CN106532936A - Dispatching method of unattended substation - Google Patents
Dispatching method of unattended substation Download PDFInfo
- Publication number
- CN106532936A CN106532936A CN201610958062.2A CN201610958062A CN106532936A CN 106532936 A CN106532936 A CN 106532936A CN 201610958062 A CN201610958062 A CN 201610958062A CN 106532936 A CN106532936 A CN 106532936A
- Authority
- CN
- China
- Prior art keywords
- message
- transformer station
- dispatching method
- power
- control
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 20
- 238000012790 confirmation Methods 0.000 claims description 16
- 238000012795 verification Methods 0.000 claims description 15
- 238000004891 communication Methods 0.000 claims description 13
- 238000009434 installation Methods 0.000 claims description 7
- 238000005259 measurement Methods 0.000 claims description 4
- 230000011664 signaling Effects 0.000 claims description 4
- 238000005516 engineering process Methods 0.000 description 2
- 230000009466 transformation Effects 0.000 description 2
- PEDCQBHIVMGVHV-UHFFFAOYSA-N Glycerine Chemical compound OCC(O)CO PEDCQBHIVMGVHV-UHFFFAOYSA-N 0.000 description 1
- 244000097202 Rathbunia alamosensis Species 0.000 description 1
- 235000009776 Rathbunia alamosensis Nutrition 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000008280 blood Substances 0.000 description 1
- 210000004369 blood Anatomy 0.000 description 1
- 230000001447 compensatory effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000686 essence Substances 0.000 description 1
- 238000004880 explosion Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- H02J13/0006—
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/16—Electric power substations
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a dispatching method of an unattended substation. The dispatching method comprises the following steps of (S1) collecting working parameters of multiple paths of power equipment lines connected with the substation in real time and transporting the working parameters to a control center; (S2) comparing a preset parameter threshold by the control center according to the working parameters of the multiple paths of power equipment lines; and (S3) when real-time power of one or more paths of power equipment lines is greater than the preset threshold, dispatching the line of which the real-time power is smaller than the preset threshold for temporary scheduling compensation by the control center. According to the dispatching method of the unattended substation, automatic dispatching of the unattended substation can be achieved and the dispatching efficiency is improved.
Description
Technical field
The invention belongs to power system regulation automatization field, more particularly to a kind of unattended operation transformer station dispatching method.
Background technology
At present, with the fast development of China the Internet, the explosion of data scale is worth inside big data
Increasingly it is subject to people's attention.People imply that the increase in productivity of a new ripple and water for the excavation and utilization of mass data
The arrival of the person's of expense surplus tide.Nowadays, client's behavior on the internet, energy being serviced device are recorded with binary form
Come, such as Sina weibo, any active ues more than 100,000,000, daily data are magnanimity.In March, 2013, CSEE
For current electric power enterprise and the situation of power industry data, issue《China Power big data develops white paper》.2015 8
The moon 31, State Council is with promulgated by the State Council【2015】No. 50 are printed and distributed《Promote big data developing activity outline》.National policy is vigorously supported,
Give power industry and be filled with fresh blood, power industry is in crucial turning point, Intelligent transformer station, instant early warning system
The construction of system, measurement and control integration system, the mobile examination and repair system in scene etc. so that originally data type is more single, growth more
There is transformation in slow situation, gradually stepped into and switch to analyze based on multiple Variable Factors and large batch of all kinds of heterogeneous resources
The novel electric power big data epoch.
The transformer station of various electric pressures is difficult to efficiently quickly by the normal work of operator in running
Power scheduling control, if it is possible to unmanned is schedulable transformation facility, is possible to effectively improve the scheduling of transformer station
Efficiency.
Therefore, need now a kind of unattended operation transformer station dispatching method badly, the automatic of unattended operation transformer station can be realized
Scheduling, uses manpower and material resources sparingly, and improves dispatching efficiency.
