CN104551580B - Method for manufacturing shell tube of heat exchanger of central air conditioner - Google Patents

Method for manufacturing shell tube of heat exchanger of central air conditioner Download PDF

Info

Publication number
CN104551580B
CN104551580B CN201310473584.XA CN201310473584A CN104551580B CN 104551580 B CN104551580 B CN 104551580B CN 201310473584 A CN201310473584 A CN 201310473584A CN 104551580 B CN104551580 B CN 104551580B
Authority
CN
China
Prior art keywords
ready
heat exchanger
central air
processed
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310473584.XA
Other languages
Chinese (zh)
Other versions
CN104551580A (en
Inventor
吴光如
文辉
张贵
王晓彬
江秀华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gree Electric Appliances Inc of Zhuhai
Zhuhai Gree Intelligent Equipment Co Ltd
Original Assignee
Gree Electric Appliances Inc of Zhuhai
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gree Electric Appliances Inc of Zhuhai filed Critical Gree Electric Appliances Inc of Zhuhai
Priority to CN201310473584.XA priority Critical patent/CN104551580B/en
Publication of CN104551580A publication Critical patent/CN104551580A/en
Application granted granted Critical
Publication of CN104551580B publication Critical patent/CN104551580B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
    • B23P15/26Making specific metal objects by operations not covered by a single other subclass or a group in this subclass heat exchangers or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Media Introduction/Drainage Providing Device (AREA)
  • Processing Of Stones Or Stones Resemblance Materials (AREA)

Abstract

The invention provides a method for manufacturing a shell tube of a heat exchanger of a central air conditioner, which comprises the following steps: 1) generating a numerical control marking instruction; 2) placing the plate to be processed on a processing table, and controlling the dotting device to move by the controller according to the marking instruction and dotting and marking the plate to be processed; 3) the controller controls the cutting device to cut the plate to be processed to manufacture a shell unfolding material with a proper size; 4) and rolling the shell unfolding material to form the shell tube of the heat exchanger. The invention adopts a dotting marking mode of slightly damaging the surface of the shell pipe, effectively solves the problem of abnormal positioning caused by measurement errors and measurement errors in the shell pipe production process, marks by punching dotting, and has obvious marking effect after sand blasting and shot blasting derusting of subsequent procedures. The design is directly converted into a numerical control marking instruction, the manufacture of the central air-conditioning equipment is converted from manual marking to digitization and intellectualization, and the problem of product consistency in the production of large central air-conditioners is solved.

