CN104452828B - Basement ramp piping point drain closure processing method - Google Patents

Basement ramp piping point drain closure processing method Download PDF

Info

Publication number
CN104452828B
CN104452828B CN201410616567.1A CN201410616567A CN104452828B CN 104452828 B CN104452828 B CN 104452828B CN 201410616567 A CN201410616567 A CN 201410616567A CN 104452828 B CN104452828 B CN 104452828B
Authority
CN
China
Prior art keywords
steel pipe
ramp
piping
piping point
guiding steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410616567.1A
Other languages
Chinese (zh)
Other versions
CN104452828A (en
Inventor
黄菊华
郑涛
赵海莲
高宓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN YIYE CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
WUHAN YIYE CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN YIYE CONSTRUCTION ENGINEERING Co Ltd filed Critical WUHAN YIYE CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201410616567.1A priority Critical patent/CN104452828B/en
Publication of CN104452828A publication Critical patent/CN104452828A/en
Application granted granted Critical
Publication of CN104452828B publication Critical patent/CN104452828B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a kind of basement ramp piping point drain closure processing method.Comprise the following steps: arranging a cut-off filter water steel pipe as filter round well, drainage steel pipe one end closure at piping mouth, other end back-off is in piping point, in order to the infiltration of periphery is all caused and encloses in well;By guiding steel pipe one end related subgroup in above-mentioned filter round well top;Outside the width of construction basement ramp, dig a sump, guide piping point percolating water into sump by filter round well and guiding steel pipe and collect;Piping point is without carrying out pouring of ramp concrete cushion in time after hydrops, after concrete cushion reaches desired strength, close guiding steel pipe with seal ring steel pipe plug;Then press normal procedure colligation ramp upper reinforcement, pour top concrete.Processing method is the most applicable, it is easy to operation;The process time is short, efficiency is high, can the effectively save construction period;Processing cost is cheap, effective, remarkable in economical benefits.

Description

Basement ramp piping point drain closure processing method
Technical field
The present invention relates to technical field of building construction, particularly relate to a kind of basement ramp piping point drain closure processing method.
Background technology
In basement ramp piping point seepage treatment, frequently with ramp blinding concrete gravity pressure blocking method, if around piping point Soil property the weakest, and ramp blinding concrete thickness is generally about 150mm, the ramp piping point weakness soil body and newly pouring Blinding concrete easily washed away by percolating water, concrete is difficult to molding, it is impossible to blocks piping point completely, affects whole Construct in individual ramp.
Summary of the invention
Present invention aim at providing a kind of basement ramp piping point drain closure processing method, by filter round well and drainage tube Setting, the infiltration of piping point is focused on an outlet, treats that blinding concrete construction in ramp is complete, outlet can be carried out Closure, creates work surface for follow-up working procedure in time, it is ensured that whole construction quality, also saves processing cost simultaneously And the time.
For reaching above-mentioned purpose, use technical scheme as follows:
Basement ramp piping point drain closure processing method, comprises the following steps:
1) arranging a cut-off filter water steel pipe as filter round well at piping mouth, drainage steel pipe one end closure, other end back-off is in piping Point, in order to the infiltration of periphery is all caused and encloses in well;
2) by guiding steel pipe one end related subgroup in above-mentioned filter round well top;One is dug outside the width of construction basement ramp Individual sump, guides piping point percolating water into sump by filter round well and guiding steel pipe and collects;
3) piping point is without carrying out pouring of ramp concrete cushion in time after hydrops, after concrete cushion reaches desired strength, uses Guiding steel pipe is closed by seal ring steel pipe plug;Then press normal procedure colligation ramp upper reinforcement, pour top concrete.
By such scheme, described drainage diameter of steel tube is 300mm, height 50mm below the concrete cushion of ramp.
By such scheme, a diameter of 50mm of described guiding steel pipe, it is embedded in below ramp concrete cushion 50mm.
By such scheme, described guiding steel pipe other end makes screw thread, facilitates seal ring steel pipe plug to seal guiding steel pipe Close.
The beneficial effects of the present invention is:
Processing method is the most applicable, it is easy to operation;The process time is short, efficiency is high, can the effectively save construction period;Processing cost Cheap, effective, remarkable in economical benefits.
Detailed description of the invention
Following example explain technical scheme further, but not as limiting the scope of the invention.
Piping point drain in basement ramp of the present invention closure processing method, process is as follows:
1) arranging a cut-off filter water steel pipe as filter round well at piping mouth, drainage steel pipe one end closure, other end back-off is in piping Point, in order to the infiltration of periphery is all caused and encloses in well;
2) by guiding steel pipe one end related subgroup in above-mentioned filter round well top;One is dug outside the width of construction basement ramp Individual sump, guides piping point percolating water into sump by filter round well and guiding steel pipe and collects;
3) piping point is without carrying out pouring of ramp concrete cushion in time after hydrops, after concrete cushion reaches desired strength, uses Guiding steel pipe is closed by seal ring steel pipe plug;Then press normal procedure colligation ramp upper reinforcement, pour top concrete.
Optimally, drainage diameter of steel tube is 300mm, height 50mm below the concrete cushion of ramp.
Optimally, a diameter of 50mm of guiding steel pipe.
Optimally, guiding steel pipe other end makes screw thread, facilitates seal ring steel pipe plug to close guiding steel pipe.

Claims (2)

1. basement ramp piping point drain closure processing method, it is characterised in that comprise the following steps:
1) arranging a cut-off filter water steel pipe as filter round well at piping mouth, drainage steel pipe one end closure, other end back-off is in piping Point, in order to the infiltration of periphery is all caused and encloses in well;Described drainage diameter of steel tube is 300mm, and drainage steel pipe top height exists 50mm below the concrete cushion of ramp;
2) by guiding steel pipe one end related subgroup in above-mentioned filter round well top;One is dug outside the width of construction basement ramp Individual sump, guides piping point percolating water into sump by filter round well and guiding steel pipe and collects;Described guiding steel pipe is a diameter of 50mm, guiding steel pipe top is embedded in below ramp concrete cushion 50mm;
3) piping point is without carrying out pouring of ramp concrete cushion in time after hydrops, after concrete cushion reaches desired strength, uses Guiding steel pipe is closed by seal ring steel pipe plug;Then press normal procedure colligation ramp upper reinforcement, pour top concrete.
2. piping point drain in basement ramp blocks processing method as claimed in claim 1, it is characterised in that described guiding steel pipe is another Screw thread is made in outer one end, facilitates seal ring steel pipe plug to close guiding steel pipe.
CN201410616567.1A 2014-10-31 2014-10-31 Basement ramp piping point drain closure processing method Active CN104452828B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410616567.1A CN104452828B (en) 2014-10-31 2014-10-31 Basement ramp piping point drain closure processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410616567.1A CN104452828B (en) 2014-10-31 2014-10-31 Basement ramp piping point drain closure processing method

Publications (2)

Publication Number Publication Date
CN104452828A CN104452828A (en) 2015-03-25
CN104452828B true CN104452828B (en) 2016-08-24

Family

ID=52899528

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410616567.1A Active CN104452828B (en) 2014-10-31 2014-10-31 Basement ramp piping point drain closure processing method

Country Status (1)

Country Link
CN (1) CN104452828B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339086B (en) * 2018-10-17 2021-01-19 中国一冶集团有限公司 Concrete underwater bottom sealing cover for piping and using method
CN110747873A (en) * 2019-11-22 2020-02-04 上海宝冶集团有限公司 Device for sealing post-pouring strip piping and construction method
CN111206610A (en) * 2020-01-16 2020-05-29 龙元建设集团股份有限公司 Construction method for treating piping of exploration hole of foundation pit by curtain grouting method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100387118C (en) * 2005-07-28 2008-05-14 上海交通大学 Installation for isolating and venting spring water
KR101434914B1 (en) * 2012-05-15 2014-11-03 송현기 Permanent drain system and construction method thereof
CN103643690A (en) * 2013-12-12 2014-03-19 南京工业大学 Deep foundation pit exploration hole water burst treatment method
CN103967028A (en) * 2014-05-27 2014-08-06 江苏南通三建集团有限公司 Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure
CN203855977U (en) * 2014-05-28 2014-10-01 武汉一冶建筑安装工程有限责任公司 Underground piping flow-diversion and pressure-reduction treatment device

Also Published As

Publication number Publication date
CN104452828A (en) 2015-03-25

Similar Documents

Publication Publication Date Title
CN202047416U (en) Well sealing device of pressure-reducing and dewatering well at elevator well pit
CN104452828B (en) Basement ramp piping point drain closure processing method
CN204552818U (en) The drainage system of ditch, side, anti-tunnel bottom leaky
CN104196562B (en) Drainage structure for controlled drainage of tunnel and tunnel drainage system with same
CN103821114B (en) A kind of reservoir culvert method for blocking discarded under seepage pressure effect
CN104278666A (en) Bag-packaged plastic drainage device
CN104404960B (en) A kind of underground diaphragm wall seam grouting device and constructional method
CN204080839U (en) A kind of Yield rainfall relation device
CN207469277U (en) The quick slip casting plugging device of diaphram wall leakage point in a kind of foundation pit
CN203856208U (en) Basement exterior wall concrete curing device
CN105019941B (en) Composite, water-drain blind pipe can be safeguarded
CN207452927U (en) Caisson drainage arrangement in a kind of super foundation
CN205259200U (en) Foundation ditch confined aquifer precipitation well plugging device
CN201599459U (en) Non-return drainer
CN208917857U (en) A kind of tool that shuts off at round sump foundation pit bottom
CN204282366U (en) A kind of diaphragm wall seam grouting device
CN209941710U (en) Heavy-pressure reverse filtering tool for treating piping phenomenon of foundation pit
CN204041082U (en) The discharge structure of tunnel limited drainage
CN103774619A (en) Quick processing device for large-flow water leakage hole in concrete body
CN203684667U (en) Mould for floor pipeline preformed hole
CN202954851U (en) Decompression and drainage device of wall
CN206070548U (en) Deep foundation pit precipitation manhole cover plate external member
CN205475290U (en) Big yield precipitation well plugging device
CN204475355U (en) Plugging structure
CN204126138U (en) Accessible roof sloping layer flat raft exhaust plant

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant