CN104278843A - Correction device applied to lifting and butting of steel structure beams and application method of correction device - Google Patents
Correction device applied to lifting and butting of steel structure beams and application method of correction device Download PDFInfo
- Publication number
- CN104278843A CN104278843A CN201410605507.XA CN201410605507A CN104278843A CN 104278843 A CN104278843 A CN 104278843A CN 201410605507 A CN201410605507 A CN 201410605507A CN 104278843 A CN104278843 A CN 104278843A
- Authority
- CN
- China
- Prior art keywords
- jack
- crossbeam
- bolt
- steel structure
- hoisting beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a correction device applied to lifting and butting of steel structure beams and an application method of the correction device. The correction device comprises an adjustable hoop, a supporting arm and a jack. The correction device is fixed to the end of the connected steel structure beams and is provided with a fulcrum, the jack is arranged on the fulcrum and is used for controlling and regulating the relative displacement of the ends of the lifted steel structure beams, and then the steel structure beams can be accurately butted and installed. The correction device is suitable for the steel structure beams with different sections, can overcome the difficulty in high altitude control and in regulation of relative displacement of a lifted beam and a fixed beam, and has the advantages of simple structure and convenience in control and regulation.
Description
Technical field
The present invention relates to project installation technical field, especially a kind of deviation correcting device of steel structure girder lifting docking and using method.
Background technology
The lifting of prior art large-scale steel structure beam, especially the lifting of steel structure girder or steel truss continuously, in hoisting process, the docking of termination be fixedly a very complicated job, be also a critical process of steel structure girder connection, Problems existing is, after steel structure girder lifting tentatively puts in place, to carry owing to being subject to wind, the impact of the factor such as crane stiff, make steel structure girder cause at high oscillating air the phenomenon of lateral displacement to can hardly be avoided, in addition work high above the ground, security risk is large; Can how to make the hoisting beam of steel structure girder accurately dock with the termination of clamped beam, be the key of dealing with problems in the relative displacement of high-altitude controlling and adjustment hoisting beam and clamped beam.
Summary of the invention
The object of the invention is deviation correcting device and using method that a kind of steel structure girder lifting docking is provided for the deficiencies in the prior art, the present invention adopts and deviation correcting device is fixed on the termination being connected steel structure girder, deviation correcting device arranges fulcrum, fulcrum arranges jack, with the relative displacement of jack controlling and adjustment lifting steel structure girder termination, realize accurate docking and the installation of steel structure girder.
The concrete technical scheme realizing the object of the invention is:
A kind of deviation correcting device of steel structure girder lifting docking, its feature comprises adjustable hoop, support arm and jack, described adjustable hoop is by crossbeam, vertical columns, active column and lock bolt composition, crossbeam is provided with adjustment bolt block and adjustment bolt, the top of active column is provided with crossbeam hole and regulates screw, the middle part of vertical columns is provided with supporting arm base, supporting arm base is provided with and supports arm aperture and trip bolt, the bottom of vertical columns and active column is also arranged with locking screw keyhole, vertical columns welds with one end of crossbeam, active column is contained in the other end of crossbeam through crossbeam borehole jack, adjustment bolt engages with the adjustment bolt block on crossbeam through the adjustment screw on active column, lock bolt connects through the locking screw keyhole on vertical columns and active column, described support arm is provided with jack pad assembly, and fix through trip bolt in the support arm aperture that support arm is through adjustable hoop, jack is located on the jack pad assembly of support arm.
Implement a using method for described device, its feature comprises the steps:
A), the lifting of steel structure girder:
Be called hoisting beam for ease of describing the following steel structure girder by wish lifting, the steel structure girder be attached thereto is called clamped beam;
With lifting appliance hoisting beam sling and tentatively put in place, being adopted the vertical height position of cushion block adjustment hoisting beam and clamped beam termination by lifting appliance;
B), the determination of correction point position:
Check hoisting beam and clamped beam two axial lines deviation in the horizontal direction, confirm the direction of hoisting beam for correction, namely determine the stressed side of hoisting beam;
C), the installation of deviation correcting device is with fixing:
To sling adjustable hoop, and make crossbeam, active column and vertical columns above clamped beam;
Lock bolt is installed, tightens the adjustment bolt on crossbeam and lock bolt, adjustable hoop and clamped beam are connected;
Jack is loaded on the jack pad assembly of support arm;
By adjustment support arm in the position supporting arm aperture, determine that jack acts on the stress point of hoisting beam, and with trip bolt, support arm and vertical columns are fixed;
D), correction is implemented:
Start jack, the top of jack acts on the stress point of hoisting beam, and the deviate between the axis of hoisting beam and the axis of clamped beam is reduced gradually, until within the misalignment of axe scope reaching technological requirement;
E), mounting clamp crab bolt:
The clamping plate that dock with clamped beam termination of hoisting beam are installed, with bolt, clamping plate hoisting beam are docked with the termination of clamped beam and fix;
F), deviation correcting device is removed:
By jack off-load, remove the lock bolt on adjustable hoop, loosen the adjustment bolt on crossbeam, hang except adjustable hoop, treat that next docking across hoisting beam correction reuses.
The present invention adopts and deviation correcting device is fixed on the termination being connected steel structure girder, deviation correcting device arranges fulcrum, fulcrum arranges jack, with the relative displacement of jack controlling and adjustment lifting steel structure girder termination, realizes accurate docking and the installation of steel structure girder.The present invention is applicable to the steel structure girder of different section, solves a difficult problem for the relative displacement at high-altitude controlling and adjustment hoisting beam and clamped beam, has that structure is simple, controlling and adjustment advantage easily.
Accompanying drawing explanation
Fig. 1 is the structural representation of apparatus of the present invention;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is using state schematic diagram of the present invention;
Fig. 4 is the using state schematic diagram of the invention process correction.
Detailed description of the invention
Consult Fig. 1, Fig. 2, apparatus of the present invention comprise adjustable hoop 1, support arm 2 and jack 3, described adjustable hoop 1 is by crossbeam 11, vertical columns 12, active column 13 and lock bolt 14 form, crossbeam 11 is provided with adjustment bolt block 111 and adjustment bolt 112, the top of active column 13 is provided with crossbeam hole 131 and regulates screw 132, the middle part of vertical columns 12 is provided with supporting arm base 122, supporting arm base 122 is provided with and supports arm aperture 124 and trip bolt 123, the bottom of vertical columns 12 and active column 13 is also arranged with locking screw keyhole 121, vertical columns 12 welds with one end of crossbeam 11, active column 13 is sleeved on the other end of crossbeam 11 through crossbeam hole 131, adjustment bolt 112 engages with the adjustment bolt block 111 on crossbeam 11 through the adjustment screw 132 on active column 13, lock bolt 14 connects through the locking screw keyhole 121 on vertical columns 12 and active column 13, described support arm 2 is provided with jack pad assembly 21, and the support arm aperture 124 that support arm 2 is through adjustable hoop 1 is interior and fixing through trip bolt 123, and jack 3 is located on the jack pad assembly 21 of support arm 2.
The embodiment of the present invention:
Consult Fig. 1, Fig. 2, Fig. 3, Fig. 4, be installed as example with Large Scale and Continuous steel structure girder, following the steel structure girder for lifting is called hoisting beam for ease of describing, the steel structure girder be attached thereto is called clamped beam, and its step is as follows:
A), the lifting of steel structure girder:
With lifting appliance hoisting beam sling and tentatively put in place, by the fine setting of lifting appliance, adopting the vertical height position of cushion block adjustment hoisting beam and clamped beam termination;
B), the determination of correction point position:
Check that hoisting beam and clamped beam two axial lines are in the deviation of horizontal level, confirm the direction of hoisting beam for correction, determine the stressed side of hoisting beam;
C), the installation of deviation correcting device is with fixing:
Remove the lock bolt 14 on adjustable hoop 1, by the adjustment bolt 112 mobile active column 13 on crossbeam 11 on adjustment crossbeam 11, make the distance between active column 13 and vertical columns 12 be greater than the width 10 ~ 30mm of clamped beam; To sling adjustable hoop 1, make vertical columns 12 be positioned at the stressed side of hoisting beam, and make crossbeam 11, active column 13 and vertical columns 12 above clamped beam; By lock bolt 14 through the locking screw keyhole 121 on vertical columns 12 and active column 13, tighten the adjustment bolt 112 on crossbeam 11 and lock bolt 14, adjustable hoop 1 and clamped beam are connected; Jack 3 is loaded on the jack pad assembly 21 of support arm 2; By adjustment support arm 2 in the position supporting arm aperture 124, determine that jack 3 acts on the stress point of hoisting beam, and with trip bolt 123, support arm 2 and vertical columns 12 are fixed;
D), correction is implemented:
Start jack 3, the top of jack 3 acts on the stress point of hoisting beam, and the deviate between the axis of hoisting beam and the axis of clamped beam is reduced gradually, until reach the misalignment of axe scope of technological requirement;
E), mounting clamp crab bolt:
The clamping plate that dock with clamped beam termination of hoisting beam are installed, with bolt, clamping plate hoisting beam are docked with the termination of clamped beam and fix;
F), deviation correcting device is removed:
By jack 3 off-load, remove the lock bolt 14 on adjustable hoop 1, loosen the adjustment bolt 112 on crossbeam 11, remove adjustable hoop 1, treat that next docking across hoisting beam correction reuses.
The present invention is not only applicable to the unsettled side direction correction of steel structure girder, steel structure truss component, is also applicable to the unsettled side direction correction of large-scale combined steel structure member.
The middle part of vertical columns 12 of the present invention is provided with and supports arm aperture 124, support arm 2 is through and supports in arm aperture 124, can be stretched out by the either end supporting arm aperture 124, what make very heavy topmast point on adjustable hoop 1 arranges two-way choice, with the hoisting beam in satisfied difference correction direction, namely tackle the hoisting beam of different stressed side.
Claims (2)
1. the deviation correcting device of a steel structure girder lifting docking, it is characterized in that it comprises adjustable hoop (1), support arm (2) and jack (3), described adjustable hoop (1) is by crossbeam (11), vertical columns (12), active column (13) and lock bolt (14) composition, crossbeam (11) is provided with adjustment bolt block (111) and adjustment bolt (112), the top of active column (13) is provided with crossbeam hole (131) and regulates screw (132), the middle part of vertical columns (12) is provided with supporting arm base (122), supporting arm base (122) is provided with and supports arm aperture (124) and trip bolt (123), the bottom of vertical columns (12) and active column (13) is also arranged with locking screw keyhole (121), vertical columns (12) welds with one end of crossbeam (11), active column (13) is sleeved on the other end of crossbeam (11) through crossbeam hole (131), adjustment bolt (112) is engaged with the adjustment bolt block (111) on crossbeam (11) through the adjustment screw (132) on active column (13), lock bolt (14) connects through the locking screw keyhole (121) on vertical columns (12) and active column (13), described support arm (2) is provided with jack pad assembly (21), and the support arm aperture (124) that support arm (2) is through adjustable hoop (1) is interior and fixing through trip bolt (123), and jack (3) is located on the jack pad assembly (21) of support arm (2).
2. implement the claims a using method for device described in 1, it is characterized in that it comprises the steps:
A), the lifting of steel structure girder:
Be called hoisting beam for ease of describing the following steel structure girder by wish lifting, the steel structure girder be attached thereto is called clamped beam;
With lifting appliance hoisting beam sling and tentatively put in place, being adopted the vertical height position of cushion block adjustment hoisting beam and clamped beam termination by lifting appliance;
B), the determination of correction point position:
Check hoisting beam and clamped beam two axial lines deviation in the horizontal direction, confirm the direction of hoisting beam for correction, namely determine the stressed side of hoisting beam;
C), the installation of deviation correcting device is with fixing:
To sling adjustable hoop (1), and make crossbeam (11), active column (13) and vertical columns (12) above clamped beam;
Lock bolt (14) is installed, tightens the adjustment bolt (112) on crossbeam (11) and lock bolt (14), adjustable hoop (1) and clamped beam are connected;
Jack (3) is loaded on the jack pad assembly (21) of support arm (2);
By adjustment support arm (2) in the position supporting arm aperture (124), determine that jack (3) acts on the stress point of hoisting beam, and with trip bolt (123), support arm (2) and vertical columns (12) are fixed;
D), correction is implemented:
Start jack (3), the top of jack (3) acts on the stress point of hoisting beam, and the deviate between the axis of hoisting beam and the axis of clamped beam is reduced gradually, until within the misalignment of axe scope reaching technological requirement;
E), mounting clamp crab bolt:
The clamping plate that dock with clamped beam termination of hoisting beam are installed, with bolt, clamping plate hoisting beam are docked with the termination of clamped beam and fix;
F), deviation correcting device is removed:
By jack (3) off-load, remove the lock bolt (14) on adjustable hoop (1), loosen the adjustment bolt (112) on crossbeam (11), hang except adjustable hoop (1), treat that next docking across hoisting beam correction reuses.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410605507.XA CN104278843B (en) | 2014-11-03 | 2014-11-03 | The deviation correcting device of a kind of steel structure girder lifting docking and using method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410605507.XA CN104278843B (en) | 2014-11-03 | 2014-11-03 | The deviation correcting device of a kind of steel structure girder lifting docking and using method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104278843A true CN104278843A (en) | 2015-01-14 |
CN104278843B CN104278843B (en) | 2016-07-06 |
Family
ID=52254144
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410605507.XA Expired - Fee Related CN104278843B (en) | 2014-11-03 | 2014-11-03 | The deviation correcting device of a kind of steel structure girder lifting docking and using method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104278843B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106320721A (en) * | 2016-09-09 | 2017-01-11 | 中国核工业二三建设有限公司 | Aligning and leveling device for metal reactor core shell of nuclear power plant |
CN108775075A (en) * | 2018-07-17 | 2018-11-09 | 北京市第三建筑工程有限公司 | A kind of adjusting apparatus for overhanging steel structure |
CN111663792A (en) * | 2020-05-29 | 2020-09-15 | 重庆建工集团股份有限公司 | Steel cantilever truss member space positioning device |
CN113530265A (en) * | 2021-07-20 | 2021-10-22 | 中国路桥工程有限责任公司 | Steel beam construction device and construction method |
CN113882697A (en) * | 2021-10-27 | 2022-01-04 | 河南省水利勘测设计研究有限公司 | Positioning adjusting rod for assembling of assembled cavity structure |
CN115492411A (en) * | 2022-10-19 | 2022-12-20 | 中铁五局集团建筑工程有限责任公司 | High-altitude cantilever steel structure unitized high-precision rapid butt joint device and butt joint method thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1037475A (en) * | 1996-07-23 | 1998-02-10 | Ohbayashi Corp | Strain correction system of steel framed building |
CN202866303U (en) * | 2012-09-19 | 2013-04-10 | 湖南金海钢结构股份有限公司 | Installing and positioning fixing support for steel structure frame primary and secondary beam and secondary beam |
CN203113811U (en) * | 2013-03-05 | 2013-08-07 | 马鞍山十七冶工程科技有限责任公司 | Simple correction device for installation perpendicularity of steel column |
CN203821865U (en) * | 2014-03-18 | 2014-09-10 | 中国三冶集团有限公司 | Adjusting device for installing gap of H-shaped steel beam |
CN203879026U (en) * | 2014-05-04 | 2014-10-15 | 安徽富煌钢构股份有限公司 | Aerial calibration adjuster for super high-rise steel structure box-shaped steel column |
CN204112752U (en) * | 2014-11-03 | 2015-01-21 | 中建七局(上海)有限公司 | A kind of deviation correcting device of steel structure girder lifting docking |
-
2014
- 2014-11-03 CN CN201410605507.XA patent/CN104278843B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1037475A (en) * | 1996-07-23 | 1998-02-10 | Ohbayashi Corp | Strain correction system of steel framed building |
CN202866303U (en) * | 2012-09-19 | 2013-04-10 | 湖南金海钢结构股份有限公司 | Installing and positioning fixing support for steel structure frame primary and secondary beam and secondary beam |
CN203113811U (en) * | 2013-03-05 | 2013-08-07 | 马鞍山十七冶工程科技有限责任公司 | Simple correction device for installation perpendicularity of steel column |
CN203821865U (en) * | 2014-03-18 | 2014-09-10 | 中国三冶集团有限公司 | Adjusting device for installing gap of H-shaped steel beam |
CN203879026U (en) * | 2014-05-04 | 2014-10-15 | 安徽富煌钢构股份有限公司 | Aerial calibration adjuster for super high-rise steel structure box-shaped steel column |
CN204112752U (en) * | 2014-11-03 | 2015-01-21 | 中建七局(上海)有限公司 | A kind of deviation correcting device of steel structure girder lifting docking |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106320721A (en) * | 2016-09-09 | 2017-01-11 | 中国核工业二三建设有限公司 | Aligning and leveling device for metal reactor core shell of nuclear power plant |
CN106320721B (en) * | 2016-09-09 | 2023-10-20 | 中国核工业二三建设有限公司 | Alignment and leveling device for metal reactor core shell of nuclear power station |
CN108775075A (en) * | 2018-07-17 | 2018-11-09 | 北京市第三建筑工程有限公司 | A kind of adjusting apparatus for overhanging steel structure |
CN111663792A (en) * | 2020-05-29 | 2020-09-15 | 重庆建工集团股份有限公司 | Steel cantilever truss member space positioning device |
CN113530265A (en) * | 2021-07-20 | 2021-10-22 | 中国路桥工程有限责任公司 | Steel beam construction device and construction method |
CN113882697A (en) * | 2021-10-27 | 2022-01-04 | 河南省水利勘测设计研究有限公司 | Positioning adjusting rod for assembling of assembled cavity structure |
CN113882697B (en) * | 2021-10-27 | 2023-01-24 | 河南省水利勘测设计研究有限公司 | Positioning adjusting rod for assembling of assembled cavity structure |
CN115492411A (en) * | 2022-10-19 | 2022-12-20 | 中铁五局集团建筑工程有限责任公司 | High-altitude cantilever steel structure unitized high-precision rapid butt joint device and butt joint method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN104278843B (en) | 2016-07-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104278843B (en) | The deviation correcting device of a kind of steel structure girder lifting docking and using method | |
CN106006404A (en) | Super-high-rise external movable arm tower crane climbing supporting device | |
CN105064670A (en) | Exterior wall suspension board pouring form board erecting support | |
CN204112752U (en) | A kind of deviation correcting device of steel structure girder lifting docking | |
CN109332980A (en) | Wielding neck means for correcting and bearing calibration | |
CN105040591A (en) | Positioning device for waveform steel web and positioning method thereof | |
CN109138456A (en) | It is a kind of for adjusting the adjustment device of factory building steel column absolute altitude | |
CN205743048U (en) | Correction positioner installed by a kind of curtain wall large-size column | |
CN206408969U (en) | A kind of support meanss for being used to adjust bent cap vertical and horizontal gradient | |
CN101492147A (en) | Crane beam scale height regulation method | |
CN102720159B (en) | Adjusting device specially for steel hoop two-way suspension supporting system | |
CN204530501U (en) | The support bearing of arc rib alignment is controlled during a kind of constructability | |
CN201347590Y (en) | Quick connection and calibration clamp for steel column joint | |
KR200462150Y1 (en) | Jig set for setting the pump tower in the cargo tank of LNG carrier | |
JP2024508194A (en) | Boom tray and boom nut attachment device for girder lifting equipment | |
CN102409866A (en) | Auxiliary component for vertical butting operation and construction method | |
CN209349757U (en) | Wielding neck means for correcting | |
CN102155097B (en) | Locating device for installing large embedded member of concrete wall and installing method thereof | |
CN205000249U (en) | Cable -stay bridge king -tower cable pipe mounting adjustment support | |
CN102530744A (en) | Connecting beam assembly and truss arm system | |
CN103031846B (en) | Straddle type stepped hydraulic support guide frame | |
CN209508801U (en) | A kind of support temporary support | |
CN105098658B (en) | A kind of insulator exchange apparatus | |
CN216272860U (en) | Adjustable hinge type jack for tied beam capping beam construction | |
CN104265003A (en) | Adjustable frame for sliding of steel structure truss |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160706 Termination date: 20211103 |