Description

The manufacturing method of central air-conditioning heat exchanger package
Technical field
The present invention relates to the manufacturing technology field of central air conditioning equipment, more particularly to a kind of central air-conditioning heat exchanger package Manufacturing method.
Background technology
Central air-conditioning belongs to large-scale industrial equipment, and during manufacture, since parts volume is big, usually many processes can only Operation is had been manually done by worker.For example, for central air-conditioning heat exchanger package, in production process, stent welding life is carried out , it is necessary to carry out line positioning to the welding position of stent group pair during production.In general, employee is tape measure using one, a drawing, Scene is measured according to drawing, is found the specific size positions of stent, is labeled, such localization method is affected by human factors Greatly, error is very easy to, causes stent installation dimension deviation.Therefore, the manufacturing method for central air conditioning equipment is, it is necessary to from hand Work is changed to digitlization, intelligence.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of manufacturing method of central air-conditioning heat exchanger package, can Effectively ensure the precision controlling of heat exchanger package production size, realize manufacturing method from craft to digitlization, intelligent transformation.
The present invention is achieved through the following technical solutions:
The manufacturing method of central air-conditioning heat exchanger package, wherein, include the following steps:
1) numerical control marking instruction is generated;
2) plate to be processed being placed in machine table, controller control device for dotting is moved according to line instruction, And ready mark is got to plate to be processed;
3) controller control cutter device cuts plate to be processed, produces the shell spread material of suitable size;
4) package to form heat exchanger is rolled to shell spread material.
In one of the embodiments, in step 1), the specific method of generation numerical control marking instruction is:
A) graphics of heat exchanger is drawn according to the true form of product and size, is determined on central air-conditioning heat exchanger package Need the specific location of progress stent welding;
B) graphics is changed into X-Y scheme;
C) X-Y scheme is changed into numerical control marking instruction, has thereby determined that and stent welding position is carried out to beat dashdotted behaviour The operational order for instructing and being cut according to plate size to be processed.
Further, in step 2), device for dotting gets rifle ready for one kind, gets plate to be processed the specific method of mark ready For:First plate to be processed is placed in machine table, getting ready for flat plasma cutting equipment is then controlled by controller Rifle moves on plate to be processed, selects a datum mark;After determining datum mark, get rifle ready and progress is instructed according to numerical control marking It is mobile, after being moved to the position for needing to carry out stent welding, carry out getting line ready.
Further, in step 3), cutter device is a kind of cutting gun, and that gets all positions of rifle completion ready gets line ready Afterwards, datum mark is returned to;Rifle will be got ready to convert with cutting gun, make cutting gun face datum mark, then cutting gun is according to cutting Operational order proceed by mobile cutting from datum mark, be cut into the shell spread material for the heat exchanger being sized for.
Further, in step 4), the shell spread material feeding of well cutting is rolled into equipment and is rolled, shell is unfolded Material volume is pressed into the heat exchanger package of tubular.
Beneficial effects of the present invention are as follows:
The manufacturing method of the central air-conditioning heat exchanger package of the present invention, due to including the following steps:1) numerical control marking is generated Instruction;2) plate to be processed is placed in machine table, controller control device for dotting is moved according to line instruction, and right Plate to be processed gets mark ready;3) controller control cutter device cuts plate to be processed, produces suitable size Shell spread material;4) package to form heat exchanger is rolled to shell spread material.It effectively solves in package production process due to measurement Error and measuring error and cause position abnormal problem, got ready and be marked by punching press, sandblasting, ball blast by down-stream After derusting, mark effect is still apparent.Present invention employs the form to package surface slight damage, so as to avoid package The influence of sandblasting, impeller blasting technique to package line effect, while complete from design and be directly translated into numerical control marking instruction, Staffing is not required.The manufacturing method of central air conditioning equipment is realized from digitlization, intelligentized transformation is scoring to by hand, is solved In Large Central Air Conditioning System of having determined production the problem of homogeneity of product.
Specific embodiment
The present invention is in order to solve problem of the prior art, it is proposed that a kind of manufacturing method of central air-conditioning heat exchanger package, Wherein, include the following steps:
1) numerical control marking instruction is generated;
2) plate to be processed being placed in machine table, controller control device for dotting is moved according to line instruction, And ready mark is got to plate to be processed;
3) controller control cutter device cuts plate to be processed, produces the shell spread material of suitable size;
4) package to form heat exchanger is rolled to shell spread material.
In one of the embodiments, in step 1), the specific method of generation numerical control marking instruction is:
D) graphics of heat exchanger is drawn according to the true form of product and size, is determined on central air-conditioning heat exchanger package Need the specific location of progress stent welding;
E) graphics is changed into X-Y scheme;
F) X-Y scheme is changed into numerical control marking instruction, has thereby determined that and stent welding position is carried out to beat dashdotted behaviour The operational order for instructing and being cut according to plate size to be processed.
Further, in step 1), the ratio of X-Y scheme and actual product is 1:1.
Further, in step 2), device for dotting gets rifle ready for one kind, gets plate to be processed the specific method of mark ready For:First plate to be processed is placed in machine table, getting ready for flat plasma cutting equipment is then controlled by controller Rifle moves on plate to be processed, selects a datum mark;After determining datum mark, get rifle ready and progress is instructed according to numerical control marking It is mobile, after being moved to the position for needing to carry out stent welding, carry out getting line ready.
Further, in step 2), get rifle ready and instructed according to numerical control marking, connect according to connection of the stent in the position of welding Shape is touched, line figure is got ready what panel surface to be processed impacted respective shapes.
Further, in step 2), the datum mark selected on plate to be processed is located at the edge of plate.
Further, in step 2), complete first stent get line ready after, get rifle ready and move directly to next need Dashdotted position is beaten to continue to get marking operation ready.
Further, in step 2), complete first stent get line ready after, get rifle ready and briefly return to datum mark, then move Moving to next needs dozen dashdotted position to carry out getting marking operation ready.
Further, in step 3), cutter device is a kind of cutting gun, and that gets all positions of rifle completion ready gets line ready Afterwards, datum mark is returned to;Rifle will be got ready to convert with cutting gun, make cutting gun face datum mark, then cutting gun is according to cutting Operational order proceed by mobile cutting from datum mark, be cut into the shell spread material for the heat exchanger being sized for.
Further, in step 4), the shell spread material feeding of well cutting is rolled into equipment and is rolled, shell is unfolded Material volume is pressed into the heat exchanger package of tubular.
Embodiment:
In the present embodiment, in the manufacturing method of central air-conditioning heat exchanger package, the detailed mistake of generation numerical control marking instruction Cheng Wei:
First, the graphics of heat exchanger is drawn in three-dimensional software POR systems, graphics is needed according to actual shape of product And size is planned, is unfolded first with designed POR graphics and (has specific backing positions on graphics), so as to It determines to need the specific location for carrying out stent welding on heat exchanger package;
2nd, graphics is changed into X-Y scheme (cad figures), the ratio of X-Y scheme and actual product is 1:1;
3rd, by FastCAM jacking softwares, jacking, programming are carried out, generation numerical control marking instruction has been thereby determined that branch Frame welding position carries out the operational order beaten dashdotted operational order and cut according to plate size to be processed.
Controller controls to get rifle ready and moved and got ready the detailed process of mark according to instruction:
First steel plate to be processed is placed in machine table, flat plasma cutting equipment is then controlled by controller Rifle is got ready to move on the steel plate, select datum mark (any position of steel plate can, but be in order at the mesh for saving material , by benchmark point selection at edges of plate position).After determining datum mark, get ready rifle according to it is above-mentioned get ready line instruct into Row movement, after being moved to the position for needing to carry out stent welding, according to connection contact shape of the stent in the position, to be processed What panel surface impacted respective shapes gets line figure ready.Complete first stent get line ready after, it is a kind of there are two types of mode Be get ready rifle move directly to it is next need beat dashdotted position operated;Another kind is to get rifle ready to briefly return to benchmark Point, then be moved to it is next need beat dashdotted position operated.The benefit of the second way is to ensure each position Accurately got ready.
Get ready rifle complete all positions get line ready after, return to datum mark.Then rifle will be got ready with cutting gun to be turned It changes, makes cutting gun face datum mark, then cutting gun proceeds by mobile cutting according to cutting instruction from datum mark, is cut into big The shell of small suitable heat exchanger.
It is rolled after completing cutting, forms heat exchanger package, stent size and position can accurately be shown on package Show, this method realizes automation cutting and automatically dotting labelling technique.
Stent size and the accurate marker of position are already had on the shell, need to only be propped up on corresponding mark The welding of frame avoids traditional to scheming, measuring, the manual operations such as rule.
The manufacturing method of the present embodiment central air-conditioning heat exchanger package, mainly solves the problems, such as exactitude position, in shell Just first the specific location of stent is marked before body steel plate cutting process, ensures product quality.The program realizes automation cutting With automatically dotting labelling technique, impact is carried out by the way of to surface of shell slight damage and is got ready, so as to avoid follow-up shell The influence of body sandblasting, impeller blasting technique to housing line effect, ensures each dimensional accuracy in package manufacturing process, is empty Adjust advanced method for manufacturing in industry.
Embodiment described above only expresses embodiments of the present invention, and description is more specific and detailed, but can not Therefore it is interpreted as the limitation to the scope of the claims of the present invention.It should be pointed out that for those of ordinary skill in the art, Without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to the protection model of the present invention It encloses.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (8)

