CN104654948B - 一种边坡与近接隧道协同爆破施工的爆破控制方法 - Google Patents

一种边坡与近接隧道协同爆破施工的爆破控制方法 Download PDF

Info

Publication number
CN104654948B
CN104654948B CN201510023750.5A CN201510023750A CN104654948B CN 104654948 B CN104654948 B CN 104654948B CN 201510023750 A CN201510023750 A CN 201510023750A CN 104654948 B CN104654948 B CN 104654948B
Authority
CN
China
Prior art keywords
tunnel
blasting
slope
side slope
parameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510023750.5A
Other languages
English (en)
Other versions
CN104654948A (zh
Inventor
吴亮
金沐
钟冬望
李雷斌
蔡路军
李凤
欧阳建华
许锋
马建军
段卫东
磨季云
李寿贵
司剑峰
蒋培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Science and Engineering WUSE
Original Assignee
Wuhan University of Science and Engineering WUSE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Science and Engineering WUSE filed Critical Wuhan University of Science and Engineering WUSE
Priority to CN201510023750.5A priority Critical patent/CN104654948B/zh
Publication of CN104654948A publication Critical patent/CN104654948A/zh
Application granted granted Critical
Publication of CN104654948B publication Critical patent/CN104654948B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种边坡与近接隧道协同爆破施工的爆破控制方法,包括以下步骤:步骤一,根据现有爆破参数,布置测点,获取实际爆破振动参数,建立实测数据对应开挖断面时的隧道动力有限元模型;步骤二,确定隧道开挖工作面到边坡坡面的安全距离和边坡开挖工作面到隧道围岩的安全距离;步骤三,边坡开挖与隧道工程施工协同进行,若隧道工作面向边坡面方向推进到上述的两个安全距离的最大值时,暂停隧道爆破;步骤四,爆破工作全部转移至边坡开挖,待隧道出口部位的坡面开挖并加固完毕,由坡面向岩体内开挖隧道的工序;步骤五,开挖后续隧道口附近的边坡。有益效果是高效、经济,提升爆破质量的同时降低对边坡岩体和隧道围岩的稳定的影响等。

Description

一种边坡与近接隧道协同爆破施工的爆破控制方法
技术领域
本发明属于边坡开挖与隧道掘进爆破控制科学技术领域,具体是一种边坡与近接隧道协同爆破施工的爆破控制方法。
背景技术
随着经济的加速发展和交通基础建设的大规模展开,许多城市开始了新一轮地铁工程、人防工程和城际铁路工程的兴建,同时,大量的工程既要开山回填,也同时在山体内修建隧道工程,这些工程往往不可避免地需要在近距离条件下施工,特别是隧道口设计在待施工边坡上的工程。在这些工程施工中,作为一种主要施工方法的边坡开挖与隧道掘进爆破技术,其爆破参数的选取和施工工艺的确定是否合理,不仅直接影响到爆破质量、边坡与隧道两者的施工效率和工程经济效益,而且还影响到边坡岩体、隧道围岩的稳定、边坡和隧道支护的效果以及周围建筑物或构筑物的安全。如何把这种影响减小到最低限度,是边坡与隧道在近距离条件下协同施工的核心问题。采用保守的施工方式,可以有效的保护边坡岩体与隧道围岩结构,但势必会增加投资成本,延长施工工期,因此,在高效、经济的爆破开挖扰动施工与需保护的边坡岩体、隧道围岩结构间建立合理的爆破参数与施工工艺是目前亟待解决的关键问题。
发明内容
本发明所要解决的技术问题是提供一种高效、经济的边坡与近接隧道协同爆破施工的爆破控制方法,提升爆破质量的同时降低对边坡岩体和隧道围岩的稳定、边坡和隧道支护的效果以及周围建筑物或构筑物的安全的影响。
本发明解决上述技术问题的技术方案如下:一种边坡与近接隧道协同爆破施工的爆破控制方法,包括以下步骤:
步骤一,根据现有爆破参数,当隧道开挖,隧道开挖工作面距边坡面30米至50米时,在距隧道开挖工作面最近的边坡面上布置第一测点,和边坡开挖,在距离爆源最近的隧道围岩上布置第二测点,获取实际爆破振动参数,根据实际地质资料、边坡与隧道方位以及断面数据,建立实测数据对应开挖断面时的隧道动力有限元模型;
步骤二,根据实际监测爆破振动数据确定隧道动力有限元的动力参数,再根据确定的动力参数,预测现有爆破参数以获取边坡岩体结构的质点振动速度峰值,根据爆破安全规程以及岩体力学性能指标,确定隧道开挖工作面到边坡坡面的安全距离,确保隧道开挖不会影响边坡岩体的稳定性,和,根据边坡开挖爆破参数,采用隧道实测爆破质点振动参数,结合隧道动力有限元模型,确定边坡开挖工作面与隧道围岩的安全距离;
步骤三,边坡开挖与隧道工程施工协同进行,将隧道工作面向边坡面方向推进到上述的两个安全距离的最大值时,暂停隧道爆破;
步骤四,爆破工作全部转移至边坡开挖,待隧道出口部位的坡面开挖并加固完毕,优化爆破参数,采用由坡面向岩体内开挖隧道的工序,即隧道工程保留部分的开挖,直到隧道贯通;
步骤五,后续隧道口附近的边坡开挖,应监测隧道口围岩的质点振动速度,及时反馈并调整爆破参数,确保已形成的隧道口围岩结构的稳定。
进一步,步骤一中所述第二测点位置能够获取所述爆源到达所述第二测点的P波振动速度,以获取实际爆破振动参数。
进一步,步骤二中所述动力参数为爆破载荷峰值和瑞利阻尼参数。
本发明的有益效果是:高效、经济,提升爆破质量的同时降低对边坡岩体和隧道围岩的稳定、边坡和支护的效果以及周围建筑物或构筑物的安全的影响。
附图说明
图1为本发明边坡开挖时的施工山体结构剖视图;
图2为本发明所述隧道动力有限元模型的结构示意图;
附图中,各标号所代表的部件列表如下:
1、爆源,2、边坡开挖工作面,3、隧道开挖工作面,4、第二测点。
具体实施方式
以下结合附图对本发明的原理和特征进行描述,所举实例只用于解释本发明,并非用于限定本发明的范围。
一种边坡与近接隧道协同爆破施工的爆破控制方法,包括以下步骤:
步骤一,根据现有爆破参数,根据现有爆破参数,当隧道开挖,隧道开挖工作面3距边坡面50米时,在距隧道开挖工作面3最近的边坡面上布置第一测点,和边坡开挖,在距离爆源1最近的隧道围岩上布置第二测点4(见图1),获取的实际爆破振动参数,根据实际地质资料、边坡与隧道方位以及断面数据,建立如图2所示的实测数据对应开挖断面时的隧道动力有限元模型;
步骤二,根据实际监测爆破振动数据确定隧道动力有限元的爆破载荷峰值pd和瑞利阻尼参数α和β,其中爆破载荷峰值pd的计算公式如下,
p d = ρ 0 D 2 1 + γ 2 ρ m c p ρ m c p + ρ 0 D
式中:pd为透射入岩石的冲击波初始压力,ρ0、ρm分别为炸药的装药密度和岩石的密度,cp、D分别为岩石中的声速和炸药的爆速,γ为爆轰产物的膨胀绝热指数;
瑞利阻尼参数α和β的计算公式如下,
α = 2 ( ξ j ω i - ξ i ω j ) ( ω i + ω j ) ( ω i - ω j ) ω i ω j
β = 2 ( ξ i ω i - ξ j ω j ) ( ω i + ω j ) ( ω i - ω j )
式中:ωi和ωj为可以通过模态分析进行计算得到的给定体系的两个不同振动频率,ξi和ξj为相对应的阻尼比。
根据确定的爆破载荷峰值和瑞利阻尼参数,预测现有爆破参数以获取边坡岩体结构的质点振动速度峰值,根据爆破安全规程以及岩体力学性能指标,确定隧道开挖工作面3到边坡坡面的安全距离,确保隧道开挖不会影响边坡岩体的稳定性,和,根据边坡开挖爆破参数,采用隧道实测爆破质点振动参数,结合隧道动力有限元模型,确定边坡开挖工作面2与隧道围岩的安全距离;
步骤三,边坡开挖与隧道工程施工协同进行,将隧道工作面向边坡面方向推进到上述的两个安全距离的最大值时,暂停隧道爆破;
步骤四,爆破工作全部转移至边坡开挖,待隧道出口部位的坡面开挖并加固完毕,优化爆破参数,采用由坡面向岩体内开挖隧道的工序,即隧道工程保留部分的开挖,直到隧道贯通;
步骤五,后续隧道口附近的边坡开挖,应监测隧道口围岩的质点振动速度,及时反馈并调整爆破参数,确保已形成的隧道口围岩结构的稳定。
优选地,第二测点4位置能够获取爆源1到达第二测点4的P波振动速度,以获取的实际爆破振动参数。
以上所述仅为本发明的较佳实施例,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。

