CN104328773B - Entirety built by sea work accommodation platform - Google Patents
Entirety built by sea work accommodation platform Download PDFInfo
- Publication number
- CN104328773B CN104328773B CN201410495428.8A CN201410495428A CN104328773B CN 104328773 B CN104328773 B CN 104328773B CN 201410495428 A CN201410495428 A CN 201410495428A CN 104328773 B CN104328773 B CN 104328773B
- Authority
- CN
- China
- Prior art keywords
- build
- overall
- entirety
- built
- weld
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0039—Methods for placing the offshore structure
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Entirety built by sea work accommodation platform, belong to ocean engineering field, comprise multiple convex module composition, multiple convex module installation drawing divides and carries out welding superposition, finally cause and build entirety, steel plate is strengthened in upper overall top weld horizontal of building, strengthen uniform welding eight hangers on steel plate, on build overall lower weld channel-section steel, on build overall before and after side the first half welding shaped form stainless steel strip, shaped form stainless steel strip is also welded and fixed with reinforcement steel plate, increase overall lifting surface area, on build overall before and after side the latter half weld semicircle steel loop, semicircle steel loop and channel-section steel weld together, prevent lifting rear lower shrinkage deformation, this builds entirety is on the way once built, build more convenient and carry out structural strengthening, making it possess can the condition of integral hoisting, finally carries out disposable lifting and completes, and have employed modular living units embedded model, shorten the time of building overall construction 20%.
Description
Technical field
The present invention relates on extra large work accommodation platform and build entirety, belong to ocean engineering field.
Background technology
Ocean is the resource of various countries of new generation competition, especially petroleum resources, therefore ocean platform development is accelerated day by day, for exploiting marine resource, but extra large work accommodation platform supporting with it develop very slow, especially construction method is still very traditional, on platform, a little builds, construction framework is unreasonable, and therefore efficiency of construction is low, is all a urgent problem.
Summary of the invention
The object of this invention is to provide on extra large work accommodation platform and build entirety.
The problem to be solved in the present invention is that existing upper organizational system makes inefficient deficiency.
For realizing object of the present invention, the technical solution used in the present invention is:
Entirety built by sea work accommodation platform, comprise multiple convex module, the installation of multiple convex module divides according to drawing carries out welding superposition, finally be built into entirety, steel plate is strengthened in upper overall top weld horizontal of building, strengthen uniform welding eight hangers on steel plate, on build overall lower weld channel-section steel, on build overall before and after side the first half welding shaped form stainless steel strip, shaped form stainless steel strip is also welded and fixed with reinforcement steel plate, increase overall lifting surface area, on build overall before and after side the latter half weld semicircle steel loop, semicircle steel loop and channel-section steel weld together, prevent lifting rear lower shrinkage deformation.
Build overall middle part on described and be provided with arch beam.
Described convex module is made up of four cuboids, and four cuboids are Container Dimensions, facilitates the living units of later stage Container Dimensions to propel and enters.
Build plane on the whole on described and be provided with four row's hangers.
Build overall and semicircle steel loop on described, the junction of shaped form stainless steel strip is provided with hex hole, be inserted with hexagon posts in hex hole, hexagon posts two ends are provided with symmetrical back-off, effectively can prevent loosening dropping.
Build on described after integral hoisting, semicircle steel loop and shaped form stainless steel strip are removed, recover original appearance.
Advantage of the present invention is: this builds entirety is on the way once built, build more convenient and carry out structural strengthening, making it possess can the condition of integral hoisting, finally carry out disposable lifting to complete, and have employed modular living units embedded model, shorten the time of building overall construction 20%, market prospects widely should be had.
Accompanying drawing explanation
Overall front view built by the present invention sea work accommodation platform to Fig. 1;
Overall top view built by the present invention sea work accommodation platform to Fig. 2;
Fig. 3 is schematic diagram the present invention sea work accommodation platform being built overall convex pattern block;
The present invention sea work accommodation platform builds overall A-A to sectional view to Fig. 4;
Fig. 5 is structural representation the present invention sea work accommodation platform being built overall hexagon posts 9;
In figure: 1, semicircle steel loop 2, shaped form stainless steel strip 3, hanger 4, reinforcement steel plate 5, channel-section steel 6, arch beam 7, horizontal hanger rod 8, convex module 9, hexagon posts 10, back-off.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is further illustrated.
Entirety built by sea work accommodation platform, comprise multiple convex module 8 to form, multiple convex module 8 installation drawing divides and carries out welding superposition, finally cause and build entirety, steel plate 4 is strengthened in upper overall top weld horizontal of building, strengthen uniform welding eight hangers 3 on steel plate 4, on build overall lower weld channel-section steel 5, on build overall before and after side the first half welding shaped form stainless steel strip 2, shaped form stainless steel strip 2 is also welded and fixed with reinforcement steel plate 4, increase overall lifting surface area, on build overall before and after side the latter half weld semicircle steel loop 1, semicircle steel loop 1 and channel-section steel 5 weld together, prevent lifting rear lower shrinkage deformation.
Build overall middle part on described and be provided with arch beam 6, withholding for settling, increasing the stability played.
Described convex module 8 is made up of four cuboids, four cuboids are Container Dimensions, and square opening size is generally 2.2*2.3 rice, and the degree of depth according to actual needs, facilitate the living units of later stage Container Dimensions to propel to enter, contribute to accelerating construction speed and the replacing in later stage.
Build plane on the whole on described and be provided with four row's hangers 3, increase overall lifting surface area, lift by crane more stable.
Build overall and semicircle steel loop 1 on described, the junction of shaped form stainless steel strip 2 is provided with hex hole, be inserted with hexagon posts 9 in hex hole, hexagon posts 9 two ends are provided with symmetrical back-off 10, effectively can prevent loosening dropping; On build overall and semicircle steel loop 1, the junction of shaped form stainless steel strip 2 also can directly weld, the later stage just needs cutting slowly to remove, and efficiency is low spot a little.
Build on described after integral hoisting, semicircle steel loop 1 and shaped form stainless steel strip 2 are removed, be inserted in outside back-off 10 with steel disc during dismounting and just can have equally extracted, recover original appearance.
Using method of the present invention: above build integral constructing good after, connect horizontal hanger rod 7 with large-scale double marine loop wheel machine by hanger 3 to lift by crane, then be slowly transported on extra large work accommodation platform, then semicircle steel loop 1 and shaped form stainless steel strip 2 are carried out removing, this completes the quick load built, shorten construction period.
Claims (6)
1. entirety built by extra large work accommodation platform, it is characterized in that: comprise multiple convex module (8), the installation of multiple convex module (8) divides according to drawing carries out welding superposition, finally be built into entirety, steel plate (4) is strengthened in upper overall top weld horizontal of building, strengthen upper uniform welding eight hangers (3) of steel plate (4), on build overall lower weld channel-section steel (5), on build overall before and after side the first half welding shaped form stainless steel strip (2), shaped form stainless steel strip (2) is also welded and fixed with reinforcement steel plate (4), increase overall lifting surface area, on build overall before and after side the latter half weld semicircle steel loop (1), semicircle steel loop (1) and channel-section steel (5) weld together, prevent lifting rear lower shrinkage deformation.
2. entirety built by extra large work accommodation platform according to claim 1, it is characterized in that: build overall middle part on described and be provided with arch beam (6).
3. entirety built by extra large work accommodation platform according to claim 1, it is characterized in that: described convex module (8) is made up of four cuboids, and four cuboids are Container Dimensions, facilitates the living units of later stage Container Dimensions to propel and enters.
4. entirety built by extra large work accommodation platform according to claim 1, it is characterized in that: build plane on the whole on described and be provided with four row's hangers (3).
5. entirety built by extra large work accommodation platform according to claim 1, it is characterized in that: build overall and semicircle steel loop (1) on described, the junction of shaped form stainless steel strip (2) is provided with hex hole, hexagon posts (9) is inserted with in hex hole, hexagon posts (9) two ends are provided with symmetrical back-off (10), can effectively prevent from loosening dropping.
6. entirety built by extra large work accommodation platform according to claim 1, it is characterized in that: build after integral hoisting on described, semicircle steel loop (1) and shaped form stainless steel strip (2) are removed, recover original appearance.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410495428.8A CN104328773B (en) | 2014-09-25 | 2014-09-25 | Entirety built by sea work accommodation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410495428.8A CN104328773B (en) | 2014-09-25 | 2014-09-25 | Entirety built by sea work accommodation platform |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104328773A CN104328773A (en) | 2015-02-04 |
CN104328773B true CN104328773B (en) | 2016-04-20 |
Family
ID=52403573
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410495428.8A Expired - Fee Related CN104328773B (en) | 2014-09-25 | 2014-09-25 | Entirety built by sea work accommodation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104328773B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110985754B (en) * | 2019-12-19 | 2021-06-18 | 南通泰胜蓝岛海洋工程有限公司 | Jacket anti-sinking plate with reinforcing structure and integral reinforcing process thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101793019A (en) * | 2010-01-28 | 2010-08-04 | 中国海洋石油总公司 | Combined type movable living module of multifunctional self-elevating supporting platform for ocean oil field |
CN102190065A (en) * | 2010-03-10 | 2011-09-21 | 烟台来福士海洋工程有限公司 | Construction method for ocean platform |
CN203213088U (en) * | 2013-04-17 | 2013-09-25 | 清华大学 | Light composite structure pipe support type ocean platform |
RU2504498C1 (en) * | 2012-12-05 | 2014-01-20 | Общество с ограниченной ответственностью "Научно-производственный центр "Родемос" | Floating platform |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6019368B2 (en) * | 1982-06-23 | 1985-05-16 | 川崎製鉄株式会社 | How to weld and assemble the legs of the Jatsuki Atsushi rig |
-
2014
- 2014-09-25 CN CN201410495428.8A patent/CN104328773B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101793019A (en) * | 2010-01-28 | 2010-08-04 | 中国海洋石油总公司 | Combined type movable living module of multifunctional self-elevating supporting platform for ocean oil field |
CN102190065A (en) * | 2010-03-10 | 2011-09-21 | 烟台来福士海洋工程有限公司 | Construction method for ocean platform |
RU2504498C1 (en) * | 2012-12-05 | 2014-01-20 | Общество с ограниченной ответственностью "Научно-производственный центр "Родемос" | Floating platform |
CN203213088U (en) * | 2013-04-17 | 2013-09-25 | 清华大学 | Light composite structure pipe support type ocean platform |
Also Published As
Publication number | Publication date |
---|---|
CN104328773A (en) | 2015-02-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205254034U (en) | Evaporative pattern casting device | |
CN201172574Y (en) | Precast beam reinforced bar hoisting rack | |
CN104328773B (en) | Entirety built by sea work accommodation platform | |
CN104310235B (en) | Maritime work accommodation platform complete superstructure lifting method | |
CN208197158U (en) | A kind of reinforcing bar tire suspender of precast segment box beam | |
CN206643894U (en) | Flange rack | |
CN205975337U (en) | Braced chain formula arch ring template system architecture | |
CN103072194B (en) | A kind of prefabricated reinforced concrete anticollision barrier mould | |
CN205669210U (en) | Steel building concrete cup-shaped foundation inner bore die carrier | |
CN204659784U (en) | A kind of seal ring electricity produces Suspension hand cart | |
CN205114102U (en) | Frame is deposited, is transported in special use of prefabricated PCF board | |
CN203546612U (en) | Wedge-shaped rail for bridge girder erection machine | |
CN201201112Y (en) | Back side elevating gear of one-side welding two-side moulding welding mechanism | |
CN209299080U (en) | A kind of rotor magnetic pole coil detachment device | |
CN203124593U (en) | Device for cleaning up waste of forklift body stamping parts of forklift | |
CN206189862U (en) | Firm cloth machine guide rail of movable | |
CN202007384U (en) | Connecting device for bottom die and side die of suspended steel box in water | |
CN206144151U (en) | Solid locking device of quick detachable concrete form | |
CN202657862U (en) | Wallboard lift-out device | |
CN205955177U (en) | Novel construct dedicated aluminum alloy template | |
CN207521804U (en) | The guider of rotor rim keyway broaching tool | |
CN208777669U (en) | A kind of elevated operating platform | |
CN204607381U (en) | A kind of superimposed sheet Steel bar hanger | |
CN210366907U (en) | Portable large-scale component roll-over stand | |
CN203448626U (en) | Shelf of process equipment for manufacturing sand boxes for castings |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160420 Termination date: 20180925 |
|
CF01 | Termination of patent right due to non-payment of annual fee |