CN104563524B - Anti-water-seepage prefabricated slab construction method - Google Patents
Anti-water-seepage prefabricated slab construction method Download PDFInfo
- Publication number
- CN104563524B CN104563524B CN201410722999.0A CN201410722999A CN104563524B CN 104563524 B CN104563524 B CN 104563524B CN 201410722999 A CN201410722999 A CN 201410722999A CN 104563524 B CN104563524 B CN 104563524B
- Authority
- CN
- China
- Prior art keywords
- load
- plate
- precoated plate
- water
- impervious
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Revetment (AREA)
Abstract
The invention discloses an anti-water-seepage prefabricated slab construction method. The method comprises a prefabricated frame formed by enclosing prefabricated beams, and a prefabricated slab overlapped in the prefabricated frame, wherein a detachable loading mechanism for loading downwardly from the upper surface of the prefabricated slab is arranged on the middle part of the prefabricated slab; the fixing end of the loading mechanism is fixedly connected to the prefabricated beams; the load output end of the loading mechanism is pressed against the upper surface of the prefabricated slab; load is applied through the loading mechanism in order that the middle part of the prefabricated slab is deformed downwardly, and the circumference of the corresponding prefabricated slab is deformed towards the middle part of the prefabricated slab, so that pouring gaps are formed between the circumference of the prefabricated slab and corresponding prefabricated beams; micro-expansion concrete is poured into the pouring gaps, and the loading mechanism is removed after the cured micro-expansion concrete reaches certain strength, so that end cracking of the prefabricated slab is avoided.
Description
Technical field
The present invention relates to precoated plate construction technology field, be specifically related to a kind of precoated plate preventing plate end from seeping water
Construction method.
Background technology
The beam column component of conventional steel bar concrete framework house building is often after the formwork of building site
Casting concrete, its component connects reliable, globality and anti-seismic performance is good, but construction period is longer,
Complex management.And framework house building uses prefabrication and assembly construction mode to represent a kind of advanced developing direction.
Fabricated construction is because of the more feature of its piece, except stress problem to be solved, more to solve to use
In waterproof problem.Present waterproof type mainly has structural waterproof, and two kinds of forms of material waterproofing,
Material waterproofing substantially uses high molecular water-proof paint and coiled material to carry out.But due to working load, building base
Plinth sedimentation and deformation iso-stress effect, concrete and not ideal enough, the local ageing of waterproof material adhesive property etc.
Factor, plate end edge joint position once ftractures and occurs seepage reparation by cumbersome, and seepage usually becomes assembled
The common fault of building.
Based on this, it is necessary to research and develop a kind of novel precoated plate form of construction work, it is possible to prevent and reduce plate end
Crack produces, it is achieved structurally waterproof.
Summary of the invention
In order to make up the shortcoming that pre existing making sheet end easily seeps water, patent of the present invention provides a kind of water-impervious
Precoated plate construction method, utilizes precoated plate self-deformation at plate end Shi Hanzhang, thus reduces plate end check
Seam prevents building from seeping water, and theory clearly more has practical value.
In order to realize above-mentioned technical purpose, the technical scheme of patent of the present invention is, a kind of water-impervious prefabricated
Board construction method, the prefabricated frame enclosing formation including precast beam and the precoated plate being overlapped in prefabricated frame,
It is provided with at the middle part of precoated plate for loading downwards load and dismountable load from the upper surface of precoated plate
Load maintainer, the fixing end of load load maintainer is fixed on precast beam, and the load of load load maintainer is defeated
Go out to hold contact at the upper surface of precoated plate;It is further applied load by load load maintainer and forces the middle part of precoated plate
Deformation downwards, deforms in the middle part of four circumference precoated plates of corresponding precoated plate so that the surrounding of precoated plate and phase
Cast gap is formed between the precast beam answered;By pouring into a mould slightly expanded concrete in cast gap, until
After reaching intensity after slightly expanded concrete maintenance, remove load load maintainer, thus complete to avoid precoated plate
The water-impervious precoated plate construction method of end cracking.
Preferably, load load maintainer includes the jack for being further applied load, is fixed in jack output
The roller bearing load plate of end and fix end and the connection iron chains of precast beam, roller bearing for connecting jack respectively
Load plate equilibrium is laid on the middle part upper surface of precoated plate.
Preferably, roller bearing load plate includes loading plate body, installing the roller bearing loaded bottom plate body and enclose
In roller bearing surrounding for limiting the spacing steel plate of roller bearing displacement.
Preferably, the bottom loading plate body is provided with four groups of roller bearings, and four groups of roller bearings are respectively parallel to load plate
Four edges of boards of body are laid, and destroy precoated plate with the concentration power avoiding jack to apply.
Preferably, the fixing end of jack is provided with jack top board, the company of being formed around of jack top board
T-Ring, the first end connecting iron chains is fixed on connection ring by crotch, connects and goes back between iron chains and crotch
It is provided with for regulating the cable wire calabash connecting iron chains length;It is embedded with screw shell on precast beam, connects ferrum
Second end of chain is screwed in screw shell pre-buried on precast beam by screw rod.
Preferably, screw shell upper end is stretched out outside precast beam upper surface.
Preferably, the fixing end of load load maintainer is fixed in prefabricated frame from least three direction.
Preferably, the affixed direction of at least three is along the circumference equidistantly distribution of load load maintainer.
Preferably, jack fixes each limit of end all by connecting iron chains with corresponding precast beam admittedly
Connect.
Preferably, each limit of end fixed by jack all has at least two to connect iron chains pre-with corresponding
Beam processed is affixed.
In order to realize above-mentioned technical purpose, the technical scheme of patent of the present invention is, a kind of water-impervious precoated plate
Construction method, including connecting iron chains, jack top board, roller bearing load plate, jack and screw shell.
Jack connects prefabricated back by connecting iron chains, applies in the roller bearing load plate being placed on precoated plate
Load, makes the precoated plate of hinged state pour slightly expanded concrete at plate end after deforming, reaches intensity
Rear dismounting augmentor, the part after precoated plate resilience recovering deformation provides plate end precompression, anti-crack arrest
Seam produces, it is achieved avoid the water-impervious precoated plate construction method that plate end ftractures from structure.
Preferably, pre-buried screw shell in precast beam, it is ensured that while top surface of the beam is smooth be connected iron chains can
By connecting.
Preferably, connecting iron chains one end has calabash, regulates iron chains length, the hinged supporting screw rod in one end, rotation
Enter the connection realized in pre-buried screw shell with beam.
Preferably, jack top board surrounding has semi-circular to connect ring, it is achieved curved be connected on iron chains calabash
Hook connects.
Preferably, it is parallel to four limits bottom roller bearing load plate and four roller bearing Distributing loads are set, it is to avoid concentrate
Power destroys precoated plate.
Preferably, roller bearing two side position bottom roller bearing load plate is welded with steel plate, to limit roller bearing displacement.
Patent of the present invention has the beneficial effects that:
The recovery utilizing precoated plate deforms and applies precompression to plate end, and plate end concrete is in pressurized shape in advance
The plate end hogging moment partial offset of operational phase, pre-cracking-proof are produced by state, reduce fracture width;Load
Assembling can be dismantled, and conveniently recycles;Back is made to keep flat by the pre-buried screw shell in precast beam
Whole, facilitate follow-up fitting-out work;Additionally, patent of the present invention also have structure clearly, make simple etc. excellent
Point, it is possible to be effectively improved the water resistance of assembling building, there is preferably practical value and economic benefit.
Below in conjunction with the accompanying drawings patent of the present invention is described further.
Accompanying drawing explanation
Fig. 1 is the structural representation of the water-impervious precoated plate of the embodiment of the present invention;
Fig. 2 is the top view of Fig. 1;、
Fig. 3 is the structural representation of the jack top board of the embodiment of the present invention;
Fig. 4 is the structural representation of the roller bearing load plate of the embodiment of the present invention;
Fig. 5 is the upward view of Fig. 4;
Fig. 6 is the structural representation connecting iron chains of the embodiment of the present invention.
Wherein 1 is precast beam, and 2 is precoated plate, and 3 is jack, and 4 is jack top board, and 5 for connecting
Ring, 6 for loading plate body, and 7 is roller bearing, and 8 is spacing steel plate, and 9 for connecting iron chains, and 10 is cable wire calabash,
11 is screw rod, and 12 is screw shell, and 13 is crotch, and 14 is cast gap.
Detailed description of the invention
Below the technology of the present invention content is further illustrated, but not restriction to flesh and blood of the present invention.
Fig. 1 is the structural representation of the water-impervious precoated plate of the embodiment of the present invention;Fig. 2 is the vertical view of Fig. 1
Figure;, Fig. 3 be the structural representation of jack top board of the embodiment of the present invention;Fig. 4 is the embodiment of the present invention
The structural representation of roller bearing load plate;Fig. 5 is the upward view of Fig. 4;Fig. 6 is the embodiment of the present invention
Connect the structural representation of iron chains.
