CN104102982A - Steelmaking working procedure management system and method - Google Patents

Steelmaking working procedure management system and method Download PDF

Info

Publication number
CN104102982A
CN104102982A CN201410372381.6A CN201410372381A CN104102982A CN 104102982 A CN104102982 A CN 104102982A CN 201410372381 A CN201410372381 A CN 201410372381A CN 104102982 A CN104102982 A CN 104102982A
Authority
CN
China
Prior art keywords
production
heat
time
module
working procedure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410372381.6A
Other languages
Chinese (zh)
Inventor
杨晓伟
巫乔顺
杜晓冬
陈子敏
戴明军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Iron and Steel Group Kunming Iron and Steel Co Ltd
Original Assignee
Wuhan Iron and Steel Group Kunming Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Iron and Steel Group Kunming Iron and Steel Co Ltd filed Critical Wuhan Iron and Steel Group Kunming Iron and Steel Co Ltd
Priority to CN201410372381.6A priority Critical patent/CN104102982A/en
Publication of CN104102982A publication Critical patent/CN104102982A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

The invention discloses a steelmaking working procedure management system and method. The steelmaking working procedure management system comprises a terminal module, a planning module, a Gantt chart module and a data storage module. The method comprises the following steps: adding a production plan; drawing all equipment state diagrams of the production line according to a practical production line equipment situation; plotting current production heat information; calculating the production beginning time and ending time of the heat in each working procedure according to the situation of each production working procedure; and drawing in the state diagrams. The invention can visually, integrally and effectively arrange plans, organize production and transfer production information among all posts, so that steelmaking production is enabled to be accurate and effective, a production process can be clearly, integrally and definitely recorded, a production process monitoring level is improved, production personnel can precisely master a rhythm of production, control production quality and improve a production level.

Description

A kind of steel making working procedure management system and method
Technical field
The invention belongs to Computer Applied Technology field, be specifically related to a kind of steel making working procedure management system and method.
Background technology
At present, in iron and steel enterprise's STEELMAKING PRODUCTION, for the production schedule arrangement between each operation of steel-making, mainly by manual type, undertaken, by each operation end time of control room personnel's manual confirmation, then notify subsequent processing operating personnel to prepare to receive molten steel and carry out operation.The operating personnel of each operation cannot be promptly and accurately scheduling of production situation, the production data information of the upper and lower operation of understanding.When operating personnel need to understand these information, can only be by contacting just and can obtain relevant information with total tune or upper and lower process operations personnel phone.The major defect of this disposal route is: the production schedule arranges validity not high, and the artificial production schedule arranging cannot be considered all process steps working condition comprehensively, can only the guestimate production time, and in actual production, plan can not accurately be carried out.Dispatcher cannot grasp the real-time condition of production of each operation in time, cannot accurately dispatch production.For each process operations personnel, cannot understand its upper and lower operation condition of production, lack effective communication.Actual conditions for producing, lack complete, effective record.Cannot provide accurate, reliable data to carry out condition of production analysis.Therefore, developing a kind of management system addressing the above problem is very important.
Summary of the invention
The first object of the present invention is to provide a kind of steel making working procedure management system; The second object is to provide the using method of described steel making working procedure management system.
The first object of the present invention is achieved in that and comprises terminal module, planning module, Gantt chart module, data memory module, wherein:
Terminal module: system is operated for operating personnel;
Planning module: for working out a production plan and storing data memory module into;
Gantt chart module: for calling each processing apparatus situation from data memory module and drawing production line real-time condition, draw plan information according to production scene real-time condition;
Data memory module: for storing steel making working procedure information.
The second object of the present invention is achieved in that and comprises the following steps:
A, first dispatcher adds the production schedule, selects casting plan, then to casting plan scheduling job route in adding the production schedule page, from converter, start to select to turn heat (batch) number, determine whether through Argon whether pass through refining furnace, final upper any platform casting machine, and definite heat order;
B, Gantt chart module can be produced line equipment situation according to reality, draw and produce the constitutional diagram of line all devices, and mark and draw current production heat information;
C, added after the production schedule, Gantt chart module can, according to producing each operation condition of production, calculate heat and start production time and end time in each operation, and draw out in the drawings;
If the temporary changes of D production line, direct control, adjusts heat process route in the drawings;
E, run into heat change of plan, or casting plan change, can directly delete in the drawings heat or water time information.
The present invention overcomes the difficulties such as iron and steel enterprise's STEELMAKING PRODUCTION planning, scheduling of production, inter process information flow, operation production data recording, has solved the problem of detached island of information of each operation in steelworks.The present invention can directly perceived, complete, effective scheme of arrangement, and tissue is produced and transmitted production information producing between each post.Make STEELMAKING PRODUCTION accurate and effective, it is clear, complete, definite that production run records, and improves production process monitoring level, allows producers can hold accurately rhythm of production, and production control quality improves production level.
Accompanying drawing explanation
Fig. 1 is module schematic flow sheet of the present invention.
Embodiment
Below in conjunction with accompanying drawing, the present invention is further illustrated, but never in any form the present invention is limited, and any conversion or the replacement based on training centre of the present invention, done, all belong to protection scope of the present invention.
Steel making working procedure management system of the present invention, comprises terminal module, planning module, Gantt chart module, data memory module, wherein:
Terminal module: system is operated for operating personnel;
Planning module: for working out a production plan and storing data memory module into;
Gantt chart module: for calling each processing apparatus situation from data memory module and drawing production line real-time condition, draw plan information according to production scene real-time condition;
Data memory module: for storing steel making working procedure information.
Described in terminal module be operating as typing, modification,, inquiry, deletion, early warning and analysis.
Working out a production plan described in planning module is to start to arrange process route from casting plan.
Described process route for arrange select to turn heat (batch) number, whether through Argon, whether through refining furnace, upper any platform casting machine, water time in order, the casting trade mark, specification, casting rate and whether heat is given.
Each processing apparatus situation described in Gantt chart module is electric consumption, gas consumption, water consumption, equipment rotating speed and equipment operation pattern.
Production scene real-time condition described in Gantt chart module is liquid steel temperature, molten steel composition, Metal Weight, the consumption that feeds intake, water time number and heat number.
Plan information described in Gantt chart module is watering time of be about to producing of converter and the concrete arrangement of time of heat, Argon station are about to produce waters time and the concrete arrangement of time of heat, refining furnace are about to produce waters time and the concrete arrangement of time of heat and conticaster are about to produce waters time and the concrete arrangement of time of heat.
Gantt chart module is the plan generating according to scheduling, automatically according to information such as plan, working condition, technological requirement, production order, maintenance schedule, raw material supply and equipment operation situations, calculate the arrangement of each operation production time, and dynamic drafting goes out planned outcome on picture, described planned outcome is heat and water in time scheduling of production, Argon heat and water in time scheduling of production, refining heat and water on time scheduling of production and casting machine heat and water time scheduling of production in converter; On picture, comprise STEELMAKING PRODUCTION all process steps machine operation picture, operation real time data, plan information, water time information, heat production process situation, the current production heat of converter details, the current production heat of Argon details, refining current production heat details and the current production heat of continuous casting details.
Steel making working procedure information described in data memory module is the information such as the per moment operating condition of each equipment, the per moment water consumption of each equipment, the per moment electric consumption of each equipment, the gas consumption of per moment of each equipment, the per moment running speed of each equipment, angle, pressure, station.