Claims (3)

1.一种边坡与近接隧道协同爆破施工的爆破控制方法,其特征在于,包括以下步骤:
步骤一,根据现有爆破参数,当隧道开挖,隧道开挖工作面(3)距边坡面30米至50米时,在距隧道开挖工作面(3)最近的边坡面上布置第一测点,和边坡开挖,在距离爆源(1)最近的隧道围岩上布置第二测点(4),获取实际爆破振动参数,根据实际地质资料、边坡与隧道方位以及断面数据,建立实测数据对应开挖断面时的隧道动力有限元模型;
步骤二,根据实际监测爆破振动数据确定隧道动力有限元的动力参数,再根据确定的动力参数,预测现有爆破参数以获取边坡岩体结构的质点振动速度峰值,根据爆破安全规程以及岩体力学性能指标,确定隧道开挖工作面(3)到边坡坡面的安全距离,确保隧道开挖不会影响边坡岩体的稳定性,和,根据边坡开挖爆破参数,采用隧道实测爆破质点振动参数,结合隧道动力有限元模型,确定边坡开挖工作面(2)与隧道围岩的安全距离;
步骤三,边坡开挖与隧道工程施工协同进行,将隧道工作面向边坡面方向推进到上述的两个安全距离的最大值时,暂停隧道爆破;
步骤四,爆破工作全部转移至边坡开挖,待隧道出口部位的坡面开挖并加固完毕,优化爆破参数,采用由坡面向岩体内开挖隧道的工序,即隧道工程保留部分的开挖,直到隧道贯通;
步骤五,后续隧道口附近的边坡开挖,应监测隧道口围岩的质点振动速度,及时反馈并调整爆破参数,确保已形成的隧道口围岩结构的稳定。
2.根据权利要求1所述的一种边坡与近接隧道协同爆破施工的爆破控制方法,其特征在于,步骤一中所述第二测点(4)位置能够获取所述爆源(1)到达所述第二测点(4)的P波振动速度,以获取实际爆破振动参数。
3.根据权利要求1或2所述的一种边坡与近接隧道协同爆破施工的爆破控制方法,其特征在于,步骤二中所述动力参数为爆破载荷峰值和瑞利阻尼参数。
CN201510023750.5A 2015-01-16 2015-01-16 一种边坡与近接隧道协同爆破施工的爆破控制方法 Expired - Fee Related CN104654948B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510023750.5A CN104654948B (zh) 2015-01-16 2015-01-16 一种边坡与近接隧道协同爆破施工的爆破控制方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510023750.5A CN104654948B (zh) 2015-01-16 2015-01-16 一种边坡与近接隧道协同爆破施工的爆破控制方法

Publications (2)

Publication Number Publication Date
CN104654948A CN104654948A (zh) 2015-05-27
CN104654948B true CN104654948B (zh) 2016-04-13

Family

ID=53246362

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510023750.5A Expired - Fee Related CN104654948B (zh) 2015-01-16 2015-01-16 一种边坡与近接隧道协同爆破施工的爆破控制方法

Country Status (1)

Country Link
CN (1) CN104654948B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107391841A (zh) * 2017-08-03 2017-11-24 中铁十局集团第五工程有限公司 临近既有病害隧道新建左右隧道的安全施工方法
CN111753401B (zh) * 2020-05-28 2024-04-09 武汉理工大学 基于悬臂梁模型的岩质高边坡爆破坡面振动速度预测方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2366890C1 (ru) * 2007-12-24 2009-09-10 Государственное образовательное учреждение высшего профессионального образования Иркутский государственный университет путей сообщения (ИрГУПС (ИрИИТ)) Способ образования врубовой полости
CN102434209A (zh) * 2011-11-03 2012-05-02 上海理工大学 隧道开挖对近接既有构筑物影响的监测方法
CN103852157A (zh) * 2014-03-18 2014-06-11 华侨大学 爆破地震波作用下深埋圆形隧道围岩质点振动规律测试方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2366890C1 (ru) * 2007-12-24 2009-09-10 Государственное образовательное учреждение высшего профессионального образования Иркутский государственный университет путей сообщения (ИрГУПС (ИрИИТ)) Способ образования врубовой полости
CN102434209A (zh) * 2011-11-03 2012-05-02 上海理工大学 隧道开挖对近接既有构筑物影响的监测方法
CN103852157A (zh) * 2014-03-18 2014-06-11 华侨大学 爆破地震波作用下深埋圆形隧道围岩质点振动规律测试方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
临近隧道掘进爆破对既有隧道的影响;钟冬望等;《爆炸与冲击》;20100925;第30卷(第5期);第456-462页 *
爆破振动对隧道洞口顺层岩质边坡稳定性影响研究;黄志强等;《爆破》;20120315;第29卷(第1期);第110-114页 *
边坡爆破振动传播规律的试验研究;钟冬望等;《武汉科技大学学报》;20100615;第33卷(第3期);第332-335页 *

Also Published As

Publication number Publication date
CN104654948A (zh) 2015-05-27

Similar Documents

Publication Publication Date Title
Liu et al. Application and development of hard rock TBM and its prospect in China
Rahimi et al. Ground behaviour analysis, support system design and construction strategies in deep hard rock mining–Justified in Western Australian's mines
Mandal et al. Evaluating extent and causes of overbreak in tunnels
Liang et al. Effect of blast-induced vibration from new railway tunnel on existing adjacent railway tunnel in Xinjiang, China
Counter Kidd Mine–dealing with the issues of deep and high stress mining–past, present and future
Abdullah A review on selection of tunneling method and parameters effecting ground settlements
Daraei et al. Prediction of overbreak depth in Ghalaje road tunnel using strength factor
Macias et al. D&B versus TBM: Review of the parameters for a right choice of the excavation method
CN104654948B (zh) 一种边坡与近接隧道协同爆破施工的爆破控制方法
Yang et al. Mining-induced deformation for a haulage drift of the hanging wall at Jinshandian iron mine in China
Bilgin et al. Rock mechanics aspects related to cutting efficiency of mechanical excavators, 25 years of experience in Istanbul
Yang et al. Deformation and failure characteristics of the roof in an unsupported area during rapid driving of coal roadway
Gustafsson Wire cutting as a complement to drill and blast in vibration sensitive environments
Sroka et al. Calculation of subsidence for room and pillar and longwall panels
Lu et al. Tunnel stability and in-situ rock stress
Pandey et al. Influence of geology on tunnel boring machine performance: A review
Radkevych et al. Overview of technologies for constructing the facilities at the Dniester pumped storage power station
Gamba et al. A TBM assembly cavern in the French Alps
Costa Feijoo Comparison analysis between D&B and mechanical excavation in underground construction
Naveen et al. Tunnel excavation in highly stressed weak rockmass condition
Stolárik et al. Analysis of load of the tunnel definitive lining due to vibrations of various sources
Garimella et al. Numerical Modelling Based Impact of Ground Vibrations
Khali et al. Design and planning of excavation sequence and blasting techniques for large UG caverns
Li et al. Mechanical response and field measurement analysis of custom-shaped steel sleeves during urban shield tunnel construction
Wang et al. Research on Active Advanced Support Technology of Backfilling and Mining Face

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160413

Termination date: 20170116

CF01 Termination of patent right due to non-payment of annual fee