CN104569503A - Lightning arrester experiment rack for substation - Google Patents
Lightning arrester experiment rack for substation Download PDFInfo
- Publication number
- CN104569503A CN104569503A CN201310479468.9A CN201310479468A CN104569503A CN 104569503 A CN104569503 A CN 104569503A CN 201310479468 A CN201310479468 A CN 201310479468A CN 104569503 A CN104569503 A CN 104569503A
- Authority
- CN
- China
- Prior art keywords
- support
- hole
- lightning arrester
- base
- supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000002474 experimental method Methods 0.000 title abstract description 12
- 230000007246 mechanism Effects 0.000 claims abstract description 14
- 229910001220 stainless steel Inorganic materials 0.000 claims description 3
- 239000010935 stainless steel Substances 0.000 claims description 3
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 230000003449 preventive effect Effects 0.000 description 2
- 230000035939 shock Effects 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Landscapes
- Testing Electric Properties And Detecting Electric Faults (AREA)
Abstract
Description
【技术领域】【Technical field】
本发明涉及一种实验架,具体涉及一种便携式变电站用避雷器实验架。 The invention relates to an experiment frame, in particular to a portable substation lightning arrester experiment frame.
【背景技术】【Background technique】
公知的,避雷器是变电站被保护设备免遭雷电冲击波袭击的设备,当沿线路传入变电站的雷电冲击波超过避雷器保护水平时,避雷器首先利用接地线放电,由接地线将高电压冲击电流安全的引入大地,利用接地装置使雷电压幅值限制在被保护设备雷电冲击水平以下,使电气设备受到保护,避雷器在施加高压电压时,避雷器不可避免地要产生泄流电流,如果避雷器存在故障或缺陷,不仅起不到保护作用,还会影响其它设备的运行,因此要对避雷器的性能进行考核,以此来衡量避雷器的质量是否合格,因为使用场所不同,避雷器的大小,粗细也不同,操作人员通常会就地取材,利用人字梯或者凳子作为支撑物来解决避雷器的安放问题,不但费时,而且会因为支撑物的不稳造成实验过程中避雷器倒落导致设备或实验仪器的损坏,目前市场上销售的变电站用避雷器实验架价格都比较昂贵,外观也较大,不方便在预防性试验的时候携带。 As we all know, the lightning arrester is a device that protects the equipment in the substation from the lightning shock wave attack. When the lightning shock wave transmitted to the substation along the line exceeds the protection level of the lightning arrester, the lightning arrester first uses the grounding wire to discharge, and the grounding wire will safely introduce high-voltage surge current. Earth, use the grounding device to limit the amplitude of the lightning voltage below the lightning impact level of the protected equipment, so that the electrical equipment is protected. When the arrester is applied with high voltage, the arrester will inevitably generate a leakage current. If the arrester has a fault or defect, Not only does it fail to protect, but it also affects the operation of other equipment. Therefore, it is necessary to evaluate the performance of the arrester to measure whether the quality of the arrester is qualified. Because the size and thickness of the arrester are different in different places of use, operators usually It will take local materials and use ladders or stools as supports to solve the placement problem of arresters. The test racks for substation surge arresters sold are relatively expensive and have a large appearance, which is inconvenient to carry during preventive tests.
【发明内容】【Content of invention】
为克服背景技术中存在的不足,本发明提供了一种变电站用避雷器实验架,利用横梁一侧面上的穿孔内设置的钩子悬挂避雷器,使避雷器在实验过程中避免了避雷器倒落导致设备或实验仪器的损坏,本发明易拆卸、携带方便,且成本较低。 In order to overcome the deficiencies in the background technology, the present invention provides a test rack for lightning arresters in substations. The lightning arresters are suspended by using the hooks provided in the perforations on one side of the beam, so that the lightning arresters can be avoided during the experiment. In case of damage to the instrument, the invention is easy to disassemble, convenient to carry, and has low cost.
