CN104314082A - Deep function pit supporting structure in karst geology condition and construction method thereof - Google Patents

Deep function pit supporting structure in karst geology condition and construction method thereof Download PDF

Info

Publication number
CN104314082A
CN104314082A CN201410634154.6A CN201410634154A CN104314082A CN 104314082 A CN104314082 A CN 104314082A CN 201410634154 A CN201410634154 A CN 201410634154A CN 104314082 A CN104314082 A CN 104314082A
Authority
CN
China
Prior art keywords
foundation pit
supporting structure
water
reinforcing body
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410634154.6A
Other languages
Chinese (zh)
Inventor
王剑非
王晓燕
殷华富
杨少真
李志平
周成明
王晓曙
杨世相
王自忠
郑云刚
孟应磊
周麟
杨成
苏兰忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd
YUNNAN NO3 CONSTRUCTIONAL ENGINEERING Co Ltd
YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd
YUNNAN NO3 CONSTRUCTIONAL ENGINEERING Co Ltd
YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd, YUNNAN NO3 CONSTRUCTIONAL ENGINEERING Co Ltd, YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd
Priority to CN201410634154.6A priority Critical patent/CN104314082A/en
Publication of CN104314082A publication Critical patent/CN104314082A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Conditioners And Soil-Stabilizing Materials (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention provides a deep foundation pit supporting structure in a karst geology condition and a construction method thereof. The deep foundation pit supporting structure comprises an encircled underground continuous wall (1), and a horizontal grouting reinforcing body (2) which is poured into an encircling area of the underground continuous wall. With the adoption of the deep foundation pit supporting structure, the problem due to serious water leakage occurring in the excavating of the foundation pit under the karst geology condition can be effectively solved; the underground continuous wall has a good effect, and the supporting structure is small in deformation; in addition, the water stopping effect of the sidewall of a foundation pit is obvious, so that the circumstance of water leaking nearly not occurs; the area in the bottom of the foundation pit is subjected to foundation processing by the grouting mode to form a grouting reinforcing body, and thus the channel for water in karst fissures at the bottom of the pit can be effectively cut, and as a result, the problem that water runs from the bottom of the pit can be completely solved; the cement and soluble glass grout is used as the grouting material which can effectively prevent the cement grout from be washed out by the groundwater, and the water blocking and permeating preventing performances of the grouting reinforcing body can be obviously improved.

Description

Deep foundation pit supporting structure under a kind of Karst Geology and construction method thereof
Technical field
The present invention relates to architecture Foundation Pit Engineering technical field, relate generally to a kind of deep foundation pit supporting structure and construction method thereof.
Background technology
Karst is also known as karst (KARST), that water carries out solublerock (carbonate rock, gypsum, rock salt etc.) based on chemical corrosion, erosion, the mechanisms such as erosion and avalanche of diving of flowing water are auxiliary geologic process, and act on the general name of the phenomenon produced by these.By landforms that karsitification causes, claim karst landform (karst features).Karst features extensively distribute in China, particularly in southwest.Along with the quick propelling of China's urban construction, increasing construction project is faced with Karst Geology.With regard to the base pit engineering under Karst Geology, owing to being rich in crevice water in Karst Geological Landscape, in Excavation Process, foundation pit side-wall and the end, hole, are all faced with serious Karst Fissures water problems, and measures of preventing water is absolutely necessary.According to the Anchored Sheet Pile Wall for Excavation structure of routine, even if add water-stop curtain can not avoid sidewall water leakage situation completely, then can not process completely for hole end water leakage situation.The supporting and protection structure of all the other forms also all faces a similar difficult problem.
Summary of the invention
The object of the invention is to overcome the base pit engineering seepy question under Karst Geology, a kind of deep foundation pit supporting structure that effectively can solve serious seepy question in Excavation Process under Karst Geology is provided.The present invention also provides the construction method of this supporting and protection structure.
Realize the technical scheme that the object of the invention takes as follows:
A deep foundation pit supporting structure under Karst Geology, this deep foundation pit supporting structure by the diaphragm wall enclosed, be cast in the horizontal grouting reinforcing body that diaphragm wall encloses in region and form.
Grouting and reinforcing body of the present invention is positioned at below design elevation at the bottom of Foundation Pit, and thickness is not less than 3.0m.
The construction method of the deep foundation pit supporting structure under Karst Geology of the present invention, first construction of diaphragm wall is carried out, after diaphragm wall encloses structure construction, then at the bottom of Foundation Pit, position slip casting forms horizontal grouting reinforcing body consolidation process ground, finally carries out excavation of foundation pit again.
Grouting and reinforcing body of the present invention selects cement-silicate slurries as injecting paste material, and described cement-silicate slurries mix water glass in cement slurry, and the water/binder ratio of cement slurry is 0.75:1 ~ 1:1, and water glass incorporation is 2% ~ 4% of cement slurry weight.
Beneficial effect of the present invention is:
(1) not only supporting effect is good, Supporting Structure deformation is little for diaphragm wall, and remarkable at the stagnant water effect of foundation pit side-wall, seldom there is water leakage situation.For the base pit engineering under the Karst Geology being rich in Karst-fissure water, diaphragm wall is compared all the other supporting and protection structure and is had certain superiority.
(2) adopt the mode of slip casting to carry out basement process for territory, Foundation Pit base area, form grouting and reinforcing body, effectively can cut off the passage of hole end Karst-fissure water, thoroughly the solution end, hole, emits water problems.
(3) with cement-silicate slurries for injecting paste material, select water glass as injecting paste material fast coagulating early strength agent and injecting paste material impervious agent, the setting time of cement paste can be reduced, prevent cement paste by underground water erosion not easily consolidation, and the water blockoff barrier performance of grouting and reinforcing body can be significantly improved.
Accompanying drawing explanation
Fig. 1 is that the present invention constructs the foundation pit supporting construction generalized section of first stage when namely carrying out construction of diaphragm wall;
Fig. 2 be the present invention construct second stage and grouting and reinforcing body construction time foundation pit supporting construction generalized section;
Fig. 3 be the present invention construct phase III and excavation of foundation pit time foundation pit supporting construction generalized section.
In figure, each label is: 1---diaphragm wall; 2---grouting and reinforcing body; A---earth's surface; B---at the bottom of foundation ditch.
Detailed description of the invention
Below by drawings and Examples, the present invention is described in further detail, but protection scope of the present invention is not limited to described content.
As shown in Figure 1, Figure 2, Figure 3 shows, the deep foundation pit supporting structure under a kind of Karst Geology by the diaphragm wall 1 enclosed, be cast in the horizontal grouting reinforcing body 2 that diaphragm wall encloses in region and form.Grouting and reinforcing body 2 is positioned at below design elevation at the bottom of Foundation Pit, and thickness is not less than 3.0m.
Deep-foundation pit engineering under Karst Geology can adopt diaphragm wall 1+ to cheat the combined support structure of rising pouring slurry reinforcing body 2, first carry out diaphragm wall 1 to construct, after the construction of diaphragm wall 1 space enclosing structure terminates, again at position, the end, design hole grout and strengthen processing ground, finally carry out excavation of foundation pit again.Concrete construction sequence is as follows:
(1) according to Foundation Pit Support Design requirement, the parameters such as the diaphragm wall degree of depth, thickness are determined;
(2) existing construction method is adopted to carry out construction of diaphragm wall;
(3), after diaphragm wall encloses structure construction, according to design mixture proportion configuration injecting paste material---cement-silicate slurries, first prepare cement slurry, then mix water glass.The water/binder ratio of cement slurry is 0.75:1 ~ 1:1, and water glass incorporation is 2% ~ 4% of cement slurry weight;
(4) at the bottom of Foundation Pit, position slip casting forms horizontal grouting reinforcing body, consolidation process ground; The shear strength of grouting and reinforcing body and deadweight should guarantee to resist its buoyancy descending underground water to produce, and both should meet stability requirement;
(5) excavation of foundation pit is carried out.
The Karst-fissure water that diaphragm wall 1 and grouting and reinforcing body 2 effectively can solve foundation pit side-wall and position, the end, hole respectively emits water problems.

Claims (4)

1. the deep foundation pit supporting structure under Karst Geology, is characterized in that, this deep foundation pit supporting structure by the diaphragm wall enclosed (1), be cast in the horizontal grouting reinforcing body (2) that diaphragm wall encloses in region and form.
2. the deep foundation pit supporting structure under Karst Geology according to claim 1, is characterized in that, described grouting and reinforcing body (2) is positioned at below design elevation at the bottom of Foundation Pit, and thickness is not less than 3.0m.
3. the construction method of the deep foundation pit supporting structure under Karst Geology according to claim 1 or 2, it is characterized in that, first diaphragm wall (1) construction is carried out, after diaphragm wall (1) encloses structure construction, at the bottom of Foundation Pit, position slip casting forms horizontal grouting reinforcing body (2) consolidation process ground again, finally carries out excavation of foundation pit again.
4. construction method according to claim 3, it is characterized in that, described grouting and reinforcing body (2) selects cement-silicate slurries as injecting paste material, described cement-silicate slurries mix water glass in cement slurry, the water/binder ratio of cement slurry is 0.75:1 ~ 1:1, and water glass incorporation is 2% ~ 4% of cement slurry weight.
CN201410634154.6A 2014-11-12 2014-11-12 Deep function pit supporting structure in karst geology condition and construction method thereof Pending CN104314082A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410634154.6A CN104314082A (en) 2014-11-12 2014-11-12 Deep function pit supporting structure in karst geology condition and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410634154.6A CN104314082A (en) 2014-11-12 2014-11-12 Deep function pit supporting structure in karst geology condition and construction method thereof

Publications (1)

Publication Number Publication Date
CN104314082A true CN104314082A (en) 2015-01-28

Family

ID=52369383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410634154.6A Pending CN104314082A (en) 2014-11-12 2014-11-12 Deep function pit supporting structure in karst geology condition and construction method thereof

Country Status (1)

Country Link
CN (1) CN104314082A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862722A (en) * 2016-04-07 2016-08-17 中建交通建设集团有限公司 Three-dimensional treatment method of subway deep foundation pit in karst intense development region
CN108824449A (en) * 2018-07-26 2018-11-16 中国建筑第八工程局有限公司 Support system and its construction method with underground horizontal support
CN110409457A (en) * 2019-06-26 2019-11-05 贵州建工集团第一建筑工程有限责任公司 Deep foundation pit supporting structure and its construction method under the conditions of a kind of karst area
CN110528523A (en) * 2019-09-02 2019-12-03 湖南宏禹工程集团有限公司 A kind of highly permeable stratum building foundation pit horizontal grouting back cover construction method
CN111042146A (en) * 2019-11-11 2020-04-21 中铁七局集团第二工程有限公司 Construction method of deep foundation pit supporting anti-seepage system of coastal karst stratum
CN111436204A (en) * 2018-11-12 2020-07-21 包尔特殊基础工程有限公司 Method for producing a sealing base in the ground
CN111691442A (en) * 2019-03-15 2020-09-22 包尔特殊基础工程有限公司 Foundation pit surrounding structure in foundation and manufacturing method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1376836A (en) * 2001-03-27 2002-10-30 同济大学 Method for controlling deformation of foundation pit's retaining wall by grouting in passive area of earth body
CN101328713A (en) * 2008-07-18 2008-12-24 华丰建设股份有限公司 Construction method of circular deep foundation pit support
KR20090007826A (en) * 2007-07-16 2009-01-21 김창근 Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
CN101418572A (en) * 2008-10-17 2009-04-29 上海隧道工程股份有限公司 Pit construction method employing precast support
KR101109520B1 (en) * 2010-09-03 2012-01-31 삼정건설 주식회사 Method for constructing earth retaining wall using steel pipe
CN103437339A (en) * 2013-07-29 2013-12-11 中铁十六局集团北京轨道交通工程建设有限公司 Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
CN103590425A (en) * 2013-11-28 2014-02-19 中铁二十局集团第五工程有限公司 Peaty soft soil stratum subway station construction technology
CN103967015A (en) * 2014-05-21 2014-08-06 刘绍国 Water-stopping deep foundation pit excavation method and structure thereof
CN204174626U (en) * 2014-11-12 2015-02-25 云南建工集团有限公司 Deep foundation pit supporting structure under a kind of Karst Geology

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1376836A (en) * 2001-03-27 2002-10-30 同济大学 Method for controlling deformation of foundation pit's retaining wall by grouting in passive area of earth body
KR20090007826A (en) * 2007-07-16 2009-01-21 김창근 Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
CN101328713A (en) * 2008-07-18 2008-12-24 华丰建设股份有限公司 Construction method of circular deep foundation pit support
CN101418572A (en) * 2008-10-17 2009-04-29 上海隧道工程股份有限公司 Pit construction method employing precast support
KR101109520B1 (en) * 2010-09-03 2012-01-31 삼정건설 주식회사 Method for constructing earth retaining wall using steel pipe
CN103437339A (en) * 2013-07-29 2013-12-11 中铁十六局集团北京轨道交通工程建设有限公司 Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
CN103590425A (en) * 2013-11-28 2014-02-19 中铁二十局集团第五工程有限公司 Peaty soft soil stratum subway station construction technology
CN103967015A (en) * 2014-05-21 2014-08-06 刘绍国 Water-stopping deep foundation pit excavation method and structure thereof
CN204174626U (en) * 2014-11-12 2015-02-25 云南建工集团有限公司 Deep foundation pit supporting structure under a kind of Karst Geology

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862722A (en) * 2016-04-07 2016-08-17 中建交通建设集团有限公司 Three-dimensional treatment method of subway deep foundation pit in karst intense development region
CN108824449A (en) * 2018-07-26 2018-11-16 中国建筑第八工程局有限公司 Support system and its construction method with underground horizontal support
CN111436204A (en) * 2018-11-12 2020-07-21 包尔特殊基础工程有限公司 Method for producing a sealing base in the ground
CN111691442A (en) * 2019-03-15 2020-09-22 包尔特殊基础工程有限公司 Foundation pit surrounding structure in foundation and manufacturing method thereof
CN110409457A (en) * 2019-06-26 2019-11-05 贵州建工集团第一建筑工程有限责任公司 Deep foundation pit supporting structure and its construction method under the conditions of a kind of karst area
CN110528523A (en) * 2019-09-02 2019-12-03 湖南宏禹工程集团有限公司 A kind of highly permeable stratum building foundation pit horizontal grouting back cover construction method
CN111042146A (en) * 2019-11-11 2020-04-21 中铁七局集团第二工程有限公司 Construction method of deep foundation pit supporting anti-seepage system of coastal karst stratum

Similar Documents

Publication Publication Date Title
CN104314082A (en) Deep function pit supporting structure in karst geology condition and construction method thereof
CN102493822B (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN101806059B (en) Drilling, grouting and sand-throwing process of ground surface of mined-out region under highway
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN204371354U (en) The compound supporting and protection structure of a kind of Karst Tunnel
CN103696416B (en) A kind of method for processing foundation
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN102877470B (en) Combined soil nailing construction method for supporting
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN110630293A (en) Double-liquid and method for grouting wall
CN107059900B (en) A kind of construction method that Double-wall sin-gle-image radiography quickly sinks in sand-pebble layer
CN208605186U (en) Shield launching and reception end bracing means in Tunneling by mining method
CN107237332A (en) A kind of foundation pit stope support containing drifting sand layer method of use composite soil-nailed retaining wall
CN104532855A (en) Combined pile supporting structure in deep and thick peat soil layer
CN104153381A (en) Waterproof curtain pile, waterproof curtain and construction method of waterproof curtain pile
CN103343534A (en) Closed precipitation method for foundation pit construction
CN104150820A (en) Synchronous grouting slurry for shield driving construction of water-enriched sandy gravel stratum
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN206971247U (en) A kind of concrete plinth foundation ruggedized construction being placed on Unloading Rock
CN101769157B (en) Construction method for tunnel working face counterpressure treatment during tunnel excavation
CN103195063B (en) Fresh water splitting post grouting construction method
CN204174626U (en) Deep foundation pit supporting structure under a kind of Karst Geology
CN208982058U (en) Vertical shaft surrounding rock supporting structure
CN209457055U (en) A kind of deep basal pit mechanical anchor anti-float anchor rod
CN110409457A (en) Deep foundation pit supporting structure and its construction method under the conditions of a kind of karst area

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Wang Jianfei

Inventor after: Wang Xiaoyan

Inventor after: Wang Xiaofang

Inventor after: Yin Huafu

Inventor after: Yang Shaozhen

Inventor after: Li Zhiping

Inventor after: Zhou Chengming

Inventor after: Wang Xiaoshu

Inventor after: Yang Shixiang

Inventor before: Wang Jianfei

Inventor before: Zheng Yungang

Inventor before: Meng Yinglei

Inventor before: Zhou Lin

Inventor before: Yang Cheng

Inventor before: Su Lanzhong

Inventor before: Wang Xiaoyan

Inventor before: Yin Huafu

Inventor before: Yang Shaozhen

Inventor before: Li Zhiping

Inventor before: Zhou Chengming

Inventor before: Wang Xiaoshu

Inventor before: Yang Shixiang

Inventor before: Wang Zizhong

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: WANG JIANFEI WANG XIAOYAN YIN HUAFU YANG SHAOZHEN LI ZHIPING ZHOU CHENGMING WANG XIAOSHU YANG SHIXIANG WANG ZIZHONG ZHENG YUNGANG MENG YINGLEI ZHOU LIN YANG CHENG SU LANZHONG TO: WANG JIANFEI WANG XIAOYAN WANG XIAOFANG YIN HUAFU YANG SHAOZHEN LI ZHIPING ZHOU CHENGMING WANG XIAOSHU YANG SHIXIANG

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150128