CN104141390A - AP1000 nuclear power dome assembling jig frame - Google Patents
AP1000 nuclear power dome assembling jig frame Download PDFInfo
- Publication number
- CN104141390A CN104141390A CN201310163894.1A CN201310163894A CN104141390A CN 104141390 A CN104141390 A CN 104141390A CN 201310163894 A CN201310163894 A CN 201310163894A CN 104141390 A CN104141390 A CN 104141390A
- Authority
- CN
- China
- Prior art keywords
- dome
- nuclear power
- upright columns
- jig frame
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
The invention relates to an AP1000 nuclear power dome assembling jig frame which comprises inner-circle upright columns, outer-circle upright columns and concrete foundations. The inner-circle upright columns are used for supporting dome ring beams and are arranged along the integral peripheral direction of the AP1000 nuclear dome assembling jig frame, each outer-circle upright column is used for supporting an end of a corresponding dome radial beam, the outer-circle upright columns are arranged along the integral peripheral direction of the AP1000 nuclear power dome assembling jig frame, each concrete foundation is used for supporting the other end of the corresponding dome radial beam, and the concrete foundations are arranged along the integral peripheral direction of the AP1000 nuclear power dome assembling jig frame. Each of the inner-circle upright columns and the outer-circle upright columns axially comprises two sections, the upper half sections of the inner-circle upright columns and the upper half sections of the outer-circle upright columns are detached after a dome body is completely assembled, and the lower half sections of the inner-circle upright columns and the lower half sections of the outer-circle upright columns are connected with one another by supporting brackets; the supporting brackets are connected with dome modules. The AP1000 nuclear power dome assembling jig frame has the advantages that the AP1000 nuclear power dome assembling jig frame is low in material consumption and easy and convenient to operate, and is easy to detach and transport owing to the fact that structural bolts are connected with joints, and large spaces of a jig frame structure and a lower opening of a dome can be used for reversely transporting and mounting materials of the internal modules; the jig assembling duration and the dome construction period can be effectively shortened, and the dome assembling precision can be improved.
Description
Technical field
The present invention relates to the assembled moulding bed of a kind of AP1000 nuclear power dome, particularly relate to a kind of technical field that belongs to nuclear power building operations, a kind of simple and easy flexible especially, the assembled jig frame special of AP1000 dome of be convenient to restructuring, dismantling, reuse.
Background technology
AP1000 nuclear power technology is the safest, state-of-the-art business nuclear power technology in current global nuclear power market, is also Chinese generation Ⅲ nuclear power proprietary technology simultaneously.AP1000 steel dome-shaped becomes superposition mode, needs the special moulding bed of design to meet the requirement of whole site operation.But it is prefabricated and assembled that traditional moulding bed majority integrates, project organization is complicated, take up room large, and the engineering time is long.Therefore need badly and provide a kind of simple and easy flexible, be convenient to the assembled jig frame special of AP1000 dome of restructuring, dismounting, recycling.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of splicing accuracy, minimizing use location, space of improving dome, shortens the assembled moulding bed of AP1000 nuclear power dome of construction period simultaneously.
For solving the problems of the technologies described above, the assembled moulding bed of a kind of AP1000 nuclear power of the present invention dome, comprises the concrete foundation along whole circumferential arrangement that supports the inner ring column along whole circumferential arrangement of dome ring beam, the outer ring column along whole circumferential arrangement that supports dome radial girders one end, the support dome radial girders other end.
Between inner ring column, by inner ring crossbeam shaped steel and diagonal brace, fix.
Between the column of outer ring, by outer ring crossbeam shaped steel and diagonal brace, fix.
Inner ring column and column corresponding position, outer ring are fixed by Internal and external cycle crossbeam and Internal and external cycle diagonal brace.
Concrete foundation is along being circumferentially evenly arranged, and quantity is 32.
Inner ring column and outer ring column form by two sections vertically, after dome body is assembled, the upper semisection of inner ring column and outer ring column are removed, and inner ring column is connected by supporting bracket with the lower semisection of outer ring column; Supporting bracket is connected with dome module.
