CN104594950B - A kind of underground coal mine flexible spray temporary airtight wall and its construction method - Google Patents

A kind of underground coal mine flexible spray temporary airtight wall and its construction method Download PDF

Info

Publication number
CN104594950B
CN104594950B CN201510002249.0A CN201510002249A CN104594950B CN 104594950 B CN104594950 B CN 104594950B CN 201510002249 A CN201510002249 A CN 201510002249A CN 104594950 B CN104594950 B CN 104594950B
Authority
CN
China
Prior art keywords
coal mine
framing
spray
underground coal
flexible
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510002249.0A
Other languages
Chinese (zh)
Other versions
CN104594950A (en
Inventor
吴怀国
韩德强
魏宏亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING RUINUOANKE NEW ENERGY TECHNOLOGY Co Ltd
Original Assignee
BEIJING RUINUOANKE NEW ENERGY TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING RUINUOANKE NEW ENERGY TECHNOLOGY Co Ltd filed Critical BEIJING RUINUOANKE NEW ENERGY TECHNOLOGY Co Ltd
Priority to CN201510002249.0A priority Critical patent/CN104594950B/en
Publication of CN104594950A publication Critical patent/CN104594950A/en
Application granted granted Critical
Publication of CN104594950B publication Critical patent/CN104594950B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation

Abstract

A kind of underground coal mine flexible spray temporary airtight wall of the present invention and its construction method, are related to a kind of closed wall construction and its construction method for playing sealing function during coal production.A kind of under underground dynamic pressure change its purpose is to provide, crack resistence Anti-air-leakage ability is strong, security is good, the underground coal mine flexible spray temporary airtight wall that uses manpower and material resources sparingly and a kind of construction method for constructing fast and easily underground coal mine flexible spray temporary airtight wall.A kind of underground coal mine flexible spray temporary airtight wall of the present invention includes framing, the framing includes some wood point columns and some crossbeams that left and right is arranged in parallel, the metope being spliced into by polylith wallboard is installed on the framing, flexible waterproof coating is coated with the metope, the flexible waterproof coating is macromolecule emulsion and the mixing cured composition of inorganic powder two parts.

Description

A kind of underground coal mine flexible spray temporary airtight wall and its construction method
Technical field
The present invention relates to a kind of wall and its construction method, is used to during coal production play more particularly to one kind close The closed wall construction and its construction method of envelope effect.
Background technology
Underground coal mine temporary airtight wall construct be double lanes exploitations efficient colliery essential one in downhole production Technology, divulges information in control, is played an important role during obstructing the pernicious gas such as goaf gas and carbon monoxide.Coal Temporary airtight wall is constructed under mine usually constructs among the horizontal river of each coal column.The country is still without unified method, colliery at present There is no specified in more detail in safety code yet.Traditional method has following several:(1) 50cm is stayed among the brick wall that thickness is 24cm Space filling loess or other high molecular foam materials;(2) mortar spraying is carried out on brick wall surface, thickness is in 10cm or so;(3) Plank in stud is put in wood or hangs up air duct fabric.The temporary airtight wall that these methods are constructed, which exists, to be changed and held by underground dynamic pressure It is easy to crack to leak out, leak the defects of securities such as gas are not high, while it is more to expend material and manpower, man-hour, is not suitable with modernization The development of high yield and high efficiency mine.
The content of the invention
The technical problem to be solved in the present invention is to provide one kind under underground dynamic pressure change, crack resistence Anti-air-leakage ability is strong, The underground coal mine flexible spray temporary airtight wall and one kind that security is good, uses manpower and material resources sparingly construct fast and easily underground coal mine The construction method of flexible spray temporary airtight wall.
A kind of underground coal mine flexible spray temporary airtight wall of the present invention, including framing, the framing include a left side Some wood that the right side is arranged in parallel put columns and some crossbeams, and the wall being spliced into by polylith wallboard is provided with the framing Face, is coated with flexible waterproof coating on the metope, the flexible waterproof coating is macromolecule emulsion and inorganic powder two parts Mixing cured composition.
A kind of underground coal mine flexible spray temporary airtight wall of the present invention, wherein pressing mass fraction in the flexible waterproof coating Inorganic powder including 1-2 parts of macromolecule emulsions and 1 part.
A kind of underground coal mine flexible spray temporary airtight wall of the present invention, wherein the macromolecule emulsion be acrylic emulsion, One or more in VAE lotions, polychloroprene latex or styrene-acrylic emulsion.
A kind of underground coal mine flexible spray temporary airtight wall of the present invention, wherein the inorganic powder include portland cement and One or both of sulphate aluminium cement, further includes silica flour, slag powders, rubber powder, cellulose ether, polymer fiber or silica flour In one or more.
A kind of underground coal mine flexible spray temporary airtight wall of the present invention, wherein the wallboard is plank or lumber core.
A kind of underground coal mine flexible spray temporary airtight wall of the present invention, wherein the left and right ends of the crossbeam reach and construct On the outside of frame, the part reached on the outside of framing is used to be inserted into the coal body of tunnel both sides to fix wall.
A kind of construction method of underground coal mine flexible spray temporary airtight wall of the present invention, comprises the following steps:
A) left and right is parallel between the coal body of the left and right sides in tunnel is provided with multiple wood point columns;
B) crossbeam is installed at the Along ent of wood point column, the crossbeam is connected with wood point column successively;
C) metope being spliced into by polylith wallboard is installed on the framing of wood point column and crossbeam composition;
D) using spray pump in metope surface spraying layer flexible water-repellent paint.
A kind of construction method of underground coal mine flexible spray temporary airtight wall of the present invention, wherein the flexible waterproof coating is Macromolecule emulsion and the mixing cured composition of inorganic powder two parts, wherein including 1-2 parts of macromolecule emulsion and 1 by mass fraction The inorganic powder of part.
A kind of construction method of underground coal mine flexible spray temporary airtight wall of the present invention, wherein the macromolecule emulsion is third One or more in olefin(e) acid lotion, VAE lotions, polychloroprene latex or styrene-acrylic emulsion.
A kind of construction method of underground coal mine flexible spray temporary airtight wall of the present invention, wherein the inorganic powder includes silicon One or both of acid salt cement and sulphate aluminium cement, it is fine to further include silica flour, slag powders, rubber powder, cellulose ether, polymer One or more in dimension or silica flour.
A kind of underground coal mine flexible spray temporary airtight wall of the present invention and its construction method difference from prior art exist Include the framing formed by wood point column and crossbeam in a kind of underground coal mine flexible spray temporary airtight wall of the present invention, in structure The metope that wallboard composition is provided with frame is built, fire dam of the invention is simple in structure, it is possible to reduce the dosage of construction material, together When be coated with metope by macromolecule emulsion and the mixing cured flexible waterproof coating formed of inorganic powder two parts, Ci Zhongrou Property water-repellent paint cure after existing stronger adhesive strength, tensile strength, and there is excellent extension property, its elongation percentage can be with 30%~200% is reached, can effectively solve the problems, such as that ore deposit buckling causes metope secondary leak out caused by cracking to be revealed with gas, Improve the security of worker's underground work.A kind of construction method operation letter of underground coal mine flexible spray temporary airtight wall of the present invention Just, cycle that fire dam constructs can be shortened, used manpower and material resources sparingly, and reduce fire dam later stage cracking maintenance times.
Below in conjunction with the accompanying drawings to the present invention a kind of underground coal mine flexible spray temporary airtight wall make and its construction method into One step explanation.
Brief description of the drawings
Fig. 1 is a kind of structure diagram of underground coal mine flexible spray temporary airtight wall of the present invention.
Embodiment
As shown in Figure 1, embodiment 1, a kind of underground coal mine flexible spray temporary airtight wall of the present invention includes framing, structure Building frame includes wood point column 5, and the present embodiment selects four wood point columns 5, and the width and thickness of wood point column 5 are 10cm, and length is slightly larger than Head-room.For four wood point columns 5 uniformly between the top plate 1 and bottom plate 6 in tunnel, wood point column 5 top is installed on top plate 1 In groove, and clamped with chock 7.Crossbeam 4 is installed on wood point column 5, the present embodiment selects two crossbeams 4, crossbeam 4 it is wide and thick Respectively 10cm and 4cm, length are slightly larger than span length.Crossbeam 4 is installed at two trisection points of wood point column 5 respectively, crossbeam 4 It is connected successively with four wood point columns 5.The left and right ends of crossbeam 4 reach the outside of framing, and are inserted at left and right sides of tunnel Coal body 3 among.The metope being spliced into by polylith wallboard 2 is installed, wallboard 2 selects plank or lumber core on framing.Wall The flexible water-repellent paint of multilayer is sprayed on face, a time thickness of spraying is generally 1~2mm, and last coating thickness is 3~6mm, and table Face is substantially smooth, uniform.Flexible waterproof coating is macromolecule emulsion and the mixing cured composition of inorganic powder two parts.Wherein high score Sub- lotion is the one or more in acrylic emulsion, VAE lotions, polychloroprene latex or styrene-acrylic emulsion.Inorganic powder includes silicic acid One or both of salt cement and sulphate aluminium cement, further include silica flour, slag powders, rubber powder, cellulose ether, polymer fiber Or the one or more in silica flour.Include 1-2 parts of macromolecule emulsion and 1 part of nothing by mass fraction in flexible waterproof coating Machine powder, the mixing situation of different proportion can make final flexible waterproof coating have different elongation percentage.In the present embodiment Select 1 part of macromolecule emulsion and 1 part of inorganic powder is mixing cured forms, wherein macromolecule emulsion selects acrylic emulsion, powder Portland cement is selected, its elongation percentage is 30% after mixing.
A kind of construction method of underground coal mine flexible spray temporary airtight wall of the present invention comprises the following steps:
A) left and right is parallel between the coal body 3 of the left and right sides in tunnel is provided with multiple wood point columns 5;
B) crossbeam 4 is installed at the Along ent of wood point column 5, crossbeam 4 is connected with wood point column 5 successively, forms framing;
C) metope being spliced into by polylith wallboard 2 is installed on framing;
D) using spray pump in metope surface spraying layer flexible water-repellent paint.
Table 1 is embodiment 2-12, wherein embodiment 2 and 3 difference from Example 1 of embodiment be macromolecule emulsion and The component of inorganic powder is different;Embodiment 4-6 and embodiment 1-3 differences are between macromolecule emulsion and inorganic powder Quality proportion is different, and macromolecule emulsion is different with the constituent of inorganic powder;Embodiment 7-12 and embodiment 1-6 differences It is that the quality proportion between macromolecule emulsion and inorganic powder is different, the constituent of macromolecule emulsion and inorganic powder is not Together, the content of each component is different in inorganic powder.
Table 1
Embodiment described above is only that the preferred embodiment of the present invention is described, not to the model of the present invention Enclose and be defined, on the premise of design spirit of the present invention is not departed from, technical side of the those of ordinary skill in the art to the present invention The various modifications and improvement that case is made, should all fall into the protection domain that claims of the present invention determines.

Claims (4)

  1. A kind of 1. underground coal mine flexible spray temporary airtight wall, it is characterised in that:Including framing, the framing includes Some wood that left and right is arranged in parallel put columns and some crossbeams, are provided with what is be spliced into by polylith wallboard on the framing Metope, is coated with flexible waterproof coating on the metope, the flexible waterproof coating is macromolecule emulsion and inorganic powder two Divide mixing cured composition, pressing mass fraction in the flexible waterproof coating includes acrylic emulsion or polychloroprene latex or VAE lotions 2 Part and 0.4 part of portland cement, 0.3 part of sulphate aluminium cement, 0.02 part of polymer fiber, 0.2 part of silica flour, silica flour 0.05 Part, the mixing cured composition of inorganic powder two parts of 0.03 part of composition of rubber powder, the flexible waterproof coating coating thickness is each Spray 1~2mm, final 3~6mm of spray layer thickness.
  2. A kind of 2. underground coal mine flexible spray temporary airtight wall according to claim 1, it is characterised in that:The wallboard is Plank or lumber core.
  3. A kind of 3. underground coal mine flexible spray temporary airtight wall according to claim 1, it is characterised in that:The crossbeam Left and right ends are reached on the outside of framing, and the part reached on the outside of framing is used for the coal body for being inserted into tunnel both sides Middle fixed wall.
  4. A kind of 4. construction method of underground coal mine flexible spray temporary airtight wall, it is characterised in that:Comprise the following steps:
    A) left and right is parallel between the coal body of the left and right sides in tunnel is provided with multiple wood point columns;
    B) crossbeam is installed at the Along ent of wood point column, the crossbeam is connected with wood point column successively;
    C) metope being spliced into by polylith wallboard is installed on the framing of wood point column and crossbeam composition;
    D) using spray pump in metope surface spraying layer flexible water-repellent paint, the flexible waterproof coating for macromolecule emulsion and The mixing cured composition of inorganic powder two parts, wherein including acrylic emulsion or 2 parts of polychloroprene latex or VAE lotions by mass fraction With 0.4 part of portland cement, 0.3 part of sulphate aluminium cement, 0.02 part of polymer fiber, 0.2 part of silica flour, 0.05 part of silica flour, 0.03 part of mixing cured composition of rubber powder, the flexible spray water-repellent paint coating thickness are 1~2mm of spraying every time, are finally sprayed 3~6mm of layer thickness, surfacing, uniformly.
CN201510002249.0A 2015-01-04 2015-01-04 A kind of underground coal mine flexible spray temporary airtight wall and its construction method Active CN104594950B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510002249.0A CN104594950B (en) 2015-01-04 2015-01-04 A kind of underground coal mine flexible spray temporary airtight wall and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510002249.0A CN104594950B (en) 2015-01-04 2015-01-04 A kind of underground coal mine flexible spray temporary airtight wall and its construction method

Publications (2)

Publication Number Publication Date
CN104594950A CN104594950A (en) 2015-05-06
CN104594950B true CN104594950B (en) 2018-04-13

Family

ID=53120959

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510002249.0A Active CN104594950B (en) 2015-01-04 2015-01-04 A kind of underground coal mine flexible spray temporary airtight wall and its construction method

Country Status (1)

Country Link
CN (1) CN104594950B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106673562A (en) * 2017-02-16 2017-05-17 西安科技大学 Inhibited mortar emulsion for fire prevention and extinguishment in coal mine and spraying method thereof
CN108101469A (en) * 2017-12-12 2018-06-01 河南金拇指防水科技股份有限公司 A kind of implementation of cement base spraying rapid hardening aqueous waterproofing paint layer
CN110410132B (en) * 2019-08-06 2021-03-02 陕西煤业化工技术研究院有限责任公司 Air leakage preventing process for reserving narrow coal pillars
CN113356927B (en) * 2021-07-20 2023-10-20 国能神东煤炭集团有限责任公司 Underground fireproof explosion-proof airtight isolation system and construction method thereof
CN113880508A (en) * 2021-09-07 2022-01-04 山西晋煤集团技术研究院有限责任公司 Material for quickly sealing easily weathered surrounding rock of coal mine bottom suction roadway and using method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102477257A (en) * 2010-11-22 2012-05-30 大连创达技术交易市场有限公司 Novel ageing-resistant waterproof coating
CN102777208A (en) * 2012-08-02 2012-11-14 兖州煤业股份有限公司 Method for constructing mining impact-resisting sealed wall
CN202578779U (en) * 2012-03-16 2012-12-05 惠兴田 Large-framework concrete gob-side separation wall
CN102888165A (en) * 2012-10-26 2013-01-23 苏州市姑苏新型建材有限公司 Quick-setting polymer latex waterproof coating
CN104164143A (en) * 2013-05-16 2014-11-26 扬州豪扬新型建筑材料有限公司 Two-component macromolecular high elastic waterproof paint

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8737526B2 (en) * 2010-06-30 2014-05-27 Qualcomm Incorporated Predistortion of complex modulated waveform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102477257A (en) * 2010-11-22 2012-05-30 大连创达技术交易市场有限公司 Novel ageing-resistant waterproof coating
CN202578779U (en) * 2012-03-16 2012-12-05 惠兴田 Large-framework concrete gob-side separation wall
CN102777208A (en) * 2012-08-02 2012-11-14 兖州煤业股份有限公司 Method for constructing mining impact-resisting sealed wall
CN102888165A (en) * 2012-10-26 2013-01-23 苏州市姑苏新型建材有限公司 Quick-setting polymer latex waterproof coating
CN104164143A (en) * 2013-05-16 2014-11-26 扬州豪扬新型建筑材料有限公司 Two-component macromolecular high elastic waterproof paint

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
煤矿防爆密闭墙技术标准探讨;滕博 等;《煤炭科学技术》;20070228;第35卷(第2期);97-100 *
红会四矿高水压下防水密闭墙的设计及应用;杜昱;《煤》;20131231;第22卷(第10期);29-30 *

Also Published As

Publication number Publication date
CN104594950A (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN104594950B (en) A kind of underground coal mine flexible spray temporary airtight wall and its construction method
CN203961040U (en) A kind of fire proof construction for steel column
CN103806609A (en) Construction method of double-faced self-adhesion waterproof roll
CN203429831U (en) Split-free composite heat insulation template for pouring concrete
CN103388367A (en) Waterproof structure for connection joint between precast wall body and wallboard building block as well as construction method
CN103089013A (en) Anti-cracking construction method of light heat preservation batten wall body
CN106592897A (en) Gypsum based fire protection material and fire protection and decoration integrated construction method for gypsum based fire protection material on steel member
CN104532968B (en) Prevent concrete structure from building the method for filling wall connecting portion crack with rear
CN204728515U (en) A kind of outer-wall crack-resisting anti-leakage structure
CN207211517U (en) It is a kind of to be provided with pre-buried electric partition plate
CN206368532U (en) A kind of wall and the aluminum wood template splicing of beam slab junction are constructed
CN215858388U (en) Composite wall with special-shaped section structure light steel keel
CN105822006B (en) Novel light aggregate concrete partition wall batten and its construction technique
CN207686123U (en) A kind of building combined wall board
CN104110128A (en) Rapid assembly wall formwork
CN104343137B (en) Underground waterproof engineering construction method
CN206616799U (en) A kind of sunk type concrete mixing plant aluminium alloy board house metope body structure
CN207776119U (en) A kind of connection structure of assembled wall
CN106049783B (en) A kind of steel plate bag column system of anticollision
CN202064480U (en) Outer separating wall built with lightweight concrete separating plates
CN206245495U (en) A kind of waterproof construction of wall joints
CN206360199U (en) A kind of high-strength waterproof partition plate
CN205577101U (en) Shaped steel gypsum combined strength structure
CN205637426U (en) Novel environment -friendly composite building material board of easily fixing
CN206769186U (en) Counterpart stings muscle cementation of fissures enhancing crack resistence Light trabses and assembled wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant