CN104590489B - Method for installing rigging guide wheel of floating production storage and offloading device ship above water - Google Patents

Method for installing rigging guide wheel of floating production storage and offloading device ship above water Download PDF

Info

Publication number
CN104590489B
CN104590489B CN201410823382.8A CN201410823382A CN104590489B CN 104590489 B CN104590489 B CN 104590489B CN 201410823382 A CN201410823382 A CN 201410823382A CN 104590489 B CN104590489 B CN 104590489B
Authority
CN
China
Prior art keywords
guide wheel
cable wheel
rigging
led
rigging guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410823382.8A
Other languages
Chinese (zh)
Other versions
CN104590489A (en
Inventor
张平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
COSCO (DALIAN) SHIPYARD Co Ltd
Original Assignee
COSCO (DALIAN) SHIPYARD Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by COSCO (DALIAN) SHIPYARD Co Ltd filed Critical COSCO (DALIAN) SHIPYARD Co Ltd
Priority to CN201410823382.8A priority Critical patent/CN104590489B/en
Publication of CN104590489A publication Critical patent/CN104590489A/en
Application granted granted Critical
Publication of CN104590489B publication Critical patent/CN104590489B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a method for installing a rigging guide wheel of a floating production storage and offloading device ship above water. The method comprises the following steps of A, welding hanging lugs to the appointed position of a chain stopper platform, welding a traction lug to the appointed position of an outer board of the floating production storage and offloading device ship, and placing a pin shaft of the rigging guide wheel below the chain stopper platform through pin shaft rigging by means of a shore tackle; B, conveying the rigging guide wheel to the position aligning to the chain stopper platform by means of the shore tackle in a hanging mode, and connecting the rigging guide wheel to a suspender; C, inversely conveying the rigging guide wheel to the installation position through a chain block of the rigging guide wheel, and regulating the connection of the chain block and the traction lug by means of the rigging guide wheel to regulate the rigging guide wheel to the right position; D, making the pin shaft of the rigging guide wheel penetrate in the rigging guide wheel and toggle plates of a rigging guide device to be fixed through a chain block of the pin shaft to complete the installation. According to the method for installing the rigging guide wheel above water, the rigging guide wheel structure is installed above water, so that dock period cost is reduced greatly. In addition, the method for installing the rigging guide wheel above water is concise in process, low in cost, wide in application range and high in maneuverability and repeatability.

Description

Cable wheel installation method waterborne led by Floating Production Storage easing gear ship
Technical field
The present invention relates to cable wheel installation method waterborne led by a kind of Floating Production Storage easing gear ship.
Background technology
Gradually it is developed with world's deepwater oilfield, international market is for FPSO【Floating Production Storage easing gear】Ship and Other marine engineering product demands are continuously increased, the typically no dynamical system of FPSO ship, and are exactly 30 in fixing marine site military service Year, so it needs the support of powerful mooring system to resist complicated marine situation, different big according to military service water environment Part FPSO all adopts multipoint mooring mode, and leading cable wheel is its very important component, positioned at fore and aft line shape region of variation, distance About 20 meters of baseline, and install highly inconvenient below chain stopper platform, former retrofit process is led cable wheel master is installed To be all and to be installed using truck crane on building berth in depressed place, cannot be mounted directly on the water, in order to shorten building berth and dock Cycle, thus a kind of science, rationally, requisite during installation method design on safe water.
Content of the invention
It is an object of the invention to provide one kind can reduce installation cost, shortens the depressed place phase, improves building berth or dock utilization rate Floating Production Storage easing gear ship lead cable wheel installation method waterborne.
The present invention be employed technical scheme comprise that for achieving the above object:Cable led by a kind of Floating Production Storage easing gear ship Take turns installation method waterborne, comprise the following steps:
A, hanger will be hung(3)It is welded on chain stopper platform(1)Specified location, then hanger will be drawn(9)It is welded on floating Formula produces the outside plate of storage easing gear ship(2)Specified location, then using shore tackle(4)By bearing pin rigging(5)Cable wheel will be led Bearing pin(7)It is placed on the lower position of chain stopper platform, then pass through bearing pin chain block(6)Cable wheel bearing pin will be led(7)Have bad luck to Chock bracket(8)Top;
B, use shore tackle(4)By leading cable wheel rigging(11)Cable wheel will be led(10)It is hoisted to and chain stopper platform(1)Concordantly Position, connects suspender belt(12);
C, using leading cable wheel chain block(13)Cable wheel will be led(10)Have bad luck to installation site, reuse and lead cable wheel adjustment handss Draw calabash(14)With traction hanger(9)Connect, cable wheel will be led(10)It is adjusted in place;
D, use bearing pin chain block(6)Cable wheel bearing pin will be led(7)Penetrate and lead cable wheel(10)With chock bracket(8)Interior solid Fixed, installation.
Described suspension hanger is at least 2.
In described step B, connect suspender belt(12)Afterwards, gradually unclamp shore tackle(4), by shore tackle(4)It is placed on chain stopper platform (1)Underface.
Cable wheel installation method waterborne led by a kind of present invention Floating Production Storage easing gear ship, carries out on the water leading cable rolling hitch Structure is installed, and break traditions mounting technique, greatly saves depressed place current cost, and installation waterborne leads that cable wheel method is simple, concise in technology, material Cost is relatively low, applied range, and operability and repeatability are strong.
Brief description
Fig. 1 be a kind of present invention Floating Production Storage easing gear ship lead cable wheel installation method waterborne lead cable wheel bearing pin lifting Schematic diagram.
Fig. 2 be a kind of present invention Floating Production Storage easing gear ship lead cable wheel installation method waterborne lead cable wheel lifting illustrate Figure.
Fig. 3 be a kind of present invention Floating Production Storage easing gear ship lead cable wheel installation method waterborne lead cable wheel adjustment positioning Figure.
Fig. 4 be a kind of present invention Floating Production Storage easing gear ship lead cable wheel installation method waterborne lead cable wheel bearing pin intert Schematic diagram.
Specific embodiment
As shown in Figures 1 to 4, Floating Production Storage easing gear ship leads cable wheel installation method waterborne, Floating Production Storage Easing gear ship is led cable wheel and is located at bow buttock line shape region of variation, and during installation, Floating Production Storage easing gear ship is in showy shape State, away from about 15 meters of the water surface, concretely comprises the following steps:A, first by least 2 suspension hangers 3 be welded on chain stopper platform 1 specified location, Again traction hanger 9 is welded on Floating Production Storage easing gear outboard plate 2 specified location, then utilizes bearing pin using shore tackle 4 Rigging 5 will be led cable wheel bearing pin 7 and be placed chain stopper platform 1 lower position, recycle bearing pin chain block 6 will lead cable wheel bearing pin 7 and fall It is transported to above chock bracket 8;B, reuse shore tackle 4 and be hoisted to put down with chain stopper using leading cable wheel rigging 11 and will lead cable wheel 10 After platform 1 flush position connects suspender belt 12, gradually unclamp shore tackle 4 and place it in immediately below chain stopper platform 1;C, using leading cable wheel Chain block 13 will be led cable wheel 10 and be had bad luck to installation site, reuse lead cable wheel adjustment chain block 14 with draw hanger 9 be connected Cable wheel 10 will be led be adjusted in place;D, cable wheel bearing pin 7 will be led using bearing pin chain block 6 penetrate and lead cable wheel 10 and chock bracket 8 Interior fixation is dead, installation, and cable wheel installation method waterborne led by Floating Production Storage easing gear ship of the present invention, is led on the water Cable wheel construction is installed, and break traditions mounting technique, greatly saves depressed place current cost, and installation waterborne leads that cable wheel method is simple, technique is simple Clean, material cost is relatively low, applied range, and operability and repeatability are strong.

Claims (3)

1. a kind of Floating Production Storage easing gear ship leads cable wheel installation method waterborne it is characterised in that comprising the following steps:
A, hanger will be hung(3)It is welded on chain stopper platform(1)Specified location, then hanger will be drawn(9)It is welded on floating life Produce the outside plate of storage easing gear ship(2)Specified location, then using shore tackle(4)By bearing pin rigging(5)Cable wheel bearing pin will be led (7)It is placed on the lower position of chain stopper platform, then pass through bearing pin chain block(6)Cable wheel bearing pin will be led(7)Have bad luck to leading cable Device bracket(8)Top;
B, use shore tackle(4)By leading cable wheel rigging(11)Cable wheel will be led(10)It is hoisted to and chain stopper platform(1)Flush position, Connect suspender belt(12);
C, using leading cable wheel chain block(13)Cable wheel will be led(10)Have bad luck to installation site, then make to lead cable wheel adjustment chain block (14)With traction hanger(9)Connect, cable wheel will be led(10)It is adjusted in place;
D, use bearing pin chain block(6)Cable wheel bearing pin will be led(7)Penetrate and lead cable wheel(10)With chock bracket(8)Interior fixation, Installation.
2. a kind of Floating Production Storage easing gear ship according to claim 1 leads cable wheel installation method waterborne, its feature It is:Described suspension hanger is at least 2.
3. a kind of Floating Production Storage easing gear ship according to claim 1 leads cable wheel installation method waterborne, its feature It is:In described step B, connect suspender belt(12)Afterwards, gradually unclamp shore tackle(4), by shore tackle(4)It is placed on chain stopper platform(1) Underface.
CN201410823382.8A 2014-12-26 2014-12-26 Method for installing rigging guide wheel of floating production storage and offloading device ship above water Expired - Fee Related CN104590489B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410823382.8A CN104590489B (en) 2014-12-26 2014-12-26 Method for installing rigging guide wheel of floating production storage and offloading device ship above water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410823382.8A CN104590489B (en) 2014-12-26 2014-12-26 Method for installing rigging guide wheel of floating production storage and offloading device ship above water

Publications (2)

Publication Number Publication Date
CN104590489A CN104590489A (en) 2015-05-06
CN104590489B true CN104590489B (en) 2017-02-22

Family

ID=53116638

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410823382.8A Expired - Fee Related CN104590489B (en) 2014-12-26 2014-12-26 Method for installing rigging guide wheel of floating production storage and offloading device ship above water

Country Status (1)

Country Link
CN (1) CN104590489B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112623151B (en) * 2020-12-23 2022-12-06 大连中远海运重工有限公司 Method for removing rudder blade of floating production, storage and unloading device on water

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2341099A (en) * 1998-01-26 1999-08-09 Continental Emsco Company Removable underwater fairlead and method
US6651580B2 (en) * 2002-02-22 2003-11-25 Globalsantafe Corporation Method and system for mooring
US7104214B2 (en) * 2003-10-03 2006-09-12 Hydralift Amclyde, Inc. Fairlead with integrated chain stopper
CN102114897B (en) * 2011-01-05 2013-12-04 大连中远船务工程有限公司 Method for installing large fair-lead structure on water
FR2984272B1 (en) * 2011-12-14 2014-06-13 Nov Blm CHAUMARD FOR GUIDING AN ANCHORING CHAIN FOR EQUIPPING AN ANCHORING SYSTEM ON THE GROUND OF A FLOATING PLATFORM

Also Published As

Publication number Publication date
CN104590489A (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN101492140B (en) Aluminum alloy catamaran whole-boat afloat process
CN104527940B (en) Ocean platform block offshore double-boat integral migration method
CN103883273A (en) Method for utilizing two cranes on saturation diving support vessel to mount vertical pipe
CN104540767A (en) Method for lowering and hoisting of a load to or from an ocean floor
CN104590489B (en) Method for installing rigging guide wheel of floating production storage and offloading device ship above water
CN102235548B (en) Installation device for deepwater stand pipes and underwater facilities
CN103373446A (en) Jacket removing ship and removing method
CN105109617B (en) A kind of Ship Structure for the large-scale A cabinet frames of reassembling type
CN100458362C (en) Quick distributing apparatus for underwater sensor chain
CN102213085A (en) Installation method of vertical pipe of guide pipe rack
CN103552655B (en) A kind of 400 tons of lifting pipe laying vessel stinger installation methods waterborne
CN208747498U (en) A kind of anti-tilting apparatus of ship's crane
CN102674138A (en) Marine screw shaft hoisting tool
CN206243392U (en) A kind of lifeboat lowering or hoisting gear
CN106564819B (en) A kind of heavy loop wheel machine peculiar to vessel and underwater mounting process
CN105644713B (en) Propeller mounting process method
CN102050377B (en) Method for installing combined hoist and oil production platform drilling equipment
CN104802925B (en) The method for dismounting of ocean platform propeller
CN113551081A (en) Kilometer water depth float type PLET broadside installation method
CN103754328B (en) A kind of method of underwater sensor chain Quick distributor
CN202557747U (en) Dismounting ship for jacket
KR101429551B1 (en) Installation module of trolley hoist for vessel or marine structure and the operating method of it
CN106628007A (en) Lifeboat lowering device
CN102114897B (en) Method for installing large fair-lead structure on water
CN206374919U (en) One kind rolling dress ramp is installed by overlap joint frock

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170222

Termination date: 20171226

CF01 Termination of patent right due to non-payment of annual fee