为实现如上所述的发明目的,本发明采用如下所述的技术方案: In order to realize the above-mentioned purpose of the invention, the present invention adopts the following technical solutions:
一种变电站用避雷器实验架,包括底部支撑机构、横支撑和钩子,所述横支撑的两端下部分别设有底部支撑机构,复数个钩子间隔设置在横支撑的一侧面上。 A lightning arrester test frame for a substation, comprising a bottom support mechanism, a horizontal support and hooks, the bottom support mechanisms are respectively provided at the lower parts of the two ends of the horizontal support, and a plurality of hooks are arranged at intervals on one side of the horizontal support.
所述的变电站用避雷器实验架,横支撑两端下部分别设置的底部支撑机构为相同结构,其中任一底部支撑机构包括支撑杆和折叠底座,所述支撑杆的下部设置在折叠底座内。 In the lightning arrester test frame for substations, the bottom supporting mechanisms provided at the lower parts of the two ends of the horizontal support are of the same structure, wherein any bottom supporting mechanism includes a supporting rod and a folding base, and the lower part of the supporting rod is arranged in the folding base.
所述的变电站用避雷器实验架,所述支撑杆包括上支杆和下支杆,所述上支杆的上端设有豁口,上支杆的下端设有缩颈的插接端,在缩颈的插接端外部面分别设有相互对应的通孔A,所述下支杆的上端设有与插接端插接的插合孔,在下支杆的上部外面分别设有相互对应的通孔B,所述上支杆与下支杆插接连接,螺钉A穿过相互对应的通孔A和通孔B由螺帽锁紧。 In the lightning arrester test frame for a substation, the support rod includes an upper support rod and a lower support rod, the upper end of the upper support rod is provided with a gap, and the lower end of the upper support rod is provided with a constricted plug-in end. The outer surface of the plug-in end of the socket is respectively provided with corresponding through holes A, the upper end of the lower support rod is provided with a plug-in hole for insertion with the plug-in end, and the outer surface of the upper part of the lower support rod is respectively provided with corresponding through-holes B, the upper pole and the lower pole are plugged and connected, the screw A passes through the through hole A and the through hole B corresponding to each other and is locked by the nut.
所述的变电站用避雷器实验架,所述折叠底座包括支撑底座、上支撑杆和下支撑杆,所述支撑底座为两个相同结构,任意一个支撑底座包括支撑盘和凸起块,所述支撑盘的外部等角度设置三个“∏”型凸起块,在 “∏”型凸起块的两个相对面上设有相互对应的穿孔A,所述下支杆的下端固定在任意一个支撑底座中部的内孔A内,另一个支撑底座与下支杆的中部间隙配合,由支撑底座外部面上设置的定位螺栓与下支杆定位,设置在下支杆下端的支撑底座与上支撑杆连接,设置在下支杆中部的支撑底座与下支撑杆连接。 In the lightning arrester test frame for substation, the folding base includes a support base, an upper support rod and a lower support rod, and the support bases are two identical structures, any one of the support bases includes a support plate and a raised block, and the support base Three "∏"-shaped raised blocks are arranged at equal angles on the outside of the disk, and corresponding perforations A are provided on the two opposite surfaces of the "∏"-shaped raised blocks. The lower end of the lower support rod is fixed on any support In the inner hole A in the middle of the base, another support base is matched with the middle part of the lower support rod, and the positioning bolts arranged on the outer surface of the support base are positioned with the lower support rod, and the support base arranged at the lower end of the lower support rod is connected with the upper support rod , the support base arranged in the middle of the lower support rod is connected with the lower support rod.
所述的变电站用避雷器实验架,所述上支撑为三根相同结构,任意一根上支撑包括支撑杆A和连接球头A,所述支撑杆A的上端设有连接球头A,所述连接球头A铰接连接在“∏”型凸起块的内部,螺钉B穿过穿孔A和连接球头A两侧中部贯通的内孔B后由螺母锁紧,在支撑杆A的中部设有相互对应的穿孔B,在两个穿孔B之间设有孔。 In the lightning arrester test frame for substations, the upper support has three identical structures, any upper support includes a support rod A and a connecting ball A, the upper end of the supporting rod A is provided with a connecting ball A, and the connecting ball The head A is hingedly connected to the inside of the "Π"-shaped raised block, and the screw B passes through the perforation A and the inner hole B that connects the middle of both sides of the ball head A, and then is locked by a nut. The perforation B is provided with a hole between two perforations B.