1. the manufacturing method of central air-conditioning heat exchanger package, which is characterized in that include the following steps:
1) numerical control marking instruction is generated;Generating the specific method that numerical control marking instructs is:
A) graphics of heat exchanger is drawn according to the true form of product and size, determines to need on central air-conditioning heat exchanger package Carry out the specific location of stent welding;
B) graphics is changed into X-Y scheme;
C) X-Y scheme is changed into numerical control marking instruction, has thereby determined that dozen dashdotted operation is carried out to stent welding position to be referred to Order and the operational order cut according to plate size to be processed;
2) plate to be processed is placed in machine table, controller control device for dotting is moved according to line instruction, and right Plate to be processed gets mark ready;Device for dotting gets rifle ready for one kind, and the specific method for getting plate to be processed mark ready is:First Plate to be processed is placed in machine table, then gets rifle ready to be added by controller control flat plasma cutting equipment It is moved on work plate, selects a datum mark;After determining datum mark, get rifle ready and moved according to numerical control marking instruction, moved It moves to the position for needing to carry out stent welding, carries out getting line ready;
3) controller control cutter device cuts plate to be processed, produces the shell spread material of suitable size;
4) package to form heat exchanger is rolled to shell spread material.
2. the manufacturing method of central air-conditioning heat exchanger package according to claim 1, which is characterized in that in step 1), two The ratio of dimension figure and actual product is 1:1.
3. the manufacturing method of central air-conditioning heat exchanger package according to claim 1 or 2, which is characterized in that in step 2), It gets rifle ready to be instructed according to numerical control marking, according to connection contact shape of the stent in the position of welding, be rushed in panel surface to be processed Hit respective shapes gets line figure ready.
4. the manufacturing method of central air-conditioning heat exchanger package according to claim 1 or 2, which is characterized in that in step 2), The datum mark selected on plate to be processed is located at the edge of plate.
5. the manufacturing method of central air-conditioning heat exchanger package according to claim 1 or 2, which is characterized in that in step 2), Complete first stent get line ready after, get ready rifle move directly to it is next need to beat dashdotted position continue to beat Point marking operation.
6. the manufacturing method of central air-conditioning heat exchanger package according to claim 1 or 2, which is characterized in that in step 2), Complete first stent get line ready after, get rifle ready and briefly return to datum mark, then be moved to and next need to beat dashdotted position It puts and carries out getting marking operation ready.
7. the manufacturing method of central air-conditioning heat exchanger package according to claim 1 or 2, which is characterized in that in step 3), Cutter device is a kind of cutting gun, get ready rifle complete all positions get line ready after, return to datum mark;Rifle and cutting will be got ready Rifle is converted, and makes cutting gun face datum mark, and then cutting gun proceeds by shifting according to the operational order of cutting from datum mark Dynamic cutting is cut into the shell spread material for the heat exchanger being sized for.
8. the manufacturing method of central air-conditioning heat exchanger package according to claim 1 or 2, which is characterized in that in step 4), The shell spread material feeding of well cutting is rolled equipment to roll, makes shell spread material crimped into the heat exchanger package of tubular.
CN201310473584.XA 2013-10-11 2013-10-11 Method for manufacturing shell tube of heat exchanger of central air conditioner Active CN104551580B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310473584.XA CN104551580B (en) 2013-10-11 2013-10-11 Method for manufacturing shell tube of heat exchanger of central air conditioner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310473584.XA CN104551580B (en) 2013-10-11 2013-10-11 Method for manufacturing shell tube of heat exchanger of central air conditioner

Publications (2)

Publication Number Publication Date
CN104551580A CN104551580A (en) 2015-04-29
CN104551580B true CN104551580B (en) 2018-06-05

Family

ID=53069213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310473584.XA Active CN104551580B (en) 2013-10-11 2013-10-11 Method for manufacturing shell tube of heat exchanger of central air conditioner

Country Status (1)

Country Link
CN (1) CN104551580B (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102328310A (en) * 2011-08-27 2012-01-25 中国二十二冶集团有限公司 Positioning dotting method for numerical control flame cutting machine

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060230617A1 (en) * 2005-04-13 2006-10-19 Kent Scott E Fabricated, brazed metal heat exchanger tube manufacture
CN101386041B (en) * 2008-10-14 2010-06-02 浙江东南网架股份有限公司 Cold roll forming technique of large-sized curve type steel tube
JP5258636B2 (en) * 2009-03-13 2013-08-07 古河スカイ株式会社 Thin brazing sheet fin material for high temperature brazing and manufacturing method of heat exchanger using the same
CN101592285B (en) * 2009-06-15 2012-07-04 江苏沪宁钢机股份有限公司 Method for processing shuttle-shape pipe
CN101596678B (en) * 2009-06-15 2011-03-16 江苏沪宁钢机股份有限公司 Method for processing oval steel member
CN201592433U (en) * 2009-12-31 2010-09-29 鲁西工业装备有限公司 Numerical control automatic marking device

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102328310A (en) * 2011-08-27 2012-01-25 中国二十二冶集团有限公司 Positioning dotting method for numerical control flame cutting machine

Also Published As

Publication number Publication date
CN104551580A (en) 2015-04-29

Similar Documents

Publication Publication Date Title
CN104289748B (en) A kind of large thin-wall covering adaptively equal wall thickness milling system and its processing method
CN104476552A (en) Machine vision based robot profile carrying device and method thereof
CN105149419B (en) CCD multiple spots micropore resetting system of processing and method
EP2584419B1 (en) CNC machine for cutting with plasma, oxygen and water jet used as a cutting tool with automatic setting up a precise position of a cutting tool in a cutting head by autocalibration and method thereof
CN103747617A (en) PCB expansion compensation method
CN103400016B (en) A kind of fast spraying path generating method for small lot structuring workpiece
CN103512511A (en) Large face automatic measurement method based on laser tracker
CN104400217A (en) Full-automatic laser welding method and full-automatic laser welding device
CN103144109B (en) Substation type precision compensation for robot system with additional external shaft
CN103659601B (en) Based on coordinate automatic compensating method in angle head cylindrical grinding machine grinding
CN103302162B (en) Mould positioning method based on feature distance
CN106647631A (en) Gantry hole making machine tool machining collision detection analysis method
CN103970071B (en) The detection of machining path and correcting method in cast(ing) surface scale removal process
CN104714473B (en) A kind of conduit surplus cutting position computational methods of pipeline flexible welding and assembling
CN106313007A (en) Parallel drilling machine teaching/playback system
CN105095605A (en) Simulation method of airplane conduit machining process
CN106734410A (en) ERW three-point bending flexibility cold bending roller position determines method
CN109903333A (en) Coordinate system modification method, device and the electronic equipment of robot workpiece
CN205415697U (en) Positioner is markd to industrial robot instrument hand elasticity
CN104551580B (en) Method for manufacturing shell tube of heat exchanger of central air conditioner
CN106546184A (en) Large complicated carved three-dimensional appearance robot flexibility measuring system
CN109318051A (en) A kind of curved surface part numerical control processing localization method
CN107486860A (en) A kind of control method of engineering machinery mechanical arm
CN104551534A (en) Numerical control machining method for large-size entire magnesium alloy casting
CN103838182B (en) Numerical Control Programming householder method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Wen Hui

Inventor after: Wu Guangru

Inventor after: Zhang Gui

Inventor after: Wang Xiaobin

Inventor after: Jiang Xiuhua

Inventor before: Wu Guangru

Inventor before: Wen Hui

Inventor before: Zhang Gui

Inventor before: Wang Xiaobin

Inventor before: Jiang Xiuhua

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201117

Address after: 519070 Guangdong city of Zhuhai Province Qianshan

Patentee after: GREE ELECTRIC APPLIANCES,Inc.OF ZHUHAI

Patentee after: ZHUHAI GREE INTELLIGENT EQUIPMENT Co.,Ltd.

Address before: 519000 No. 6 Jinji Road West, Zhuhai, Guangdong

Patentee before: GREE ELECTRIC APPLIANCES,Inc.OF ZHUHAI