As shown in Fig. 1,2,3,4,5 and 6, the embodiment of the present invention, the precoated plate of a kind of water-impervious is executed
Work method, the prefabricated frame enclosing formation including precast beam 1 and the precoated plate 2 being overlapped in prefabricated frame,
The middle part of precoated plate 2 is provided with for loading downwards load and dismountable lotus from the upper surface of precoated plate 2
Carrying load maintainer, the fixing end of load load maintainer is fixed on precast beam 1, the lotus of load load maintainer
Carry the outfan contact upper surface at precoated plate 2;It is further applied load by load load maintainer and forces precoated plate 2
Middle part deform downwards, corresponding precoated plate 2 four circumference precoated plates 2 in the middle part of deform so that precoated plate 2
Surrounding and corresponding precast beam 1 between formed cast gap 14;Micro-by pouring into a mould in cast gap 14
Expansive concrete, until after reaching intensity after slightly expanded concrete maintenance, removing load load maintainer, from
And complete water-impervious precoated plate 2 construction method avoiding precoated plate 2 end to ftracture.
As shown in Fig. 1,2,3,4,5 and 6, it also resides in, and load load maintainer includes for applying
The jack 3 of load, it is fixed in the roller bearing load plate of jack 3 outfan and very heavy for connecting respectively
The fixing end in top 3 and the connection iron chains 9 of precast beam 1, the equilibrium of roller bearing load plate is laid in the middle part of precoated plate 2
On upper surface.
As shown in Fig. 1,2,3,4,5 and 6, it also resides in, roller bearing load plate include load plate body 6,
The roller bearing 7 loaded bottom plate body 6 is installed and is enclosed in roller bearing 7 surrounding for limiting roller bearing 7 displacement
Spacing steel plate 8.
As shown in Fig. 1,2,3,4,5 and 6, it also resides in, and the bottom loading plate body 6 is provided with four
Group roller bearing 7, four groups of roller bearings 7 are respectively parallel to load four edges of boards layings of plate body 6, to avoid jack
3 concentration powers applied destroy precoated plate 2.
As shown in Fig. 1,2,3,4,5 and 6, it also resides in, and the fixing end of jack 3 is provided with thousand
Jin top top board 4, being formed around of jack top board 4 connects ring 5, connects the first end of iron chains 9 by curved
Hook 13 is fixed on connection ring 5, connects to be additionally provided with between iron chains 9 and crotch 13 and is connected ferrum for regulating
The cable wire calabash 10 of chain 9 length;It is embedded with screw shell 12 on precast beam 1, connects the second of iron chains 9
End is screwed in screw shell 12 pre-buried on precast beam 1 by screw rod 11.
As illustrated in fig. 1 and 2, it also resides in, and screw shell 12 upper end is stretched out outside precast beam 1 upper surface.
As shown in Fig. 1,2,3,4,5 and 6, it also resides in, the fixing end of load load maintainer to
Few three directions are fixed on prefabricated frame.
As shown in Fig. 1,2,3,4,5 and 6, it also resides in, and the affixed direction of at least three adds along load
The equidistantly distribution of the circumference of mounted mechanism.
As shown in Fig. 1,2,3,4,5 and 6, it also resides in, each limit of the fixing end of jack 3
All affixed with corresponding precast beam 1 by connecting iron chains 9.
It also resides in, and each limit of the fixing end of jack 3 all has at least two to connect iron chains 9 with relative
The precast beam 1 answered is affixed.
During enforcement, it is provided that a kind of water-impervious precoated plate construction method, including connecting iron chains 9, jack top board
4, roller bearing load plate 6, jack 3 and screw shell 12.Fig. 1 and Fig. 2 is the anti-of the embodiment of the present invention
Infiltration precoated plate construction method schematic diagram.As shown in Fig. 3, Fig. 4 and Fig. 6, would know that water-impervious precoated plate
Mainly comprising and embodiment of construction method, roller bearing load plate 6 and jack top board 4 make in factory
Completing, roller bearing load plate 6 is welded with the spacing steel plate 8 limiting roller bearing 7 displacement in roller bearing 7 both sides, very heavy
Top top board 4 reserves connection ring 5 on four limits.First the precast beam 1 of pre-buried for middle part screw shell 12 is pacified
Dress construction is complete, and precast beam 1 end face thickness of slab height is stretched out in screw shell 12 upper end, then by precoated plate 2
End is shelved on one fixed width on precast beam 1, and is connected by upper reinforcement, on precoated plate 2 from bottom to top
Place roller bearing load plate 6, jack 3 and jack top board 4 with roller bearing 7.Respectively by jack top
Plate 4 connects the crotch 13 connection ring 5 through jack top board 4 of cable wire calabash 10 end, the spiral shell of the other end
Bar 11 screws in the pre-buried screw shell 12 in the middle part of precast beam 1, completes the erection of force application apparatus.Jack 3
The system constituted with connection iron chains 9 and jack top board 4 forms self-locking device by roller bearing 7 device in advance
Making sheet 2 is further applied load, make precoated plate 2 reach allow amount of deflection 10% after pour into a mould in the cast-in-place region of plate end 14
Microdilatancy pea gravel concreten, removes force application apparatus, by precoated plate 2 times after concrete strength reaches requirement
Part after bullet recovers deformation provides plate end precompression to prevent crack from producing, and i.e. completes whole water-impervious prefabricated
Board construction method.
