CN104266631A CN201410549797.0A CN201410549797A CN104266631A CN 104266631 A CN104266631 A CN 104266631A CN 201410549797 A CN201410549797 A CN 201410549797A CN 104266631 A CN104266631 A CN 104266631A
Authority
CN
China
Prior art keywords
power tower
module
monitoring device
monitoring
acceleration sensor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410549797.0A
Other languages
English (en)
Inventor
梁晓芝
赵博
李晓璐
郭鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Datong Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Datong Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Datong Power Supply Co of State Grid Shanxi Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410549797.0A priority Critical patent/CN104266631A/zh
Publication of CN104266631A publication Critical patent/CN104266631A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C9/00Measuring inclination, e.g. by clinometers, by levels

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Electric Cable Installation (AREA)

Abstract

本发明具体为一种电力塔倾斜监测装置,解决了电力塔倾斜后不易监测和调整的问题。电力塔倾斜监测装置,包括在电力塔四个支脚处埋设液压泵,在电力塔正中水平平台设立三轴加速度传感器模块,液压泵均连接到油箱其油路上设有电磁阀,三轴加速度传感器模块连接到CPU模块,CPU模块连出有GPRS模块,CPU模块还连接到电磁阀。本发明结构简单、判断精确、工作可靠、不易发生误操作且不受使用环境的限制。本发明解决了人工查巡耗费人力、物力的问题,特别是破坏性倾斜能够实时报告,起到重要的监测作用。

Description

电力塔倾斜监测装置
技术领域
本发明涉及电铁塔监测装置,具体为一种电力塔倾斜监测装置。
背景技术
在输电线路中,电力塔起着十分重要的作用。在电力塔所在的地方往往会由于地质结构的变化或其它原因造成电力塔倾斜。在以往的监测设备中,有的需要人工查看的方式进行查巡,有的则会由于灰尘等的遮挡,导致检测不准,或难以实现监测功能,起不到应有的作用。
发明内容
本发明为了解决电力塔倾斜后不易监测和调整的问题,提供了一种电力塔倾斜监测装置。
本发明是采用如下技术方案实现的:电力塔倾斜监测装置,包括在电力塔四个支脚处埋设液压泵,在电力塔正中水平平台设立三轴加速度传感器模块,液压泵均连接到油箱其油路上设有电磁阀,三轴加速度传感器模块连接到CPU模块,CPU模块连出有GPRS模块,CPU模块还连接到电磁阀。
工作时,三轴加速度传感器监测电力塔倾斜数据,将角度数据发送给CPU模块,CPU模块先判断角度数据是否在可控范围内,若不在可控范围内,则启动GPRS模块以短信方式通知管理人员;若在可控范围内,CPU模块通过角度数据换算四个支角的液压泵伸出高度,然后利用电磁阀控制液压泵伸缩,直至三轴加速度传感器监测电力塔没有倾斜,然后关断电磁阀,液压泵停止工作。
本发明的有益效果如下:本发明在电力塔四个支脚处埋设液压泵通过三轴加速度传感器监测来控制进行倾斜监测并调整。本发明结构简单、判断精确、工作可靠、不易发生误操作且不受使用环境的限制。本发明解决了人工查巡耗费人力、物力的问题,特别是破坏性倾斜能够实时报告,起到重要的监测作用。
附图说明
图1为本发明系统连接结构示意图;
图中:1-CPU模块,2-GPRS模块,3-三轴加速度传感器模块,4-油箱,5-电磁阀,6-液压泵。
具体实施方式
电力塔倾斜监测装置,包括在电力塔四个支脚处埋设液压泵6,在电力塔正中水平平台设立三轴加速度传感器模块3,液压泵6均连接到油箱4其油路上设有电磁阀5,三轴加速度传感器模块3连接到CPU模块1,CPU模块1连出有GPRS模块2,CPU模块1还连接到电磁阀5。

Claims (1)

