CN104652448B - 一种不平衡基坑支护设计方法 - Google Patents
一种不平衡基坑支护设计方法 Download PDFInfo
- Publication number
- CN104652448B CN104652448B CN201510011722.1A CN201510011722A CN104652448B CN 104652448 B CN104652448 B CN 104652448B CN 201510011722 A CN201510011722 A CN 201510011722A CN 104652448 B CN104652448 B CN 104652448B
- Authority
- CN
- China
- Prior art keywords
- supporting construction
- foundation ditch
- pit
- depth
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
一种不平衡基坑支护设计方法,包括:确定基坑设计模型参数;确定支护结构位移模式;确定内支撑(3)位置;按照传统单支点桩静力平衡法确定基坑较深一侧的支护结构的参数;按照与传统方式相反的土压力计算方法确定基坑较浅侧支护结构的参数;在深浅基坑交界面上采用传统的悬臂支护结构进行支护;根据各部分支护结构的最大弯矩及最大剪力确定支护结构材料及配筋;最后进行整体稳定性验算、抗倾覆验算、抗隆起稳定性验算。采用本发明提供的不平衡基坑支护设计方法,充分利用了不平衡基坑的两侧侧压力不平衡的特性,发挥土体的抗压性能,在确保安全的前提下,节省材料,缩短工期,具有很高的推广应用价值。
Description
技术领域
本发明涉及一种不平衡基坑支护设计方法,属土木建筑工程施工技术领域。
背景技术
随着城市化的发展,用地紧张问题日益突出,地下空间的开发愈来愈占据着重要地位。地下空间开发规模越来越大,相应的基坑支护技术也就被要求不断提高以解决各种工程难题。
目前针对各种复杂环境的基坑支护技术不断完善,但由于这些深大基坑通常都位于密集城市中心,常常紧邻建筑物、交通干道、地铁隧道及各种地下管线等,施工条件复杂,重大恶性基坑事故仍时有发生。而且当前的基坑支护技术涉及的都是对称基坑(基坑相对两侧的侧压力相同)的支护,支护的目地主要是防止基坑外围的土体向坑中坍塌,但在工程实际中,由于工程环境的限制和施工的需要,电梯井、集水坑等坑中坑的存在,使得基坑往往是不平衡的(基坑相对两侧的侧压力不相同),可能出现基坑开挖较深一侧的支护结构通过内撑压迫开挖较浅一侧的支护结构向坑外倾斜,造成基坑围护结构失稳,甚至破坏周围的建筑物。而且对称基坑的设计,都是按照支护结构向坑中发生位移的模式来进行设计,不能充分利用土体的抗压能力,造成了极大的浪费。
因此,对于不平衡基坑,依据基坑可能发生的位移形式,进行合理的分析设计,找到一种经济有效的支护方法,是一个很现实的技术问题。
发明内容
本发明的目的是,针对上述基坑支护技术存在的问题,为了实现合理设计支护结构,达到安全经济有效的支护,本发明提供一种不平衡基坑支护设计方法。
实现本发明目的的技术方案是,本发明所提供的一种不平衡基坑的支护方法包括以下步骤:
(1)根据工程的工程地质报告、建筑结构施工图、明确各开挖面标高,简化基坑设计模型,确定不对称基坑的剖面参数,主要包括基坑较深侧的基坑深度与基坑较前侧的基坑深度,以及3倍深基坑深度范围内的地层土体的内摩擦角、粘聚力及有效重度。
(2)不对称基坑的两侧通过刚度足够大的支撑连接起来,考虑到基坑较深一侧的侧压力大于基坑较浅一侧的侧压力,则位移模式可以按照深基坑一侧向着浅基坑一侧发生位移的方式进行确定。
(3)在基坑较深的一侧,根据一般工程经验,在充分发挥内撑作用的同时,为避免内撑的位置太低,造成基坑整体侧移,可设内撑位于距地面0.3倍基坑深度的位置;采用传统单支点桩静力平衡法对基坑较深一侧的支护结构进行支护设计和计算:
在支护结构外侧按照朗肯主动土压力进行计算,距离地面z处的土压力值为其中称为主动土压力系数;c是计算点所在土体的粘聚力,单位为kPa;是计算点所在土体的内摩擦角,单位为度;γi是计算点上覆第i层土体的容重(水位以下的要按有效容重参与计算),单位为KN/m3;zi是计算点上覆第i层土体的厚度,单位为m。在支护结构的内侧按照朗肯被动土压力进行计算,距离坑底h处的土压力值为其中称为被动土压力系数;c是计算点所在土体的粘聚力,单位为kPa;是计算点所在土体的内摩擦角,单位为度;γi是计算点上覆基坑底以下的第i层土体的容重(水位以下的要按有效容重参与计算),单位为KN/m3;hi是计算点上覆基坑底以下的第i层土体的厚度,单位为m。计算支护结构外侧各层土压力的合力Eai与支护结构内侧基坑底以下各层土压力的合力Epi,对内支撑点取矩,依据ΣMai=ΣMPi,其中Mai为Eai对内支撑点产生的弯矩,MPi为EPi对内支撑点产生的弯矩;确定基坑较深一侧支护结构的深度L1,并可得内支撑的反力R=ΣEai-ΣEPi,计算最大弯矩Mmax,最大剪力FSmax。
(4)对于基坑较浅的一侧,与传统模式不同,支护结构外侧的土压力,按照步骤(3)中的朗肯被动土压力计算方法进行计算,在支护结构内侧基坑底部以下的部分,按照步骤(3)中朗肯主动土压力计算方法进行计算。求得支护结构外侧各层土压力的合力Epi与支护结构内侧基坑底以下各层土压力的合力Eai,根据静力平衡条件中的弯矩平衡ΣMai=ΣMPi确定桩长L2,再根据静力平衡条件中的水平方向力平衡R=ΣEpi-ΣEai确定桩L2′,取L2与L2′中较大的值作为基坑较浅一侧的支护结构深度。根据土压力分布及内支撑反力确定最大弯矩Mmax,最大剪力FSmax。