The foregoing is only the preferred embodiments of the present invention, not thereby limit the scope of the invention,
Every equivalent structure transformation utilizing description of the invention content to be made, or directly or indirectly it is used in other
Relevant technical field, is the most in like manner included in the scope of patent protection of the present invention.
Claims (10)
1. a precoated plate construction method for water-impervious, precast beam (1) enclose formation prefabricated frame and
Water-impervious construction is carried out, it is characterised in that in advance on the basis of the precoated plate (2) being overlapped in prefabricated frame
The middle part of making sheet (2) is provided with for loading downwards load and detachable from the upper surface of precoated plate (2)
Load load maintainer, the fixing end of load load maintainer is fixed on precast beam (1), and load adds carrier aircraft
The load outfan contact of the structure upper surface in precoated plate (2);It is further applied load urgent by load load maintainer
The middle part making precoated plate (2) deforms downwards, in four circumferences precoated plate (2) of corresponding precoated plate (2)
Portion deforms so that form cast gap (14) between the surrounding of precoated plate (2) with corresponding precast beam (1);
By cast slightly expanded concrete in cast gap (14), until reaching after slightly expanded concrete maintenance
After intensity, remove load load maintainer, thus the water-impervious completing to avoid precoated plate (2) end to ftracture is prefabricated
Plate (2) construction method.
The precoated plate construction method of water-impervious the most according to claim 1, it is characterised in that load
Load maintainer includes the jack (3) for being further applied load, is fixed in the roller bearing of jack (3) outfan
Load plate and the connection iron chains (9) held with precast beam (1) for connecting jack (3) to fix respectively,
The equilibrium of roller bearing load plate is laid on the middle part upper surface of precoated plate (2).
The precoated plate construction method of water-impervious the most according to claim 2, it is characterised in that roller bearing
Load plate includes loading plate body (6), installing the roller bearing (7) loaded bottom plate body (6) and be enclosed in
Roller bearing (7) surrounding is used for limiting the spacing steel plate (8) of roller bearing (7) displacement.
The precoated plate construction method of water-impervious the most according to claim 3, it is characterised in that load
The bottom of plate body (6) is provided with four groups of roller bearings (7), and four groups of roller bearings (7) are respectively parallel to load plate body
(6) four edges of boards are laid, and destroy precoated plate (2) with the concentration power avoiding jack (3) to apply.
The precoated plate construction method of water-impervious the most according to claim 2, it is characterised in that very heavy
Top (3) fixing end be provided with jack top board (4), jack top board (4) be formed around connect
Ring (5), the first end connecting iron chains (9) is fixed in connection ring (5) by crotch (13), even
Connect and be additionally provided with between iron chains (9) with crotch (13) for regulating the cable wire calabash being connected iron chains (9) length
Reed (10);Being embedded with screw shell (12) on precast beam (1), the second end connecting iron chains (9) leads to
Cross screw rod (11) to be screwed in the upper pre-buried screw shell (12) of precast beam (1).
The precoated plate construction method of water-impervious the most according to claim 5, it is characterised in that screw thread
Sleeve (12) upper end is stretched out outside precast beam (1) upper surface.
The precoated plate construction method of water-impervious the most according to any one of claim 1 to 6, it is special
Levying and be, the fixing end of load load maintainer is fixed in prefabricated frame from least three direction.
The precoated plate construction method of water-impervious the most according to claim 7, it is characterised in that at least
Three affixed directions are equidistantly distributed along the circumferential of load load maintainer.
9., according to the precoated plate construction method of the water-impervious according to any one of claim 2 to 6, it is special
Levying and be, each limit of the fixing end of jack (3) is all pre-with corresponding by connecting iron chains (9)
Beam processed (1) is affixed.
The precoated plate construction method of water-impervious the most according to claim 9, it is characterised in that very heavy
Each limit of the fixing end in top (3) all has at least two to connect iron chains (9) and corresponding precast beam (1)
Affixed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410722999.0A CN104563524B (en) | 2014-12-02 | 2014-12-02 | Anti-water-seepage prefabricated slab construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410722999.0A CN104563524B (en) | 2014-12-02 | 2014-12-02 | Anti-water-seepage prefabricated slab construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104563524A CN104563524A (en) | 2015-04-29 |
CN104563524B true CN104563524B (en) | 2017-01-11 |
Family
ID=53080524
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410722999.0A Expired - Fee Related CN104563524B (en) | 2014-12-02 | 2014-12-02 | Anti-water-seepage prefabricated slab construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104563524B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109238844B (en) * | 2016-07-08 | 2020-12-01 | 长安大学 | Tunnel lining structure crack treatment experimental method |
CN109537787B (en) * | 2018-12-28 | 2024-02-13 | 上海建工五建集团有限公司 | Assembled prestress large plate reverse camber self-adjusting system and using method thereof |
CN112681766B (en) * | 2020-12-15 | 2022-09-09 | 安徽晶宫绿建集团有限公司 | Construction device and method for water seepage prevention prefabricated slab |
CN113057102B (en) * | 2021-03-25 | 2022-04-29 | 山东大学 | Flexible waterproof method for prefabricated excrement slot plate seam |
CN113068621A (en) * | 2021-03-25 | 2021-07-06 | 山东大学 | Waterproof method for prefabricated excrement groove plate seam |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5469684A (en) * | 1993-08-10 | 1995-11-28 | Franklin; James W. | Concrete building frame construction method |
JPH09317183A (en) * | 1996-05-28 | 1997-12-09 | Sato Kogyo Co Ltd | Construction method of building |
KR100454478B1 (en) * | 2002-04-18 | 2004-10-28 | 한봉길 | Construction method for SRC structured high rise building |
CN202390978U (en) * | 2011-12-21 | 2012-08-22 | 东南大学 | Self-centering prestressed concrete frame floor slab structure |
-
2014
- 2014-12-02 CN CN201410722999.0A patent/CN104563524B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN104563524A (en) | 2015-04-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104563524B (en) | Anti-water-seepage prefabricated slab construction method | |
CN103243817B (en) | A kind of assembled beam-column attachment means | |
CN102704491B (en) | Sectional steel and reinforced concrete beam combination foundation pit supporting protection surrounding purlin and construction method of purlin | |
KR100837608B1 (en) | J.K Bracket Method | |
CN110042768A (en) | A kind of combination beam cable-stayed bridge main-beam binodal section circulation construction method | |
CN102561690A (en) | Construction method for supporting structures on two sides of post-cast strip by use of brick column | |
CN109184189A (en) | A kind of diameter Silo conical shell silo roof construction method | |
CN109440634A (en) | The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off | |
CN106894346A (en) | A kind of the continuous beam bridge construction method | |
CN104405165B (en) | The assembled mixing station storage bin partition wall of a kind of repeatable utilization and construction method thereof | |
CA3023390A1 (en) | An improved reinforcement apparatus for reinforcing a structure comprising a pier and a cross-beam | |
KR20070115813A (en) | The earthquake resistant reinforcement method for preexistence bridges | |
KR101661449B1 (en) | Methods for controlling the camber of the cantilever truss half precast panel and, constructing methods using the same | |
CN106013784A (en) | Angle iron frame template and construction method | |
CN105821908A (en) | Multiple water stop belt, waterproof structure and construction method of waterproof structure | |
KR100842062B1 (en) | The steel composite rahmen bridge construction technique for which preflexion steel girder was used | |
JP6027389B2 (en) | Foundation structure built using the frame of an existing structure | |
CN108678181A (en) | Silo roof steel truss and concrete combined structure high-altitude construction method | |
CN210216478U (en) | Open caisson construction work platform | |
CN102359185A (en) | Connecting structure of large steel structural member and concrete member and construction method | |
KR101605011B1 (en) | Repair and Reinforcement method of lower structure of bridge | |
CN210105373U (en) | Replacement, reinforcement and support device for concrete building shear wall | |
KR20120100052A (en) | Bridge leg correcting method using oil compressure jack and broken parts compensation structure | |
RU2435917C1 (en) | Method to strengthen power transmission line support | |
CN105625202B (en) | The construction method of the cast-in-place box culvert of the porous overlength of big cross section |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170111 Termination date: 20191202 |
|
CF01 | Termination of patent right due to non-payment of annual fee |