CN104278843B - The deviation correcting device of a kind of steel structure girder lifting docking and using method - Google Patents

The deviation correcting device of a kind of steel structure girder lifting docking and using method Download PDF

Info

Publication number
CN104278843B
CN104278843B CN201410605507.XA CN201410605507A CN104278843B CN 104278843 B CN104278843 B CN 104278843B CN 201410605507 A CN201410605507 A CN 201410605507A CN 104278843 B CN104278843 B CN 104278843B
Authority
CN
China
Prior art keywords
jack
crossbeam
steel structure
support arm
hoisting beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410605507.XA
Other languages
Chinese (zh)
Other versions
CN104278843A (en
Inventor
肖必建
刘光星
张少波
陈旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Original Assignee
China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Bureau Shanghai Corp Ltd filed Critical China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Priority to CN201410605507.XA priority Critical patent/CN104278843B/en
Publication of CN104278843A publication Critical patent/CN104278843A/en
Application granted granted Critical
Publication of CN104278843B publication Critical patent/CN104278843B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses the deviation correcting device of a kind of steel structure girder lifting docking and using method, including adjustable hoop, support arm and jack;The present invention adopts the termination that deviation correcting device is fixed on connected steel structure girder, deviation correcting device arranges fulcrum, fulcrum arranges jack, with jack control and the relative displacement adjusting lifting steel structure girder termination, it is achieved the accurately docking of steel structure girder and installation.The present invention is applicable to the steel structure girder of different section, solves in high-altitude control and the difficult problem adjusting hoisting beam and the relative displacement of fixing beam, has simple in construction, control and advantage easy to adjust.

Description

The deviation correcting device of a kind of steel structure girder lifting docking and using method
Technical field
The present invention relates to project installation technical field, especially a kind of steel structure girder lifts deviation correcting device and the using method of docking.
Background technology
The lifting of prior art large-scale steel structure beam, especially the lifting of steel structure girder or steel truss continuously, in hoisting process, docking and fixing of termination is a sufficiently complex job, is also a critical process of steel structure girder connection, there is problems of, after steel structure girder lifting tentatively puts in place, owing to being subject to the impact of the factor such as wind load, crane stiff, steel structure girder is made to cause the phenomenon of lateral displacement to can hardly be avoided at high oscillating air, in addition work high above the ground, security risk is big;How to make the hoisting beam of steel structure girder accurately dock with the termination of fixing beam, can be the key of solution problem in the relative displacement of high-altitude control and adjustment hoisting beam and fixing beam.
Summary of the invention
It is an object of the invention to provide deviation correcting device and the using method of the lifting docking of a kind of steel structure girder for the deficiencies in the prior art, the present invention adopts the termination that deviation correcting device is fixed on connected steel structure girder, deviation correcting device arranges fulcrum, fulcrum arranges jack, with jack control and the relative displacement adjusting lifting steel structure girder termination, it is achieved the accurately docking of steel structure girder and installation.
The concrete technical scheme realizing the object of the invention is:
A kind of deviation correcting device of steel structure girder lifting docking, its feature includes adjustable hoop, support arm and jack, described adjustable hoop is by crossbeam, vertical columns, active column and clamping screw composition, crossbeam is provided with adjustment bolt block and adjusts bolt, the top of active column is provided with crossbeam hole and regulates screw, the middle part of vertical columns is provided with supporting arm base, supporting arm base is provided with support arm aperture and trip bolt, the bottom of vertical columns and active column is also arranged with locking screw keyhole, vertical columns welds with one end of crossbeam, active column is contained in the other end of crossbeam through crossbeam borehole jack, adjust bolt to engage through the screw that regulates on active column with the adjustment bolt block on crossbeam, clamping screw connects through the locking screw keyhole on vertical columns and active column;Described support arm is provided with jack pad assembly, and support arm is through in the support arm aperture of adjustable hoop and fixes through trip bolt, and jack is located on the jack pad assembly of support arm.
A kind of using method implementing described device, its feature comprises the steps:
A), the lifting of steel structure girder:
Being called hoisting beam for ease of describing the following steel structure girder being intended to lifting, the steel structure girder being attached thereto is called fixing beam;
With lifting appliance hoisting beam sling and tentatively put in place, adopting cushion block to adjust the vertical height position of hoisting beam and fixing beam-ends head by lifting appliance;
B), the determination of correction point position:
Check hoisting beam and fixing beam two axial lines deviation in the horizontal direction, confirm that hoisting beam is intended to the direction of correction, namely determine the stress side of hoisting beam;
C), the installation of deviation correcting device is with fixing:
Sling adjustable hoop, and make crossbeam, active column and vertical columns above fixing beam;
Clamping screw is installed, tightens the adjustment bolt on crossbeam and clamping screw, adjustable hoop and fixing beam are connected;
Jack is loaded on the jack pad assembly of support arm;
By adjusting support arm in the position supporting arm aperture, it is determined that jack acts on the stress point of hoisting beam, and support arm and vertical columns is fixed with trip bolt;
D), correction is implemented:
Starting jack, the top of jack acts on the stress point of hoisting beam, makes the deviation value between the axis of hoisting beam and the axis of fixing beam be gradually reduced, until it reaches within the misalignment of axe scope of technological requirement;
E), clamping plate bolt is installed:
The clamping plate that hoisting beam docks with fixing beam-ends head are installed, with bolt, clamping plate, the termination of hoisting beam with fixing beam are docked and fixed;
F), deviation correcting device is removed:
By jack off-load, remove the clamping screw on adjustable hoop, loosen the adjustment bolt on crossbeam, hang except adjustable hoop, treat that next reuses across the docking correction of hoisting beam.
The present invention adopts the termination that deviation correcting device is fixed on connected steel structure girder, deviation correcting device arranges fulcrum, fulcrum arranges jack, with jack control and the relative displacement adjusting lifting steel structure girder termination, it is achieved the accurately docking of steel structure girder and installation.The present invention is applicable to the steel structure girder of different section, solves in high-altitude control and the difficult problem adjusting hoisting beam and the relative displacement of fixing beam, has simple in construction, control and advantage easy to adjust.
Accompanying drawing explanation
Fig. 1 is the structural representation of apparatus of the present invention;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is the use view of the present invention;
Fig. 4 is the use view of the invention process correction.
Detailed description of the invention
nullConsult Fig. 1、Fig. 2,Apparatus of the present invention include adjustable hoop 1、Support arm 2 and jack 3,Described adjustable hoop 1 is by crossbeam 11、Vertical columns 12、Active column 13 and clamping screw 14 form,Crossbeam 11 is provided with adjustment bolt block 111 and adjusts bolt 112,The top of active column 13 is provided with crossbeam hole 131 and regulates screw 132,The middle part of vertical columns 12 is provided with supporting arm base 122,Supporting arm base 122 is provided with support arm aperture 124 and trip bolt 123,The bottom of vertical columns 12 and active column 13 is also arranged with locking screw keyhole 121,Vertical columns 12 welds with one end of crossbeam 11,Active column 13 is sleeved on the other end of crossbeam 11 through crossbeam hole 131,Adjust bolt 112 to engage through the screw 132 that regulates on active column 13 with the adjustment bolt block 111 on crossbeam 11,Clamping screw 14 connects through the locking screw keyhole 121 on vertical columns 12 and active column 13;Described support arm 2 is provided with jack pad assembly 21, and support arm 2 is through in the support arm aperture 124 of adjustable hoop 1 and fixes through trip bolt 123, and jack 3 is located on the jack pad assembly 21 of support arm 2.
The embodiment of the present invention:
Consulting Fig. 1, Fig. 2, Fig. 3, Fig. 4, be installed as example with Large Scale and Continuous steel structure girder, be called hoisting beam for ease of describing the following steel structure girder being intended to lifting, the steel structure girder being attached thereto is called fixing beam, and its step is as follows:
A), the lifting of steel structure girder:
With lifting appliance hoisting beam sling and tentatively put in place, by the fine setting of lifting appliance, adopting cushion block to adjust the vertical height position of hoisting beam and fixing beam-ends head;
B), the determination of correction point position:
Check hoisting beam and the fixing beam two axial lines deviation at horizontal level, confirm that hoisting beam is intended to the direction of correction, it is determined that the stress side of hoisting beam;
C), the installation of deviation correcting device is with fixing:
Remove the clamping screw 14 on adjustable hoop 1, by adjusting the adjustment bolt 112 mobile active column 13 on crossbeam 11 on crossbeam 11, make the width 10~30mm more than fixing beam of the distance between active column 13 and vertical columns 12;Sling adjustable hoop 1, make vertical columns 12 be positioned at the stress side of hoisting beam, and make crossbeam 11, active column 13 and vertical columns 12 above fixing beam;By clamping screw 14 through the locking screw keyhole 121 on vertical columns 12 and active column 13, tightening the adjustment bolt 112 on crossbeam 11 and clamping screw 14, adjustable hoop 1 is connected with fixing beam;Jack 3 is loaded on the jack pad assembly 21 of support arm 2;By adjusting support arm 2 in the position supporting arm aperture 124, it is determined that jack 3 acts on the stress point of hoisting beam, and support arm 2 and vertical columns 12 is fixed with trip bolt 123;
D), correction is implemented:
Starting jack 3, the top of jack 3 acts on the stress point of hoisting beam, makes the deviation value between the axis of hoisting beam and the axis of fixing beam be gradually reduced, until it reaches the misalignment of axe scope of technological requirement;
E), clamping plate bolt is installed:
The clamping plate that hoisting beam docks with fixing beam-ends head are installed, with bolt, clamping plate, the termination of hoisting beam with fixing beam are docked and fixed;
F), deviation correcting device is removed:
By jack 3 off-load, remove the clamping screw 14 on adjustable hoop 1, loosen the adjustment bolt 112 on crossbeam 11, remove adjustable hoop 1, treat that next reuses across the docking correction of hoisting beam.
The present invention is not only applicable to the unsettled lateral correction of steel structure girder, steel structure truss component, applies also for the unsettled lateral correction of large-scale combined steel structure member.
The middle part of vertical columns 12 of the present invention is provided with support arm aperture 124, support arm 2 is through in support arm aperture 124, can be stretched out by the either end supporting arm aperture 124, what make very heavy topmast point on adjustable hoop 1 arranges two-way choice, with the hoisting beam in satisfied different correction directions, i.e. the hoisting beam of the different stress side of reply.

Claims (2)

  1. null1. the deviation correcting device of a steel structure girder lifting docking,It is characterized in that it includes adjustable hoop (1)、Support arm (2) and jack (3),Described adjustable hoop (1) is by crossbeam (11)、Vertical columns (12)、Active column (13) and clamping screw (14) composition,Crossbeam (11) is provided with adjustment bolt block (111) and adjusts bolt (112),The top of active column (13) is provided with crossbeam hole (131) and regulates screw (132),The middle part of vertical columns (12) is provided with supporting arm base (122),Supporting arm base (122) is provided with support arm aperture (124) and trip bolt (123),The bottom of vertical columns (12) and active column (13) is also arranged with locking screw keyhole (121),Vertical columns (12) welds with one end of crossbeam (11),Active column (13) is sleeved on the other end of crossbeam (11) through crossbeam hole (131),Adjust bolt (112) to engage through the adjustment screw (132) on active column (13) with the adjustment bolt block (111) on crossbeam (11),Clamping screw (14) connects through the locking screw keyhole (121) on vertical columns (12) and active column (13);Described support arm (2) is provided with jack pad assembly (21), and support arm (2) is through in the support arm aperture (124) of adjustable hoop (1) and fixes through trip bolt (123), and jack (3) is located on the jack pad assembly (21) of support arm (2).
  2. 2. the using method implementing device described in claim 1, it is characterised in that it comprises the steps:
    A), the lifting of steel structure girder:
    Being called hoisting beam for ease of describing the following steel structure girder being intended to lifting, the steel structure girder being attached thereto is called fixing beam;
    With lifting appliance hoisting beam sling and tentatively put in place, adopting cushion block to adjust the vertical height position of hoisting beam and fixing beam-ends head by lifting appliance;
    B), the determination of correction point position:
    Check hoisting beam and fixing beam two axial lines deviation in the horizontal direction, confirm that hoisting beam is intended to the direction of correction, namely determine the stress side of hoisting beam;
    C), the installation of deviation correcting device is with fixing:
    Sling adjustable hoop (1), and make crossbeam (11), active column (13) and vertical columns (12) above fixing beam;
    Clamping screw (14) is installed, tightens the adjustment bolt (112) on crossbeam (11) and clamping screw (14), adjustable hoop (1) is connected with fixing beam;
    Jack (3) is loaded on the jack pad assembly (21) of support arm (2);
    By adjusting support arm (2) in the position supporting arm aperture (124), it is determined that jack (3) acts on the stress point of hoisting beam, and is fixed with vertical columns (12) by support arm (2) with trip bolt (123);
    D), correction is implemented:
    Starting jack (3), the top of jack (3) acts on the stress point of hoisting beam, makes the deviation value between the axis of hoisting beam and the axis of fixing beam be gradually reduced, until it reaches within the misalignment of axe scope of technological requirement;
    E), clamping plate bolt is installed:
    The clamping plate that hoisting beam docks with fixing beam-ends head are installed, with bolt, clamping plate, the termination of hoisting beam with fixing beam are docked and fixed;
    F), deviation correcting device is removed:
    By jack (3) off-load, remove the clamping screw (14) on adjustable hoop (1), loosen the adjustment bolt (112) on crossbeam (11), hang except adjustable hoop (1), treat that next reuses across the docking correction of hoisting beam.
CN201410605507.XA 2014-11-03 2014-11-03 The deviation correcting device of a kind of steel structure girder lifting docking and using method Expired - Fee Related CN104278843B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410605507.XA CN104278843B (en) 2014-11-03 2014-11-03 The deviation correcting device of a kind of steel structure girder lifting docking and using method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410605507.XA CN104278843B (en) 2014-11-03 2014-11-03 The deviation correcting device of a kind of steel structure girder lifting docking and using method

Publications (2)

Publication Number Publication Date
CN104278843A CN104278843A (en) 2015-01-14
CN104278843B true CN104278843B (en) 2016-07-06

Family

ID=52254144

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410605507.XA Expired - Fee Related CN104278843B (en) 2014-11-03 2014-11-03 The deviation correcting device of a kind of steel structure girder lifting docking and using method

Country Status (1)

Country Link
CN (1) CN104278843B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320721B (en) * 2016-09-09 2023-10-20 中国核工业二三建设有限公司 Alignment and leveling device for metal reactor core shell of nuclear power station
CN108775075A (en) * 2018-07-17 2018-11-09 北京市第三建筑工程有限公司 A kind of adjusting apparatus for overhanging steel structure
CN111663792B (en) * 2020-05-29 2021-07-27 重庆建工集团股份有限公司 Steel cantilever truss member space positioning device
CN113530265B (en) * 2021-07-20 2022-05-27 中国路桥工程有限责任公司 Steel beam construction device and construction method
CN113882697B (en) * 2021-10-27 2023-01-24 河南省水利勘测设计研究有限公司 Positioning adjusting rod for assembling of assembled cavity structure
CN115492411B (en) * 2022-10-19 2023-06-16 中铁五局集团建筑工程有限责任公司 High-precision rapid butt joint device and butt joint method for unitized high-altitude overhanging steel structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1037475A (en) * 1996-07-23 1998-02-10 Ohbayashi Corp Strain correction system of steel framed building
CN202866303U (en) * 2012-09-19 2013-04-10 湖南金海钢结构股份有限公司 Installing and positioning fixing support for steel structure frame primary and secondary beam and secondary beam
CN203113811U (en) * 2013-03-05 2013-08-07 马鞍山十七冶工程科技有限责任公司 Simple correction device for installation perpendicularity of steel column
CN203821865U (en) * 2014-03-18 2014-09-10 中国三冶集团有限公司 Adjusting device for installing gap of H-shaped steel beam
CN203879026U (en) * 2014-05-04 2014-10-15 安徽富煌钢构股份有限公司 Aerial calibration adjuster for super high-rise steel structure box-shaped steel column
CN204112752U (en) * 2014-11-03 2015-01-21 中建七局(上海)有限公司 A kind of deviation correcting device of steel structure girder lifting docking

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1037475A (en) * 1996-07-23 1998-02-10 Ohbayashi Corp Strain correction system of steel framed building
CN202866303U (en) * 2012-09-19 2013-04-10 湖南金海钢结构股份有限公司 Installing and positioning fixing support for steel structure frame primary and secondary beam and secondary beam
CN203113811U (en) * 2013-03-05 2013-08-07 马鞍山十七冶工程科技有限责任公司 Simple correction device for installation perpendicularity of steel column
CN203821865U (en) * 2014-03-18 2014-09-10 中国三冶集团有限公司 Adjusting device for installing gap of H-shaped steel beam
CN203879026U (en) * 2014-05-04 2014-10-15 安徽富煌钢构股份有限公司 Aerial calibration adjuster for super high-rise steel structure box-shaped steel column
CN204112752U (en) * 2014-11-03 2015-01-21 中建七局(上海)有限公司 A kind of deviation correcting device of steel structure girder lifting docking

Also Published As

Publication number Publication date
CN104278843A (en) 2015-01-14

Similar Documents

Publication Publication Date Title
CN104278843B (en) The deviation correcting device of a kind of steel structure girder lifting docking and using method
CN106494588B (en) A kind of adjustable line style docking block suitable under various working
US10711428B2 (en) Supporting device and method for calculating jacking force thereof
CN204112752U (en) A kind of deviation correcting device of steel structure girder lifting docking
KR20170040837A (en) Heavy lifting device
CN206408969U (en) A kind of support meanss for being used to adjust bent cap vertical and horizontal gradient
CN109332980A (en) Wielding neck means for correcting and bearing calibration
JP6470285B2 (en) scaffold
CN106368322B (en) A kind of installation method for the bi-directional symmetrical inclination steel column between super high-rise building conversion layer
CN102720159B (en) Adjusting device specially for steel hoop two-way suspension supporting system
CN204530501U (en) The support bearing of arc rib alignment is controlled during a kind of constructability
KR200462150Y1 (en) Jig set for setting the pump tower in the cargo tank of LNG carrier
JP2016142097A (en) Portable hoist unit and horizontal member dismantling method
KR102045025B1 (en) Roundness Maintaining Device of Large Cylindrical Structure and Manufacturing Method Thereof
KR20130011018A (en) Adjustment apparatus for support of ship
CN204663027U (en) For the bracing or strutting arrangement that rack is installed
KR101586376B1 (en) Structure lifting method using steel pipe member with lifting jack
CN209349757U (en) Wielding neck means for correcting
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
KR20140006180U (en) Apparatus for supporting a joint pipe
CN110144927B (en) Device for embedding foundation bolt group
CN103132461A (en) Flexible bracket device for steel truss girder bridge cantilever construction
CN104729935A (en) Adjustable fastener-type template system supporting test device
CN216272860U (en) Adjustable hinge type jack for tied beam capping beam construction
CN209508801U (en) A kind of support temporary support

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160706

Termination date: 20211103