(5)在深浅基坑交界面上可采用传统的悬臂排桩支护方法进行支护,计算其最大弯矩及剪力。
(6)根据各部分支护结构的最大弯矩及最大剪力确定各部分支护结构材料及配筋。
(7)进行整体稳定性验算、抗倾覆验算、抗隆起稳定性验算。
本发明的有益效果是,本发明充分利用了不平衡基坑的两侧侧压力不平衡的特性,因地制宜,根据不平衡基坑的受力分布,分析变形形式,根据变形特性,合理设计支护结构,发挥土体的抗压性能,在确保安全的前提下,节省材料,缩短工期,实现安全经济有效的支护,具有很高的推广应用价值。
附图说明
图1是简化基坑剖面模型图;
图2是基坑较深侧的受力图;
图3是基坑较浅侧的受力图;
图4是支护结构剖面图;
图中,1是地面;2是基坑底面;3是内支撑;4是基坑较深侧支护结构;5是基坑较浅侧支护结构;6是坑中坑交界处支护结构;7是位移趋势线。
具体实施方式
现结合附图和具体实施例对本发明提出的不平衡基坑支护设计方法作进一步详细说明。在湖北省武汉市青山区某长江南岸某改造工程中,根据工程的相关资料查得地面1标高为0.0m,浅侧基坑底面2标高-5.0m,深侧基坑底面2标高-10.0m,,地下水位一般为-6.0m左右。
各层土体的参数如表1:
表1各土层参数设计值一览表
设置内支撑3位于-3.0m处,对基坑较深侧的支护结构进行计算,在支护结构外侧按照朗肯主动土压力进行计算,支护结构的内侧按照朗肯被动土压力进行计算,得到计算支护结构外侧各层土压力的合力Eai与支护结构内侧基坑底以下各层土压力的合力Epi,对内支撑点取矩,依据ΣMai=ΣMPi确定基坑较深一侧支护结构4的深度为20m。
对于基坑较浅的一侧,在支护结构外侧按照朗肯被动土压力进行计算,支护结构的内侧按照朗肯主动土压力进行计算,根据静力平衡条件中的弯矩平衡ΣMai=ΣMPi确定支护结构深度为9m,再根据静力平衡条件中的水平方向力平衡R=ΣEpi-ΣEai确定支护结构深度为13m,故取基坑较浅一侧的支护结构5深度为13m。
跟一般对称基坑设计方法相比,本发明提供的方法对于基坑较浅侧的支护,每延米节省支护结构长7m,经济效益显著。
Claims (5)
1.一种不平衡基坑支护设计方法,其特征在于,包括:
确定不对称基坑的剖面参数;
确定支护结构位移模式;
设置内支撑距离地面的距离为0.3倍的较深侧基坑的深度;
确定基坑较深一侧的支护结构的深度、最大弯矩、最大剪力及内支撑内力;
计算基坑较浅侧支护结构的内外侧土压力,并分别根据静力平衡法中的水平力平衡和弯矩平衡确定基坑较浅侧支护结构的深度,取较大值作为设计值;
在深浅基坑交界面上采用传统的悬臂支护结构进行支护,计算支护结构深度、最大弯矩及剪力;
根据各部分支护结构的最大弯矩及最大剪力确定支护结构材料及配筋;
进行整体稳定性验算、抗倾覆验算、抗隆起稳定性验算。
2.根据权利要求1所述的一种不平衡基坑支护设计方法,其特征在于,所述不对称基坑的剖面参数主要是基坑较深侧的基坑深度与基坑较前侧的基坑深度,以及3倍深基坑深度范围内的地层土体的内摩擦角、粘聚力及有效重度。
3.根据权利要求1所述的一种不平衡基坑支护设计方法,其特征在于,所述位移模式按照深基坑一侧向着浅基坑一侧发生位移的方式进行确定。
4.根据权利要求1所述的一种不平衡基坑支护设计方法,其特征在于,所述确定基坑较深一侧的支护结构的支护设计和计算:
计算支护结构外侧各层土压力的合力Eai与支护结构内侧基坑底以下各层土压力的合力Epi,对内支撑点取矩,依据ΣMai=ΣMPi确定基坑较深一侧支护结构的深度L1,并可得内支撑的反力R=ΣEai-ΣEPi,计算最大弯矩Mmax,最大剪力FSmax。
5.根据权利要求1所述的一种不平衡基坑支护设计方法,其特征在于,所述确定基坑较浅一侧的支护结构的支护设计和计算:
支护结构外侧的土压力,按照朗肯被动土压力计算方法进行计算,在支护结构内侧基坑底部以下的部分,按照朗肯主动土压力计算方法进行计算;求得支护结构外侧各层土压力的合力Epi与支护结构内侧基坑底以下各层土压力的合力Eai,根据静力平衡条件中的弯矩平衡ΣMai=ΣMPi确定桩长L2,再根据静力平衡条件中的水平方向力平衡R=ΣEpi-ΣEai确定桩L2′,取L2与L2′中较大的值作为基坑较浅一侧的支护结构深度;根据土压力分布及内支撑反力确定最大弯矩Mmax,最大剪力FSmax。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510011722.1A CN104652448B (zh) | 2015-01-10 | 2015-01-10 | 一种不平衡基坑支护设计方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510011722.1A CN104652448B (zh) | 2015-01-10 | 2015-01-10 | 一种不平衡基坑支护设计方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104652448A CN104652448A (zh) | 2015-05-27 |
CN104652448B true CN104652448B (zh) | 2016-06-15 |
Family
ID=53244042
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510011722.1A Expired - Fee Related CN104652448B (zh) | 2015-01-10 | 2015-01-10 | 一种不平衡基坑支护设计方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104652448B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108487258A (zh) * | 2018-03-28 | 2018-09-04 | 华东交通大学 | 一种粉砂土地层刚性围护结构非平衡设计方法 |
Families Citing this family (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105569050A (zh) * | 2015-12-29 | 2016-05-11 | 华东交通大学 | 一种相邻边界侧压力不均衡基坑角撑支护结构设计方法 |
CN107315868B (zh) * | 2017-06-20 | 2020-06-26 | 广州建设工程质量安全检测中心有限公司 | 一种基于Revit二次开发的基坑工程稳定性的设计方法及系统 |
CN108468335A (zh) * | 2018-03-26 | 2018-08-31 | 华东交通大学 | 一种非等长组合围护桩设计方法 |
CN108509376B (zh) * | 2018-03-26 | 2021-06-18 | 华东交通大学 | 一种基于位移模式修正的土压力计算方法 |
CN108951647A (zh) * | 2018-07-18 | 2018-12-07 | 中铁十二局集团第二工程有限公司 | 明挖隧道的坑中坑挖掘支护施工方法 |
CN108978677A (zh) * | 2018-09-04 | 2018-12-11 | 中铁大桥局集团有限公司 | 复杂地形下深基坑开挖组合支护结构 |
CN109558659B (zh) * | 2018-11-20 | 2022-04-19 | 华东交通大学 | 一种基于变形控制的悬臂式支护结构设计方法 |
CN110674545B (zh) * | 2019-09-03 | 2022-11-18 | 四川农业大学 | 一种复杂边界基坑模型构建方法 |
CN110777799B (zh) * | 2019-09-28 | 2020-10-02 | 深圳市地质局 | 基于非对称载荷的基坑设计方法 |
CN111827368A (zh) * | 2020-06-04 | 2020-10-27 | 中铁第四勘察设计院集团有限公司 | 一种地下结构抗浮设计方法 |
CN112647515A (zh) * | 2020-11-27 | 2021-04-13 | 中铁西安勘察设计研究院有限责任公司 | 人工挖孔井微型灌注桩支护后开挖进尺的预测方法 |
CN113591183B (zh) * | 2021-07-19 | 2023-10-13 | 浙江大学 | 一种黏性土地层多支点式围护结构非平衡计算方法 |
CN113591184B (zh) * | 2021-07-19 | 2023-10-20 | 浙江大学 | 一种邻近地下室外墙基坑悬臂式刚性围护结构设计计算方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102116029A (zh) * | 2009-12-30 | 2011-07-06 | 上海市第七建筑有限公司 | 土压力不平衡条件下环形支撑的加固方法 |
KR101410443B1 (ko) * | 2013-04-17 | 2014-06-20 | 주식회사 인우 (Inwoo.Co.Ltd) | 다용도 프리캐스트 콘크리트 블럭 및 이를 이용한 벽체 구조물 |
KR101431621B1 (ko) * | 2013-03-11 | 2014-08-21 | 주식회사 엔티에스건설 | 지하주차장 증축을 위한 지하 벽체 시공공법 |
-
2015
- 2015-01-10 CN CN201510011722.1A patent/CN104652448B/zh not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102116029A (zh) * | 2009-12-30 | 2011-07-06 | 上海市第七建筑有限公司 | 土压力不平衡条件下环形支撑的加固方法 |
KR101431621B1 (ko) * | 2013-03-11 | 2014-08-21 | 주식회사 엔티에스건설 | 지하주차장 증축을 위한 지하 벽체 시공공법 |
KR101410443B1 (ko) * | 2013-04-17 | 2014-06-20 | 주식회사 인우 (Inwoo.Co.Ltd) | 다용도 프리캐스트 콘크리트 블럭 및 이를 이용한 벽체 구조물 |
Non-Patent Citations (3)
Title |
---|
不平衡堆载作用下深基坑开挖支护结构性状研究;林刚等;《岩土力学》;20100831(第8期);第2592-2598页 * |
土压力不平衡情况下深基坑支护设计与实践;刘志方;《岩土工程学报》;20141130;第36卷(第Z1期);第141-147页 * |
非对称开挖条件下基坑变形性状分析;徐长节等;《岩土力学》;20140731(第7期);第1929-1934页 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108487258A (zh) * | 2018-03-28 | 2018-09-04 | 华东交通大学 | 一种粉砂土地层刚性围护结构非平衡设计方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104652448A (zh) | 2015-05-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104652448B (zh) | 一种不平衡基坑支护设计方法 | |
Li et al. | Investigation of steady water inflow into a subsea grouted tunnel | |
Liu et al. | Bearing behavior of wide-shallow bucket foundation for offshore wind turbines in drained silty sand | |
Zheng et al. | Strength reduction and step-loading finite element approaches in geotechnical engineering | |
CN109137930B (zh) | 一种适用于狭窄基坑的嵌固稳定性分析方法 | |
CN104005777B (zh) | 一种大型地下洞室群布置设计方法 | |
CN110188413A (zh) | 一种基坑开挖引起的旁侧盾构隧道围压变化的预测方法 | |
Wang et al. | Analysis of deep foundation pit construction monitoring in a metro station in Jinan city | |
Xu et al. | Shanghai center project excavation induced ground surface movements and deformations | |
CN109183838B (zh) | 一种高抗浮抗裂性能地下室底板结构及其设计方法 | |
Lueprasert et al. | Three dimensional finite element analysis for preliminary establishment of tunnel influence zone subject to pile loading. | |
Zhang et al. | Prediction of water inflow in Tsingtao subsea tunnel based on the superposition principle | |
Lin et al. | Deformation monitoring analysis and numerical simulation in a deep foundation pit | |
Yang et al. | Influence of deep excavation on adjacent bridge piles considering underlying karst cavern: A case history and numerical investigation | |
CN109087028A (zh) | 岩溶地层地铁施工盾构区间风险评价方法及系统 | |
Gunn et al. | Finite element modelling of installation effects | |
CN207295773U (zh) | 一种地下槽形体抗浮构造 | |
CN105569050A (zh) | 一种相邻边界侧压力不均衡基坑角撑支护结构设计方法 | |
CN111851515B (zh) | 邻接基坑协同施工围护结构及其施工方法 | |
Li et al. | Effect of the blocking water and limiting discharge and surrounding rock permeability on the stability of subsea tunnel | |
Li et al. | Numerical Analysis on the Performance of the Underwater Excavation | |
CN103821533A (zh) | 端墙式隧道洞门整体抗倾覆设计方法 | |
CN110472314A (zh) | 一种评估隧道存在软弱夹层下掌子面稳定性的方法 | |
Hoa | Pile design with consideration of down drag | |
Wang et al. | Study of the Mechanical Behavior of Retaining Structures and Adjacent Buildings during the Excavation of Deep and Long Pits |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160615 Termination date: 20170110 |