The present invention is meeting under the prerequisite of the assembled requirement of dome unit, and moulding bed material usage is few, easy and simple to handle, structural bolts connected node, and quick detachable easy transportation, jig structure and dome end opening space are larger, can be used for having bad luck, installing of internal module material; Interior construction space is large, and support is not established in centre, and the limitation in the constructing operation of having avoided causing too much because of intermediate supports can effectively shorten the assembled duration of mold and the construction period of dome, improves the assembly precision of dome.
Accompanying drawing explanation
Fig. 1 is the assembled layout plan of dome moulding bed.
Fig. 2 is that the outer coil unit of dome launches schematic diagram.
Fig. 3 is coil unit deploying portion figure in dome.
Fig. 4 is dome radial girders support figure.
Fig. 5 is dome modular platform support figure.
In figure: 1 is outer ring column, 2 is inner ring column, and 3 is that outer ring crossbeam shaped steel, 4 is inner ring crossbeam shaped steel, and 5 is Internal and external cycle crossbeam, 6 for supporting bracket, and 7 is diagonal brace, and 8 is Internal and external cycle diagonal brace, and 9 is dome module, 10 is dome radial girders, and 11 is dome ring beam, and 12 is concrete foundation.
The specific embodiment
Below in conjunction with drawings and Examples, the present invention is further detailed explanation.
Moulding bed installation procedure: measurement unwrapping wire-column unit installation-intercolumniation support and connection on leveling-basis are installed on moulding bed basis.
Outer coil unit embodiment: along being connected with outer ring crossbeam shaped steel 3, diagonal brace 7 by bolt between the outer ring column 1 of whole circumferential arrangement, form and stablize trussed construction, as shown in Figure 2.
Interior coil unit embodiment: along being connected with inner ring crossbeam shaped steel 4, diagonal brace 7 by bolt between the inner ring column 2 of whole circumferential arrangement, form and stablize trussed construction, as shown in Figure 3.
Embodiment between inside and outside circle: outer ring column 1, inner ring column 2 corresponding positions employing bolts and Internal and external cycle diagonal brace 8, Internal and external cycle crossbeam 5 connected modes, form the trussed construction between inside and outside circle column, guarantee the plane stability of hoop framework.
The embodiment of dome and moulding bed: dome radial girders 10 one end are bearing in concrete foundation 12, the other end is bearing on outer ring column 1, forms dome body construction with 11 welding of dome ring beam.Concrete foundation 12 is along being circumferentially evenly arranged, and quantity is 32.Dome ring beam 11 is supported by inner ring column 2.Between basis and steel column, do not establish support, for the accessory module of dome body provides enough assembled spaces.As shown in Figure 4.
Each forms by two sections vertically for outer ring column 1, inner ring column 2, two is intersegmental with bolts, after dome body is assembled, the upper semisection of outer ring column 1, inner ring column 2 to be removed, the lower semisection of outer ring column 1, inner ring column 2 is with bolts with support bracket 6.Support bracket and by bolt, be connected with dome module 9 again, play a supporting role, as shown in Figure 5.
Claims (6)
- The assembled moulding bed of 1.AP1000 nuclear power dome, is characterized in that: comprise the concrete foundation along whole circumferential arrangement that supports the inner ring column along whole circumferential arrangement of dome ring beam, the outer ring column along whole circumferential arrangement that supports dome radial girders one end, the support dome radial girders other end.
- 2. the assembled moulding bed of a kind of AP1000 nuclear power dome according to claim 1, is characterized in that: between described inner ring column, by inner ring crossbeam shaped steel and diagonal brace, fix.
- 3. the assembled moulding bed of a kind of AP1000 nuclear power dome according to claim 1, is characterized in that: between the column of described outer ring, by outer ring crossbeam shaped steel and diagonal brace, fix.
- 4. the assembled moulding bed of a kind of AP1000 nuclear power dome according to claim 1, is characterized in that: described inner ring column and column corresponding position, outer ring are fixed by Internal and external cycle crossbeam and Internal and external cycle diagonal brace.
- 5. the assembled moulding bed of a kind of AP1000 nuclear power dome according to claim 1, is characterized in that: described concrete foundation is along being circumferentially evenly arranged, and quantity is 32.
- 6. the assembled moulding bed of a kind of AP1000 nuclear power dome according to claim 1, it is characterized in that: described inner ring column and outer ring column form by two sections vertically, after dome body is assembled, the upper semisection of inner ring column and outer ring column is removed, and inner ring column is connected by supporting bracket with the lower semisection of outer ring column; Supporting bracket is connected with dome module.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310163894.1A CN104141390B (en) | 2013-05-07 | 2013-05-07 | AP1000 nuclear power dome assembly moulding bed |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310163894.1A CN104141390B (en) | 2013-05-07 | 2013-05-07 | AP1000 nuclear power dome assembly moulding bed |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104141390A true CN104141390A (en) | 2014-11-12 |
CN104141390B CN104141390B (en) | 2016-11-23 |
Family
ID=51850707
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310163894.1A Active CN104141390B (en) | 2013-05-07 | 2013-05-07 | AP1000 nuclear power dome assembly moulding bed |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104141390B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105401732A (en) * | 2016-02-03 | 2016-03-16 | 中国核工业华兴建设有限公司 | Assembling method of large steel structure module of nuclear power plant |
CN105665952A (en) * | 2014-11-21 | 2016-06-15 | 中国核工业第五建设有限公司 | Process for assembling module of vapor generator compartment and refueling channel of nuclear power station |
CN109610848A (en) * | 2018-12-06 | 2019-04-12 | 中国建筑第八工程局有限公司 | Moulding bed device and its construction method for assembled cambered surface network |
CN114986445A (en) * | 2022-06-09 | 2022-09-02 | 浙江东南网架股份有限公司 | Factory assembly method for spherical reticulated shell dome structure |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07292992A (en) * | 1994-04-22 | 1995-11-07 | Horiuchi Komuten:Kk | Method for assembling steel structure and centering pin for use therein |
JPH08291579A (en) * | 1995-04-24 | 1996-11-05 | Shinyou:Kk | Pitching roof construction method of concrete house and jig to be used in its construction method |
CN2568714Y (en) * | 2002-08-06 | 2003-08-27 | 黄达余 | Green ecological house |
CN201460242U (en) * | 2009-07-21 | 2010-05-12 | 上海市第一建筑有限公司 | Assembly jig frame with net rack structure |
CN102146732A (en) * | 2011-03-09 | 2011-08-10 | 中国建筑第八工程局有限公司 | Extra-large-area hyperboloid welding ball network frame sliding construction method |
CN102179651A (en) * | 2011-04-06 | 2011-09-14 | 中国建筑第八工程局有限公司 | On-site plane trusses of extra-large welded ball net frame and method for splicing three-dimensional sections |
CN103061506A (en) * | 2012-12-28 | 2013-04-24 | 中国华冶科工集团有限公司 | Construction method of steel structure dome |
CN103061412A (en) * | 2013-01-01 | 2013-04-24 | 北京工业大学 | Method for constructing stiff supporting dome structure |
CN203284883U (en) * | 2013-05-07 | 2013-11-13 | 中国核工业二四建设有限公司 | AP1000 nuclear power dome assembly jig frame |
-
2013
- 2013-05-07 CN CN201310163894.1A patent/CN104141390B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07292992A (en) * | 1994-04-22 | 1995-11-07 | Horiuchi Komuten:Kk | Method for assembling steel structure and centering pin for use therein |
JPH08291579A (en) * | 1995-04-24 | 1996-11-05 | Shinyou:Kk | Pitching roof construction method of concrete house and jig to be used in its construction method |
CN2568714Y (en) * | 2002-08-06 | 2003-08-27 | 黄达余 | Green ecological house |
CN201460242U (en) * | 2009-07-21 | 2010-05-12 | 上海市第一建筑有限公司 | Assembly jig frame with net rack structure |
CN102146732A (en) * | 2011-03-09 | 2011-08-10 | 中国建筑第八工程局有限公司 | Extra-large-area hyperboloid welding ball network frame sliding construction method |
CN102179651A (en) * | 2011-04-06 | 2011-09-14 | 中国建筑第八工程局有限公司 | On-site plane trusses of extra-large welded ball net frame and method for splicing three-dimensional sections |
CN103061506A (en) * | 2012-12-28 | 2013-04-24 | 中国华冶科工集团有限公司 | Construction method of steel structure dome |
CN103061412A (en) * | 2013-01-01 | 2013-04-24 | 北京工业大学 | Method for constructing stiff supporting dome structure |
CN203284883U (en) * | 2013-05-07 | 2013-11-13 | 中国核工业二四建设有限公司 | AP1000 nuclear power dome assembly jig frame |
Non-Patent Citations (2)
Title |
---|
年发扬: "AP1000核电站模块化建造浅析", 《中国核科学技术进展报告(第一卷)》, 30 November 2009 (2009-11-30), pages 249 - 253 * |
李忠卫 等: "山东省博物馆新馆大跨度三维双曲面穹顶钢结构安装技术", 《施工技术》, vol. 40, no. 349, 30 September 2011 (2011-09-30) * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105665952A (en) * | 2014-11-21 | 2016-06-15 | 中国核工业第五建设有限公司 | Process for assembling module of vapor generator compartment and refueling channel of nuclear power station |
CN105665952B (en) * | 2014-11-21 | 2018-06-12 | 中国核工业第五建设有限公司 | The steam generator compartment of nuclear power station and the channel module packaging technology that reloads |
CN105401732A (en) * | 2016-02-03 | 2016-03-16 | 中国核工业华兴建设有限公司 | Assembling method of large steel structure module of nuclear power plant |
CN105401732B (en) * | 2016-02-03 | 2018-03-23 | 中国核工业华兴建设有限公司 | A kind of assemble method of nuclear power station large-sized steel construction module |
CN109610848A (en) * | 2018-12-06 | 2019-04-12 | 中国建筑第八工程局有限公司 | Moulding bed device and its construction method for assembled cambered surface network |
CN109610848B (en) * | 2018-12-06 | 2020-12-15 | 中国建筑第八工程局有限公司 | Jig frame device for assembling cambered surface grid structure and construction method thereof |
CN114986445A (en) * | 2022-06-09 | 2022-09-02 | 浙江东南网架股份有限公司 | Factory assembly method for spherical reticulated shell dome structure |
CN114986445B (en) * | 2022-06-09 | 2023-12-01 | 浙江东南网架股份有限公司 | Factory assembling method for spherical reticulated shell dome structure |
Also Published As
Publication number | Publication date |
---|---|
CN104141390B (en) | 2016-11-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104141390A (en) | AP1000 nuclear power dome assembling jig frame | |
CN203284883U (en) | AP1000 nuclear power dome assembly jig frame | |
CN204327103U (en) | A kind of reaction frame started for tunneling shield | |
CN203768942U (en) | Positioning device for embedded anchor bolts | |
CN104746862A (en) | Temporary installation operating platform on overhead equipment foundation and erecting method thereof | |
CN102535870A (en) | Tooling support for assembling and transporting nuclear-power containment-vessel cover head | |
CN211548750U (en) | Cylindrical wallboard formwork support | |
CN102146492A (en) | Method for installing converter body equipment and tooling platform | |
CN106013784A (en) | Angle iron frame template and construction method | |
CN201460303U (en) | Rapid-loading type multi-functional platform cabin | |
CN102454294A (en) | Construction method of reinforced concrete and steel structure storage bin combined frame structure | |
CN213683264U (en) | Inner ring beam joint combined assembling structure for steel structure awning of stadium | |
CN212612598U (en) | Pile and beam splicing combined type wind power foundation structure | |
CN104499707A (en) | Slip form system of large-diameter cylindrical structure and construction method thereof | |
JP4779765B2 (en) | Container support structure modification method | |
CN109235262A (en) | A kind of bridge tower steel reinforced concrete segment structure and its construction technology | |
CN102817322A (en) | Shrinkable internal model without draw bar | |
CN206091252U (en) | A interim strutting arrangement for supporting construction of cone dysmorphism steel construction | |
JP2017179827A (en) | Reinforcement structure for underground volume structure | |
CN104763159B (en) | Nuclear power CB20 module integral assembling shipping platform | |
CN112499467A (en) | Subway station expanded end assembled gantry crane track foundation and construction method thereof | |
CN211898915U (en) | Reinforced structure of steel beam column hinged joint | |
CN219241487U (en) | Steel structure cooling tower | |
CN109610332A (en) | The method and its auxiliary device of a kind of installation of Steel Pipe Concrete Tied-arch Bridge and application | |
JP2012107514A (en) | Column base used for turbine pedestal and assembling method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |