CN104533134B - A kind of concreting method of concrete filled steel tube steel tower - Google Patents

A kind of concreting method of concrete filled steel tube steel tower Download PDF

Info

Publication number
CN104533134B
CN104533134B CN201410762534.8A CN201410762534A CN104533134B CN 104533134 B CN104533134 B CN 104533134B CN 201410762534 A CN201410762534 A CN 201410762534A CN 104533134 B CN104533134 B CN 104533134B
Authority
CN
China
Prior art keywords
concrete
main material
tower
tower body
flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410762534.8A
Other languages
Chinese (zh)
Other versions
CN104533134A (en
Inventor
郭咏华
张斌
武韩青
岳延鹏
张建明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Henan Electric Power Survey and Design Institute Co Ltd
Original Assignee
Hennan Electric Power Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hennan Electric Power Survey and Design Institute filed Critical Hennan Electric Power Survey and Design Institute
Priority to CN201410762534.8A priority Critical patent/CN104533134B/en
Publication of CN104533134A publication Critical patent/CN104533134A/en
Application granted granted Critical
Publication of CN104533134B publication Critical patent/CN104533134B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/12Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The concreting method of a kind of concrete filled steel tube steel tower, comprises the following steps: a, with bolt by ring flange and tower body main material Flange joint;B, the sling point that rises using coaster to pass through on cantilever lift by crane concrete;C, concrete is poured in the main material of tower body by grouting mouth reserved on ring flange;D, complete the pouring of one section of main material of tower body after, remove the bolt of mounting flange and tower body main material flange, movable concrete lifting steelframe rises along with the group of iron tower main material is vertical, carries out pouring of next section of iron tower main material concrete;E, when pouring on next section of main material of tower body, repeat step a, b, c, d, until all main materials have poured.The present invention can realize the cast-in-place of concrete, but the requirement to construction machinery is relatively low, form of construction work is flexible, the area being difficult to arrive for concrete mixer can use the casting method of the present invention, the movable concrete lifting repeatable utilization of steelframe that the present invention uses, simple to operate, consumption of materials is few.

Description

A kind of concreting method of concrete filled steel tube steel tower
Technical field
The present invention relates to the form of construction work of a kind of iron tower of power transmission line, be specifically related to a kind of for concrete filled steel tube steel tower Concreting method.
Background technology
Along with the development of work transmission line, the size of steel tower, load there occurs the change of matter, and steel tower tends to maximizing, As the component that bearing capacity is higher, concrete filled steel tube has begun to be applied to electric power line pole tower design.Steel tube concrete Soil is remarkably improved the comprcssive strength of component compared with steel pipe, and it is long-pending to effectively reduce steel tube section, thus reduces bar cost, saves Investment.The at present construction of concrete filled steel tube steel tower, mostly is after iron tower main material group founds certain altitude, by concrete mixer by outstanding Concrete, to pipe top, is then poured in steel pipe by arm pump concrete.Owing to concrete mixer volume is relatively big, it is not suitable for landform Big rise and fall and the poor area of transportation condition, have certain limitation.It is thus desirable to a kind of novel steel tube concrete steel tower of design Concreting mode, to meet the concrete filled steel tube tower erection requirement of various orographic condition and transportation condition.
At present, adaptable to poor landform, the concreting method of easy construction has opens on iron tower main material Hole, uses concrete mixer, by tapping, concrete pump is delivered to specific bit and puts, need again to iron tower main material after having poured On perforate carry out repair welding.
Summary of the invention
In order to solve the problems referred to above, the present invention provides a kind of concreting speed fast, and the construction period is short, to various landform The concreting method of the concrete filled steel tube steel tower that condition and transportation condition are all suitable for.
The purpose of the present invention is achieved through the following technical solutions:
The concreting method of a kind of concrete filled steel tube steel tower, comprises the following steps:
A. with bolt by ring flange and tower body main material Flange joint;
B. coaster is used to lift by crane concrete by the sling point that rises on cantilever;
C. concrete is poured in the main material of tower body by grouting mouth reserved on ring flange;
D., after completing the pouring of one section of main material of tower body, the bolt of mounting flange and tower body main material flange is removed, movable Concrete lifting steelframe rises along with the group of iron tower main material is vertical, carries out pouring of next section of iron tower main material concrete;
When e. pouring on next section of main material of tower body, repeat step a, b, c, d, until all main materials have poured.
The lifting steelframe of movable concrete described in step d is made up of steel pipe, ring flange and cantilever.
At least 4 kinds of apertures and at least 10 screws are set on ring flange described in step a.
The present invention can realize the cast-in-place of concrete, and the requirement to construction machinery is relatively low, and form of construction work is flexible, for mixed The area that solidifying soil pump truck is difficult to arrive can use the casting method of the present invention, the movable concrete lifting steelframe that the present invention uses Repeatable utilization, simple to operate, consumption of materials is few.
Accompanying drawing explanation
Fig. 1 is the structural representation of movable concrete lifting steelframe in the present invention.
Fig. 2 is the section structure schematic diagram of ring flange in movable concrete lifting steelframe in the present invention.
In figure 1, play sling point, 2, cantilever, 3, steel pipe, 4, ring flange, 5, grouting mouth, 6, aperture be the screw of 1mm, 7, hole Footpath is the screw of 2mm, 8, aperture be the screw of 3mm, 9, aperture be the screw of 4mm.
Detailed description of the invention
Embodiment 1
The concreting method of a kind of concrete filled steel tube steel tower, comprises the following steps:
A. with bolt by ring flange 4 and tower body main material Flange joint;
B. coaster is used to lift by crane concrete by the sling point 1 that rises on cantilever 2;
C. concrete is poured in the main material of tower body by grouting mouth 5 reserved on ring flange 4;
D., after completing the pouring of one section of main material of tower body, the bolt of mounting flange 4 and tower body main material flange is removed, movable Concrete lifting steelframe rises along with the group of iron tower main material is vertical, carries out pouring of next section of iron tower main material concrete;
When e. pouring on next section of main material of tower body, repeat step a, b, c, d, until all main materials have poured.
The lifting steelframe of movable concrete described in step d is made up of steel pipe 3, ring flange 4 and cantilever 2.
At least 4 kinds of apertures and at least 10 screws are set on described ring flange 4.As it is shown in figure 1, on ring flange 4 from interior to Outer be respectively provided with successively 12 apertures be the screw 6 of 1mm, aperture be the screw 7 of 2mm, aperture be that the screw 8 of 3mm, aperture are The screw 9 of 4mm, to adapt to the main material Flange joint requirement of the tower body of different size, is carried out even by bolt and tower body main material flange Connect.
In the present invention, movable concrete lifts by crane steelframe and the connected mode of iron tower main material and the shape of ring flange preformed hole Formula can be adopted in other ways.

Claims (3)

1. the concreting method of a concrete filled steel tube steel tower, it is characterised in that: comprise the following steps:
A. with bolt by ring flange (4) and tower body main material Flange joint;
B. coaster is used to lift by crane concrete by the sling point (1) that rises on cantilever (2);
C. concrete is poured in the main material of tower body by the upper reserved grouting mouth (5) of ring flange (4);
D., after completing the pouring of one section of main material of tower body, the bolt of mounting flange (4) and tower body main material flange is removed, movable mixed Solidifying soil lifting steelframe rises along with the group of iron tower main material is vertical, carries out pouring of next section of iron tower main material concrete;
When e. pouring on next section of main material of tower body, repeat step a, b, c, d, until all main materials have poured.
The concreting method of a kind of concrete filled steel tube steel tower the most according to claim 1, it is characterised in that: step d Described in movable concrete lifting steelframe be made up of steel pipe (3), ring flange (4) and cantilever (2).
The concreting method of a kind of concrete filled steel tube steel tower the most according to claim 1, it is characterised in that: step a Described in ring flange (4) is upper arranges at least 4 kinds of apertures and at least 10 screws.
CN201410762534.8A 2014-12-14 2014-12-14 A kind of concreting method of concrete filled steel tube steel tower Expired - Fee Related CN104533134B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410762534.8A CN104533134B (en) 2014-12-14 2014-12-14 A kind of concreting method of concrete filled steel tube steel tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410762534.8A CN104533134B (en) 2014-12-14 2014-12-14 A kind of concreting method of concrete filled steel tube steel tower

Publications (2)

Publication Number Publication Date
CN104533134A CN104533134A (en) 2015-04-22
CN104533134B true CN104533134B (en) 2017-01-04

Family

ID=52848741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410762534.8A Expired - Fee Related CN104533134B (en) 2014-12-14 2014-12-14 A kind of concreting method of concrete filled steel tube steel tower

Country Status (1)

Country Link
CN (1) CN104533134B (en)

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0633701B2 (en) * 1990-02-19 1994-05-02 日本コンクリート工業株式会社 Embedded nut adapter for steel tube concrete utility pole
CN100462518C (en) * 2007-03-09 2009-02-18 罗定市水泥制品有限公司 Prestressed concrete electrical pole and its production
CN101403256B (en) * 2008-10-22 2012-07-04 宁夏送变电工程公司 Grouting apparatus and method for stand steel pipe
CN101936070A (en) * 2010-09-03 2011-01-05 王亚运 Automatic tower crane concrete pumping system
CN203320963U (en) * 2013-06-19 2013-12-04 中冶天工上海十三冶建设有限公司 Detachable discharging cylinder for concrete casting
CN103469894B (en) * 2013-09-29 2016-02-17 天津二十冶建设有限公司 A kind of servicing unit for steel frame columns jacking grouting and using method thereof
CN103510702B (en) * 2013-09-29 2016-01-20 广州建筑股份有限公司 Steel core concrete column pin type concrete pouring construction method

Also Published As

Publication number Publication date
CN104533134A (en) 2015-04-22

Similar Documents

Publication Publication Date Title
CN104746422A (en) Bridge prefabricated hollow pier column post-poured connecting structure and construction method
CN206233596U (en) Building block exterior wall constructional column concrete casting device
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN203200771U (en) Connection structure for pile extension top and bearing platform
CN201883746U (en) Base of movable high-voltage wire pole
CN104727546A (en) Method for using aluminum alloy form board to pour concrete floor and transmission hole mould of method
CN104533134B (en) A kind of concreting method of concrete filled steel tube steel tower
CN204780928U (en) Major diameter bored concrete pile concrete first set groundwater increment controlling means
CN109763658A (en) A kind of support device and its construction method for arrangement material distributing machine in elevator
CN103362123A (en) Reverse Y-shaped filling pile and construction method thereof
CN203514341U (en) Mold supporting structure for concrete foundation hole of large device
CN204139190U (en) A kind of Liftable preformed bricks fetal membrane
CN204435200U (en) High ferro prefabricated case beam end-blocking rubber sleeve
CN203004045U (en) Hopper for concrete falling
CN202689569U (en) Concrete pouring hopper
CN202108042U (en) Unbonded back tension pre-stress stiffening core composite pile
CN201883695U (en) Spherical net rack vertical jacking equipment
CN205530400U (en) Batter pile test model steel reinforcement cage cushion inclines
CN202500140U (en) Simple concrete conical water blocking plug device
CN205012336U (en) Area is pile driver of feed bin down
CN205012326U (en) A double -deck lower equipment
CN204687076U (en) The mixed earth stirrer of a kind of skyscraper
CN204875839U (en) Mould is pour on iron tower basis
CN203905025U (en) Foundation pit supporting wall with special-shaped reinforced concrete and cement soil separately arranged
CN203626243U (en) Transmission hole mould for pouring concrete floor slab through aluminum alloy formworks

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 450007 Zhengzhou Zhongyuan Road, Henan, No. 212

Patentee after: China Electric Power Construction Group Henan electric survey and Design Institute Co., Ltd.

Address before: 450007 Zhengzhou Zhongyuan Road, Henan, No. 212

Patentee before: Hennan Electric Power Survey & Design Institute

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170104

Termination date: 20191214

CF01 Termination of patent right due to non-payment of annual fee