The using method of steel making working procedure management system of the present invention, comprises the following steps:
A, first dispatcher adds the production schedule, selects casting plan, then to casting plan scheduling job route in adding the production schedule page, from converter, start to select to turn heat (batch) number, determine whether through Argon whether pass through refining furnace, final upper any platform casting machine, and definite heat order;
B, Gantt chart module can be produced line equipment situation according to reality, draw and produce the constitutional diagram of line all devices, and mark and draw current production heat information;
C, added after the production schedule, Gantt chart module can, according to producing each operation condition of production, calculate heat and start production time and end time in each operation, and draw out in the drawings;
If the temporary changes of D production line, direct control, adjusts heat process route in the drawings;
E, run into heat change of plan, or casting plan change, can directly delete in the drawings heat or water time information.
The object of the invention is in order to overcome the difficulties such as iron and steel enterprise's STEELMAKING PRODUCTION planning, scheduling of production, inter process information flow, operation production data recording, the problem of detached island of information that solves each operation in steelworks, provides a kind of production operation scheduling method that is applicable to iron and steel enterprise's STEELMAKING PRODUCTION.Scheduling mode mainly by terminal automatically according to each operation production real-time condition in producing, the production schedule is decomposed and is arranged into each operation, and on Gantt chart, take timeline as benchmark, laterally rectangle is sign, clear each production process scheduling of production situation that marks out, and dynamic by auxiliary picture and the current production of each operation of explanatory note.Make in the production schedule all water time produce that plan information, heat information, each operation produce that real-time dynamic information can be timely, accurate, complete pass to steel-making dispatcher and all production station operating personnel, before solving, link up the problem of detached island of information having some setbacks not in time, get through information channel, make the condition of production very clear.
The technical solution adopted for the present invention to solve the technical problems is: system is comprised of planning module, Gantt chart module.Scheduling is according to production schedule task, and in planning module, establishment casting plan group are watered, and sets plan process route, and arranges heat to produce.The plan that Gantt chart module generates according to scheduling, automatically according to information such as plan, working condition, technological requirements, calculate the arrangement of each operation production time, and dynamic drafting goes out planned outcome on picture.On picture, comprise STEELMAKING PRODUCTION all process steps machine operation picture, operation real time data, plan information, water time information, heat production process situation etc.All time information of watering, the heat condition of production shows with Gantt chart square form, coordinates time shaft and current time line, picture can show all main informations of STEELMAKING PRODUCTION directly perceived, clear, accurately.For dispatching and producing, provide accurate foundation.
Method of work of the present invention:
1) first dispatcher adds the production schedule, selects casting plan, then to casting plan scheduling job route in adding the production schedule page, from converter, start to select to turn heat (batch) number, determine whether through Argon whether pass through refining furnace, final upper any platform casting machine, and definite heat order.
2) Gantt chart module can be produced line equipment situation according to reality, draws and produces the constitutional diagram of line all devices, and mark and draw current production heat information.
3) added after the production schedule, Gantt chart module can, according to producing each operation condition of production, calculate heat and start production time and end time in each operation, and draw out in the drawings.
4) if production line temporary changes, direct control in the drawings, adjusts heat process route.
5) run into heat change of plan, or casting plan change, can directly delete in the drawings heat or water time information.To complete heat plan or to be time plan modification.
The invention has the beneficial effects as follows directly perceived, complete, the effective scheme of arrangement of energy, tissue is produced and transmit production information between each post of production.Make STEELMAKING PRODUCTION accurate and effective, it is clear, complete, definite that production run records, and improves production process monitoring level, allows producers can hold accurately rhythm of production, and production control quality improves production level.
The present invention is in order to overcome the difficulties such as iron and steel enterprise's STEELMAKING PRODUCTION planning, scheduling of production, inter process information flow, operation production data recording, the problem of detached island of information that solves each operation in steelworks, provides a kind of production operation scheduling method that is applicable to iron and steel enterprise's STEELMAKING PRODUCTION.Comprise 2 modules 1, planning module 2, Gantt chart module.As shown in Figure 1.Dispatcher works out a production plan in planning module 1.Work out a production plan from casting plan, then process route be set, process route mainly comprise arrange select to turn heat (batch) number, whether through Argon, whether through refining furnace, finally go up any platform casting machine and water time in sequentially.Then in Gantt chart module, first Gantt chart module 2 can draw and produce line real-time condition according to each processing apparatus situation, then, according to each the on-the-spot condition of production and arrangements in real time, draws in the drawings plan information.If the condition of production and plan change in real time, dispatcher can carry out direct control in Gantt chart module 2.
Feature of the present invention:
A. planning module operation is simple, and it is clear that the production schedule arranges.
B. Gantt chart module can reflect current each device fabrication situation, running status in real time.
C. Gantt chart module can reflect that the production schedule arranges situation in real time.
D. data clear display in Gantt chart module, understand, complete.All information is very clear.
E. plan target can directly be revised, be deleted to Gantt chart module in data plot.
As shown in Figure 1, this figure shows working-flow and realizes disposal route, and concrete methods of realizing is as follows:
A. when staff planners carry out after the production schedule, dispatcher can arrange heat production task according to the production schedule in planning module.
B. heat scheduling of production comprise heat heat (batch) number, start the production time, heat process route, whether through argon station, order etc. information through refining furnace, upper which casting machine and in watering time whether.
C. Gantt chart module can Real-time Collection each processing apparatus service data, the current production status of automatic decision equipment then, and used picture form to draw out.
D. Gantt chart module can decompose arranged heat production task in each operation, then according to the operation condition of production, and the task of arranging production successively.
E. in Gantt chart module, can inquire about intuitively the arrangement situation of each heat production schedule.

Claims (10)

1. a steel making working procedure management system, is characterized in that comprising terminal module, planning module, Gantt chart module, data memory module, wherein:
Terminal module: system is operated for operating personnel;
Planning module: for working out a production plan and storing data memory module into;
Gantt chart module: for calling each processing apparatus situation from data memory module and drawing production line real-time condition, draw plan information according to production scene real-time condition;
Data memory module: for storing steel making working procedure information.
2. steel making working procedure management system according to claim 1, is characterized in that being operating as typing, modification, inquiry, deletion, early warning and analysis described in terminal module.
3. steel making working procedure management system according to claim 1, is characterized in that working out a production plan described in planning module is to start to arrange process route from casting plan.
4. steel making working procedure management system according to claim 3, it is characterized in that described process route for arrange select to turn heat (batch) number, whether through Argon, whether through refining furnace, upper any platform casting machine, water time in order, the trade mark, specification, the casting rate of casting and whether heat is given.
5. steel making working procedure management system according to claim 1, each processing apparatus situation described in Gantt chart module that it is characterized in that is electric consumption, gas consumption, water consumption, equipment rotating speed and equipment operation pattern.
6. steel making working procedure management system according to claim 1, is characterized in that the production scene real-time condition described in Gantt chart module is liquid steel temperature, molten steel composition, Metal Weight, the consumption that feeds intake, waters time number and heat number.
7. steel making working procedure management system according to claim 1, is characterized in that the plan information described in Gantt chart module is converter watering time of being about to produce and the concrete arrangement of time of heat, Argon station are about to produce waters time and the concrete arrangement of time of heat, refining furnace are about to produce waters time and the concrete arrangement of time of heat and conticaster are about to produce waters time and the concrete arrangement of time of heat.
8. steel making working procedure management system management according to claim 1, it is characterized in that Gantt chart module is the plan generating according to scheduling, automatically according to information such as plan, working condition, technological requirement, production order, maintenance schedule, raw material supply and equipment operation situations, calculate the arrangement of each operation production time, and dynamic drafting goes out planned outcome on picture, described planned outcome is heat and water in time scheduling of production, Argon heat and water in time scheduling of production, refining heat and water on time scheduling of production and casting machine heat and water time scheduling of production in converter; On picture, comprise STEELMAKING PRODUCTION all process steps machine operation picture, operation real time data, plan information, water time information, heat production process situation, the current production heat of converter details, the current production heat of Argon details, refining current production heat details and the current production heat of continuous casting details.
9. steel making working procedure management system according to claim 1, is characterized in that the steel making working procedure information described in data memory module is for information such as the per moment operating condition of each equipment, the per moment water consumption of each equipment, the per moment electric consumption of each equipment, the gas consumption of per moment of each equipment, the per moment running speed of each equipment, angle, pressure, stations.
10. a using method for the arbitrary described steel making working procedure management system of claim 1 ~ 9, is characterized in that comprising the following steps:
A, first dispatcher adds the production schedule, selects casting plan, then to casting plan scheduling job route in adding the production schedule page, from converter, start to select to turn heat (batch) number, determine whether through Argon whether pass through refining furnace, final upper any platform casting machine, and definite heat order;
B, Gantt chart module can be produced line equipment situation according to reality, draw and produce the constitutional diagram of line all devices, and mark and draw current production heat information;
C, added after the production schedule, Gantt chart module can, according to producing each operation condition of production, calculate heat and start production time and end time in each operation, and draw out in the drawings;
If the temporary changes of D production line, direct control, adjusts heat process route in the drawings;
E, run into heat change of plan, or casting plan change, can directly delete in the drawings heat or water time information.
CN201410372381.6A 2014-07-31 2014-07-31 Steelmaking working procedure management system and method Pending CN104102982A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410372381.6A CN104102982A (en) 2014-07-31 2014-07-31 Steelmaking working procedure management system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410372381.6A CN104102982A (en) 2014-07-31 2014-07-31 Steelmaking working procedure management system and method

Publications (1)

Publication Number Publication Date
CN104102982A true CN104102982A (en) 2014-10-15

Family

ID=51671115

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410372381.6A Pending CN104102982A (en) 2014-07-31 2014-07-31 Steelmaking working procedure management system and method

Country Status (1)

Country Link
CN (1) CN104102982A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105624360A (en) * 2015-12-29 2016-06-01 中冶南方工程技术有限公司 Converter equipment conflict resolution method with fettling time taken into consideration
CN106897832A (en) * 2017-02-24 2017-06-27 西门子传感器与通讯有限公司 The production scheduling method of production line, the production scheduling system of production line
CN112526952A (en) * 2020-12-14 2021-03-19 安徽巨一科技股份有限公司 Method and system for acquiring and analyzing rhythm based on linear body
CN112859762A (en) * 2020-12-04 2021-05-28 广州明珞装备股份有限公司 Control logic checking method and device, computer equipment and storage medium
CN113627736A (en) * 2021-07-19 2021-11-09 常州皓鸣信息科技有限公司 Gantt chart-based plan scheduling system
CN113969330A (en) * 2021-10-22 2022-01-25 山信软件股份有限公司 Real-time furnace number generation method and system based on converter steelmaking

