CN104502167A - Multi-functional mold and method for preparing artificial core - Google Patents

Multi-functional mold and method for preparing artificial core Download PDF

Info

Publication number
CN104502167A
CN104502167A CN201410784940.4A CN201410784940A CN104502167A CN 104502167 A CN104502167 A CN 104502167A CN 201410784940 A CN201410784940 A CN 201410784940A CN 104502167 A CN104502167 A CN 104502167A
Authority
CN
China
Prior art keywords
test specimen
pressure head
rock core
base
threaded hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410784940.4A
Other languages
Chinese (zh)
Other versions
CN104502167B (en
Inventor
金志远
张益东
季明
程亮
李忠
张猛
张明磊
崔满堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201410784940.4A priority Critical patent/CN104502167B/en
Publication of CN104502167A publication Critical patent/CN104502167A/en
Application granted granted Critical
Publication of CN104502167B publication Critical patent/CN104502167B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sampling And Sample Adjustment (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

The invention discloses a multi-functional mold and a method for preparing an artificial core. The mold comprises a test piece pressure head, core pieces, a base and a hoop, wherein the core pieces are aligned to form a hollow cylindrical inner cavity; the hoop is adaptive to the outer part of the core piece; a base hole is formed in the base and the base hole is adaptive to the outer part of each core piece; the test piece pressure head is adaptive to the cylindrical inner cavity, scales are arranged on the test piece pressure head, a threaded hole is formed in the center position of one end surface of the test piece pressure head, a flat nut and a bore log are matched with the threaded hole, and threads matched with the threaded hole are formed at one end of the flat nut and one end of the pore log. When the artificial core is prepared, materials are weighed twice, the weight of the materials required by the a single artificial core can be determined, the accurate size can be obtained in a pressing manner by the scales on the test piece pressure head, and the prepared artificial cores are consistent in densities and sizes.

Description

A kind of multifunctional mold and method preparing synthetic core
Technical field
The present invention relates to mould, particularly a kind of making mould of cylindrical standard test specimen and method for making.
Background technology
The mechanical property parameters of material is that the basic data that must provide is carried out in PHYSICAL MODELING OF IN work; In addition, also need to carry out material properties of rock parameter testing in material development performance history.Therefore, production standard test specimen is particularly important with the fracture seepage feature of test material mechanical property parameters or research test specimen quickly and easily.
In manual manufacture standard specimen, there is the deficiency of following three aspects: the first, when adopting pressue device compacting test specimen, often stop for compacting in a certain numerical value a period of time with constant pressure, cannot ensure that sample dimensions is sought unity of standard; Second: before grinding tool poured into by the material of configuration, do not carry out secondary weighing, cannot ensure that the Sample density made is identical; 3rd, it is single that common synthetic core test specimen makes functional die, can not make (non-penetrating) with holes rock core test piece.
Summary of the invention
For the deficiencies in the prior art, the present invention proposes a kind of technical scheme preparing the multifunctional mold of synthetic core.
Prepare a multifunctional mold for synthetic core, comprise test specimen pressure head, rock core lobe, base and clip; The cylindrical cavity of hollow is formed after described rock core lobe alignment; Described clip and rock core lobe external adapter; Described base is provided with base holes, described base holes and rock core lobe external adapter; Described test specimen pressure head and cylindrical cavity adaptation, described test specimen pressure head is provided with scale, test specimen presses the center of first end face to be provided with threaded hole, and be provided with flat nut and Kong Zhu with this threaded hole is supporting, one end of described flat nut and Kong Zhu is provided with the screw thread mated with threaded hole.
Prepare a method for synthetic core, comprise the following steps that order performs:
If the first step prepares synthetic core standard specimen, flat nut is arranged in the threaded hole bottom test specimen pressure head, and ensures that test specimen pressure head bottom surface is smooth; If prepare synthetic core standard specimen with holes, Kong Zhu is arranged in the threaded hole bottom test specimen pressure head;
Second step, by rock core lobe align, make rock core lobe fastening with clip, then rock core lobe put into the base holes of base;
The material mixture ratio that 3rd step, basis set carries out material weighing, and stirs;
Take the material of single test specimen weight in 4th step, the material that obtains from step 3, the material of single test specimen weight is inserted in the cylindrical cavity of hollow, and constantly carry out compacting with compacting instrument inserting in process;
5th step, when the material of single test specimen weight put into completely hollow cylindrical cavity and after carrying out compacting, the rock core lobe that material is housed is taken out from base and is placed on the platen that adds and present a theatrical performance as the last item on a programme, pressue device is provided with above platen, test specimen pressure head is put into the rock core lobe that material is housed, on the material that test specimen pressure head is pressed in cylindrical cavity;
6th step, unlatching add the pressue device on presenting a theatrical performance as the last item on a programme and act on test specimen pressure head, carry out abundant compacting, and observe the scale on test specimen pressure head surface to the material in rock core lobe;
7th step, when the scale mark on test specimen pressure head surface reaches design load, stop pressurization, material is pressed into test specimen;
8th step, test specimen pressure head to be taken off, after test specimen consolidation certain hour, carry out the test specimen demoulding;
After 9th step, the demoulding, test specimen is put and naturally dries in the shade in the cool.
Beneficial effect:
Synthetic core standard specimen of the present invention makes mould several functions, can making artificial rock core cylindrical standard test specimen, carry out uniaxial compressive, uniaxial tension and single shaft shearing resistance experiment, the synthetic core cylindrical standard test specimen making (not penetrating) with holes can be used for again, carry out the uniaxial compressive experiment of fracture seepage;
According to test specimen prepared by the inventive method, owing to having carried out second weighing and being prepared in strict accordance with scale, the deficiency in the past making mould and method can be overcome, ensure the Sample density that makes and measure-alike, this method for making is easy, be easy to operation, has practicality and generalization widely.
Accompanying drawing explanation
Fig. 1 is the structural representation of synthetic core hole cylinder shape standard test specimen mold of the present invention;
Fig. 2 is the structural representation of synthetic core cylindrical standard test piece mould of the present invention.
Embodiment
Below in conjunction with accompanying drawing, the present invention is further described.
As depicted in figs. 1 and 2, a kind of multifunctional mold of synthetic core cylindrical standard test specimen, comprises test specimen pressure head 1, rock core lobe 2, base 3 and clip 4;
Described rock core lobe 2 has 2, and rock core lobe 2 is highly 200mm, and rock core lobe 2 alignment splicing composition cylindrical outer diameter is 60mm, and the diameter forming the cylindrical cavity of hollow is 50mm;
Described clip 4 is made up of two semicircular ring, and clip 4 internal diameter of two semicircular ring compositions is 60mm, lucky and rock core lobe 2 external adapter; Clip 4 there is threaded hole, makes clip fastening with bolt and nut;
Described base 3 is highly 50mm, and the middle part of base 3 is provided with the base holes that internal diameter is 60mm, height 30mm, and described base holes coordinates with rock core lobe 2 outer gap;
The diameter of described test specimen pressure head 1 is 50mm, height 200mm, and test specimen pressure head 1 is adaptive with cylindrical cavity, and belong to clearance fit, test specimen pressure head 1 is provided with scale, the center of test specimen pressure head 1 one end faces is provided with threaded hole 6;
Yi word pattern flat nut and hole post 5 is provided with this threaded hole 6 is supporting, one end of described yi word pattern flat nut and hole post 5 is provided with the screw thread mated with threaded hole 6, wherein, hole post 5 diameter and height can be decided according to the actual requirements, be generally round platform cylindrical, and the diameter of hole post 5 threaded end is less than the diameter of non-threaded end, and hole post 5 is highly generally less than 70mm.
The preparation utilizing apparatus of the present invention to carry out synthetic core comprises the steps:
If the first step prepares synthetic core standard specimen, flat nut is arranged in the threaded hole 6 bottom test specimen pressure head 1, and ensures that test specimen pressure head 1 bottom surface is smooth; If prepare synthetic core standard specimen with holes, hole post 5 is arranged in the threaded hole 6 bottom test specimen pressure head 1;
Second step, rock core lobe 2 to be alignd, make rock core lobe 2 fastening with clip 4, then rock core lobe 2 is put into the base holes of base 3;
The material mixture ratio that 3rd step, basis set carries out material weighing, and stirs;
Take the material of single test specimen weight in 4th step, the material that obtains from step 3, the material of single test specimen weight is inserted in the cylindrical cavity of hollow, and constantly carry out compacting with compacting instrument inserting in process;
5th step, when the material of single test specimen weight put into completely hollow cylindrical cavity and after carrying out compacting, the rock core lobe 2 that material is housed is taken out from base 3 and is placed on the platen that adds and present a theatrical performance as the last item on a programme, pressue device is provided with above platen, test specimen pressure head 1 is put into the rock core lobe 2 that material is housed, on the material that test specimen pressure head 1 is pressed in cylindrical cavity;
6th step, unlatching add the pressue device on presenting a theatrical performance as the last item on a programme and act on test specimen pressure head 1, carry out abundant compacting, and observe the scale on test specimen pressure head 1 surface to the material in rock core lobe 2;
7th step, when the scale mark on test specimen pressure head 1 surface reaches design load, stop pressurization, material is pressed into test specimen;
8th step, test specimen pressure head 1 to be taken off, after test specimen consolidation certain hour, carry out the test specimen demoulding;
After 9th step, the demoulding, test specimen is put and naturally dries in the shade in the cool.
The above is only the preferred embodiment of the present invention; be noted that for those skilled in the art; under the premise without departing from the principles of the invention, can also make some improvements and modifications, these improvements and modifications also should be considered as protection scope of the present invention.