所述的变电站用避雷器实验架,所述下支撑为三根相同结构,任意一根下支撑包括支撑杆B和连接球头B,所述下支撑的上端设有连接球头B,所述连接球头B铰接连接在“∏”型凸起块的内部,螺钉B穿过穿孔A和连接球头B两侧中部贯通的内孔B后由螺母锁紧,支撑杆B的下端设置在支撑杆A中部的孔内,螺钉C穿过穿孔B和穿孔C后由螺帽锁紧。 In the lightning arrester test frame for a substation, the lower supports have three identical structures, any one of the lower supports includes a support rod B and a connecting ball B, the upper end of the lower support is provided with a connecting ball B, and the connecting ball The head B is hingedly connected to the inside of the "Π"-shaped raised block, the screw B passes through the perforation A and the inner hole B that connects the middle of both sides of the ball head B, and then is locked by a nut, and the lower end of the support rod B is set on the support rod A In the middle hole, the screw C is locked by the nut after passing through the hole B and the hole C.
所述的变电站用避雷器实验架,所述横支撑包括横梁、挂钩、挡片和向下延伸,在横梁的两端上部设有挡片,在挡片的下部设有向下延伸,所述挡片和向下延伸形成“7”型结构,在横梁的一侧面上间隔设有至少个挂钩孔,在挂钩孔设有挂钩,所述横梁的两端分别设置在两根上支杆的豁口内,向下延伸设置在上支杆上端外部。 In the lightning arrester test frame for substation, the horizontal support includes a crossbeam, a hook, a baffle and a downward extension, a baffle is provided at the upper part of both ends of the beam, and a downward extension is provided at the lower part of the baffle, and the baffle The sheet and extend downwards to form a "7"-shaped structure. At least one hook hole is arranged at intervals on one side of the beam, and a hook is provided in the hook hole. The two ends of the beam are respectively arranged in the gaps of the two upper poles. The downward extension is arranged outside the upper end of the upper support rod.
所述的变电站用避雷器实验架,所述上支杆和下支杆为空心不锈钢钢管。 In the lightning arrester test frame for a substation, the upper support rod and the lower support rod are hollow stainless steel pipes.
采用如上所述的技术方案,本发明具有如下所述的优越性: Adopt the above-mentioned technical scheme, the present invention has the following advantages:
本发明所述的变电站用避雷器实验架,通过将避雷器悬挂在横梁1一侧面上的穿孔6内设置的钩子5上,便可检测避雷器的质量是否合格,本发明操作简单、易携带且制作成本较低,不但解决了实验时对避雷器的安放问题,也为操作人员大大节省了实验时间。 The lightning arrester test rack for substations of the present invention can detect whether the quality of the lightning arrester is qualified by hanging the lightning arrester on the hook 5 provided in the perforation 6 on one side of the beam 1. The present invention is simple in operation, easy to carry and low in production cost It not only solves the problem of placing the arrester during the experiment, but also greatly saves the experiment time for the operator.
【附图说明】【Description of drawings】
图1是本发明结构示意图; Fig. 1 is a structural representation of the present invention;
图2是本发明横梁1的结构示意图; Fig. 2 is the structural representation of beam 1 of the present invention;
图3是本发明上支杆6的结构示意图; Fig. 3 is a schematic structural view of the upper strut 6 of the present invention;
图4是本发明下支杆9的结构示意图; Fig. 4 is a schematic structural view of the lower strut 9 of the present invention;
图5是本发明支撑底座的结构示意图; Fig. 5 is a schematic structural view of the support base of the present invention;
图6是本发明上支撑的结构示意图; Fig. 6 is a schematic structural view of the upper support of the present invention;
图7是本发明下支撑的结构示意图。 Fig. 7 is a schematic structural view of the lower support of the present invention.
在图中:1、横梁;2、挂钩孔;3、挂钩;4、挡片;5、向下延伸;6、上支杆;7、插接端;8、螺钉A;9、下支杆;10、凸起块;11、螺钉B;12、支撑盘;13、连接球头A;14、支撑杆A;15、支撑杆B;16、豁口;17、通孔A;18、插合孔;19、通孔B;20、内孔A;21、穿孔A;22、螺母;23、孔;24、穿孔B;25、内孔B;26、连接球头B;27、穿孔C;28、内孔C;29、定位螺栓;30、螺钉。 In the figure: 1. Beam; 2. Hook hole; 3. Hook; 4. Block; 5. Extend downward; 6. Upper pole; 7. Plug-in end; 8. Screw A; 9. Lower pole ;10, protruding block; 11, screw B; 12, support plate; 13, connecting ball head A; 14, support rod A; 15, support rod B; 16, gap; 17, through hole A; 18, insert Hole; 19, through hole B; 20, inner hole A; 21, through hole A; 22, nut; 23, hole; 24, through hole B; 25, inner hole B; 26, connecting ball B; 27, through hole C; 28. Inner hole C; 29. Positioning bolts; 30. Screws.
【具体实施方式】【Detailed ways】
通过下面的实施例可以更详细的解释本发明,本发明并不局限于下面的实施例; The present invention can be explained in more detail by the following examples, and the present invention is not limited to the following examples;
结合附图1或2或3所述的变电站用避雷器实验架,包括底部支撑机构、横支撑和钩子5,所述横支撑的两端下部分别设有底部支撑机构,横支撑两端下部分别设置的底部支撑机构为相同结构,其中任一底部支撑机构包括支撑杆和折叠底座,所述支撑杆的下部设置在折叠底座内;所述支撑杆包括上支杆6和下支杆9,所述上支杆6的上端设有豁口16,上支杆6的下端设有缩颈的插接端7,在缩颈的插接端7外部面分别设有相互对应的通孔A17,所述下支杆9的上端设有与插接端7插接的插合孔18,在下支杆9的上部外面分别设有相互对应的通孔B19,所述上支杆6与下支杆9插接连接,螺钉A8穿过相互对应的通孔A17和通孔B19由螺帽锁紧;所述折叠底座包括支撑底座、上支撑杆和下支撑杆,所述支撑底座为两个相同结构,任意一个支撑底座包括支撑盘12和凸起块10,所述支撑盘12的外部等角度设置三个“∏”型凸起块10,在 “∏”型凸起块10的两个相对面上设有相互对应的穿孔A21,所述下支杆9的下端固定在任意一个支撑底座中部的内孔A20内,另一个支撑底座与下支杆9的中部间隙配合,由支撑底座外部面上设置的定位螺栓29与下支杆9定位,设置在下支杆9下端的支撑底座与上支撑杆连接,设置在下支杆9中部的支撑底座与下支撑杆连接;所述上支撑为三根相同结构,任意一根上支撑包括支撑杆A14和连接球头A13,所述支撑杆A14的上端设有连接球头A13,所述连接球头A13铰接连接在“∏”型凸起块10的内部,螺钉B11穿过穿孔A21和连接球头A13两侧中部贯通的内孔B25后由螺母22锁紧,在支撑杆A14的中部设有相互对应的穿孔B24,在两个穿孔B24之间设有孔23,所述下支撑为三根相同结构,任意一根下支撑包括支撑杆B15和连接球头B26,所述下支撑的上端设有连接球头B26,所述连接球头B26铰接连接在“∏”型凸起块10的内部,螺钉B11穿过穿孔A21和连接球头B26两侧中部贯通的内孔B28后由螺母22锁紧,支撑杆B15的下端设置在支撑杆A14中部的孔23内,螺钉C30穿过穿孔B24和穿孔C27后由螺帽锁紧;所述上支杆6和下支杆9为空心不锈钢钢管;复数个钩子5间隔设置在横支撑的一侧面上,所述横支撑包括横梁1、挂钩3、挡片4和向下延伸5,在横梁1的两端上部设有挡片4,在挡片4的下部设有向下延伸5,所述挡片4和向下延伸5形成“7”型结构,在横梁1的一侧面上间隔设有至少3个挂钩孔2,在挂钩孔2设有挂钩3,所述横梁1的两端分别设置在两根上支杆6的豁口16内,向下延伸5设置在上支杆6上端外部。 The lightning arrester test frame for substation described in conjunction with accompanying drawings 1 or 2 or 3 includes a bottom support mechanism, a horizontal support and a hook 5, the lower parts of the two ends of the horizontal support are respectively provided with a bottom support mechanism, and the lower parts of the two ends of the horizontal support are respectively provided with The bottom support mechanism of the above is the same structure, wherein any bottom support mechanism includes a support rod and a folding base, and the bottom of the support rod is arranged in the folding base; the support rod includes an upper pole 6 and a lower pole 9, and the The upper end of the upper strut 6 is provided with a gap 16, and the lower end of the upper strut 6 is provided with a constricted plug-in end 7, and the outer surfaces of the constricted plug-in end 7 are respectively provided with mutually corresponding through holes A17. The upper end of the support rod 9 is provided with an insertion hole 18 for plugging in with the plug-in end 7, and there are respectively provided through holes B19 corresponding to each other outside the upper part of the lower support rod 9, and the upper support rod 6 is plugged with the lower support rod 9. connection, the screw A8 passes through the through hole A17 and the through hole B19 corresponding to each other and is locked by the nut; the folding base includes a support base, an upper support rod and a lower support rod, and the support base is two identical structures, any one The support base includes a support plate 12 and a raised block 10. Three “∏” shaped raised blocks 10 are arranged at an equal angle on the outside of the supported plate 12, and two opposite surfaces of the “∏” shaped raised block 10 are provided Corresponding perforations A21, the lower end of the lower support rod 9 is fixed in the inner hole A20 in the middle of any one support base, and the other support base cooperates with the middle part of the lower support rod 9 in clearance, and the positioning provided on the outer surface of the support base The bolt 29 is positioned with the lower pole 9, the supporting base arranged at the lower end of the lower pole 9 is connected with the upper supporting pole, and the supporting base arranged at the middle part of the lower pole 9 is connected with the lower supporting pole; the upper support is three identical structures, any one The support on the root includes a support rod A14 and a connecting ball A13. The upper end of the supporting rod A14 is provided with a connecting ball A13. The connecting ball A13 is hingedly connected to the inside of the "Π"-shaped raised block 10, and the screw B11 passes through The perforated hole A21 and the inner hole B25 connecting the middle parts of both sides of the ball head A13 are locked by the nut 22, and the middle part of the support rod A14 is provided with a corresponding perforated hole B24, and a hole 23 is provided between the two perforated holes B24. The lower support has three identical structures. Any one of the lower supports includes a support rod B15 and a connecting ball B26. The upper end of the lower support is provided with a connecting ball B26. Inside the block 10, the screw B11 passes through the hole A21 and the inner hole B28 through the middle of the two sides of the connecting ball head B26 and is locked by the nut 22. The lower end of the support rod B15 is set in the hole 23 in the middle of the support rod A14, and the screw C30 passes through After passing through the hole B24 and the hole C27, it is locked by a nut; the upper support rod 6 and the lower support rod 9 are hollow stainless steel pipes; a plurality of hooks 5 are arranged at intervals on one side of the horizontal support, and the horizontal support includes a crossbeam 1 , a hook 3, a catch 4 and a downward extension 5, a catch 4 is provided at the upper part of both ends of the beam 1, and a downward extension 5 is provided at the bottom of the catch 4, and the catch 4 and the downward extension 5 form "7" type structure, on one side of beam 1, there are at least 3 A hook hole 2 is provided with a hook 3 in the hook hole 2. The two ends of the crossbeam 1 are respectively arranged in the gap 16 of the two upper poles 6, and the downward extension 5 is arranged on the outside of the upper pole 6 upper ends.
实施本发明所述的变电站用避雷器实验架,在使用时,先将上支杆6和下支杆9通过螺钉A8对接起来,把下支杆9的下端固定在其中一个支撑底座的内孔A20中,另一个支撑底座设置在下支杆9的中部,由定位螺栓29定位,所述螺钉B11的中部为光杆,将支撑杆A14的连接球头A13通过螺钉B11与设置在下支杆9中部的支撑底座铰接连接,将支撑杆B15的连接球头B26通过螺钉B11与设置在下支杆9下端的支撑底座铰接连接,支撑杆B15的下端通过螺钉C30与支撑杆A14的中部连接,由两个支撑底座、上支撑和下支撑形成了折叠底座,将避雷器悬挂在横梁1一侧面的穿孔6内设置的钩子5上,在避雷器试验架上挂接地线和对避雷器连接兆欧表,便可检测避雷器的质量是否合格,在不使用时,可拆卸折叠底座和支撑杆,拆卸完后的各个部件都比较短,可随手放进操作工人的工具包内,以便在预防性试验的时候携带;本发明操作简单、易携带且制作成本较低,不但解决了实验时对避雷器的安放问题,也为操作人员大大节省了实验时间。 To implement the lightning arrester test frame for substations of the present invention, when in use, the upper strut 6 and the lower strut 9 are butted together by the screw A8, and the lower end of the lower strut 9 is fixed in the inner hole A20 of one of the support bases. Among them, the other support base is arranged in the middle part of the lower pole 9, and is positioned by the positioning bolt 29. The middle part of the screw B11 is a polished rod. The base is hingedly connected, the connecting ball head B26 of the support rod B15 is hingedly connected with the support base provided at the lower end of the lower support rod 9 through the screw B11, the lower end of the support rod B15 is connected with the middle part of the support rod A14 through the screw C30, and two support bases , The upper support and the lower support form a folding base, hang the arrester on the hook 5 set in the perforation 6 on one side of the beam 1, hang the ground wire on the arrester test frame and connect the megger to the arrester, and then the arrester can be detected Whether the quality is qualified, when not in use, the foldable base and the support rod can be disassembled, and each part after disassembly is relatively short, and can be put into the operator's tool bag at hand, so that it can be carried during the preventive test; the operation of the present invention Simple, easy to carry and low production cost, it not only solves the problem of placing the arrester during the experiment, but also greatly saves the experiment time for the operator.
本发明未详述部分为现有技术。 The unspecified parts of the present invention are prior art.
为了公开本发明的发明目的而在本文中选用的实施例,当前认为是适宜的,但是,应了解的是,本发明旨在包括一切属于本构思和发明范围内的实施例的所有变化和改进。 The embodiments selected herein for the purpose of disclosing the invention of the present invention are considered suitable at present, but it should be understood that the present invention is intended to include all changes and improvements of the embodiments belonging to the concept and scope of the invention .
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310479468.9A CN104569503A (en) | 2013-10-15 | 2013-10-15 | Lightning arrester experiment rack for substation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310479468.9A CN104569503A (en) | 2013-10-15 | 2013-10-15 | Lightning arrester experiment rack for substation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104569503A true CN104569503A (en) | 2015-04-29 |
Family
ID=53086048
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310479468.9A Pending CN104569503A (en) | 2013-10-15 | 2013-10-15 | Lightning arrester experiment rack for substation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104569503A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106526251A (en) * | 2016-12-09 | 2017-03-22 | 国网浙江省电力公司丽水供电公司 | 10 kV lightning arrester test support |
CN107785880A (en) * | 2017-11-30 | 2018-03-09 | 国网河南省电力公司南阳供电公司 | Intelligent arrester |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2324226Y (en) * | 1998-04-08 | 1999-06-16 | 于爽英 | Foldable V-bracing frame |
CN201092742Y (en) * | 2007-09-03 | 2008-07-30 | 刘立民 | Folding type trigone bracing frame |
CN201522505U (en) * | 2009-09-28 | 2010-07-07 | 石家庄供电公司 | A high-voltage test lead wire connection tool for electric equipment |
CN202330473U (en) * | 2011-11-18 | 2012-07-11 | 安徽省电力公司滁州供电公司 | Bracket special for universal meter |
CN202548160U (en) * | 2012-04-12 | 2012-11-21 | 湖北省电力公司襄阳供电公司 | Test rack of lightning arrester |
CN203054017U (en) * | 2013-02-20 | 2013-07-10 | 广州南方电力集团技术有限公司 | Insulating support frame for improving high-voltage lead arrangement in alternating current voltage withstanding test |
CN103323629A (en) * | 2013-06-06 | 2013-09-25 | 国家电网公司 | Test support for lightning arrester test |
CN203572842U (en) * | 2013-10-15 | 2014-04-30 | 国家电网公司 | Lightning arrester experiment rack for transformer substation |
-
2013
- 2013-10-15 CN CN201310479468.9A patent/CN104569503A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2324226Y (en) * | 1998-04-08 | 1999-06-16 | 于爽英 | Foldable V-bracing frame |
CN201092742Y (en) * | 2007-09-03 | 2008-07-30 | 刘立民 | Folding type trigone bracing frame |
CN201522505U (en) * | 2009-09-28 | 2010-07-07 | 石家庄供电公司 | A high-voltage test lead wire connection tool for electric equipment |
CN202330473U (en) * | 2011-11-18 | 2012-07-11 | 安徽省电力公司滁州供电公司 | Bracket special for universal meter |
CN202548160U (en) * | 2012-04-12 | 2012-11-21 | 湖北省电力公司襄阳供电公司 | Test rack of lightning arrester |
CN203054017U (en) * | 2013-02-20 | 2013-07-10 | 广州南方电力集团技术有限公司 | Insulating support frame for improving high-voltage lead arrangement in alternating current voltage withstanding test |
CN103323629A (en) * | 2013-06-06 | 2013-09-25 | 国家电网公司 | Test support for lightning arrester test |
CN203572842U (en) * | 2013-10-15 | 2014-04-30 | 国家电网公司 | Lightning arrester experiment rack for transformer substation |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106526251A (en) * | 2016-12-09 | 2017-03-22 | 国网浙江省电力公司丽水供电公司 | 10 kV lightning arrester test support |
CN107785880A (en) * | 2017-11-30 | 2018-03-09 | 国网河南省电力公司南阳供电公司 | Intelligent arrester |
CN107785880B (en) * | 2017-11-30 | 2019-04-19 | 国网河南省电力公司南阳供电公司 | Smart arrester |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108169519B (en) | Arrester testing support | |
CN203572842U (en) | Lightning arrester experiment rack for transformer substation | |
CN103560004B (en) | The special discharging rod of capacitor | |
CN203705486U (en) | 500kV zinc-oxide lightning-arrester dc tester | |
CN103383400B (en) | A kind of insulation safety device preventability test device | |
CN204595023U (en) | A kind of 10kV arrester testing support | |
CN204028135U (en) | The reassembling type verifying attachment of small-sized lightning arrester | |
CN104569503A (en) | Lightning arrester experiment rack for substation | |
CN203941195U (en) | A kind of 10kV test of lightning arrester base | |
CN204189992U (en) | Special leading wire for test of lightning arrester of power transmission cable pole tower bracing frame | |
CN204855569U (en) | Support of experimental arrester | |
CN103323629A (en) | Test support for lightning arrester test | |
CN212433388U (en) | Portable multi-function calibrator operating platform | |
CN205786702U (en) | A kind of high-voltage insulating rod testboard bay | |
CN204595032U (en) | A kind of high-potting line insulating carriage | |
CN104237571A (en) | Supporting device of voltage applying line for lightning arrester test | |
CN201724954U (en) | Rack dedicated for lightning arrester experiments | |
CN117471133A (en) | A high-voltage arrester electrical test auxiliary device | |
CN203798834U (en) | Lightning arrester calibration and test bracket | |
CN105301300B (en) | A kind of 10kV zinc oxide arrester tests fixture | |
CN203981710U (en) | A kind of Assisted Combinatorial device that is applicable to megger method test power distribution network stake resistance | |
CN205229395U (en) | A pressure resistance test installation for insulator spindle or earth bar | |
CN204155751U (en) | High-power transformer sleeve pipe installation and repairing frock | |
CN204142869U (en) | Portable test of lightning arrester platform | |
CN202956405U (en) | A kind of lightning arrester test seat |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150429 |
|
RJ01 | Rejection of invention patent application after publication |