CN104328904A CN201410556445.8A CN201410556445A CN104328904A CN 104328904 A CN104328904 A CN 104328904A CN 201410556445 A CN201410556445 A CN 201410556445A CN 104328904 A CN104328904 A CN 104328904A
Authority
CN
China
Prior art keywords
steel pipe
pipe body
scaffold
wall
fixed sleeving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410556445.8A
Other languages
Chinese (zh)
Inventor
冯建平
冯涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHANGJIAGANG RENHE HIGH-PRECISION TUBE Co Ltd
Original Assignee
ZHANGJIAGANG RENHE HIGH-PRECISION TUBE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHANGJIAGANG RENHE HIGH-PRECISION TUBE Co Ltd filed Critical ZHANGJIAGANG RENHE HIGH-PRECISION TUBE Co Ltd
Priority to CN201410556445.8A priority Critical patent/CN104328904A/en
Publication of CN104328904A publication Critical patent/CN104328904A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a scaffold steel pipe structure. The scaffold steel pipe structure comprises a steel pipe body, wherein a circular structure is arranged at the middle part of the steel pipe body, the steel pipe body is provided with a steel pipe outer wall and a steel pipe inner wall, bulges are arranged at the two ends of the steel pipe body, the bulge structures are rectangular bulge structures, rectangular grooves are formed in the middle of the steel pipe, and when a scaffold is used, the bulges are fit with the grooves to jointly complete the setup of the scaffold. The scaffold steel pipe structure has the beneficial effects that the pipe body wear resistance is high, the corrosion resistance is excellent, the service life is long, the steel pipe structure connection is firm, and the potential safety hazard that a circular pipe cannot be firmly fixed is greatly reduced.

Description

A kind of scaffolding steel pipe structure
Technical field
The present invention relates to steel pipe field, particularly relate to a kind of scaffolding steel pipe structure.
Background technology
Along with the development of society, seamless steel pipe is applied to every field, and scaffold adopts round steel pipe mostly, traditional steel tubular structure also exists to install and connects unsteady defect, at bridge construction, building aspect, scaffolding steel pipe is owing to being rounded face, not firmly easily to cause danger if fixing, serious meeting causes casualties, and current scaffold is regular length scaffold, and Long-Time Service, scaffold requires steel pipe support resistance to deformation, corrosion-resistant.
The invention provides the scaffolding steel pipe structure that a kind of solid drawn tube makes, structure is simple, uses reliable simultaneously.
Summary of the invention
The technical problem that the present invention mainly solves is to provide a kind of scaffolding steel pipe structure, can stable connection between steel pipe and steel pipe, use safety, convenient, and fast, the scaffold length adjustment simultaneously set up is convenient.
A kind of scaffolding steel pipe structure, comprise steel pipe body, described steel pipe body middle part is circular configuration, and described steel pipe body is provided with outer wall of steel pipe and steel pipe inner wall.
Described scaffolding steel pipe structure material can adopt alloy pipe, stainless steel or clad pipe.
Described steel pipe body two ends are provided with projection, and bulge-structure is rectangular preiection structure, is provided with rectangular recess in the middle of steel pipe simultaneously, in scaffold use procedure, protruding and groove cooperatively interacts, and jointly complete the building of scaffold, building speed is fast.
In order to better fixing feet hand cradle, described each steel pipe body two ends are provided with hexagonal fixed sleeving, described hexagonal fixed sleeving is socketed on the outer wall of steel pipe body, be convenient to fixing between scaffold, be outside equipped with fixed sleeving fastening bolt at hexagonal fixed sleeving simultaneously, be convenient to the intensity regulating fixed sleeving.
Between groove and steel pipe body, be provided with clip screw, be convenient to fixing between groove and projection, be convenient to building of scaffold.
The invention has the beneficial effects as follows: scaffolding steel pipe structure body abrasion resistance of the present invention is high, corrosion-resistant excellent, long service life, it is firm that steel tubular structure connects, and greatly reduces circular fixing illusive potential safety hazard.
Accompanying drawing explanation
Fig. 1 is a kind of scaffolding steel pipe structural representation of the present invention.
In accompanying drawing, the mark of each parts is as follows: 1 is steel pipe body, and 2 is outer wall of steel pipe, and 3 is steel pipe inner wall, and 4 is clip screw, and 5 is groove, and 6 is protruding, and 7 is hexagonal fixed sleeving, 8 fixed sleeving fastening bolts.
Detailed description of the invention
Below in conjunction with accompanying drawing, preferred embodiment of the present invention is described in detail, can be easier to make advantages and features of the invention be readily appreciated by one skilled in the art, thus more explicit defining is made to protection scope of the present invention.
Refer to Fig. 1, the embodiment of the present invention comprises:
A kind of scaffolding steel pipe structure, comprise steel pipe body, described steel pipe body middle part is circular configuration, and described steel pipe body is provided with outer wall of steel pipe and steel pipe inner wall.
Described steel pipe material can adopt alloy pipe, stainless steel or clad pipe.
Described steel pipe body two ends are provided with projection, and bulge-structure is rectangular preiection structure, is provided with rectangular recess in the middle of steel pipe simultaneously, and in scaffold use procedure, protruding and groove cooperatively interacts, and jointly completes the building of scaffold.Building speed is fast.
In order to better fixing feet hand cradle, described each steel pipe body two ends are provided with hexagonal fixed sleeving, described hexagonal fixed sleeving is socketed on the outer wall of steel pipe body, be convenient to fixing between scaffold, be outside equipped with fixed sleeving fastening bolt at hexagonal fixed sleeving simultaneously, be convenient to the intensity regulating fixed sleeving.
Between groove and steel pipe body, be provided with clip screw, be convenient to fixing between groove and projection, be convenient to building of scaffold.
The foregoing is only embodiments of the invention; not thereby the scope of the claims of the present invention is limited; every utilize manual of the present invention and accompanying drawing content to do equivalent structure or equivalent flow process conversion; or be directly or indirectly used in other relevant technical fields, be all in like manner included in scope of patent protection of the present invention.

Claims (1)

1. a scaffolding steel pipe structure, it is characterized in that, comprise: steel pipe body, described steel pipe body middle part is circular configuration, described steel pipe body is provided with outer wall of steel pipe and steel pipe inner wall, described steel pipe material adopts alloy pipe, stainless steel or clad pipe, described steel pipe body two ends are provided with projection, bulge-structure is rectangular preiection structure, in the middle of steel pipe, be provided with rectangular recess simultaneously, described each steel pipe body two ends are provided with hexagonal fixed sleeving, described hexagonal fixed sleeving is socketed on the outer wall of steel pipe body, be outside equipped with fixed sleeving fastening bolt at hexagonal fixed sleeving simultaneously, clip screw is provided with between groove and steel pipe body, be convenient to fixing between groove and projection.
CN201410556445.8A 2014-10-20 2014-10-20 Scaffold steel pipe structure Pending CN104328904A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410556445.8A CN104328904A (en) 2014-10-20 2014-10-20 Scaffold steel pipe structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410556445.8A CN104328904A (en) 2014-10-20 2014-10-20 Scaffold steel pipe structure

Publications (1)

Publication Number Publication Date
CN104328904A true CN104328904A (en) 2015-02-04

Family

ID=52403704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410556445.8A Pending CN104328904A (en) 2014-10-20 2014-10-20 Scaffold steel pipe structure

Country Status (1)

Country Link
CN (1) CN104328904A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11350717A (en) * 1998-06-05 1999-12-21 Kawasaki Heavy Ind Ltd Handrail attaching device
CN2575221Y (en) * 2002-10-31 2003-09-24 侯川临 Clamping form fastening
CN201649620U (en) * 2010-02-11 2010-11-24 刘琦 Retractable support connection tie rod
CN204225468U (en) * 2014-10-20 2015-03-25 张家港市人和高精管有限公司 A kind of scaffolding steel pipe structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11350717A (en) * 1998-06-05 1999-12-21 Kawasaki Heavy Ind Ltd Handrail attaching device
CN2575221Y (en) * 2002-10-31 2003-09-24 侯川临 Clamping form fastening
CN201649620U (en) * 2010-02-11 2010-11-24 刘琦 Retractable support connection tie rod
CN204225468U (en) * 2014-10-20 2015-03-25 张家港市人和高精管有限公司 A kind of scaffolding steel pipe structure

Similar Documents

Publication Publication Date Title
CN204357104U (en) Scaffolding steel pipe connector
CN204225468U (en) A kind of scaffolding steel pipe structure
CN204326483U (en) A kind of construction safety scaffold
CN104328904A (en) Scaffold steel pipe structure
CN103615088B (en) Shaped stone material point hanging hang structure
CN204645589U (en) A kind of tool-type builder's jack bracing device
CN204899038U (en) Overcoat straight thread connection structure in reinforcing bar
CN204163197U (en) The cross circumference steel pipe connected node of reinforcing ring is established in a kind of
CN203770869U (en) Industrial corrosion-resistant PP pipe
CN204491422U (en) A kind of variable-sized high-adaptability pier stud anchor ear
CN203758393U (en) Micrometer stand with universal joint
CN209277392U (en) A kind of corrosion resistance steel pipe column for assembled architecture
CN205244060U (en) Novel expand end crab -bolt
CN203961088U (en) For the scaffolding steel pipe linkage of multistory building
CN204531332U (en) A kind of bananas type scaffold
CN204590566U (en) A kind of scaffold fixed connection structure of novel improved
CN203808367U (en) Composite carbon fiber threaded bar
CN103806640A (en) Fastener with good skid resistance
CN203517020U (en) Seamless steel tube
CN210738491U (en) Reducing joint of hollow sucker rod
CN105863246A (en) Three-way connecting piece
CN205421539U (en) Steel structure
CN211289055U (en) Novel water delivery pipe
CN211346502U (en) Rubber sleeve for connecting spray pipe on cooling tower
CN211058285U (en) External scaffold wall connecting piece

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150204