CN104315083B CN201410571464.8A CN201410571464A CN104315083B CN 104315083 B CN104315083 B CN 104315083B CN 201410571464 A CN201410571464 A CN 201410571464A CN 104315083 B CN104315083 B CN 104315083B
Authority
CN
China
Prior art keywords
wire rope
steel wire
welding
becket bridle
line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410571464.8A
Other languages
Chinese (zh)
Other versions
CN104315083A (en
Inventor
李森
周井华
王雷
俞丽
郭敏
罗庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhenghua Heavy Industries Co Ltd
Original Assignee
Shanghai Zhenghua Heavy Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhenghua Heavy Industries Co Ltd filed Critical Shanghai Zhenghua Heavy Industries Co Ltd
Priority to CN201410571464.8A priority Critical patent/CN104315083B/en
Publication of CN104315083A publication Critical patent/CN104315083A/en
Application granted granted Critical
Publication of CN104315083B publication Critical patent/CN104315083B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16GBELTS, CABLES, OR ROPES, PREDOMINANTLY USED FOR DRIVING PURPOSES; CHAINS; FITTINGS PREDOMINANTLY USED THEREFOR
    • F16G11/00Means for fastening cables or ropes to one another or to other objects; Caps or sleeves for fixing on cables or ropes
    • F16G11/08Fastenings for securing ends of driving-cables to one another, the fastenings having approximately the same diameter as the cables
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Wire Processing (AREA)

Abstract

The invention discloses a kind of steel wire rope welding becket bridle and docking calculation thereof, the docking of different-diameter steel wire rope when connecting, it is achieved connecting of Large-diameter Steel cord for steel wire rope.Its technical scheme is: directly carries out numerical control cutting machine blanking using steel plate mother metal as becket bridle main body, processes steel wire rope by drilling machine and pass through hole in becket bridle main body.Steel wire rope messenger fag end is passed through from welding becket bridle steel wire rope and after hole passes through, is spliced fag end, complete the docking of messenger and steel wire rope, then complete steel wire rope according to wire rope handling technique and connect work.

Description

The docking calculation of steel wire rope welding becket bridle
Technical field
The present invention relates to the technology in crane rope winding system, particularly relate to when steel wire rope connects different straight The technology of wire-diameter steel rope docking.
Background technology
Steel cable winding system is widely used in crane, and particularly in floating crane, steel wire rope used has Diameter is big, length length and need the features such as pretension after connecting, and wirerope diameter is generally at about 60mm, and length exists Between 2000m~7000m.With the construction of some super-huge crane barges, wirerope diameter that winding system uses and Tractive force when connecting is also increasing, the 12000T crane barge manufacturing such as Zhenhua heavy industry, variable-amplitude steel wire rope diameter Reached 22T to pulling force when 78mm, wire rope handling, used in the past in steel wire rope end head welded nut conduct The method of traction fag end can not meet such major diameter and the steel wire rope of pulling force connects.
Content of the invention
The brief overview of one or more aspect given below is to provide to the basic comprehension in terms of these.This general introduction The extensive overview of the not all aspect contemplating, and be both not intended to identify the key of all aspects or determine The qualitative key element also non-scope attempting in terms of defining any or all.Its unique purpose be intended in simplified form to Some concepts going out one or more aspect think the sequence of more detailed description given later.
It is an object of the invention to solve the problems referred to above, provide a kind of steel wire rope welding becket bridle and docking calculation thereof, The docking of different-diameter steel wire rope when connecting for steel wire rope, it is achieved connecting of Large-diameter Steel cord.
The technical scheme is that and present invention is disclosed a kind of steel wire rope welding becket bridle, direct with steel plate mother metal Carry out numerical control cutting machine blanking as becket bridle main body, in becket bridle main body, process steel wire rope by drilling machine pass through hole.
According to the present invention steel wire rope welding becket bridle an embodiment, the model of steel plate mother metal be WDB620E or Q690E。
The invention also discloses the docking calculation of a kind of steel wire rope welding becket bridle, comprising:
The blank blanking step of steel wire rope welding becket bridle: with steel plate as mother metal, utilize numerical control cutting machine blanking, will The appearance and size of welding becket bridle is all cut and is put in place, forms blank;
The machining steps of steel wire rope welding becket bridle: include passing through blank integral marking, steel wire rope hole line, The line of thickness surplus, overall mach process;
The welding step of steel wire rope welding becket bridle: include welding front preparation, tack welding and backing welding, filling and capping The process of weldering;
The messenger threading step of steel wire rope welding becket bridle: carry out steel wire rope and connect.
One embodiment of the docking calculation of the steel wire rope welding becket bridle according to the present invention, at blank integral marking During, weld wedge angle and the semicircle cambered surface of the blank of becket bridle by steel wire rope on the basis of, mark steel wire rope The cross centre line of welding becket bridle;During steel wire rope passes through hole line, with the ten of steel wire rope welding becket bridle On the basis of word center line, mark steel wire rope on becket bridle and pass through the cross centre line in hole, Excircle machining dimension line and school Test line;During the line of thickness surplus, draw on the basis of the baseplane of the blank of steel wire rope welding becket bridle Going out thickness direction cross centre line, then the cross centre line with thickness direction marks thickness direction allowance line And checkout line;During integrated machine processing, pass through according to the steel wire rope that first line size processes on becket bridle Hole, then the two-sided processing thickness surplus at becket bridle, passes through the inside and outside circular arc of hole machined further according to steel wire rope.
One embodiment of the docking calculation of the steel wire rope welding becket bridle according to the present invention, at steel wire rope welding becket bridle In welding step, the process preparing before weldering includes welding the type selecting of becket bridle, steel wire rope end head is processed, it is manual to prepare Arc-welding electrode is as wlding and welding becket bridle process;The process of tack welding and backing welding is will to weld becket bridle Carry out weld preheating after aliging with steel wire rope end head and adjusting vertically, then use manual electric arc welding welding rod to use The method of DC reverse connection carries out tack welding and backing welding;Fill and the process of cosmetic welding is to use manual electric arc welding to use Welding rod uses the method for DC reverse connection to be filled with and cosmetic welding, uses the method control that two-sided hoop symmetry freezes Welding deformation is vertical with steel wire rope end head to ensure after welding becket bridle welding.
One embodiment of the docking calculation of the steel wire rope welding becket bridle according to the present invention, at steel wire rope welding becket bridle In messenger threading step, the size passing through hole according to rope traction pulling force and welding becket bridle steel wire rope selects steel wire Steel wire rope messenger fag end is passed through from welding becket bridle steel wire rope and is spliced fag end after passing through hole, completes to draw by rope messenger Rope and the docking of steel wire rope, then complete steel wire rope according to wire rope handling technique and connect work.
One embodiment of the docking calculation of the steel wire rope welding becket bridle according to the present invention, as the type of the steel plate of mother metal It number is WDB620E or Q690E.
The present invention contrasts prior art a following beneficial effect: the present invention according in winding system in crane often Wirerope diameter, messenger diameter and tractive pulling force, devise steel wire rope welding becket bridle, its scheme has as follows Feature: the 1st, manufactured and designed steel wire rope welding becket bridle, with high-strength steel sheets such as WDB620E, Q690E as mother Material, machining after utilizing numerical control cutting machine blanking.According to wirerope diameter different select different materials and Specification, it is adaptable to multiple Large-diameter Steel cords are docked with messenger.2nd, a kind of Large-diameter Steel cord docking is devised Method, use J607 welding rod that steel wire rope welding becket bridle is welded on major diameter cable wire end end, then will Traction messenger penetrates after the steel wire rope on docking becket bridle passes through hole and is spliced fag end, it is achieved different-diameter steel wire rope Docking.3rd, have employed steel wire rope welding becket bridle and the special welding method of operating of steel wire rope welding, be used for welding rope Ring and the welding of steel wire rope.4th, the steel wire rope banjo fixing butt jointing using steel wire rope welding becket bridle and docking calculation to realize can Bear corresponding tractive force, and wire rope pulley group can be passed through, it is achieved connecting of Large-diameter Steel cord.
Brief description
Figure 1A and 1B shows the structure chart of the preferred embodiment of the steel wire rope welding becket bridle of the present invention.
Fig. 2 shows the flow chart of the preferred embodiment of the docking calculation of the steel wire rope welding becket bridle of the present invention.
Fig. 3 A, 3B show the schematic diagram of the blank blanking of the steel wire rope welding becket bridle of the present invention.
Fig. 4 shows the mach schematic diagram of steel wire rope welding becket bridle.
Fig. 5 shows steel wire rope welding becket bridle and the schematic diagram of steel wire rope welding.
Fig. 6 A, 6B show that messenger and welding becket bridle are spliced the schematic diagram of docking.
Detailed description of the invention
After reading the detailed description that embodiment of the disclosure in conjunction with the following drawings, better understood when this Bright features described above and advantage.In the accompanying drawings, each assembly is not necessarily drawn to scale, and has similar The assembly of correlation properties or feature is likely to be of same or like reference.
Figure 1A and 1B shows the structure of the preferred embodiment of the steel wire rope welding becket bridle of the present invention.Refer to figure 1A and 1B, the steel wire rope welding becket bridle of the present embodiment directly carries out numerical control cutting machine blanking as rope using steel plate mother metal The 1st, ring main body processes steel wire rope by drilling machine in becket bridle main body and passes through hole 2.Main body 1 is with WDB620E Or the high-strength steel sheets such as Q690E material are mother metal, select the steel plate of corresponding thickness of slab to utilize numerical control cutting machine blanking.
Appearance and size L1 of becket bridle main body 1, L2, L3, L4, R1, R2 are according to selection steel wire rope welding becket bridle figure Paper size direct numerical control blanking puts in place and does not stays allowance, and steel wire rope passes through hole 2 and do not cuts out, becket bridle thickness t side To reserved allowance.
Utilize drilling machine to process steel wire rope after steel wire rope welding becket bridle blanking and pass through hole 2, then two-sided processing thickness Surplus is to drawing requirement size t, and finally machining welding becket bridle outline circular arc R the 3rd, steel wire rope passes through hole 2 four The circular arc R 3 and R4 in week.
During use, freezed with being threaded cable wire end docking in the termination of welding becket bridle, then that pull rope is incoming Steel wire rope passes through hole 2, it is achieved the docking of pull rope and steel wire rope.
Fig. 2 shows the enforcement step of the preferred embodiment of the docking calculation of the steel wire rope welding becket bridle of the present invention. Referring to Fig. 2, the detailed step of the docking calculation of the steel wire rope welding becket bridle of the present embodiment is as follows.
Step S1: the blank blanking step of steel wire rope welding becket bridle.
Please referring also to Fig. 3 A and 3B, in this step, with high-strength steel sheets such as WDB620E, Q690E as mother Material, utilizes numerical control cutting machine to carry out CNC cutting, all cuts the appearance and size of welding becket bridle and puts in place, steel wire Rope passes through hole and does not cuts out, is formed blank.
Step S2: the machining steps of steel wire rope welding becket bridle.
Referring to Fig. 4, this step includes passing through hole line, thickness surplus to blank integral marking, steel wire rope Line, overall mach process.
During blank integral marking, weld wedge angle and the semicircle cambered surface of the blank of becket bridle with steel wire rope On the basis of, mark the cross centre line of steel wire rope welding becket bridle.
During steel wire rope passes through hole line, on the basis of the cross centre line of steel wire rope welding becket bridle, draw Go out steel wire rope on becket bridle and pass through the cross centre line in hole, Excircle machining dimension line and checkout line.
During the line of thickness surplus, mark on the basis of the baseplane of the blank of steel wire rope welding becket bridle Thickness direction cross centre line, then the cross centre line with thickness direction mark thickness direction allowance line and Checkout line.
During integrated machine processing, pass through hole according to the steel wire rope that first line size processes on becket bridle, so After in the two-sided processing thickness surplus of becket bridle, pass through the inside and outside circular arc of hole machined further according to steel wire rope.
Step S3: the welding step of steel wire rope welding becket bridle.
This step includes the process welding front preparation, tack welding and backing welding, filling and cosmetic welding.
In the welding step of steel wire rope welding becket bridle, the process preparing before weldering includes type selecting, the steel welding becket bridle Cord termination processes, prepares manual electric arc welding welding rod as wlding and welding becket bridle process.Wherein welding rope The type selecting of ring is according to connecting wirerope diameter selection corresponding welding becket bridle, by WDB620E or Q690E material Steel plate CNC cutting after machining.Steel wire rope end head processes and refers to use at distance steel wire rope end head 50mm The seizing wire binding of diameter 2mm firmly, bundlees 2 times of a length of wirerope diameter, by steel cord ends 50mm In the range of the eliminating impurities such as greasy dirt, iron rust, steam clean, end polishing is smooth.Wlding prepares to refer to that wlding selects Arc-welding electrode by hand, is placed on curer interior under high temperature (such as 350 to 380 degrees Celsius) before using Bakee 1 hour and be incubated, ready access upon use.It is by 90 ° of end welding scopes of welding becket bridle that welding becket bridle is processed Inside polish smooth, remove the foreign material such as removing rust, oxide skin.
Shown in Figure 5, the process of tack welding and backing welding is to align simultaneously welding becket bridle and steel wire rope end head Carry out weld preheating (preferably preheating temperature e.g. 160 to 230 DEG C) after adjusting vertically, then make by hand Arc-welding electrode uses the method for DC reverse connection to carry out tack welding and backing welding, and welding current e.g. 120 ± 10A, voltage is 21.4 to 24.6 volts.
Continuing with seeing Fig. 5, fill and the process of cosmetic welding is to use manual electric arc welding welding rod to use direct current anti- The method connecing is filled with and cosmetic welding, welding current e.g. 170 ± 10A, and voltage is 21.5 to 24.6 volts, Note control interlayer temperature at 160 to 230 degrees Celsius during welding.Use the method control that two-sided hoop symmetry freezes Welding deformation processed is vertical with steel wire rope end head to ensure after welding becket bridle welding.
Step S4: the messenger threading step of steel wire rope welding becket bridle.
As shown in Figure 6 A and 6B, this step carries out steel wire rope and connects.That is, according to rope traction pulling force and weldering The size that splicing ring steel wire rope passes through hole selects steel wire rope messenger, by steel wire rope messenger fag end from welding becket bridle steel wire Rope passes through after passing through in hole and is spliced fag end, completes the docking of messenger and steel wire rope, then completes according to wire rope handling technique Steel wire rope connects work.
Although illustrate for making explanation simplify said method and be described as a series of actions, it should be understood that and lead Meeting, these methods are not limited by the order of action, because according to one or more embodiments, some actions can be pressed Different order occur and/or with from depicted and described herein or not shown herein and description but this area skill Art personnel may be appreciated other actions and occur concomitantly.
Of this disclosure being previously described is provided to be for making any person skilled in the art all can make or use this Open.Various modification of this disclosure all will be apparent from for a person skilled in the art, and herein Defined generic principles can be applied to the spirit or scope without departing from the disclosure for other variants.Thus, The disclosure is not intended to be limited to example described herein and design, but should be awarded and institute herein Disclosed principle and the consistent the widest scope of novel features.

Claims (4)

1. the docking calculation of a steel wire rope welding becket bridle, it is characterised in that include:
The blank blanking step of steel wire rope welding becket bridle: with steel plate as mother metal, utilize numerical control cutting machine blanking, will The appearance and size of welding becket bridle is all cut and is put in place, forms blank;
The machining steps of steel wire rope welding becket bridle: include passing through blank integral marking, steel wire rope hole line, The line of thickness surplus, overall mach process;
The welding step of steel wire rope welding becket bridle: include welding front preparation, tack welding and backing welding, filling and capping The process of weldering;
The messenger threading step of steel wire rope welding becket bridle: carry out steel wire rope and connect;
Wherein during blank integral marking, weld wedge angle and the semicircle of the blank of becket bridle with steel wire rope On the basis of cambered surface, mark the cross centre line of steel wire rope welding becket bridle;Pass through the mistake of hole line at steel wire rope Cheng Zhong, on the basis of the cross centre line of steel wire rope welding becket bridle, marks steel wire rope on becket bridle and passes through the cross in hole Center line, Excircle machining dimension line and checkout line;During the line of thickness surplus, with steel wire rope welding rope Thickness direction cross centre line is marked, then with in the cross of thickness direction on the basis of the baseplane of the blank of ring Heart line marks thickness direction allowance line and checkout line;During integrated machine processing, first according to line size The steel wire rope first processing on becket bridle passes through hole, then the two-sided processing thickness surplus at becket bridle, further according to steel wire Rope passes through the inside and outside circular arc of hole machined.
2. the docking calculation of steel wire rope according to claim 1 welding becket bridle, it is characterised in that at steel wire The process in the welding step of welding becket bridle, preparing before weldering of restricting includes at the type selecting of welding becket bridle, steel wire rope end head Reason, preparation manual electric arc welding welding rod are as wlding and welding becket bridle process;Tack welding and the process of backing welding Be welding becket bridle and steel wire rope end head are alignd and adjust vertical after carry out weld preheating, then use manual arc Weldering welding rod uses the method for DC reverse connection to carry out tack welding and backing welding;Fill and the process of cosmetic welding is to use Manual electric arc welding welding rod uses the method for DC reverse connection to be filled with and cosmetic welding, uses the symmetrical burning of two-sided hoop The method control welding deformation of weldering is vertical with steel wire rope end head to ensure after welding becket bridle welding.
3. the docking calculation of steel wire rope according to claim 1 welding becket bridle, it is characterised in that at steel wire In the messenger threading step of rope welding becket bridle, pass through hole according to rope traction pulling force and welding becket bridle steel wire rope Size selects steel wire rope messenger, passes through steel wire rope messenger fag end from welding becket bridle steel wire rope and is spliced after passing through hole Fag end, completes the docking of messenger and steel wire rope, then completes steel wire rope according to wire rope handling technique and connect work.
4. the docking calculation of steel wire rope according to claim 1 welding becket bridle, it is characterised in that as mother The model of the steel plate of material is WDB620E or Q690E.
CN201410571464.8A 2014-10-23 2014-10-23 The docking calculation of steel wire rope welding becket bridle Active CN104315083B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410571464.8A CN104315083B (en) 2014-10-23 2014-10-23 The docking calculation of steel wire rope welding becket bridle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410571464.8A CN104315083B (en) 2014-10-23 2014-10-23 The docking calculation of steel wire rope welding becket bridle

Publications (2)

Publication Number Publication Date
CN104315083A CN104315083A (en) 2015-01-28
CN104315083B true CN104315083B (en) 2016-11-09

Family

ID=52370362

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410571464.8A Active CN104315083B (en) 2014-10-23 2014-10-23 The docking calculation of steel wire rope welding becket bridle

Country Status (1)

Country Link
CN (1) CN104315083B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105134875B (en) * 2015-06-16 2018-02-16 李先登 A kind of steel wire rope spiral eliminant jointing method
CN106466755B (en) * 2015-08-22 2018-08-14 湖北汽车工业学院 A kind of automation steel wire rope annulus welder
CN105090349B (en) * 2015-08-25 2017-11-28 李先登 The knotting method of steel wire rope spiral noose
CN109385921B (en) * 2017-08-14 2022-04-01 上海外高桥造船海洋工程项目管理有限公司 Steel wire rope of riser tensioner and rope threading method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2901822A (en) * 1955-12-15 1959-09-01 Robert B Hayden Method of forming a harness cord end terminal
GB2239664A (en) * 1990-01-04 1991-07-10 Griffin Woodhouse Limited End fittings for wire rope
CA2431350A1 (en) * 2003-06-06 2004-12-06 Wire Rope Industries Ltd./Industries De Cables D'acier Ltee Wire rope installation connector
CN101786572A (en) * 2010-03-08 2010-07-28 武汉船用机械有限责任公司 Fixed connection method of chip lifting hook piece
CN103089917A (en) * 2013-01-31 2013-05-08 徐工集团工程机械股份有限公司 Lantern ring and inhaul cable structure
CN204239603U (en) * 2014-10-23 2015-04-01 上海振华重工(集团)股份有限公司 Wire rope welding becket bridle

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2901822A (en) * 1955-12-15 1959-09-01 Robert B Hayden Method of forming a harness cord end terminal
GB2239664A (en) * 1990-01-04 1991-07-10 Griffin Woodhouse Limited End fittings for wire rope
CA2431350A1 (en) * 2003-06-06 2004-12-06 Wire Rope Industries Ltd./Industries De Cables D'acier Ltee Wire rope installation connector
CN101786572A (en) * 2010-03-08 2010-07-28 武汉船用机械有限责任公司 Fixed connection method of chip lifting hook piece
CN103089917A (en) * 2013-01-31 2013-05-08 徐工集团工程机械股份有限公司 Lantern ring and inhaul cable structure
CN204239603U (en) * 2014-10-23 2015-04-01 上海振华重工(集团)股份有限公司 Wire rope welding becket bridle

Also Published As

Publication number Publication date
CN104315083A (en) 2015-01-28

Similar Documents

Publication Publication Date Title
CN104315083B (en) The docking calculation of steel wire rope welding becket bridle
EP3166746B1 (en) Method and device for quick and reliable tool changing in the process of friction stir welding
CN204000423U (en) A kind of steel wire rope dissolution of partnership device
CN103921009A (en) Straight welded joint crack sensitivity evaluation method and multivariant restraining plate for evaluating
CN104118530B (en) Stern tube shaft installation method
CN108723266A (en) A kind of processing of spiral and sleeve install equipment
CN205363073U (en) Mouth of pipe butt joint anchor clamps
CN103357697A (en) Manufacturing technology of longitudinal submerged arc welded pipe
CN202840387U (en) Caron fiber composite core wire for connection
CN209363528U (en) A kind of processing of spiral and sleeve install equipment
CN105537738B (en) The welding method of nuclear power station large posted sides part banjo fixing butt jointing
CN107538112A (en) A kind of H profile steel thickness web welding method
CN105171347B (en) The field installation process of experimental cabin
CN206869569U (en) A kind of casting inner hole grinding device
CN104198279B (en) Standard specimen union joint is used in a kind of stretching
CN106002120A (en) Machining process for marine propeller shaft with length of 22 metres and hollow middle
CN204239603U (en) Wire rope welding becket bridle
CN203712058U (en) Fixing device used for welding pipe flange
CN204747731U (en) Groove welding system of marine major diameter nozzle stub and flange
CN203853874U (en) Tooth grinding device
CN102407469A (en) Special grinding machine for pipeline inner hole
CN106312261B (en) A kind of aluminium alloy wheel hub repair in melting welding fill process
CN105583497A (en) High strength alloy steel plate welding technology
CN207087511U (en) A kind of stainless steel tube weldering thorn detection sanding apparatus
CN205464731U (en) Thin space pipe sealing of tube aircraft nose

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170426

Address after: 201913 Shanghai City, Chongming County town of Phoenix Road, No. 666, building No. 20,

Patentee after: Shanghai Zhenhua Heavy Industries Ltd.

Address before: 200125 Pudong South Road, Shanghai, No. 3470, No.

Patentee before: Shanghai Zhenhua Heavy Industries (Group) Co., Ltd.