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011159230A (en) * 2010-02-03 2011-08-18 Jfe Steel Corp Scheduling support system, scheduling support method, and scheduling support program
CN103646098A (en) * 2013-12-18 2014-03-19 东北大学 Online imaging man-machine interaction scheduling method for steel making and continuous casting production process
CN103839114A (en) * 2014-03-13 2014-06-04 中冶南方工程技术有限公司 Timing sequence plan automatic making system for steelmaking workshop

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011159230A (en) * 2010-02-03 2011-08-18 Jfe Steel Corp Scheduling support system, scheduling support method, and scheduling support program
CN103646098A (en) * 2013-12-18 2014-03-19 东北大学 Online imaging man-machine interaction scheduling method for steel making and continuous casting production process
CN103839114A (en) * 2014-03-13 2014-06-04 中冶南方工程技术有限公司 Timing sequence plan automatic making system for steelmaking workshop

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
卢克斌: "炼钢-连铸生产计划与调度的优化方法研究及应用", 《中国博士学位论文全文数据库 经济与管理科学辑》 *
宁树实 等: "一种炼钢-连铸生产计划一体化编制方法", 《控制理论与应用》 *
马军文 等: "数据可视化技术在炼钢-连铸生产调度中的应用", 《广东科技》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105624360A (en) * 2015-12-29 2016-06-01 中冶南方工程技术有限公司 Converter equipment conflict resolution method with fettling time taken into consideration
CN106897832A (en) * 2017-02-24 2017-06-27 西门子传感器与通讯有限公司 The production scheduling method of production line, the production scheduling system of production line
CN112859762A (en) * 2020-12-04 2021-05-28 广州明珞装备股份有限公司 Control logic checking method and device, computer equipment and storage medium
CN112859762B (en) * 2020-12-04 2022-07-26 广州明珞装备股份有限公司 Control logic checking method and device, computer equipment and storage medium
CN112526952A (en) * 2020-12-14 2021-03-19 安徽巨一科技股份有限公司 Method and system for acquiring and analyzing rhythm based on linear body
CN113627736A (en) * 2021-07-19 2021-11-09 常州皓鸣信息科技有限公司 Gantt chart-based plan scheduling system
CN113627736B (en) * 2021-07-19 2023-05-26 常州皓鸣信息科技有限公司 Gantt chart-based planning and scheduling system
CN113969330A (en) * 2021-10-22 2022-01-25 山信软件股份有限公司 Real-time furnace number generation method and system based on converter steelmaking

Similar Documents

Publication Publication Date Title
CN104102982A (en) Steelmaking working procedure management system and method
CN108763550B (en) Blast furnace big data application system
CN104835012A (en) Iron and steel enterprise production scheduling management system and production scheduling management method
CN100495272C (en) Integrative data source based automatic optimization scheduling system and method for energy source of steel and iron
CN103472811A (en) Steelmaking second-stage process control system and steelmaking second-stage process control method
CN105353733A (en) Steel-making production process intelligent scheduling method
CN101152668A (en) Method for centralized monitoring of continuous casting production working procedure of steel-smelting
CN111047257A (en) Production order management system based on 5G network
CN105931029A (en) Production management system for girder fabrication yard based on BIM
CN104133415B (en) A kind of steelmaking converter molten steel management system and method
CN103667674A (en) Material tracking control system of medium-thickness plate thermal treatment production line
CN102968689A (en) Intelligent monitoring method for remote control of power transformation overhaul work
CN110442090A (en) A kind of steel-making whole process materials stream informationization method based on Internet of Things
CN104133451A (en) Management system and method for steel-making argon blowing ladle
CN109151003A (en) Device intelligence Internet of things system
CN109299851A (en) A kind of intelligence progress kinetic-control system
CN101760578B (en) Converter smelting operation decision supporting system
CN201489347U (en) Ladle tracking management system
CN104444821B (en) The control method that a kind of iron and steel slab storehouse loop wheel machine runs
CN102385367A (en) Remote intelligent monitoring and feedback system and method of hoist
CN106355256A (en) Multivariate visualization overhaul management system
CN104020750A (en) Steelmaking input-output monitoring system
CN104122873B (en) Steel-making process data management system and method
CN104213561A (en) Concrete casting construction method for large dam with high casting strength
CN113554331A (en) Steelmaking digital scheduling optimization method based on process rhythm management and control

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20141015

RJ01 Rejection of invention patent application after publication