by Pg、Pz+n、PxThan Compared with meeting Pg< Pz+n< PxWhen, then n-th subsystem in substation is set to into the subsystem in substation at open loop point, and controls open loop point The remote automatic bus transfer equipment of the subsystem in substation at place closes the switch of the subsystem in substation open loop point at open loop point;
Form module, for after the setting time delay of the available line switching of the open loop point that closes, the transformer station at tripping open loop point The former main confession line switching of substation, forms a new open loop point.
6. the open loop point of remote automatic bus transfer equipment according to claim 5 adjusts system, it is characterised in that the detection mould Block is further used for:
The realtime power of its main confession route is detected by the first subsystem in substation remote automatic bus transfer equipment;According to the realtime power Judge whether the main confession route transships with the relation of the power limitation of main confession route;
If the realtime power judges the main confession circuit overload of the substation more than the power limitation of main confession route.
7. the open loop point of remote automatic bus transfer equipment according to claim 5 adjusts system, it is characterised in that the transmission mould Block is further used for:
If the main confession route overload, the remote automatic bus transfer equipment of the first subsystem in substation is by the mistake information carrying of its main confession route Breath and overload power are sent to the subsystem in substation at open loop point;If first subsystem in substation is located at open loop point, no Overload messages and overload power are forwarded again.
8. the open loop point of remote automatic bus transfer equipment according to claim 5 adjusts system, it is characterised in that the formation mould Block is further used for:
After the available line switching of the open loop point that closes, through setting time delay, a distant place for the subsystem in substation at open loop point is controlled Backup auto-activating device sends confirmation to former open loop point substation, and the remote automatic bus transfer equipment of former open loop point substation is closed after receiving confirmation The available line switching of upper our station, while send feedback information is to the subsystem in substation at open loop point, the transformer station at open loop point Substation receives feedback information, and tripping this station owner supplies line switching, forms a new open loop point.
CN201510050954.8A 2015-01-30 2015-01-30 Method and system for adjusting open loop point by remote automatic bus transfer devices Active CN104682383B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510050954.8A CN104682383B (en) 2015-01-30 2015-01-30 Method and system for adjusting open loop point by remote automatic bus transfer devices

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510050954.8A CN104682383B (en) 2015-01-30 2015-01-30 Method and system for adjusting open loop point by remote automatic bus transfer devices

Publications (2)

Publication Number Publication Date
CN104682383A CN104682383A (en) 2015-06-03
CN104682383B true CN104682383B (en) 2017-04-12

Family

ID=53317121

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510050954.8A Active CN104682383B (en) 2015-01-30 2015-01-30 Method and system for adjusting open loop point by remote automatic bus transfer devices

Country Status (1)

Country Link
CN (1) CN104682383B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106532936A (en) * 2016-11-03 2017-03-22 合肥华义电气科技有限公司 Dispatching method of unattended substation
CN106712274B (en) * 2016-12-14 2019-03-29 广东电网有限责任公司电力调度控制中心 The accurate cutting load method of element overload is eliminated after a kind of movement of remote spare power source automatic transfer
CN111900803A (en) * 2020-08-07 2020-11-06 国网湖北省电力有限公司荆门供电公司 Recursive remote backup power automatic switching method and device based on GOOSE communication

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5936825A (en) * 1982-08-25 1984-02-29 Meidensha Electric Mfg Co Ltd Adjusting device of ac voltage
CN201274417Y (en) * 2008-08-19 2009-07-15 衡水供电公司 Locking remote self-start apparatus for electric grid
CN102738891A (en) * 2012-07-03 2012-10-17 国电南瑞科技股份有限公司 Wide-area spare power automatic switching logic unified expression method and after-operation overload processing method
CN103607038B (en) * 2013-11-25 2015-06-24 广东电网公司电力调度控制中心 Method for implementing serial power supplying of multistage spare power automatic switching devices in power grid

Also Published As

Publication number Publication date
CN104682383A (en) 2015-06-03

Similar Documents

Publication Publication Date Title
CN104518564B (en) Backup automatic switching apparatus with area automatic switching function, and backup automatic switching method
CN103730945B (en) Quick power switching method and system
CN104682383B (en) Method and system for adjusting open loop point by remote automatic bus transfer devices
CN106300285A (en) It is independent of the self adaptation type feeder automation fault handling method on the spot of network topology
CN105527541B (en) A method of judgement distribution line failure tripping
CN112165090A (en) Cooperative self-healing system and method
CN101777879A (en) Bypass control method for two-path bidirectional tower amplifier
CN109066775A (en) A kind of grid type micro electric network coordination control system and its method
CN104410165A (en) Micro-network interconnection method and system
CN102880172A (en) Real-time control strategy checking method of safety stability control device
CN102593798B (en) Comprehensive relay protection method applied to intelligent switch
US11588331B2 (en) Method and system for transferring a load in a thunder and lightning weather
CN106787131B (en) A kind of two rank region spare power automatic switching system and prepared auto restart control method
CN109560556A (en) A kind of voltage-regulating system adjusted based on flexible multimode regulating switch
CN103384062B (en) Isolation control system of grid power distribution fault detection
EP3238310A1 (en) A method for controlled energising of a transformer
CN104124697B (en) A kind of imaginary power automatic compensation system
CN110518702A (en) Line feed terminals, feeder line control system and power network monitoring method
CN205945214U (en) 380V uses power spare power automatic switching system in station
CN103746354B (en) One kind is based on transformer station's overcurrent protection method for isolating power distribution network fault without constant time lag in
JP2009183122A (en) Automatic control system for distribution line compensation reactor
CN107240958A (en) A kind of switch jump processing method for the standby throwing of network
CN103533626A (en) Dormancy awakening method based on cascading skip wireless communication network
CN109995003B (en) Intelligent distributed feeder automation method based on state quantity
CN108667059B (en) Method and system for controlling impact of direct-current power depression on transmission-end power grid

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant