CN104594922A - Tunnel steel arch installation method - Google Patents
Tunnel steel arch installation method Download PDFInfo
- Publication number
- CN104594922A CN104594922A CN201410694187.XA CN201410694187A CN104594922A CN 104594922 A CN104594922 A CN 104594922A CN 201410694187 A CN201410694187 A CN 201410694187A CN 104594922 A CN104594922 A CN 104594922A
- Authority
- CN
- China
- Prior art keywords
- steel arch
- shelf
- lifting
- tunnel
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/40—Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
Abstract
The invention discloses a tunnel steel arch installation method. The method comprises the steps that an operation rack is set up, and a lifting rack and a moving track are installed on an excavation trolley; a lifting trolley is installed; steel arches are lifted, wherein the lifting trolley is used for lifting steel arch components onto the operation rack; the steel arches are connected on the operation rack; the steel arches are installed, wherein the lifting rack is used for installing the steel arches. The tunnel steel arch installation method has the advantages that the installation speed of the tunnel steel arches is increased, waste of labor of workers is reduced, safety and reliability are achieved, and the actual installation cost of the tunnel steel arches is lowered.
Description
Technical field
The present invention relates to a kind of tunnel steel arch frame mounting method.
Background technology
In construction of tunnel, various Modelling of Tunnel Excavation in Soft Rock uses steel arch-shelf as the one of preliminary bracing in a large number, wherein shaped steel arch application is more frequent, steel arch-shelf conventional at present mainly comprises reinforcing bar grid bow member and shaped steel arch, its concrete work progress is: in tunnel portal steel beam column factory according to each component of country rock design size processing type steel arch-shelf residing for tunnel, after tunnel excavation, loader is utilized to have bad luck to face place by manufactured Steel section member, adopt digging machine to coordinate and manually carry out in-site installation, this constructure scheme Problems existing is mainly in installation, need digging machine to coordinate during installation manually to install, it is artificial that at substantial vertically had bad luck by shaped steel, and heavy mechanical equipment is not because having working space, use not smooth.Tunnel steel arch frame is installed and is adopted hand fit digging machine, loader is installed, and during installation, not only causes mounting cost higher, and big machinery appropriate to the occasionly causes machine security accident with artificial construction simultaneously.And in city, workman's labor wage is generally higher, tunnel steel arch frame is installed and is adopted artificial installation to cause expenses of labour higher, added cost, and because artificial steel arch-shelf efficiency of installing is too low, overlong time, causes tunnel can not carry out steel arch-shelf installation and lower step construction of shotcrete in time after excavation.
Summary of the invention
Its object of the present invention is just to provide a kind of tunnel steel arch frame mounting method, has increase tunnel steel arch frame installation rate, minimizing workman manually wastes, safe and reliable feature, and reduce tunnel steel arch frame installation actual cost.
Realize above-mentioned purpose and the technical scheme taked, comprise step,
1) setting of operation platform, is mounted on excavation chassis by lifting rack and moving track;
2) lifting dolly is installed;
3) steel arch-shelf lifting, utilizes lifting dolly to winch on operation platform by steel arch-shelf component;
4) steel arch-shelf connects, and operation platform connects steel arch-shelf;
5) steel arch-shelf is installed, and utilizes lifting rack, carries out steel arch-shelf installation.
Compared with prior art the present invention has the following advantages.
There is increase tunnel steel arch frame installation rate, minimizing workman manually wastes, safe and reliable feature, and reduce tunnel steel arch frame installation actual cost.
Detailed description of the invention
Comprise step,
1) setting of operation platform, is mounted on excavation chassis by lifting rack and moving track;
2) lifting dolly is installed;
3) steel arch-shelf lifting, utilizes lifting dolly to winch on operation platform by steel arch-shelf component;
4) steel arch-shelf connects, and operation platform connects steel arch-shelf;
5) steel arch-shelf is installed, and utilizes lifting rack, carries out steel arch-shelf installation.
Embodiment
1) setting of operation platform, lifting rack and moving track are mounted on excavation chassis, moving track is fixed on above operation platform, lifting rack is arranged on moving track, so that lifting rack is by after steel arch-shelf picking-up, move to design mileage position, then raise lifting rack by steel arch-shelf installation in position.
2) lifting dolly is installed;
Lifting dolly is arranged on operation platform, above the convenient lifting rack be promoted to by the steel arch-shelf processed on chassis.
3) steel arch-shelf lifting, utilizes lifting dolly to winch on lifting rack by steel arch-shelf component;
4) steel arch-shelf connects, and is connected by arch springing place, both sides steel arch-shelf with the steel arch-shelf on lifting rack;
5) steel arch-shelf is installed, and utilizes lifting rack, carries out steel arch-shelf installation.
Claims (1)
1. a tunnel steel arch frame mounting method, is characterized in that, comprises step,
1) setting of operation platform, is mounted on excavation chassis by lifting rack and moving track;
2) lifting dolly is installed;
3) steel arch-shelf lifting, utilizes lifting dolly to winch on operation platform by steel arch-shelf component;
4) steel arch-shelf connects, and operation platform connects steel arch-shelf;
5) steel arch-shelf is installed, and utilizes lifting rack, carries out steel arch-shelf installation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410694187.XA CN104594922A (en) | 2014-11-27 | 2014-11-27 | Tunnel steel arch installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410694187.XA CN104594922A (en) | 2014-11-27 | 2014-11-27 | Tunnel steel arch installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104594922A true CN104594922A (en) | 2015-05-06 |
Family
ID=53120931
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410694187.XA Pending CN104594922A (en) | 2014-11-27 | 2014-11-27 | Tunnel steel arch installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104594922A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005083014A (en) * | 2003-09-05 | 2005-03-31 | Ishikawajima Constr Materials Co Ltd | Pre-cast tunnel method and member conveyor used therefor |
CN202970736U (en) * | 2012-12-26 | 2013-06-05 | 中铁一局集团有限公司 | Steel arch mounting device |
CN203285453U (en) * | 2013-04-15 | 2013-11-13 | 中铁十八局集团第一工程有限公司 | Tunnel steel arch auxiliary installation device |
CN103643963A (en) * | 2013-12-23 | 2014-03-19 | 中铁工程装备集团有限公司 | Multifunctional tunneling machine |
-
2014
- 2014-11-27 CN CN201410694187.XA patent/CN104594922A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005083014A (en) * | 2003-09-05 | 2005-03-31 | Ishikawajima Constr Materials Co Ltd | Pre-cast tunnel method and member conveyor used therefor |
CN202970736U (en) * | 2012-12-26 | 2013-06-05 | 中铁一局集团有限公司 | Steel arch mounting device |
CN203285453U (en) * | 2013-04-15 | 2013-11-13 | 中铁十八局集团第一工程有限公司 | Tunnel steel arch auxiliary installation device |
CN103643963A (en) * | 2013-12-23 | 2014-03-19 | 中铁工程装备集团有限公司 | Multifunctional tunneling machine |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104695984A (en) | Multifunctional tunnel construction trolley | |
CN204627636U (en) | The multi-functional chassis of wheeled four arm constructing tunnel | |
CN208650880U (en) | A kind of arch installation manipulator for tunnel support construction equipment | |
CN103244151A (en) | Multifunctional support trolley for tunnel arches | |
CN104295307A (en) | Mounting machine for steel arch of tunnel and mounting method of steel arch | |
CN204716257U (en) | Guarantee that shield whole starts and the variable door opening cribbing of station main body synchronous construction | |
JP2015206200A (en) | Construction method and construction device of shield tunnel | |
CN205000974U (en) | A tire formula automatic rising equipment rack for tunnel excavation construction | |
CN104314577B (en) | Shield machine assembly and disassembly methods in tunnel | |
CN204627622U (en) | The multi-functional construction trolley in a kind of tunnel | |
CN105714829A (en) | Construction device for deep foundation pit excavation and underground station construction and construction method adopting same | |
CN102785243A (en) | Multi-directional regulating mechanical hand | |
CN203959689U (en) | A kind of large-type sinterer depositing dust pipeline is installed and is adjusted with operation car | |
CN103410532A (en) | T-typed step-by-step parallel excavation method of soft-rock tunnel cavern | |
CN103669882A (en) | Method for conducting component installation with steel wire ropes serving as rails in industrial factory building | |
CN205743934U (en) | Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis | |
CN107143293A (en) | A kind of all-hydraulic coal mine down-hole drilling auxiliary machinery | |
CN103967503A (en) | Production-stop-free transformation method for tower type interior shaft elevating system | |
CN104594922A (en) | Tunnel steel arch installation method | |
CN203685233U (en) | Loading device of coal mine fully-mechanized mining equipment | |
CN108018882B (en) | Shallow comprehensive pipe rack engineering integrated construction device | |
CN105863686A (en) | Invert formwork hosting traveling trolley | |
CN103742193B (en) | The mounting method of the soft filter pipe of a kind of underground goaf hydraulic fill | |
CN204941571U (en) | A kind of railway tunnel supporting and protection structure of improvement | |
CN104405425A (en) | Self-moving advanced supporting equipment of heading machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |