CN104328920B - Construction material carrying method - Google Patents

Construction material carrying method Download PDF

Info

Publication number
CN104328920B
CN104328920B CN201410510071.6A CN201410510071A CN104328920B CN 104328920 B CN104328920 B CN 104328920B CN 201410510071 A CN201410510071 A CN 201410510071A CN 104328920 B CN104328920 B CN 104328920B
Authority
CN
China
Prior art keywords
level
hoist engine
translating trolleys
track
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410510071.6A
Other languages
Chinese (zh)
Other versions
CN104328920A (en
Inventor
王成武
王健
单宏伟
陈耀毅
龚家军
赵祺
谢良兵
吴云飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
China Construction Fifth Engineering Bureau Co Ltd Dongguan Branch
Original Assignee
China Construction Fifth Engineering Bureau Co Ltd
China Construction Fifth Engineering Bureau Co Ltd Dongguan Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Engineering Bureau Co Ltd, China Construction Fifth Engineering Bureau Co Ltd Dongguan Branch filed Critical China Construction Fifth Engineering Bureau Co Ltd
Priority to CN201410510071.6A priority Critical patent/CN104328920B/en
Publication of CN104328920A publication Critical patent/CN104328920A/en
Application granted granted Critical
Publication of CN104328920B publication Critical patent/CN104328920B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Construction material carrying method, comprises the steps: that step A, hanging device are built, and it includes the following operation of order in no particular order: operation one, build hoisting bracket;Operation two, top of building are provided for the electric block of lifting cross beam;Operation three, be provided on crossbeam lift material hoist engine;Operation four, set up level transhipment track and translating trolleys at material conveying destination floor;Step B, material is lifted on hoist engine, utilizes hoist engine by above material lifting to level transhipment track;Step C, material is untied from hoist engine and makes material be placed on translating trolleys;Step D, by translating trolleys level transport material;Step E, utilizing electric block to promote hoisting bracket, level transports track and translating trolleys is transferred to the floor of top, repeat the above steps B is to step D.The present invention can effectively improve the efficiency of material conveying, improves the safety of construction.

Description

Construction material carrying method
Technical field
The present invention relates to technical field of building construction, be specifically related to the conveying side of a kind of construction material Method.
Background technology
At present, when building for skyscraper, it is common that successively build, used builds Building material needs carrying out successively to carry, and existing construction material is typically with the tower of great cantilever Lift up into row lifting.
In architectural process, safety is matter of utmost importance, lifts building material currently with tower crane Time, owing to material is suspended from outside building, there is the risk of bigger falling from high altitude;Additionally, In hoisting process, lifting material first with tower crane, then tower crane swings to corresponding position, Afterwards material being laterally moved to materials station, the whole process used time is longer, and the efficiency of conveying is relative Relatively low, affect the duration.
Summary of the invention
For the deficiencies in the prior art, the purpose of the present invention is intended to provide a kind of construction material defeated Delivery method, it has higher safety, and can improve the efficiency of material conveying.
For achieving the above object, the present invention adopts the following technical scheme that
Construction material carrying method, comprises the steps:
Step A, hanging device are built, it include in no particular order order following operation:
Operation one, pre-buried support seat, support respectively in two opposed inner walls of building elevator Fall arrest support member it is hinged with on Zuo;Hoisting bracket is set in elevator, this hoisting bracket bag Including crossbeam and two vertical beams being oppositely arranged, two vertical beams are individually fixed on the two ends of crossbeam Side, and the outside of vertical beam be provided with along height arrangement multiple teeth groove, elevator two opposed inner walls On support seat fall arrest support member be embedded in respectively in the teeth groove of two vertical beams;
Operation two, top of building are provided for the electric block of lifting cross beam;
Operation three, be provided on crossbeam lift material hoist engine;
Operation four, material conveying destination floor set up level transhipment track, this level transport Track extends to inside elevator, and level transhipment track arranges translating trolleys;
Step B, material is lifted on hoist engine, utilizes hoist engine to lift material to level Above transhipment track;
Below step C, mobile translating trolleys to material, material is untied from hoist engine and makes Material is placed on translating trolleys;
Step D, by translating trolleys level transport material;
Step E, utilize electric block promote hoisting bracket, level is transported track and translation Dolly is transferred to the floor of top, and repeat the above steps B is to step D.
Hoisting bracket includes two crossbeams parallel to each other, and the body bridging of hoist engine is fixed on two The centre position of root crossbeam length direction.
Level transhipment track includes straightway and bend section.
Support to be additionally provided with on seat and limit the stopper slot that vertical beam moves up and down.
The beneficial effects of the present invention is:
Compared to prior art, due to the fact that the mode using vertical lifting material, can be effective The efficiency improving material conveying, thus shorten the construction duration, and the conveying of whole material Process is to complete in pouring the elevator within thing, there is not outdoor work, improves building The safety of construction.
Accompanying drawing explanation
Fig. 1 is the structural representation of hanging device of the present invention;
Fig. 2 is the sectional view of hanging device of the present invention;
Fig. 3 is the zoomed-in view in Fig. 2 at A;
Wherein: 10, elevator;20, hoisting bracket;21, crossbeam;22, vertical beam;30、 Hoist engine;40, level transhipment track;50, translating trolleys;60, seat is supported;61, anti-fall Fall support member.
Detailed description of the invention
Below, in conjunction with accompanying drawing and detailed description of the invention, the present invention is described further:
Building material carrying method, it comprises the steps:
Step A, foundation build hanging device shown in Fig. 1,2,3, and this step specifically includes not The successively following operation of order:
Operation one, in the opposed inner walls of the elevator 10 of building respectively pre-buried support seat 60, Support chain connection on seat 60 and have fall arrest support member 61, permissible when building elevator 10 It is the internal pre-embedding metal part of cement components at elevator 10, then support seat 60 is welded on On pre-buried metalwork;Hoisting bracket 20 is set inside elevator 10, this hoisting bracket 20 Including crossbeam 21 and two vertical beams being oppositely arranged 22, two vertical beams 22 are individually fixed in horizontal stroke Above the two ends of beam 21, and the outside of vertical beam 22 be provided with along short transverse arrangement multiple Teeth groove, makes to be oppositely arranged by the cross-under respectively of two vertical beams 22 in the stopper slot supported on seat 60 Fall arrest support member 61 be plugged in the teeth groove of two vertical beams 22 respectively, thus utilize fall arrest to prop up Support member 61 supports hoisting bracket 20, and when hoisting bracket 20 moves upward, anti-fall The support member 61 that falls rotates towards the direction supporting seat 60, stops moving up hoisting bracket 20, Fall arrest support member 61 supports vertical beam 22 again.In order to ensure stability, prevent vertical beam 22 Beat, the above-mentioned stopper slot supported on seat 60 is consistent with the width of vertical beam 22, is used for limiting Moving up and down of vertical beam 22, it is also possible to be for each with vertical beam 22 adaptive two or more Support seat 60, can either limit moving up and down of vertical beam 22 further, can disperse simultaneously Hoisting bracket 20 and the gravity of material thereon.
Operation two, it is provided for the electric block of lifting cross beam 21 at top of building;
Operation three, be provided on crossbeam 21 lift material hoist engine 30;Above-mentioned hangs Dress support 20 can be to include two crossbeams 21, and the body part of hoist engine 30 is connected across two The centre position of crossbeam 21 length direction;
Operation four, material conveying destination floor set up level transhipment track 40, this level It is internal that transhipment track 40 extends to elevator 10, level transhipment track 40 arranges translation little Car 50;
Step B, material is lifted on hoist engine 30, utilizes hoist engine 30 to be lifted by material Above level transhipment track 40;
Below step C, mobile translating trolleys 50 to material, material is solved from hoist engine 30 Open and make material be placed on translating trolleys 50;
Step D, by translating trolleys 50 level transport material;
Step E, utilize electric block promote hoisting bracket 20, level is transported track 40 with And the floor above translating trolleys 50 transfer, repeat the above steps B is to step D.
In the said method of the present invention, owing to using the mode of vertical lifting material, can be effective Improve the efficiency of material conveying, thus shorten the construction duration, and whole material carried Journey is to complete in the elevator 10 poured within thing, there is not outdoor work, improves and build Build the safety of construction.
It will be apparent to those skilled in the art that can technical scheme as described above and structure Think, make other various corresponding changes and deformation, and all these changes and deformation Within all should belonging to the protection domain of the claims in the present invention.

Claims (3)

1. construction material carrying method, it is characterised in that comprise the steps:
Step A, hanging device are built, it include in no particular order order following operation:
Operation one, pre-buried support seat, support respectively in two opposed inner walls of building elevator Fall arrest support member it is hinged with on Zuo;Hoisting bracket is set in elevator, this hoisting bracket bag Including crossbeam and two vertical beams being oppositely arranged, two vertical beams are individually fixed on the two ends of crossbeam Side, and the outside of vertical beam be provided with along height arrangement multiple teeth groove, elevator two opposed inner walls On support seat fall arrest support member be embedded in respectively in the teeth groove of two vertical beams;Support and go back on seat It is provided with and limits the stopper slot that vertical beam moves up and down, the width of described stopper slot and described vertical beam one Cause;
Operation two, top of building are provided for the electric block of lifting cross beam;
Operation three, be provided on crossbeam lift material hoist engine;
Operation four, material conveying destination floor set up level transhipment track, this level transport Track extends to inside elevator, and level transhipment track arranges translating trolleys;
Step B, material is lifted on hoist engine, utilizes hoist engine to lift material to level Above transhipment track;
Below step C, mobile translating trolleys to material, material is untied from hoist engine and makes Material is placed on translating trolleys;
Step D, by translating trolleys level transport material;
Step E, utilize electric block promote hoisting bracket, level is transported track and translation Dolly is transferred to the floor of top, and repeat the above steps B is to step D.
2. construction material carrying method as claimed in claim 1, it is characterised in that lifting Frame includes two crossbeams parallel to each other, and the body bridging of hoist engine is fixed on two crossbeam length The centre position in direction.
3. construction material carrying method as claimed in claim 1, it is characterised in that level turns Fortune track includes straightway and bend section.
CN201410510071.6A 2014-09-28 2014-09-28 Construction material carrying method Expired - Fee Related CN104328920B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410510071.6A CN104328920B (en) 2014-09-28 2014-09-28 Construction material carrying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410510071.6A CN104328920B (en) 2014-09-28 2014-09-28 Construction material carrying method

Publications (2)

Publication Number Publication Date
CN104328920A CN104328920A (en) 2015-02-04
CN104328920B true CN104328920B (en) 2016-09-28

Family

ID=52403720

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410510071.6A Expired - Fee Related CN104328920B (en) 2014-09-28 2014-09-28 Construction material carrying method

Country Status (1)

Country Link
CN (1) CN104328920B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105565178B (en) * 2015-12-30 2017-07-07 华北冶建工程建设有限公司 Elevator material lifting device
CN112408288A (en) * 2020-09-21 2021-02-26 上海宝冶冶金工程有限公司 Jacking sliding equipment special for blast furnace

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2236477Y (en) * 1995-05-08 1996-10-02 大连第二建筑工程公司 High bulk material lifting apparatus
CN2703832Y (en) * 2004-05-10 2005-06-08 唐裕新 Elevator well creeping formwork hoisting frame
WO2005084185A3 (en) * 2004-02-20 2005-12-29 Otis Elevator Co A device for moving a platform along elevator guide rails
CN1982193A (en) * 2005-12-16 2007-06-20 王�忠 Installation of high-building construction vertical transferring apparatus by elevator well
CN102341336A (en) * 2009-03-06 2012-02-01 通力股份公司 Elevator arrangement and method
CN102459053A (en) * 2009-04-06 2012-05-16 通力股份公司 Method and elevator arrangement

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2236477Y (en) * 1995-05-08 1996-10-02 大连第二建筑工程公司 High bulk material lifting apparatus
WO2005084185A3 (en) * 2004-02-20 2005-12-29 Otis Elevator Co A device for moving a platform along elevator guide rails
CN2703832Y (en) * 2004-05-10 2005-06-08 唐裕新 Elevator well creeping formwork hoisting frame
CN1982193A (en) * 2005-12-16 2007-06-20 王�忠 Installation of high-building construction vertical transferring apparatus by elevator well
CN102341336A (en) * 2009-03-06 2012-02-01 通力股份公司 Elevator arrangement and method
CN102459053A (en) * 2009-04-06 2012-05-16 通力股份公司 Method and elevator arrangement

Also Published As

Publication number Publication date
CN104328920A (en) 2015-02-04

Similar Documents

Publication Publication Date Title
CN205955236U (en) Container formula of taking pulley platform of unloading of encorbelmenting
CN203383148U (en) Span internal lifting device for small prefabricated box girders
CN103774857A (en) Hoisting construction method for fixed hydraulic lifting large-sized equipment in frame
CN103754800A (en) Crane type multi-directional horizontal-movement multifunctional hydraulic lifting construction method
CN104310195A (en) Hoisting cage for hoisting electromechanical device
CN104328920B (en) Construction material carrying method
CN104120701B (en) A kind of construction method of vertical ship lift great good lifting and device
CN105129271A (en) Automatic disassembling device for container rotating lock, system comprising same and disassembling method
CN203247031U (en) Hoisting device for curtain board transporting
CN203820331U (en) Material hoist with built-in steel wire rope
CN204626998U (en) A kind of attached lift scaffold discharging platform
CN104016260A (en) Compartment funnel slipping mounting method and slipping mounting mechanism
CN106276602B (en) A kind of across high ferro Business Line beam body hangs method
CN202810176U (en) Mobile operation platform
CN203333143U (en) Building construction basket
CN202245929U (en) Hoister
CN209353734U (en) For installing the double-track device of curtain wall
RU2016111128A (en) Tower structure
JP4984493B2 (en) Blast furnace demolition method and blast furnace construction method
CN207047703U (en) A kind of beam piece prestressed stretch-draw jack easy device in place
CN205397851U (en) Hanger
CN105436852B (en) Mill housing protective demolition and transportation resources
CN204139067U (en) A kind of mobile formwork reinforced mesh transporter
CN208980193U (en) The curtain wall hanging apparatus of anticollision
CN203213090U (en) Transferring and hoisting device for ship reception chamber of ship lift

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160928

Termination date: 20170928

CF01 Termination of patent right due to non-payment of annual fee