The content of the invention
The present invention proposes a kind of unattended operation transformer station dispatching method, solves in prior art by the normal of operator
Work is difficult to efficiently the quickly problem of power scheduling control.
The technical scheme is that what is be achieved in that:Unattended operation transformer station dispatching method, comprises the steps:
S1:The running parameter of the electric installation lines that Real-time Collection multichannel is connected with transformer station, and by the running parameter
It is transported to control centre;
S2:Running parameter of the control centre according to multiple power equipment, is compared with parameter preset threshold values;
S3:When the realtime power of certain road or a few road power equipments is more than the pre-set threshold value, control centre's scheduling is real
When power carry out temporary scheduling compensation less than the circuit of the pre-set threshold value.
As one kind preferred embodiment, line of the power less than pre-set threshold value when control centre's debugging is real-time
Road carries out temporary scheduling compensation, including control transformer station correspondence switches on-off operation, and the break-make is instructed
Guan Qian, first carries out security constraint verification, determines whether make-break operation meets safety requirements.
As one kind preferred embodiment, line of the power less than pre-set threshold value when control centre's debugging is real-time
Road carries out temporary scheduling compensation, including calculates the parameter value of certain road or a few roads beyond pre-set threshold value, and determines idle line
Realtime power and pre-set threshold value difference and target compensation information, according to the difference, it is determined that per the power of road idle line
Offset.
As one kind preferred embodiment, control centre determines and believes more than pre-set threshold value power lines and compensation control
Breath, including the corresponding address of Real-time Collection circuit and net door information, the address and net door information is carried out with actual track
Verification matching.
As one kind preferred embodiment, step S4 is provided with after step S3:Control centre's recording power scheduling
Compensation record, generates scheduled record trendgram according to scheduled record.
Preferred embodiment the address and net door information are carried out into verification with actual track and is matched as a kind of, wrapped
Include the heart in the controlling and be provided with background data base, using the communication packet received from electric installation lines, by communication packet
It is analyzed with background data base and compares, so that it is determined that the selecting object of verification matching.
As one kind preferred embodiment, determine whether make-break operation meets safety requirements, when make-break operation meets peace
When requiring entirely, corresponding operating is carried out;When make-break operation has illegal information, control centre carries out police instruction and points out illegal
Information, and do not carry out make-break operation.
As it is a kind of preferred embodiment, the communication packet includes that the STARTDT of U forms comes into force message, U forms
STARTDT confirmation messages, total calling start message, always call confirmation message, always call end message, full remote signalling message, Quan Yao
Observe and predict text, remote control select message, remote control return to school message, remote control perform message, remote control perform confirmation message, remote control revocation message,
Remote control revocation confirmation message, COS messages and SOE messages.
As one kind preferred embodiment, the communication packet is expressed as:68+ length+4Byte control domains.
As one kind preferred embodiment, it is determined that the selecting object of verification matching, is also included using according to traffic order
Identification needs the selecting object and check point table of scheduling and far goes a table to carry out examining judgement.
After employing above-mentioned technical proposal, the invention has the beneficial effects as follows:The reality of different electric installation lines can be passed through
When power situation and circuit rated power situation, determine whether the power of electric installation lines exceeded, when more than pre-set threshold value
When, automatically controlling idle line carries out the compensative dispatching of power, meets its requirement.
Description of the drawings
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing
Accompanying drawing to be used needed for having technology description is briefly described, it should be apparent that, drawings in the following description are only this
Some embodiments of invention, for those of ordinary skill in the art, without having to pay creative labor, may be used also
To obtain other accompanying drawings according to these accompanying drawings.
Fig. 1 is the schematic flow sheet of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than the embodiment of whole.It is based on
Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made
Embodiment, belongs to the scope of protection of the invention.
As shown in figure 1, this unattended operation transformer station dispatching method, comprises the steps:
S1:The running parameter of the electric installation lines that Real-time Collection multichannel is connected with transformer station, and by the running parameter
It is transported to control centre;
S2:Running parameter of the control centre according to multiple power equipment, is compared with parameter preset threshold values;
S3:When the realtime power of certain road or a few road power equipments is more than the pre-set threshold value, control centre's scheduling is real
When power carry out temporary scheduling compensation less than the circuit of the pre-set threshold value.
When the control centre debugs real-time, power carries out temporary scheduling compensation less than the circuit of the pre-set threshold value, including
Control transformer station correspondence switches on-off operation, and the break-make is instructed before controlling switch is assigned, and first carries out security constraint verification,
Determine whether make-break operation meets safety requirements.
When the control centre debugs real-time, power carries out temporary scheduling compensation less than the circuit of the pre-set threshold value, including
The parameter value of certain road or a few roads beyond pre-set threshold value is calculated, and determines the realtime power of idle line and the difference of pre-set threshold value
Value and target compensation information, according to the difference, it is determined that per the power compensating value of road idle line.
Control centre is determined more than pre-set threshold value power lines and compensation control information, including Real-time Collection circuit correspondence
Address and net door information, the address and net door information are carried out into verification with actual track and are matched.
Step S4 is provided with after step S3:Control centre's recording power scheduled record, mends according to the scheduling
Repay record and generate scheduled record trendgram.
The address and net door information are carried out verification with actual track to match, control centre is included in and is provided with rear number of units
According to storehouse, using the communication packet received from electric installation lines, communication packet is analyzed with background data base and is compared,
So that it is determined that the selecting object of verification matching.
Determine whether make-break operation meets safety requirements, when make-break operation meets safety requirements, carry out corresponding operating;When
When make-break operation has illegal information, control centre carries out police instruction and points out illegal information, and does not carry out make-break operation.
The communication packet include the STARTDT of U forms come into force message, the STARTDT confirmation messages of U forms, total call
Start message, always call confirmation message, always call end message, full remote signalling message, full remote measurement message, remote control to select message, distant
Control message of returning to school, remote control execution message, remote control execution confirmation message, remote control revocation message, remote control revocation confirmation message, COS to report
Text and SOE messages.
The communication packet is expressed as:68+ length+4Byte control domains.
It is determined that verification matching selecting object, also include using according to traffic order recognize needs scheduling selecting object and
Check point table and a table is far gone to carry out examining judgement.
Specific communication packet shows as:
The STARTDT of 1.U forms comes into force message (main website → substation)
68 04 07 00 00 00
The STARTDT confirmation messages (substation → main website) of 2.U forms
68 04 0B 00 00 00
3. total calling starts message (main website → substation)
68 0E 00 00 00 00 64 01 06 00 00 00 00 00 00 14
4. it is total to call confirmation message (substation → main website)
68 0E 0E 00 02 00 64 01 07 00 00 00 00 00 00 14
5. it is total to call end message (substation → main website)
68 0E 18 00 02 00 64 01 0A 00 00 00 00 00 00 14
6. full remote signalling message
68 2D 14 00 02 00 01A0 14 00 00 00 81 00 00 00 00 00 00 00 00 00 00
00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00
7. full remote measurement message
68 2D 16 00 02 00 15 90 14 00 00 00 01 07 00 00 00 00 00 00 00 00 00
00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00 00
8. remote control selects message
68 0E 00 00 00 00 2E 01 06 00 00 00 21 0B 00 85
9. remote control is returned to school message
68 0E 00 00 00 00 2E 01 07 00 00 00 21 0B 00 85
10. remote control performs message
68 0E 00 00 00 00 2E 01 06 00 00 00 21 0B 00 05
11. remote controls perform confirmation message
68 0E 00 00 00 00 2E 01 07 00 00 00 21 0B 00 05
12. remote controls cancel message
68 0E 00 00 00 00 2E 01 08 00 00 00 21 0B 00 05
13. remote controls cancel confirmation message
68 0E 00 00 00 00 2E 01 09 00 00 00 21 0B 00 05
14.COS messages
68 0E 00 00 00 00 01 01 03 00 00 00 01 00 00 01
15.SOE messages
68 11 00 00 00 00 02 01 03 00 00 00 01 00 00 01 21 01 20。
Presently preferred embodiments of the present invention is the foregoing is only, not to limit the present invention, all essences in the present invention
Within god and principle, any modification, equivalent substitution and improvements made etc. should be included within the scope of the present invention.
Claims (10)
1. a kind of unattended operation transformer station dispatching method, it is characterised in that comprise the steps:
S1:The running parameter of the electric installation lines that Real-time Collection multichannel is connected with transformer station, and the running parameter is conveyed
To control centre;
S2:Running parameter of the control centre according to multiple power equipment, is compared with parameter preset threshold values;
S3:When the realtime power of certain road or a few road power equipments is more than the pre-set threshold value, real-time work(is dispatched by control centre
Rate carries out temporary scheduling compensation less than the circuit of the pre-set threshold value.
2. unattended operation transformer station dispatching method according to claim 1, it is characterised in that control centre's debugging is real
Constantly power carries out temporary scheduling compensation less than the circuit of the pre-set threshold value, including control transformer station correspondence switches on-off behaviour
Make, and the break-make is instructed before controlling switch is assigned, and first carries out security constraint verification, determine whether make-break operation meets safety and want
Ask.
3. unattended operation transformer station dispatching method according to claim 2, it is characterised in that control centre's debugging is real
Constantly power carries out temporary scheduling compensation less than the circuit of the pre-set threshold value, including calculates certain road or a few roads beyond default
The parameter value of threshold values, and determine the realtime power of idle line and the difference of pre-set threshold value and target compensation information, according to described
Difference, it is determined that per the power compensating value of road idle line.
4. unattended operation transformer station dispatching method according to claim 3, it is characterised in that control centre is determined more than pre-
If valve value rate circuit and compensation control information, including the corresponding address of Real-time Collection circuit and net door information, will be described
Address and net door information carry out verification with actual track and match.
5. unattended operation transformer station dispatching method according to claim 4, it is characterised in that be provided with after step S3
Step S4:Control centre's recording power scheduled record, generates scheduled record trend according to scheduled record
Figure.
6. unattended operation transformer station dispatching method according to claim 5, it is characterised in that the address and net door are believed
Breath carries out verification with actual track and matches, and is included in control centre and is provided with background data base, is set from electric power using receiving
The communication packet of reserve line, communication packet is analyzed with background data base and is compared, so that it is determined that the selection of verification matching is right
As.
7. unattended operation transformer station dispatching method according to claim 6, it is characterised in that determine whether make-break operation accords with
Safety requirements is closed, when make-break operation meets safety requirements, corresponding operating is carried out;When there is illegal information in make-break operation, control
Center processed carries out police instruction and points out illegal information, and does not carry out make-break operation.
8. unattended operation transformer station dispatching method according to claim 7, it is characterised in that the communication packet includes U
Come into force message, the STARTDT confirmation messages of U forms, total callings of the STARTDT of form starts message, always calls confirmation message, total
Calling end message, full remote signalling message, full remote measurement message, remote control select return to school message, remote control of message, remote control to perform message, distant
Control performs confirmation message, remote control revocation message, remote control revocation confirmation message, COS messages and SOE messages.
9. unattended operation transformer station dispatching method according to claim 8, it is characterised in that the communication packet is represented
For:68+ length+4Byte control domains.
10. unattended operation transformer station dispatching method according to claim 9, it is characterised in that it is determined that the choosing of verification matching
Object is selected, is also included using the selecting object and check point table that needs scheduling is recognized according to traffic order and is far gone a table to carry out core
It is real to judge.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610958062.2A CN106532936A (en) | 2016-11-03 | 2016-11-03 | Dispatching method of unattended substation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610958062.2A CN106532936A (en) | 2016-11-03 | 2016-11-03 | Dispatching method of unattended substation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106532936A true CN106532936A (en) | 2017-03-22 |
Family
ID=58325706
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610958062.2A Pending CN106532936A (en) | 2016-11-03 | 2016-11-03 | Dispatching method of unattended substation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106532936A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111191967A (en) * | 2020-04-09 | 2020-05-22 | 图灵人工智能研究院(南京)有限公司 | Energy supply data processing method, system, energy supply control device and storage medium |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104078969A (en) * | 2014-07-18 | 2014-10-01 | 国家电网公司 | Circuit overloading processing method used for direct current transmission system |
CN104682383A (en) * | 2015-01-30 | 2015-06-03 | 广东电网有限责任公司梅州供电局 | Method and system for adjusting open loop point by remote automatic bus transfer devices |
CN105978159A (en) * | 2016-06-29 | 2016-09-28 | 国网福建省电力有限公司 | Telecontrol testing online execution-free check method for transformer station |
-
2016
- 2016-11-03 CN CN201610958062.2A patent/CN106532936A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104078969A (en) * | 2014-07-18 | 2014-10-01 | 国家电网公司 | Circuit overloading processing method used for direct current transmission system |
CN104682383A (en) * | 2015-01-30 | 2015-06-03 | 广东电网有限责任公司梅州供电局 | Method and system for adjusting open loop point by remote automatic bus transfer devices |
CN105978159A (en) * | 2016-06-29 | 2016-09-28 | 国网福建省电力有限公司 | Telecontrol testing online execution-free check method for transformer station |
Non-Patent Citations (1)
Title |
---|
田劲: "电力系统站所远方终端DTU的设计与应用研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111191967A (en) * | 2020-04-09 | 2020-05-22 | 图灵人工智能研究院(南京)有限公司 | Energy supply data processing method, system, energy supply control device and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105739460B (en) | A kind of method and apparatus for the control interface automatically generating Internet of Things household electrical appliances | |
GB0422192D0 (en) | Transfer of a user equipment in a communication system | |
WO2006073641A3 (en) | Method and system for targeted broadcasting | |
WO2007051073A3 (en) | Method and apparatus for transmitting a pilotreport message in a wireless communication system | |
CN106155812A (en) | Method, device, system and the electronic equipment of a kind of resource management to fictitious host computer | |
CN102299833A (en) | Intelligent remote household control system and method | |
CN102026357A (en) | Power control method and device for base station | |
CN107015038A (en) | A kind of power consumption reminding method, device and ammeter based on intelligent electric meter | |
CN108171339A (en) | Distribution comprehensive business management system and its emergency repair method based on mobile interchange | |
CN103781122A (en) | Flow management device and method | |
CN104750458A (en) | Control method, control device, monitoring processing method and monitoring processing device for terminal application | |
CN108973760A (en) | A kind of charging pile management method based on Internet of Things | |
CN106532936A (en) | Dispatching method of unattended substation | |
CN103530737A (en) | State based maintenance method and state based maintenance system of urban rail transit equipment | |
CN105137779A (en) | Information processing method and smart home environment control equipment | |
CN109343488A (en) | Fieldbus monitoring early-warning system and method based on wechat and FDT technology | |
CN109587161A (en) | The monitoring method of smart grid remote control command transmission overall process information | |
SE0301933D0 (en) | Remote control | |
CN103647884B (en) | Traffic dispatching patcher based on intelligent terminal APP and method | |
CN102938113A (en) | Power grid failure recovery method and system based on power failure management system platform | |
CN108908343A (en) | Intelligent Mobile Robot and scheduling system business operations linkage system and method | |
CN103702277A (en) | Data transmission method and electronic equipment | |
CN106254448A (en) | A kind of information getting method and device | |
CN110544032A (en) | cloud platform-based remote dispatching system and method for generator cars | |
CN112351080B (en) | Internet of things terminal of power distribution system and communication method of Internet of things terminal and external device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170322 |
|
RJ01 | Rejection of invention patent application after publication |