CN104495618B - Method for installing underwater overweight member by using small-sized hoisting equipment - Google Patents

Method for installing underwater overweight member by using small-sized hoisting equipment Download PDF

Info

Publication number
CN104495618B
CN104495618B CN201410711618.9A CN201410711618A CN104495618B CN 104495618 B CN104495618 B CN 104495618B CN 201410711618 A CN201410711618 A CN 201410711618A CN 104495618 B CN104495618 B CN 104495618B
Authority
CN
China
Prior art keywords
floating drum
water
injection hole
small
lifting equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410711618.9A
Other languages
Chinese (zh)
Other versions
CN104495618A (en
Inventor
林本华
漆晓宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Construction Engineering Co ltd
Original Assignee
China Gezhouba Group No 6 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 6 Engineering Co Ltd filed Critical China Gezhouba Group No 6 Engineering Co Ltd
Priority to CN201410711618.9A priority Critical patent/CN104495618B/en
Publication of CN104495618A publication Critical patent/CN104495618A/en
Application granted granted Critical
Publication of CN104495618B publication Critical patent/CN104495618B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

A method for installing an underwater overweight member by using small-sized hoisting equipment adopts the small-sized hoisting equipment, and comprises the following steps of: hoisting the component to be installed and the buoy fixed together with the component to be installed to the position below the water surface at the minimum hoisting amplitude and the maximum hoisting arm angle; after the floating barrel is gradually immersed into water, the lifting capacity born by the small-sized hoisting equipment is gradually reduced due to the buoyancy effect of the floating barrel, and the working amplitude of the small-sized hoisting equipment is gradually increased until the small-sized hoisting equipment reaches an installation position; after the member is in place, the float bowl is filled with water, the float bowl is separated from the member, the float bowl is lifted out of the water surface, and the next installation cycle is started. The method for installing the underwater overweight member by using the small-sized hoisting equipment effectively increases the weight of the hoisting member within the working range of the hoisting equipment, namely the working range of the hoisting equipment is remarkably increased when the members with the same weight are hoisted.

Description

A kind of method utilizing small lifting equipment to install super-heavy component under water
Technical field
A kind of method utilizing small lifting equipment to install super-heavy component under water of the present invention, it is adaptable to overweight in the boat engineering of port, super large component lifting installation.
Background technology
In the boat engineering construction of port, when carrying out large-scale component lifting installation, owing to the lifting capacity of crane gear is limited by work range, along with the increase of work range, lifting capacity significantly reduces.Just can complete as a result, it is often necessary to use large-scale crane ship or large-scale land crane to coordinate.Use large-scale crane hoisting equipment installation, costly, positioning difficulty inefficient, waterborne big.Particularly the remotest when engineered locations, when large lifting equipment dispatches difficulty, this tradition hanging method cannot meet construction needs.
Summary of the invention
For solving above-mentioned technical problem, the present invention provides a kind of method utilizing small lifting equipment to install super-heavy component under water, increase effectively the weight of hoisting component in the range of crane gear work range, i.e. when lifting by crane the component of identical weight, significantly increase the work range of crane gear.
The technical scheme that the present invention takes is:
A kind of method utilizing small lifting equipment to install super-heavy component under water, uses small lifting equipment, the duty optimal: minimum lifting amplitude, maximum boom angle, and component to be installed and the floating drum that is fixed together with this component are hoisted to below the water surface;After floating drum is progressively immersed in the water, due to the buoyancy of floating drum, the lifting capacity that small lifting equipment undertakes gradually decreases, and small lifting equipment incrementally increases work range, until it reaches installation position;After component is in place, to floating drum water-filling, floating drum separates with component, and floating drum hangs out the water surface, starts the next one and installs circulation.
A kind of method utilizing small lifting equipment to install super-heavy component under water, comprises the following steps:
1), floating drum is hung on the suspension hook of small lifting equipment, and floating drum of slinging;
2), under floating drum, hang component to be installed, floating drum and component one to be installed are lifted to the water surface that offshore limit is nearest;
3), when floating drum is progressively immersed in the water, small lifting equipment progressively luffing, until meeting the amplitude of installation requirement;
4), component to be installed install and put in place, pull the control line of water injection hole valve above floating drum, in floating drum, fill water, floating drum breaks off relations with component to be installed;
5), floating drum emerge, by water injection hole valve close water injection hole, start the next one rise re-mount circulation.
Described floating drum is provided with four reserved cavitys, and four reserved cavitys are symmetrically arranged in four corners on floating drum top, and reserved cavity arranges relieving device at lowest part.
Water injection hole valve, valve opening device it is provided with bottom described floating drum, water injection hole valve is contact valve, sets rubber water-proof sheet with floating drum contact position, and rubber water-proof sheet is fixed on water injection hole valve (15) inner side, between floating drum (1) and water injection hole valve (15), play sealing effect.Described valve opening device is crank structure, and valve opening device middle part is articulated with on floating drum, and valve opening device one end connects at the switch of water injection hole valve, the valve opening device other end connects with the control line of water injection hole valve, when needing, gently draw control line, open water injection hole valve.
Described breather joint on floating drum is combined fastening, it is ensured that airtight, and this breather end picks out to the place of safety outside the water surface.
Steel pipe runs through floating drum, and control line passes steel pipe, and control line one end is connected to diving boat or on the bank;The control line other end connects water injection hole valve.
A kind of method utilizing small lifting equipment to install super-heavy component under water of the present invention, uses the small lifting equipment such as small crane or small-sized crane ship to coordinate device with float, can complete the lifting installation of super large, super-heavy component under water.The method has played crane gear function to greatest extent, takes full advantage of device resource, flexible operation, construct convenient, accurate positioning, economy, safe and efficient.
Accompanying drawing explanation
Fig. 1 is invention implementation process structural representation;
Fig. 2 is spar structures schematic diagram in invention.
Detailed description of the invention
As shown in Figure 1 and Figure 2, a kind of method utilizing small lifting equipment to install super-heavy component under water,
Use small lifting equipment, component to be installed and the floating drum that is fixed together with this component are hoisted to below the water surface;After floating drum is progressively immersed in the water, due to the buoyancy of floating drum, the lifting capacity that small lifting equipment undertakes gradually decreases, and small lifting equipment incrementally increases work range, until it reaches installation position;After component is in place, to floating drum water-filling, floating drum separates with component, and floating drum hangs out the water surface, starts the next one and installs circulation.
The present invention utilizes floating drum 1 to coordinate small lifting equipment 6 to complete the installation of superduty component lifting under water.Component and floating drum 1 are hoisted to together nearest to meet the position that the depth of water requires and be advisable by small lifting equipment 6 to meet.Floating drum 1 is generally made into cube shaped, and the weight of the buoyancy of floating drum 1 and component 2 to be installed deducts the buoyancy of component 2 itself and matches.Floating drum 1 shell is typically made by the steel plate of thick 4 ~ 6MM, and inner skeleton is lightweight steel construction.
Floating drum 1 is provided with reserved cavity 9, and the making of reserved cavity 9 requires: after floating drum 1 fills water, the gravity of the floatage energy of this reserved cavity 9 just balanced floating cylinder 1.This reserved cavity 9 totally 4, is symmetrically arranged in four corners on floating drum 9 top.Reserved cavity 9 arranges relieving device 17 at lowest part, when this relieving device 17 runs, seals with lid, twists the lid off during maintenance, and emptying may penetrate into the infiltration in cavity 9 in running.
Breather 4 ensures when to floating drum 1 water filling, discharges the air in floating drum 1, it is ensured that water filling smoothly completes, and the general plastic flexible pipe using φ 10 ~ 15MM, the joint on floating drum 1 is combined fastening, it is ensured that airtight.This breather 4 end picks out the place to the outer safety of the water surface 18.
Water injection hole valve 15 is contact valve, sets rubber water-proof sheet with floating drum 1 contact position.Rubber water-proof sheet one end hinged on floating drum 1, the other end takes and is held on floating drum 1.
Valve opening device 14 is crank structure, and middle part is hinged on floating drum 1, and valve opening device 14 one end connects at the switch of water injection hole valve 15, and valve opening device 14 other end connects with the control line 10 of water injection hole valve 15.When needing, gently draw control line 10, open water injection hole valve 15.
Hanging on the suspension hook 3 of small lifting equipment 6 by one end of floating drum 1 by the first suspension ring 12, the other end is connected with component 2 to be installed by the second suspension ring 16.
Floating drum 1 is run through by the steel pipe 10 of φ 80MM, and control line 10 is through steel pipe 10, and control line 10 one end is connected to diving boat or on the bank;Control line 10 other end connects water injection hole valve 15.It is easy to manually hold control line 10 from the water surface and opens the water injection hole valve 15 bottom floating drum.
Concrete enforcement step is as follows:
: small lifting equipment 6 be installed to rockfill dike 7 in place → 2.: floating drum 1 is hung on the suspension hook 3 of small lifting equipment 6, and the floating drum 1 sling → 3.: hang component to be installed 2 → 4. for 1 time at floating drum: floating drum 1 and component 2 one to be installed are lifted to the water surface nearest from rockfill dike 7 bank → 5.: when being progressively immersed in the water until floating drum 1, small lifting equipment 6 progressively luffing, until meeting the amplitude of installation requirement → 6.: component 2 to be installed install put in place → 7.: pull the control line 10 of water injection hole valve 15, water → 8. is filled: component 2 to be installed breaks off relations → 9. in floating drum 1: floating drum 1 emerges → 10.: close water injection hole valve 15, start the next one and re-mount circulation.

Claims (4)

1. one kind utilizes the method that small lifting equipment installs super-heavy component under water, it is characterized in that, use small lifting equipment (6), duty optimal: minimum lifting amplitude, maximum boom angle, is hoisted to below the water surface by component to be installed (2) and the floating drum (1) that is fixed together with this component (2);After floating drum (1) is progressively immersed in the water, due to the buoyancy of floating drum (1), the lifting capacity that small lifting equipment (6) undertakes gradually decreases, and small lifting equipment (6) incrementally increases work range, until it reaches installation position (8);After component (2) is in place, to floating drum (1) water-filling, floating drum (1) separates with component (2), and floating drum (1) hangs out the water surface, starts the next one and installs circulation;Described floating drum (1) bottom is provided with water injection hole valve (15), valve opening device (14), water injection hole valve (15) is contact valve, rubber water-proof sheet is set with floating drum (1) contact position, rubber water-proof sheet is fixed on water injection hole valve (15) inner side, between floating drum (1) and water injection hole valve (15), play sealing effect;Described valve opening device (14) is crank structure, valve opening device (14) middle part is articulated with on floating drum (1), valve opening device (14) one end connects at the switch of water injection hole valve (15), valve opening device (14) other end connects with the control line (10) of water injection hole valve (15), when needing, gently draw control line (10), open water injection hole valve (15).
A kind of method utilizing small lifting equipment to install super-heavy component under water, it is characterised in that described floating drum (1) Being provided with four reserved cavitys (9), four reserved cavitys (9) are symmetrically arranged in four corners on floating drum (1) top, and reserved cavity (9) arranges relieving device (17) at lowest part.
A kind of method utilizing small lifting equipment to install super-heavy component under water, it is characterized in that, the breather (4) joint on floating drum (1) is combined fastening, it is ensured that airtight, and this breather (4) end picks out to outer safe place.
A kind of method utilizing small lifting equipment to install super-heavy component under water, it is characterized in that, steel pipe (10) runs through floating drum (1), and control line (10) passes steel pipe (10), and control line (10) one end is connected to diving boat or on the bank;Control line (10) other end connects water injection hole valve (15).
CN201410711618.9A 2014-12-01 2014-12-01 Method for installing underwater overweight member by using small-sized hoisting equipment Active CN104495618B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410711618.9A CN104495618B (en) 2014-12-01 2014-12-01 Method for installing underwater overweight member by using small-sized hoisting equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410711618.9A CN104495618B (en) 2014-12-01 2014-12-01 Method for installing underwater overweight member by using small-sized hoisting equipment

Publications (2)

Publication Number Publication Date
CN104495618A CN104495618A (en) 2015-04-08
CN104495618B true CN104495618B (en) 2016-09-21

Family

ID=52937100

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410711618.9A Active CN104495618B (en) 2014-12-01 2014-12-01 Method for installing underwater overweight member by using small-sized hoisting equipment

Country Status (1)

Country Link
CN (1) CN104495618B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012188A (en) * 2020-07-22 2020-12-01 海洋石油工程股份有限公司 Method for in-situ dragging and laying down of deepwater abandoned jacket

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2765855Y (en) * 2004-12-14 2006-03-22 覃伟军 Pontoon hoisting apparatus
CN101062751A (en) * 2007-05-31 2007-10-31 何富荣 Beach working hoister
CN102359122A (en) * 2011-10-17 2012-02-22 沈迪州 Method for installing buttress under assistance of buoyant boxes
CN102398856A (en) * 2010-09-02 2012-04-04 Dmc株式会社 Active heave compensation system for crane operated in deep sea
CN103241668A (en) * 2012-02-08 2013-08-14 中国石油化工股份有限公司 Device and method for installing deep sea submarine storage tank

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2765855Y (en) * 2004-12-14 2006-03-22 覃伟军 Pontoon hoisting apparatus
CN101062751A (en) * 2007-05-31 2007-10-31 何富荣 Beach working hoister
CN102398856A (en) * 2010-09-02 2012-04-04 Dmc株式会社 Active heave compensation system for crane operated in deep sea
CN102359122A (en) * 2011-10-17 2012-02-22 沈迪州 Method for installing buttress under assistance of buoyant boxes
CN103241668A (en) * 2012-02-08 2013-08-14 中国石油化工股份有限公司 Device and method for installing deep sea submarine storage tank

Also Published As

Publication number Publication date
CN104495618A (en) 2015-04-08

Similar Documents

Publication Publication Date Title
CN111469993B (en) Self-installation floating type fan foundation anchored by bucket foundation and self-installation method
CN110359843A (en) A kind of suction anchor formula surface layer shaft building device being suitable for deep water exploitation of gas hydrates
CN105460183B (en) Self-floating waterproof cabin and its application method under water
CN110761315B (en) Method for constructing suction anchor by using drilling ship
CN103883273B (en) Utilize saturation diving to support the double crane on ship that the method for standpipe is installed
CN104960644A (en) Auxiliary lifting pontoon and method for lifting underwater object by using the same
CN105775078B (en) Aqueous vapor displacement type underwater equipment auxiliary installation device and installation method
CN103241668A (en) Device and method for installing deep sea submarine storage tank
CN107933843B (en) FDPSO based on separable inner cupola formula anchoring system
CN201566808U (en) Hydraulic control system of dinghy collecting and releasing device for ship use
CN104495618B (en) Method for installing underwater overweight member by using small-sized hoisting equipment
CN113651238B (en) Guiding positioning and buffering device for integral hoisting of offshore wind turbine generator
CN110185057A (en) A kind of tooling and construction method for the lifting staking out of offshore wind farm single-pile foundation steel-pipe pile
CN207049435U (en) Siphon piping water intake transporting and hoisting is with regard to bit platform
CN212243734U (en) Self-installation floating type fan foundation anchored by bucket foundation
RU2539508C1 (en) Independent unit for lifting mineral resources from water zone bottom
CN109774857B (en) Novel lifting device and lifting method for cabin cover at bottom of ship moon pool
CN204265212U (en) A kind of floating drum for installing super-heavy component under water
CN106218814B (en) A kind of suction anchor mechanism for being easy to marine towage to transport and install
CN206766292U (en) Middle-size and small-size submarine handling torpedo new exclusive landing stage
CN216834154U (en) Negative pressure anchorage block body for tension type single point mooring
CN104806763A (en) Base device, sealing cover thereof and mobile offshore platform
CN206557397U (en) A kind of lifting of exploration ship focus array high pressure airgun is with hanging gunwale
CN204785056U (en) Device is changed in maintenance of offshore platform crude oil riser
CN211167294U (en) Operating system for opening and closing moon pool bottom cover

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: Guandu District of Yunnan city in Kunming province 650206 New Asia sports star city international headquarters base business district office building 19

Applicant after: CHINA GEZHOUBA GROUP NO.6 ENGINEERING CO., LTD.

Address before: 443002 Xiling, Hubei Province sheep mountain road, No. 29, No.

Applicant before: CHINA GEZHOUBA GROUP NO.6 ENGINEERING CO., LTD.

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 650217 Building 2, class E industrial building, International Jewelry City (No. 31, Shuntong Avenue), Kunming Export Processing Zone, Kunming Economic and Technological Development Zone, Yunnan Province

Patentee after: China Gezhouba Group Construction Engineering Co.,Ltd.

Address before: 650206 building 19, business office area, Xingdu international headquarters base, New Asia Sports City, Guandu District, Kunming City, Yunnan Province

Patentee before: CHINA GEZHOUBA GROUP NO.6 ENGINEERING Co.,Ltd.