Claims (2)

1. prepare a multifunctional mold for synthetic core, it is characterized in that: comprise test specimen pressure head (1), rock core lobe (2), base (3) and clip (4); The cylindrical cavity of hollow is formed after described rock core lobe (2) alignment; Described clip (4) and rock core lobe (2) external adapter; (3) are provided with base holes to described base, described base holes and rock core lobe (2) external adapter; Described test specimen pressure head (1) is adaptive with cylindrical cavity, described test specimen pressure head (1) is provided with scale, the center of test specimen pressure head (1) end face is provided with threaded hole (6), be provided with flat nut and Kong Zhu (5) with this threaded hole (6) is supporting, one end of described flat nut and Kong Zhu (5) is provided with the screw thread mated with threaded hole (6).
2. prepare a method for synthetic core, it is characterized in that: comprise the following steps that order performs:
If the first step prepares synthetic core standard specimen, flat nut is arranged in the threaded hole (6) of test specimen pressure head (1) bottom, and ensures that test specimen pressure head (1) bottom surface is smooth; If prepare synthetic core standard specimen with holes, Kong Zhu (5) is arranged in the threaded hole (6) of test specimen pressure head (1) bottom;
Second step, by rock core lobe (2) align, make rock core lobe (2) fastening with clip (4), then rock core lobe (2) put into the base holes of base (3);
The material mixture ratio that 3rd step, basis set carries out material weighing, and stirs;
Take the material of single test specimen weight in 4th step, the material that obtains from step 3, the material of single test specimen weight is inserted in the cylindrical cavity of hollow, and constantly carry out compacting with compacting instrument inserting in process;
5th step, when the material of single test specimen weight put into completely hollow cylindrical cavity and after carrying out compacting, the rock core lobe (2) that material is housed is taken out from base (3) and is placed on the platen that adds and present a theatrical performance as the last item on a programme, pressue device is provided with above platen, test specimen pressure head (1) is put into the rock core lobe (2) that material is housed, make test specimen pressure head (1) be pressed on the material in cylindrical cavity;
6th step, unlatching add the pressue device on presenting a theatrical performance as the last item on a programme and act on test specimen pressure head (1), carry out abundant compacting to the material in rock core lobe (2), and observe the scale on test specimen pressure head (1) surface;
7th step, when test specimen pressure head (1) surface scale mark reach design load time, stop pressurization, material is pressed into test specimen;
8th step, test specimen pressure head (1) to be taken off, after test specimen consolidation certain hour, carry out the test specimen demoulding;
After 9th step, the demoulding, test specimen is put and naturally dries in the shade in the cool.
CN201410784940.4A 2014-12-17 2014-12-17 A kind of mould and method for preparing the artificial core with non-penetrating hole Active CN104502167B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410784940.4A CN104502167B (en) 2014-12-17 2014-12-17 A kind of mould and method for preparing the artificial core with non-penetrating hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410784940.4A CN104502167B (en) 2014-12-17 2014-12-17 A kind of mould and method for preparing the artificial core with non-penetrating hole

Publications (2)

Publication Number Publication Date
CN104502167A true CN104502167A (en) 2015-04-08
CN104502167B CN104502167B (en) 2018-04-27

Family

ID=52943586

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410784940.4A Active CN104502167B (en) 2014-12-17 2014-12-17 A kind of mould and method for preparing the artificial core with non-penetrating hole

Country Status (1)

Country Link
CN (1) CN104502167B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105300771A (en) * 2015-11-27 2016-02-03 中国科学院武汉岩土力学研究所 Manufacturing die of low-intensity similar-material standard test pieces
CN108709783A (en) * 2018-05-17 2018-10-26 长江大学 Artificial cores preparation facilities and preparation method thereof
CN109374387A (en) * 2018-09-18 2019-02-22 中国石油大学(华东) Combined central axis, rock core mold and core preparing device and method including it
CN109443908A (en) * 2018-12-28 2019-03-08 机械工业勘察设计研究院有限公司 A kind of indoor model test device and method of the shearing test that drills
CN109459290A (en) * 2018-12-25 2019-03-12 重庆交通大学 A kind of NSCB sample preparation device and its application method for testing compacted cohesive soil I type fracture toughness
CN109556936A (en) * 2018-12-29 2019-04-02 贵州省地质矿产勘查开发局五地质大队 Artificial rock core small-batch manufacturing device
CN114428006A (en) * 2021-12-31 2022-05-03 中国矿业大学 Weak cemented rock sample preparation device and preparation method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1281971A1 (en) * 1985-01-07 1987-01-07 Всесоюзный научно-исследовательский и проектно-конструкторский институт геофизических исследований геологоразведочных скважин Device for preparing block-shaped specimens from core
GB2184835A (en) * 1985-12-19 1987-07-01 Redwood Corex Core container
WO1987004790A1 (en) * 1986-02-08 1987-08-13 Edinburgh Petroleum Development Services Limited Method and apparatus for preparation of rock core samples
FR2953593A1 (en) * 2009-12-08 2011-06-10 Brgm PROCESS FOR PREPARING A CARROT OF CHARCOAL
CN202599725U (en) * 2012-04-25 2012-12-12 广西大学 Disturbed soil cutting ring sample-pressing device
CN102914458A (en) * 2012-10-16 2013-02-06 绍兴文理学院 Sample preparing device for remolded soil direct shear test sample and sample preparing method thereof
CN103543050A (en) * 2013-09-06 2014-01-29 中国石油大学(北京) Preparation mould for manual simulated rock core test piece with central hole
CN203705235U (en) * 2014-01-01 2014-07-09 浙江省建设工程质量检验站有限公司 Static shear sample part instrument

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1281971A1 (en) * 1985-01-07 1987-01-07 Всесоюзный научно-исследовательский и проектно-конструкторский институт геофизических исследований геологоразведочных скважин Device for preparing block-shaped specimens from core
GB2184835A (en) * 1985-12-19 1987-07-01 Redwood Corex Core container
WO1987004790A1 (en) * 1986-02-08 1987-08-13 Edinburgh Petroleum Development Services Limited Method and apparatus for preparation of rock core samples
FR2953593A1 (en) * 2009-12-08 2011-06-10 Brgm PROCESS FOR PREPARING A CARROT OF CHARCOAL
CN202599725U (en) * 2012-04-25 2012-12-12 广西大学 Disturbed soil cutting ring sample-pressing device
CN102914458A (en) * 2012-10-16 2013-02-06 绍兴文理学院 Sample preparing device for remolded soil direct shear test sample and sample preparing method thereof
CN103543050A (en) * 2013-09-06 2014-01-29 中国石油大学(北京) Preparation mould for manual simulated rock core test piece with central hole
CN203705235U (en) * 2014-01-01 2014-07-09 浙江省建设工程质量检验站有限公司 Static shear sample part instrument

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105300771A (en) * 2015-11-27 2016-02-03 中国科学院武汉岩土力学研究所 Manufacturing die of low-intensity similar-material standard test pieces
CN108709783A (en) * 2018-05-17 2018-10-26 长江大学 Artificial cores preparation facilities and preparation method thereof
CN109374387A (en) * 2018-09-18 2019-02-22 中国石油大学(华东) Combined central axis, rock core mold and core preparing device and method including it
CN109459290A (en) * 2018-12-25 2019-03-12 重庆交通大学 A kind of NSCB sample preparation device and its application method for testing compacted cohesive soil I type fracture toughness
CN109443908A (en) * 2018-12-28 2019-03-08 机械工业勘察设计研究院有限公司 A kind of indoor model test device and method of the shearing test that drills
CN109556936A (en) * 2018-12-29 2019-04-02 贵州省地质矿产勘查开发局五地质大队 Artificial rock core small-batch manufacturing device
CN114428006A (en) * 2021-12-31 2022-05-03 中国矿业大学 Weak cemented rock sample preparation device and preparation method
CN114428006B (en) * 2021-12-31 2024-01-30 中国矿业大学 Weak cemented rock sample preparation device and preparation method

Also Published As

Publication number Publication date
CN104502167B (en) 2018-04-27

Similar Documents

Publication Publication Date Title
CN104502167A (en) Multi-functional mold and method for preparing artificial core
CN107941592B (en) Simulation prefabrication experimental method for built-in precisely controlled variable fracture rock
CN105628470A (en) Preparation method of penetrated crack rock mass test specimen based on 3D (three-dimensional) printing technology
CN104003655A (en) Similar material of brittle rock and preparation method thereof
CN103278360B (en) Reserved chamber simulating test piece manufacturing die assembly and method used for manufacturing test piece
CN104198233B (en) Three axle remoulded sample forming method and devices thereof
CN110376039B (en) Device and method for manufacturing prefabricated cracks of standard rock-like sample
CN105067411A (en) Sampling device for laboratory test of sludge solidification treatment and sampling method thereof
CN102866050A (en) Preparation method of irregular easily-broken coal rock block test piece
CN103543048A (en) Preparation mould for standard manual simulated rock core test piece
CN204556375U (en) A kind of concrete crushing strength measures test specimen locating device
CN212301069U (en) Sample preparation mold of three-dimensional fractured rock mass test piece based on 3D printing technology
CN207439782U (en) A kind of Brazil of platform containing crack sample machining device
CN103543050A (en) Preparation mould for manual simulated rock core test piece with central hole
CN203414321U (en) Molding mould of test piece for testing early strength of sprayed concrete
CN109283113B (en) Concrete impermeability test device and test method for eliminating horizontal hoop pressure
CN204514768U (en) Impervious test piece cover mould of concrete cube
CN205719685U (en) A kind of standard cylindrical specimen assembling die containing layer reason
CN207964399U (en) A kind of inorganic binder cylinder specimen molding die trial
CN107817142B (en) Shale dual-medium artificial rock core and preparation method thereof
CN210690180U (en) Quick pressure-bearing forming device for physical similar material test piece
CN210465061U (en) Standard rock sample prefabricated crack manufacturing device
CN208488306U (en) A kind of pervious concrete Special experimental molding machine
CN106338433A (en) Cast section bar biaxially oriented sample die tool used for mechanical test
CN205538396U (en) Well cementation cement stone triaxial test specimen preparation mould

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 221116 Jiangsu province Xuzhou City University Road Copper Mountain China University of Mining and Technology Research Institute

Applicant after: China University of Mining & Technology

Address before: 221116 Research Institute, China University of Mining and Technology, Xuzhou University, Jiangsu, China,

Applicant before: China University of Mining & Technology

CB02 Change of applicant information
CB03 Change of inventor or designer information

Inventor after: Ji Ming

Inventor after: Zhang Yidong

Inventor after: Jin Zhiyuan

Inventor after: Guo Hongjun

Inventor after: Cheng Liang

Inventor after: Li Zhong

Inventor after: Zhang Meng

Inventor after: Zhang Minglei

Inventor after: Cui Mantang

Inventor before: Jin Zhiyuan

Inventor before: Zhang Yidong

Inventor before: Ji Ming

Inventor before: Cheng Liang

Inventor before: Li Zhong

Inventor before: Zhang Meng

Inventor before: Zhang Minglei

Inventor before: Cui Mantang

CB03 Change of inventor or designer information
GR01 Patent grant