1. 一种电力塔倾斜监测装置,其特征在于:包括在电力塔四个支脚处埋设液压泵(6),在电力塔正中水平平台设立三轴加速度传感器模块(3),液压泵(6)均连接到油箱(4)其油路上设有电磁阀(5),三轴加速度传感器模块(3)连接到CPU模块(1),CPU模块(1)连出有GPRS模块(2),CPU模块(1)还连接到电磁阀(5)。
CN201410549797.0A 2014-10-17 2014-10-17 电力塔倾斜监测装置 Pending CN104266631A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410549797.0A CN104266631A (zh) 2014-10-17 2014-10-17 电力塔倾斜监测装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410549797.0A CN104266631A (zh) 2014-10-17 2014-10-17 电力塔倾斜监测装置

Publications (1)

Publication Number Publication Date
CN104266631A true CN104266631A (zh) 2015-01-07

Family

ID=52158172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410549797.0A Pending CN104266631A (zh) 2014-10-17 2014-10-17 电力塔倾斜监测装置

Country Status (1)

Country Link
CN (1) CN104266631A (zh)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09125405A (ja) * 1995-10-26 1997-05-13 Shirakawa Denki Doboku Kk 傾斜塔脚深礎基礎
WO2001040585A1 (en) * 1999-11-30 2001-06-07 Brosnihan, Gail, Anne Foundation structure and erection of towers
CN103556649A (zh) * 2013-11-08 2014-02-05 广东明阳风电产业集团有限公司 海上风力发电机组的导管架调平机构
CN103575335A (zh) * 2013-11-11 2014-02-12 东北农业大学 输电杆塔在线监测系统
CN203668981U (zh) * 2013-12-01 2014-06-25 国家电网公司 地质沉降区输电线路铁塔倾斜检测与抬升系统

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09125405A (ja) * 1995-10-26 1997-05-13 Shirakawa Denki Doboku Kk 傾斜塔脚深礎基礎
WO2001040585A1 (en) * 1999-11-30 2001-06-07 Brosnihan, Gail, Anne Foundation structure and erection of towers
CN103556649A (zh) * 2013-11-08 2014-02-05 广东明阳风电产业集团有限公司 海上风力发电机组的导管架调平机构
CN103575335A (zh) * 2013-11-11 2014-02-12 东北农业大学 输电杆塔在线监测系统
CN203668981U (zh) * 2013-12-01 2014-06-25 国家电网公司 地质沉降区输电线路铁塔倾斜检测与抬升系统

Similar Documents

Publication Publication Date Title
CN204080880U (zh) 一种监测基坑变形的预警装置
CN102681553B (zh) 泵车臂架收回的控制方法、系统和泵车
CN204286436U (zh) 一种全站仪辅助调平装置
CN205175360U (zh) 一种利用激光位移传感器监测滑坡的装置
CN202186366U (zh) 一种防倾翻装置及工程机械
CN202729612U (zh) 起重机移动配重的控制装置和起重机
CN105258650A (zh) 一种利用激光位移传感器监测滑坡的装置
CN203224235U (zh) 一种杆塔倾斜监测装置
CN108205878A (zh) 崩塌监测方法及崩塌监测系统
CN202882009U (zh) 装载机及其油缸限位保护装置、油缸限位保护系统
CN203705107U (zh) 一种测力装置和起重机
CN207062917U (zh) 边坡位移监控自动报警装置
CN203024774U (zh) 水平平衡报警器
CN104266631A (zh) 电力塔倾斜监测装置
CN109764801B (zh) 位移监测站及地质监测预警系统
CN104480976B (zh) 一种可视化桩基静载试验远程无线监控系统
CN207608901U (zh) 一种用于建筑地基的钎探装置
CN106193626A (zh) 一种装配式楼体的墙板吊装装置和吊装方法
CN208635780U (zh) 一种分布式地质载荷实验实时自动监测系统
CN109932119A (zh) 一种接地线挂接状态监测装置、接地线及接地线系统
CN202928681U (zh) 自带限位的称重传感器模块
CN213118498U (zh) 一种用于供水管网的在线监控装置
CN109764988A (zh) 土压力监测站及地灾监测预警系统
CN202522233U (zh) 防止倒杆报警装置
CN203587098U (zh) 一种用于超大拼接平台的台下监测系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150107