CN104614698B CN201510055022.2A CN201510055022A CN104614698B CN 104614698 B CN104614698 B CN 104614698B CN 201510055022 A CN201510055022 A CN 201510055022A CN 104614698 B CN104614698 B CN 104614698B
Authority
CN
China
Prior art keywords
phase
phase simulation
electric power
power meter
simulation load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510055022.2A
Other languages
Chinese (zh)
Other versions
CN104614698A (en
Inventor
李卫胜
黄文博
张提
李大鹏
张善刚
马谦
韩晓东
王宪太
许光宇
孙海龙
李耀荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Jining Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510055022.2A priority Critical patent/CN104614698B/en
Publication of CN104614698A publication Critical patent/CN104614698A/en
Application granted granted Critical
Publication of CN104614698B publication Critical patent/CN104614698B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Device, including three-phase simulation load are loaded with three-phase simulation the invention discloses a kind of electric power meter field-checking, the three-phase simulation load is three groups of inductance coils, and every group of inductance coil is wrapped on the cylindrical plunger of one;And the electric power meter of the electric energy size for detecting three-phase simulation load;And for connecting the connecting line between three-phase simulation load and electric power meter;And for switching the switch of three-phase simulation load, it is serially connected between three-phase simulation load and three phase mains;And the indicator lamp to instruction simulation load.This invention ensures that substation line bringing onto load operation after metering device safe and accurate and reliability service;Compact of the present invention, it is easy to carry, it is practical flexible.

Description

Electric power meter field-checking loads device with three-phase simulation
Technical field
The invention belongs to Electric Energy Metering Technology field, and in particular to a kind of electric power meter field-checking three-phase simulation Load device.
Background technology
In practical application, generally use electric power meter on-site calibrator carries out the wiring inspection of electric energy metering secondary Look into, electric energy metering secondary wiring check and judgement need to can be carried out in the case where electric energy meter carries load, therefore power transmission The same day can not complete it is powered in the case of wiring check, need to wait until circuit carry load after, do wiring check to scene again.If Fail in time by wiring check find mistake, there is security incident or economic accident, caused by consequence will be hardly imaginable.To be true Protect power network safe operation and metering accurately and reliably, before entering row line on-load connection box of electric energy meter inspection be very important.
It can be seen from the measuring principle of electric energy meter field check meter, no matter three-phase three-wire electric energy meter or three-phase and four-line electric energy Table, to carry out connection box of electric energy meter inspection using electric power meter on-site calibrator, the circuit that electric energy meter is measured must band There is certain load, it is contemplated that the no-load running situation after newly-built transformer station's power transmission, only with electric power meter field-checking Instrument can not complete zero load circuit electric energy meter wiring check.
The content of the invention
In order to solve the above problems, the present invention provides a kind of electric power meter field-checking and loads device with three-phase simulation.
To achieve the above object, the present invention uses following technical scheme:
A kind of electric power meter field-checking loads device, including three-phase simulation load, the three-phase mould with three-phase simulation It is three groups of inductance coils to intend load, and every group of inductance coil is wrapped on the cylindrical plunger of one;And born for detecting three-phase simulation The electric power meter of the electric energy size of load;And for connecting the connecting line between three-phase simulation load and electric power meter; And for switching the switch of three-phase simulation load, it is serially connected between three-phase simulation load and three phase mains;And to indicate mould Intend the indicator lamp of load.
It is described to be used to connect the connecting line between three-phase simulation load and electric power meter, including three-phase simulation load electricity Lead-out wire and the voltage connecting wire of three-phase simulation load are flowed, the voltage connecting wire of the three-phase simulation load is connected to electric energy metrical The voltage port of device, the three-phase simulation load current lead-out wire are connected to the electric current port of electric power meter.
The electric power meter is three-phase three-wire electric energy meter.
The indicator lamp is serially connected in three-phase simulation load current and drawn between port and the electric current port of electric power meter Three-phase simulation load current lead-out wire on.
If described three-phase simulation load current lead-out wire is the carried interest copper conductor being wrapped on inductance coil.
The cylindrical plunger is hollow cylinder iron core.
A kind of electric power meter field-checking loads device, including three-phase simulation load, the three-phase mould with three-phase simulation It is three groups of inductance coils to intend load, and every group of inductance coil is wrapped on the cylindrical plunger of one;And born for detecting three-phase simulation The electric power meter of the electric energy size of load;And for connecting the connecting line between three-phase simulation load and electric power meter; And for switching the switch of three-phase simulation load, it is serially connected between three-phase simulation load and three phase mains;And to indicate mould Intend the indicator lamp of load;The electric power meter is three-phase and four-line electric energy meter.
It is described to be used to connect the connecting line between three-phase simulation load and electric power meter, including three-phase simulation load electricity Flow the zero line lead-out wire of lead-out wire, the voltage connecting wire of three-phase simulation load and three-phase simulation load;The three-phase simulation load Voltage connecting wire be connected to the voltage port of electric power meter, the three-phase simulation load current lead-out wire is connected to electric energy The electric current port of metering device, the zero line lead-out wire of three-phase simulation load are connected to the zero line port of electric power meter.
The indicator lamp is serially connected in three-phase simulation load current and drawn between port and the electric current port of electric power meter Three-phase simulation load current lead-out wire on.
If described three-phase simulation load current lead-out wire is the carried interest copper conductor being wrapped on inductance coil.
Beneficial effects of the present invention are:
Electric power meter field-checking proposed by the present invention loads device with three-phase simulation, is filled in the electric energy metrical of transformer station Threephase load is simulated in addition in the case of putting no load, coordinates practicality with existing electric energy meter on-site calibrator, to electric energy meter Measure device and carry out wiring check;Ensure that substation line bringing onto load operation after metering device safe and accurate, reliability service; Compact of the present invention, it is easy to carry, it is practical flexible.
Brief description of the drawings
Fig. 1 is the electrical schematic diagram of the present invention;
Fig. 2 is the phase three-wire three fictitious load device wiring diagram of the present invention;
Fig. 3 is the three-phase and four-line fictitious load device wiring diagram of the present invention.
Embodiment
The present invention will be further described with embodiment below in conjunction with the accompanying drawings:
As shown in figure 1, a kind of electric power meter field-checking loads device, including three-phase simulation load with three-phase simulation, The three-phase simulation load is three groups of inductance coils L1, L2 and L3, and every group of inductance coil is wrapped in the hollow cylinder iron core of one On;And the electric power meter of the electric energy size for detecting three-phase simulation load;And for connecting three-phase simulation load and electricity Connecting line between energy metering device;And for switching switch K1, K2 and K3 of three-phase simulation load, it is serially connected with three-phase respectively Between fictitious load and three phase mains;And indicator lamp HL1, HL2 and HL3 to instruction simulation load;The electric energy meter Amount device is electric energy meter.
Every group of described inductance coil size is 0.154H;Set according to required fictitious load size and carry out loading switching Switch K1, K2, K3;The voltage connecting wire of described fictitious load is that the sub-thread copper being connected with electric energy meter tail voltage port is led Line, described three-phase current lead-out wire are the multiply copper conductor being wrapped on inductance coil;Described indicator lamp HL1, HL2, HL3 For three be correspondingly arranged with threephase load, indicator lamp HL1 series connection A phase current lead-out wires, indicator lamp HL2 series connection B phase currents draw Outlet, indicator lamp HL3 series connection C phase current lead-out wires, to indicate the size of switching load.
Fig. 2 show the phase three-wire three fictitious load device wiring diagram of invention.The A phase currents lead of three-phase simulation load device connects Connect electric energy meter A phase currents port;The C phase currents lead connection electric energy meter C phase currents port of three-phase simulation load device;Three-phase simulation Load the A phase voltages lead connection electric energy meter A phase voltages port of device;The C phase voltages lead connection electric energy of three-phase simulation load device Table C phase voltages port;The N phase voltages lead connection electric energy meter B phase voltages port of three-phase simulation load device.
Fig. 3 show the three-phase and four-line fictitious load device wiring diagram of invention.The A phase currents lead of three-phase simulation load device connects Connect electric energy meter A phase currents port;The B phase currents lead connection electric energy meter B phase currents port of three-phase simulation load device;Three-phase simulation Load the C phase currents lead connection electric energy meter C phase currents port of device;The A phase voltages lead connection electric energy of three-phase simulation load device Table A phase voltage port;The B phase voltages lead connection electric energy meter B phase voltages port of three-phase simulation load device;Three-phase simulation loads device C phase voltages lead connection electric energy meter C phase voltages port;The N phase terminals connection electric energy meter N phases port of three-phase simulation load device.
The N phases of the three-phase simulation load device load the zero line of device for three-phase simulation.
Three-phase three-wire electric energy meter phase voltage is 57.7V, and three-phase and four-line electric energy meter phase voltage is 220V, to ensure three-phase simulation The sensitivity and security of device verification are loaded, the rated voltage of fictitious load device is 300V, bearing power 3kW.
The electric power meter field-checking of the present invention is as follows using step with three-phase simulation load device:
(1) according to connection box of electric energy meter mode, the mode of connection of three-phase simulation load device is determined, three-phase simulation is loaded into device Voltage port is consecutively connected to electric energy meter voltage port and electric current port with electric current port;Selecting switch K1, K2 and K3 are got to Divide position;
(2) threephase load is connected by work with K3 according to practical operation situation, selecting switch K1, K2, selecting switch shares Three class:Zero load, semi-load, full load, and check whether indicator lamp work is normal, beginning field-checking work after confirming normally Make;
(3) after field-checking terminates, electric energy meter control source should be first disconnected, whether checks three-phase simulation load device indicator lamp Extinguish, after lamp to be instructed extinguishes, can off voltage electric current connecting line, power cut-off.
Although above-mentioned the embodiment of the present invention is described with reference to accompanying drawing, model not is protected to the present invention The limitation enclosed, one of ordinary skill in the art should be understood that on the basis of technical scheme those skilled in the art are not Need to pay various modifications or deformation that creative work can make still within protection scope of the present invention.

Claims (6)

1. a kind of electric power meter field-checking loads device with three-phase simulation, it is characterised in that is loaded including three-phase simulation, institute It is three groups of inductance coils to state three-phase simulation load, and every group of inductance coil is wrapped on a cylindrical plunger;And
For the electric power meter for the electric energy size for detecting three-phase simulation load;And
For connecting the connecting line between three-phase simulation load and electric power meter;And
For switching the switch of three-phase simulation load, it is serially connected between three-phase simulation load and three phase mains;And
To indicate the indicator lamp of three-phase simulation load;
It is described to be used to connect the connecting line between three-phase simulation load and electric power meter, including three-phase simulation load current draws Outlet and the voltage connecting wire of three-phase simulation load, the voltage connecting wire of the three-phase simulation load are connected to electric power meter Voltage port, the three-phase simulation load current lead-out wire is connected to the electric current port of electric power meter;
The indicator lamp is serially connected in three between three-phase simulation load current extraction port and the electric current port of electric power meter On phase fictitious load electric current lead-out wire.
2. a kind of electric power meter field-checking as claimed in claim 1 loads device with three-phase simulation, it is characterised in that institute It is three-phase three-wire electric energy meter to state electric power meter.
3. a kind of electric power meter field-checking as claimed in claim 1 loads device with three-phase simulation, it is characterised in that institute If the three-phase simulation load current lead-out wire stated is the carried interest copper conductor being wrapped on inductance coil.
4. a kind of electric power meter field-checking as claimed in claim 1 loads device with three-phase simulation, it is characterised in that institute It is hollow cylinder iron core to state cylindrical plunger.
5. a kind of electric power meter field-checking loads device with three-phase simulation, it is characterised in that is loaded including three-phase simulation, institute It is three groups of inductance coils to state three-phase simulation load, and every group of inductance coil is wrapped on a cylindrical plunger;And
For the electric power meter for the electric energy size for detecting three-phase simulation load;And
For connecting the connecting line between three-phase simulation load and electric power meter;And
For switching the switch of three-phase simulation load, it is serially connected between three-phase simulation load and three phase mains;And
To indicate the indicator lamp of three-phase simulation load;The electric power meter is three-phase and four-line electric energy meter;
It is described to be used to connect the connecting line between three-phase simulation load and electric power meter, including three-phase simulation load current draws The zero line lead-out wire of outlet, the voltage connecting wire of three-phase simulation load and three-phase simulation load;The electricity of the three-phase simulation load Pressure connecting line is connected to the voltage port of electric power meter, and the three-phase simulation load current lead-out wire is connected to electric energy metrical The electric current port of device, the zero line lead-out wire of three-phase simulation load are connected to the zero line port of electric power meter;
The indicator lamp is serially connected in three between three-phase simulation load current extraction port and the electric current port of electric power meter On phase fictitious load electric current lead-out wire.
6. a kind of electric power meter field-checking as claimed in claim 5 loads device with three-phase simulation, it is characterised in that institute If the three-phase simulation load current lead-out wire stated is the carried interest copper conductor being wrapped on inductance coil.
CN201510055022.2A 2015-02-03 2015-02-03 Electric power meter field-checking loads device with three-phase simulation Active CN104614698B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510055022.2A CN104614698B (en) 2015-02-03 2015-02-03 Electric power meter field-checking loads device with three-phase simulation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510055022.2A CN104614698B (en) 2015-02-03 2015-02-03 Electric power meter field-checking loads device with three-phase simulation

Publications (2)

Publication Number Publication Date
CN104614698A CN104614698A (en) 2015-05-13
CN104614698B true CN104614698B (en) 2017-12-29

Family

ID=53149232

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510055022.2A Active CN104614698B (en) 2015-02-03 2015-02-03 Electric power meter field-checking loads device with three-phase simulation

Country Status (1)

Country Link
CN (1) CN104614698B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108196216A (en) * 2016-11-20 2018-06-22 国网江西省电力公司赣东北供电分公司 A kind of electric energy meter verifies three-phase voltage attachment device
CN113466777B (en) * 2021-06-06 2022-11-11 国网河北省电力有限公司辛集市供电分公司 Intelligent electric energy meter error rapid determination device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202649459U (en) * 2012-05-28 2013-01-02 新安县电业公司 Temporary load device for electric energy metering device field calibration
EP2555425A2 (en) * 2011-08-04 2013-02-06 Tektronix, Inc. Means of providing variable reactive load capability on an electronic load
CN103777172A (en) * 2013-12-27 2014-05-07 珠海中慧微电子有限公司 Reliability testing system of intelligent electric meter and method thereof
CN204374405U (en) * 2015-02-03 2015-06-03 国家电网公司 Electric power meter field-checking three-phase simulation load device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120101760A1 (en) * 2010-10-26 2012-04-26 Praveen Sutrave Method of Enabling Calibration of a Current Transformer, and Associated Apparatus

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2555425A2 (en) * 2011-08-04 2013-02-06 Tektronix, Inc. Means of providing variable reactive load capability on an electronic load
CN202649459U (en) * 2012-05-28 2013-01-02 新安县电业公司 Temporary load device for electric energy metering device field calibration
CN103777172A (en) * 2013-12-27 2014-05-07 珠海中慧微电子有限公司 Reliability testing system of intelligent electric meter and method thereof
CN204374405U (en) * 2015-02-03 2015-06-03 国家电网公司 Electric power meter field-checking three-phase simulation load device

Also Published As

Publication number Publication date
CN104614698A (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN104345245B (en) Method for checking voltage transformer wiring correctness by using transformer turn ratio & group tester
CN104614698B (en) Electric power meter field-checking loads device with three-phase simulation
CN205484654U (en) Electric capacity disturbance route selection device
CN202886592U (en) Virtual load device of single-phase electric energy meter
CN102608414B (en) Embedded electric energy measuring method and application extension method of high voltage electrical switchgear
CN203745563U (en) Low-voltage switchgear electrical performance integrated testing stand
CN206208997U (en) A kind of transforming plant primary flow device
CN204374405U (en) Electric power meter field-checking three-phase simulation load device
CN104183379A (en) Connecting device for maintenance of secondary side of electric power current transformer
CN101661090A (en) Through-flow tester of neutral point current transformer of transformer
CN103630831B (en) The check system of grounding direction protective relay
CN103454553A (en) Secondary side phase checking device of voltage transformer
CN204789785U (en) Portable intelligent substation relay protection testing arrangement
CN205039053U (en) High accuracy zero sequence protection integral type current transformer
CN204789879U (en) Test system is put in electrified office of cubical switchboard and voltage signal extraction element thereof
CN203324397U (en) Passive AC micro-current collection amplifying apparatus
CN203745584U (en) Hexagonal chart drawing device
CN205509359U (en) Intelligent automatic supervision and control low pressure inlet wire switch board
CN105353181A (en) Electric power metering device
CN110780221A (en) Electrical measurement system for source end of circuit breaker on primary and secondary fusion complete set of column
CN201307154Y (en) Comprehensive test instrument for motor
CN202256414U (en) Portable-type multifunctional test power supply device
CN201682264U (en) Leakage protector
CN203910508U (en) Outdoor anti-ferromagnetic resonance voltage transformer
CN205003236U (en) Inspect device of high -pressure energy metering equipment wiring

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Li Weisheng

Inventor after: Sun Hailong

Inventor after: Li Yaorong

Inventor after: Huang Wenbo

Inventor after: Zhang Ti

Inventor after: Li Dapeng

Inventor after: Zhang Shangang

Inventor after: Ma Qian

Inventor after: Han Xiaodong

Inventor after: Wang Xiantai

Inventor after: Xu Guangyu

Inventor before: Huang Wenbo

Inventor before: Li Yaorong

Inventor before: Zhang Ti

Inventor before: Li Dapeng

Inventor before: Zhang Shangang

Inventor before: Ma Qian

Inventor before: Han Xiaodong

Inventor before: Wang Xiantai

Inventor before: Xu Guangyu

Inventor before: Sun Hailong

GR01 Patent grant
GR01 Patent grant