CN104392276A CN201410639266.0A CN201410639266A CN104392276A CN 104392276 A CN104392276 A CN 104392276A CN 201410639266 A CN201410639266 A CN 201410639266A CN 104392276 A CN104392276 A CN 104392276A
Authority
CN
China
Prior art keywords
assessment
planning
subregion
distribution network
comprehensive
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410639266.0A
Other languages
Chinese (zh)
Inventor
刘瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410639266.0A priority Critical patent/CN104392276A/en
Publication of CN104392276A publication Critical patent/CN104392276A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Public Health (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a power distribution network evaluation planning method. The method specifically comprises three major steps of planning scheme formation, comprehensive evaluation and zonal statistics, and then the whole evaluation statistical method is completed at last. In the specific implementation process, data items used by the method are prepared firstly, and then comprehensive evaluation planning is started in an invoking order from planning scheme formation to comprehensive evaluation and to zonal statistics. The power distribution network evaluation planning method is mainly used for solving the problem of a new zonal partitioning way in the planning process. However, the problem can be discovered more visually by virtue of the comparison of results after the comprehensive evaluation so as to better direct the planning result.

Description

A kind of power distribution network assessment planing method
Technical field
The present invention relates to a kind of power distribution network assessment planing method, belong to power industry power distribution network assessment technology field.
Background technology
Power distribution network is the ingredient of electric system, whether power distribution network running well depends on the Plan and design whether science of power distribution network, whether economical rationality, for the power supply enterprise that fixed assets yield is huge, distribution network planning is operated in the survival and development of power supply enterprise and plays conclusive effect all the time, be the important base of power network development, its level and quality directly have influence on the security of mains supply, reliability and economy level.But the evaluation measures in existing electrical network in planning process mostly is each index classification to carry out, and comprehensively can not analyze consideration; Again because the definition and statistics increased different electricity consumption divisional type planned in directive/guide by new state's net " 12 ", original statistical will adjust.Need to modify to meet the planing method constantly changed to existing planing method based on above 2.
Traditional power distribution network assessment is mainly from individual event assessments such as reliability, security, power supply qualitys, and the mode that the method for this invention utilizes various index comprehensive to carry out weighing gives objective, comprehensive, comprehensive quality of power supply evaluation, this planing method is improved method according to state's net " 12 " planning directive/guide simultaneously, adds the concept of subregion in planning process in the past.Thus the planning needs that this planing method is more realistic.
Summary of the invention
It is single that the inventive method is intended to solve original appraisal procedure pattern in the new planning process of power distribution network, the problems such as planning efficiency is low.
For achieving the above object, technical scheme of the present invention is as follows:
A kind of power distribution network assessment planing method, specifically comprise programme formation, comprehensive assessment and subregion statistics three large steps, finally complete whole assessment statistical method, wherein each step is as follows:
(1) programme is formed:
This function mainly carries out substation site selection to present situation electrical network, self routing between high pressure electrical network station, and the programme of low-voltage distribution network self routing is formulated, and programme is combined with map simultaneously and carries out visual deployment.Specifically comprise:
(1a) load prediction: native system mainly applies saturation load forecasting, saturation loading is the load scale of need for electricity saturation stage, is the new ideas proposed in Electric Power Network Planning.The research of existing saturation load forecasting mainly concentrates on the saturation load forecasting of City-level load, and the saturation load forecasting that the partition load that still lacks to power is object is applied.Apply this function and will carry out load prediction to subregion, and bear each power supply zone load prediction results.
(1b) Bus stop planning: Bus stop planning depends on load prediction, the block that planning unit is different from the past, but power supply zone is planned, based on load prediction results, to each power supply zone be analyzed to build the capacity of the quantity of transformer station and transformer station's inside main transformer, finally by substation planning on the map of reality.
(1c) high pressure distribution planning: high pressure distribution planning is then select different two electric pressures of high pressure distribution, and then by transformer stations all between analysis two electric pressures, program results is then the automatic layout of different substation being carried out circuit.This function will consider that the comprehensive practical factor such as existing circuit, N-1, line load rate carries out suitable circuit type selecting and deployment.
(1d) low-voltage distribution network planning: low-voltage distribution network planning then carries out automatic connecting to 10KV low-voltage distribution network circuit to distribution transforming, and the prerequisite of this functional realiey depends on the load data of distribution transforming.During planning, main line and distribution transforming are carried out automatic connecting.
(2) comprehensive assessment: multiple index to be assessed is mainly carried out comprehensively by comprehensive assessment function, after assessment, assessment result is carried out integrating and formed different year, different program results rack index contrast, to different single project evaluation than ever, this function has more comprehensive, intuitively can find out the quality of program results, and standby directive significance is had more to reality.Specifically comprise:
(2a) Reliability Evaluation: the basic thought of reliability assessment computing method is that research is to picture with load point, search for all to the influential equipment of this load point tool, and the impact after its fault of position analysis residing for faulty equipment, frequency of power cut and the power off time of load point caused.When analyzing each load point, the equipment calculated is only relevant to this load, and the fault analysis of unrelated equipment is all skipped over, and will greatly reduce the consumption of calculating like this.Searching method adopts the recursive algorithm of depth-first.
(2b) evaluation of power supply capability: this function will provide to be assessed its power supply capacity selected critic network model and load level, relate to the aspects such as Load flow calculation, main transformer capacity-load ratio, layout of roads load factor, low-voltage circuit radius of electricity supply, and provide the power supply capacity index summarized results of this electrical network.
(2c) power supply quality assessment: power supply quality assessment is mainly added up the theoretical pressure drop of circuit, thus counts the line theory pressure drop qualification rate after planning.
(2d) power supply economics assessment: power supply economics assessment is mainly added up network loss in electrical network after planning, and network loss is made up of transformer loss and line loss two parts.Result of calculation will list the meritorious computed losses of transformer active computed losses and circuit respectively.
(2e) short-circuit current assessment: short-circuit current assessment is a function of subregion internal short-circuit level being carried out to quantitative evaluation, and evaluation object is circuit and transformer, result will list respective short-circuit current and whether out-of-limit situation.
(2f) N-1 assessment: N-1 assessment will be done percent of pass to transformer and outlet in all transformer stations and detect, and then count opposite equip. further for the circuit passed through, transformer.
(3) subregion statistics:
Subregion statistical function, then in planning, carry out after comprehensive assessment function, follows the definition carrying out different subregion according to load type difference belonging to power supply area, and combines assessment to the subregion after definition and program results is added up, and finally bears subregion statistical report.
Unijunction fruit is divided into export and two Comparative result in report the test.Unijunction fruit export main with subregion be dividing unit to the comprehensive assessment result index in subregion by each classification indicators formatted output; Two Comparative result is then pressed two kinds of different results, and a point index is compared, and then deck watch is exported, and for clear result of checking comparison, thus more easily draws the good and bad degree of different program results.
This beneficial effect of the invention is: patent of the present invention is mainly used to solve in planning process with a point Division new paragon.And Comparative result can be pinpointed the problems place more intuitively after comprehensive assessment, thus better guiding plan result.
" formation of programme " function in this method, more quickly the large amount of complex data in a larger electrical network can be carried out the calculating of robotization, thus draw a planning cloth station, wiring result visualization result, solve the problem that artificial manually planning amount of calculation is large in the past preferably.
" comprehensive assessment " function in this method, " N-1 assessment " will find not possess the feeder line turning power supply capacity better and be shown, for adjusting new main transformer capacity or feeder line connected mode." evaluation of power supply capability ", " power supply quality assessment ", " Reliability Evaluation " whether, by qualified for the power supply capacity and quality better judging the rear new electrical network of planning, whether the electrical network cooked up is reliable." short-circuit current assessment " can solve the problem of circuit selection type number discontented sufficient actual requirement in planning process.Its comprehensive assessment is then summarized from comprehensive angle to program results, instructs preferably to planning.
Form with subregion is added up by " subregion statistics " function in this method, thus solves the subregion statistical requirements in new planning, different program results can be carried out thinner datumization comparison simultaneously, more convincing to the quality of result.
Embodiment
Below in conjunction with embodiment, the specific embodiment of the present invention is described, better to understand the present invention.
Embodiment
Power distribution network assessment planing method in the present embodiment, first data item used to this method in concrete implementation process prepares, then will start " comprehensive assessment planning ", the order called is " formation of programme "-> " comprehensive assessment "-> " subregion statistics "." formation of programme " data to input are added up, and carry out load prediction to partition data, and then to carry out Bus stop planning result be transformer station's distribution plan on subregion in each block.Again carry out high pressure distribution planning, by forming the self routing between high pressure Liang Ge electric pressure transformer station, finally carrying out low-voltage distribution network planning, by the automatic subordinate of the circuit of minimum voltage grade to distribution transforming, completing whole planning.The result data that " comprehensive assessment " will utilize after planning, then respectively from " N-1 assessment ", " evaluation of power supply capability ", " power supply quality assessment ", " Reliability Evaluation ", analysis and evaluation is carried out to data in aspects such as " short-circuit current assessments ", right assessment result done one and gathers, and carry out pointing out or providing suggestion for gathering information, form comprehensive assessment report." report the test output " compares assessment result, carries out statistical, finally export analysis report from the angle of data subitem to every good and bad degree.
The above is the preferred embodiment of the present invention; it should be pointed out that for those skilled in the art, under the premise without departing from the principles of the invention; can also make some improvements and modifications, these improvements and modifications are also considered as protection scope of the present invention.

Claims (5)

1. a power distribution network assessment planing method, is characterized in that: specifically comprise programme formation, comprehensive assessment and subregion statistics three large steps, finally complete whole assessment statistical method, wherein each step is as follows:
(1) programme is formed: this function mainly carries out substation site selection to present situation electrical network, self routing between high pressure electrical network station, and the programme of low-voltage distribution network self routing is formulated, and programme is combined with map simultaneously and carries out visual deployment;
(2) comprehensive assessment: multiple index to be assessed is mainly carried out comprehensively by comprehensive assessment function, after assessment, assessment result is carried out integrating and formed different year, different program results rack index contrast, to different single project evaluation than ever, this function has more comprehensive, intuitively can find out the quality of program results;
(3) subregion statistics: subregion statistical function then carries out after planning, comprehensive assessment function, follow and carry out the definition of different subregion according to load type difference belonging to power supply area, and the subregion combination assessment after definition and program results are added up, finally bear subregion statistical report.
2. power distribution network assessment planing method according to claim 1, is characterized in that: described programme forms concrete function and comprises: (1a) load prediction; (1b) Bus stop planning; (1c) high pressure distribution planning; (1d) low-voltage distribution network planning.
3. power distribution network assessment planing method according to claim 1, is characterized in that: described comprehensive assessment concrete function comprises: (2a) Reliability Evaluation; (2b) evaluation of power supply capability; (2c) power supply quality assessment; (2d) power supply economics assessment; (2e) short-circuit current assessment; (2f) N-1 assessment.
4. power distribution network assessment planing method according to claim 1, is characterized in that: in described subregion statistics, is divided into unijunction fruit to export and two Comparative result in report the test; Unijunction fruit export main with subregion be dividing unit to the comprehensive assessment result index in subregion by each classification indicators formatted output; Two Comparative result is then pressed two kinds of different results, and a point index is compared, and then deck watch is exported, and for clear result of checking comparison, thus more easily draws the good and bad degree of different program results.
5. the power distribution network assessment planing method according to Claims 1-4, it is characterized in that: the concrete implementation process of described method is: data item first used to this method prepares, then will start " comprehensive assessment planning ", the order called is " formation of programme "-> " comprehensive assessment "-> " subregion statistics ";
Described " formation of programme " data to input are added up, and carry out load prediction to partition data, and then to carry out Bus stop planning result be transformer station's distribution plan on subregion in each block; Again carry out high pressure distribution planning, by forming the self routing between high pressure Liang Ge electric pressure transformer station, finally carrying out low-voltage distribution network planning, by the automatic subordinate of the circuit of minimum voltage grade to distribution transforming, completing whole planning;
The result data that described " comprehensive assessment " will utilize after planning, then respectively from " N-1 assessment ", " evaluation of power supply capability ", " power supply quality assessment ", " Reliability Evaluation ", analysis and evaluation is carried out to data in " short-circuit current assessment " aspect, right assessment result done one and gathers, and carry out pointing out or providing suggestion for gathering information, form comprehensive assessment report;
Described " report the test output " compares assessment result, carries out statistical, finally export analysis report from the angle of data subitem to every good and bad degree.
CN201410639266.0A 2014-11-13 2014-11-13 Power distribution network evaluation planning method Pending CN104392276A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410639266.0A CN104392276A (en) 2014-11-13 2014-11-13 Power distribution network evaluation planning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410639266.0A CN104392276A (en) 2014-11-13 2014-11-13 Power distribution network evaluation planning method

Publications (1)

Publication Number Publication Date
CN104392276A true CN104392276A (en) 2015-03-04

Family

ID=52610176

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410639266.0A Pending CN104392276A (en) 2014-11-13 2014-11-13 Power distribution network evaluation planning method

Country Status (1)

Country Link
CN (1) CN104392276A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104680340A (en) * 2015-03-30 2015-06-03 国家电网公司 Distribution network planning method and system
CN105303259A (en) * 2015-11-06 2016-02-03 国网上海市电力公司 Gridding concept based power distribution network planning management method
CN109818350A (en) * 2019-03-26 2019-05-28 深圳市九众能源科技有限公司 A kind of electric energy intelligent management and its management system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101320449A (en) * 2008-07-17 2008-12-10 上海电力学院 Power distribution network estimation method based on combination appraisement method
CN103426120A (en) * 2013-04-24 2013-12-04 华北电力大学 Medium and low voltage power distribution network comprehensive evaluation method based on reliability
CN105095971A (en) * 2014-05-07 2015-11-25 国网山东省电力公司泰安供电公司 Comprehensive assessment planning method based on power distribution network subareas

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101320449A (en) * 2008-07-17 2008-12-10 上海电力学院 Power distribution network estimation method based on combination appraisement method
CN103426120A (en) * 2013-04-24 2013-12-04 华北电力大学 Medium and low voltage power distribution network comprehensive evaluation method based on reliability
CN105095971A (en) * 2014-05-07 2015-11-25 国网山东省电力公司泰安供电公司 Comprehensive assessment planning method based on power distribution network subareas

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104680340A (en) * 2015-03-30 2015-06-03 国家电网公司 Distribution network planning method and system
CN105303259A (en) * 2015-11-06 2016-02-03 国网上海市电力公司 Gridding concept based power distribution network planning management method
CN109818350A (en) * 2019-03-26 2019-05-28 深圳市九众能源科技有限公司 A kind of electric energy intelligent management and its management system

Similar Documents

Publication Publication Date Title
CN105095971A (en) Comprehensive assessment planning method based on power distribution network subareas
CN108318782B (en) Power distribution network fault area identification method based on network topology and distribution transformer power failure information
CN100595990C (en) Method for configuring PMU taking regard of high risk cascading failure path
CN107730093B (en) System and method for power grid accident re-routing path
CN106058876B (en) Consider the dynamic reactive Site Selection analysis method and system of Enhancement of Transient Voltage Stability
CN103607042B (en) The distribution network failure processing method of long fault indicator for overhead lines towards outskirts of a town
CN104156835A (en) Wide-area distributed integrated topology analysis method for large power grid
CN102290811B (en) Method for evaluating accident prearranged plan and running way
CN105069692A (en) Accurate power grid safety risk assessment method
CN103996147A (en) Comprehensive evaluation method for power distribution network
CN105205590A (en) Method and system for analyzing health state of transformer
CN102983594A (en) Control method of grid closed loop operation impact current
CN109492874A (en) A kind of decision-making technique of three levels power distribution network investment decision system
CN104166944B (en) A kind of grid switching operation bill automatic generation method of railway substation
CN103500999B (en) Low voltage distribution area power supply radius optimization method based on real-time loss
CN103544652A (en) Power grid industry classification load automatic statistical method and system
CN106526468A (en) Breaker state detection method based on waveform characteristics identification
CN106327081B (en) Distribution network project reliability benefit evaluation method based on life cycle
CN108053095A (en) A kind of electrical energy power quality disturbance affair character extracting method and system
Xie et al. Efficiency evaluation of China's provincial power systems based on the dynamic network slacks-based measure model
CN104392276A (en) Power distribution network evaluation planning method
CN106447209A (en) Determination method and device for evaluation factor of power distribution network project
CN115965258A (en) Gridding platform management method, system, terminal device and storage medium
CN107453354A (en) A kind of weak link recognition methods of power distribution network
CN107944659A (en) A kind of substation supervisory control system auto report completing method and apparatus

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150304

RJ01 Rejection of invention patent application after publication