CN104097253B - Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system - Google Patents

Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system Download PDF

Info

Publication number
CN104097253B
CN104097253B CN201410322613.7A CN201410322613A CN104097253B CN 104097253 B CN104097253 B CN 104097253B CN 201410322613 A CN201410322613 A CN 201410322613A CN 104097253 B CN104097253 B CN 104097253B
Authority
CN
China
Prior art keywords
steel
formwork
beams
formwork system
longitudinal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410322613.7A
Other languages
Chinese (zh)
Other versions
CN104097253A (en
Inventor
朱尔玉
刘炀
郭占明
王宏亮
潘卫兵
何春晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiaotong University
Original Assignee
Beijing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiaotong University filed Critical Beijing Jiaotong University
Priority to CN201410322613.7A priority Critical patent/CN104097253B/en
Publication of CN104097253A publication Critical patent/CN104097253A/en
Application granted granted Critical
Publication of CN104097253B publication Critical patent/CN104097253B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0029Moulds or moulding surfaces not covered by B28B7/0058 - B28B7/36 and B28B7/40 - B28B7/465, e.g. moulds assembled from several parts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

跨座式单轨交通环保型活动式预制轨道梁模板系统,涉及跨座式单轨交通预制轨道梁模板体系。该系统包括钢框架系统、轨道梁运输系统和钢模板系统。钢框架由钢支柱、顶梁、底梁、斜撑中的部分或全部构件连接而成,相邻钢框架之间用纵梁进行纵向连接。钢模板系统安装在钢框架系统内。利用该发明的模板体系,可以降低混凝土建筑垃圾的排放和对环境的污染,同时,模板系统实现可随线路架设地点进行移动、组拼和反复使用,减少轨道梁运输时通过桥梁、隧道和街道等的限制条件;缩短了制梁场的施工周期,降低单轨交通土建工程的建设成本。

The utility model relates to an environment-friendly movable prefabricated track beam formwork system for straddle-type monorail traffic, which relates to a straddle-type monorail traffic prefabricated track beam formwork system. The system includes a steel frame system, rail beam transport system and steel formwork system. The steel frame is composed of steel pillars, top beams, bottom beams, and part or all of the components in the diagonal braces, and longitudinal beams are used to connect adjacent steel frames. The steel formwork system is installed within the steel framing system. Utilizing the formwork system of this invention can reduce the discharge of concrete construction waste and pollution to the environment. At the same time, the formwork system can be moved, assembled and reused along with the line erection site, reducing the need for rail beams to pass through bridges, tunnels and streets during transportation. and other constraints; shorten the construction period of the beam yard, and reduce the construction cost of monorail civil engineering.

Description

跨座式单轨交通环保型活动式预制轨道梁模板系统Environmentally friendly movable prefabricated track beam formwork system for straddle-type monorail traffic

技术领域technical field

本发明涉及跨座式单轨交通预制轨道梁模板系统,应用于跨座式单轨交通轨道梁的预制过程中。The invention relates to a straddle type monorail traffic prefabricated track beam formwork system, which is applied in the prefabrication process of the straddle type monorail traffic track beam.

背景技术Background technique

跨座式单轨交通中的轨道梁既是承载的梁体又是车辆通行的轨道,轨道梁在车辆通过时其顶面、两个侧面共三个面为轮轨接触面,即在这三个面上承受车辆轮胎荷载。轨道梁的三个轮轨接触面除承载外,还是车辆运行的轨道。轨道梁的三个轮轨接触面呈空间曲面变化,轨道梁的制作精度要求高。因此,对模板系统的要求严格。The track beam in the straddle monorail traffic is not only the load-carrying beam body but also the track for vehicles to pass. bear the load of the vehicle tires. The three wheel-rail contact surfaces of the track beam are not only load-bearing, but also the track on which the vehicle runs. The three wheel-rail contact surfaces of the track beam change in a spatial curved surface, and the manufacturing precision of the track beam is required to be high. Therefore, strict requirements are placed on the formwork system.

目前,跨座式单轨交通中的预制轨道梁模板系统主要包括混凝土基础、左右混凝土反力墙、钢模板系统和轨道梁运输系统。其中,钢模板系统包括侧模板、端模板、底模板、顶梁、吊具、机械式千斤顶;轨道梁运输系统包括底模台车、钢轨线路。左右混凝土反力墙与混凝土基础浇筑为一个整体,钢模板系统中顶梁的梁端固定在混凝土反力墙上。钢模板系统中的底模板置于底模台车的顶面,端模板放置在底模板上。钢模板系统中的机械式千斤顶安装在混凝土反力墙上,吊具安装在顶梁上。侧模板吊在吊具下,并分别与机械式千斤顶连接。轨道梁运输系统中钢轨线路铺设在左右混凝土反力墙之间的混凝土基础上。轨道梁运输系统底模台车通过钢轨线路在制梁前运输预制轨道梁所需的钢筋骨架、支座和端模板到左右混凝土反力墙之间的钢模板系统内。调整机械式千斤顶,以使侧模板满足轨道梁的线形要求。在预制梁浇筑完毕后,运出预制的轨道梁。由于基础和反力墙均为混凝土现浇而成,需要使用大量的混凝土。同时,该模板系统后期拆除时会产生大量的建筑垃圾,对环境造成很大的破坏。另外,该模板系统无法跟随线路地点进行移动和组拼,并且浇筑混凝土基础和混凝土反力墙等现场作业将制约制梁场的投产周期。At present, the prefabricated track beam formwork system in straddle monorail traffic mainly includes concrete foundation, left and right concrete reaction walls, steel formwork system and track beam transportation system. Among them, the steel formwork system includes side formwork, end formwork, bottom formwork, top beams, spreaders, and mechanical jacks; the track beam transportation system includes bottom formwork trolleys and rail lines. The left and right concrete reaction walls and the concrete foundation are poured as a whole, and the beam ends of the top beams in the steel formwork system are fixed on the concrete reaction walls. The bottom formwork in the steel formwork system is placed on the top surface of the bottom formwork trolley, and the end formwork is placed on the bottom formwork. The mechanical jack in the steel formwork system is installed on the concrete reaction wall, and the hoist is installed on the top beam. The side formwork is hung under the spreader and connected with mechanical jacks respectively. In the track beam transportation system, the rail line is laid on the concrete foundation between the left and right concrete reaction walls. The bottom form trolley of the track beam transportation system transports the steel skeleton, support and end formwork required for the prefabricated track beam to the steel formwork system between the left and right concrete reaction walls before beam making through the rail line. Adjust the mechanical jacks so that the side formwork meets the alignment requirements of the track beams. After the prefabricated beams are poured, the prefabricated track beams are transported out. Since both the foundation and the reaction wall are cast-in-situ concrete, a large amount of concrete is required. At the same time, when the formwork system is dismantled in the later stage, a large amount of construction waste will be generated, which will cause great damage to the environment. In addition, the formwork system cannot be moved and assembled following the location of the line, and on-site operations such as pouring concrete foundations and concrete reaction walls will restrict the commissioning period of the beam yard.

现有的预制轨道梁模板系统,决定了建造该模板系统时需要使用大量的混凝土来浇筑基础和反力墙。当全部预制轨道梁制作工作完成后,需拆除轨道梁模板系统所使用的大体积混凝土基础和反力墙,以及恢复土地平整等工作,这些工作会造成噪音污染和大量的建筑垃圾。另外,现有的轨道梁模板系统的工作特点,决定了预制轨道梁的制作地点与轨道梁安装架设地点距离较远,轨道梁在远距离运输过程中需要对沿途线路提前进行勘查、封闭和加固处理。尤其是在受限制的桥梁、隧道和街道等路段上运送轨道梁时,将耗费大量的人力和物力。同时,现有的轨道梁模板系统占用的制梁场面积大,需征用较大的场地以便保存大量的预制轨道梁体。The existing prefabricated track beam formwork system determines that a large amount of concrete needs to be used to pour the foundation and the reaction wall when constructing the formwork system. When all the prefabricated track beams are completed, the mass concrete foundation and reaction walls used in the track beam formwork system need to be removed, and the land leveling needs to be restored. These tasks will cause noise pollution and a large amount of construction waste. In addition, the working characteristics of the existing track beam formwork system determine that the manufacturing site of the prefabricated track beam is far away from the installation and erection site of the track beam. During the long-distance transportation of the track beam, the route along the route needs to be surveyed, closed and reinforced in advance. Especially when transporting track girders on road sections such as restricted bridges, tunnels and streets, it will consume a lot of manpower and material resources. At the same time, the existing track beam formwork system occupies a large area of the beam making field, and a larger site needs to be requisitioned in order to store a large number of prefabricated track beam bodies.

发明内容Contents of the invention

本发明所要解决的技术问题是:解决预制轨道梁模板系统需使用大量混凝土的弊端,减少混凝土的使用量,降低建筑垃圾的排放和对环境的污染;解决现有模板系统不可移动的弊端,使轨道梁模板系统可随线路架设地点进行移动、组拼和反复使用,减少轨道梁运输时通过桥梁、隧道和街道等的限制条件,缩短轨道梁的运输距离,降低运输成本;缩短制梁场的投产周期,提高轨道梁模板系统的使用效率,降低跨座式单轨交通土建工程的建设成本。The technical problems to be solved by the present invention are: to solve the disadvantages that the prefabricated track beam formwork system needs to use a large amount of concrete, reduce the amount of concrete used, reduce the discharge of construction waste and the pollution to the environment; solve the disadvantages of the existing formwork system that cannot be moved, so that The track beam formwork system can be moved, assembled and used repeatedly with the line erection site, reducing the constraints of bridges, tunnels and streets when transporting the track beams, shortening the transportation distance of the track beams, and reducing transportation costs; The commissioning period is shortened, the use efficiency of the track beam formwork system is improved, and the construction cost of the straddle-type monorail traffic civil engineering is reduced.

本发明解决其技术问题所采用的技术方案是:The technical solution adopted by the present invention to solve its technical problems is:

跨座式单轨交通环保型活动式预制轨道梁模板系统,该模板系统包括:轨道梁运输系统和钢模板系统;轨道梁运输系统包括底模台车、钢轨线路;钢模板系统包括侧模板、底模板、顶梁、吊具、机械式千斤顶;底模台车置于钢轨线路上,底模板置于底模台车上;吊具安装在部分或全部顶梁上;侧模板吊在吊具下,侧模板的外侧与机械式千斤顶连接;The straddle-type monorail traffic environment-friendly movable prefabricated track beam formwork system includes: track beam transportation system and steel formwork system; track beam transportation system includes bottom mold trolley, rail line; steel formwork system includes Formwork, top beam, spreader, mechanical jack; the bottom formwork trolley is placed on the rail line, and the bottom formwork is placed on the bottom formwork trolley; the spreader is installed on part or all of the top beam; the side formwork is hung under the spreader , the outer side of the side formwork is connected with a mechanical jack;

跨座式单轨交通环保型活动式预制轨道梁模板系统,其特征是:除轨道梁运输系统和钢模板系统外,还包括钢框架系统;The environment-friendly movable prefabricated track beam formwork system for straddle-type monorail traffic is characterized by: besides the track beam transportation system and steel formwork system, it also includes a steel frame system;

钢框架系统包括顶梁、钢支柱、纵梁,或顶梁、钢支柱、纵梁、底梁,或顶梁、钢支柱、纵梁、斜撑,或顶梁、钢支柱、纵梁、底梁、斜撑;Steel framing systems comprising roof beams, steel struts, stringers, or roof beams, steel struts, stringers, bottom beams, or roof beams, steel struts, stringers, diagonal braces, or top beams, steel struts, stringers, beams, braces;

一榀钢框架包括一根顶梁和两根钢支柱,顶梁的两端分别与两根钢支柱的上端进行连接;钢支柱在其侧面用斜撑支撑,或在其下端用底梁连接,或在其侧面用斜撑支撑并在其下端用底梁连接;钢支柱和斜撑下端固定在地面上,或固定在底梁上;相邻钢框架或相邻底梁之间采用纵梁进行纵向连接;机械式千斤顶固定在钢支柱上;A steel frame includes a top beam and two steel pillars, the two ends of the top beam are respectively connected to the upper ends of the two steel pillars; the steel pillars are supported by diagonal braces on their sides, or connected by bottom beams at their lower ends Or it is supported by diagonal braces on its side and connected by bottom beams at its lower ends; the lower ends of steel pillars and diagonal braces are fixed on the ground or on bottom beams; longitudinal beams are used between adjacent steel frames or adjacent bottom beams Longitudinal connection; mechanical jack fixed on the steel pillar;

纵梁包括上纵梁、中间纵梁、下纵梁、底纵梁。The longitudinal beams include upper longitudinal beams, middle longitudinal beams, lower longitudinal beams and bottom longitudinal beams.

所述顶梁、钢支柱、斜撑、底梁和纵梁之间的连接采用螺栓连接、焊接或销接。The connection between the top beam, steel pillar, diagonal brace, bottom beam and longitudinal beam adopts bolt connection, welding or pin connection.

所述钢框架、斜撑、底梁和纵梁均采用型钢或钢板加工制作。The steel frame, diagonal braces, bottom girders and longitudinal girders are all made of section steel or steel plates.

所述跨座式单轨交通环保型活动式预制轨道梁模板系统包括N榀钢框架,N的取值为10~30;相邻钢框架之间的纵向间距为0.5~10m。The environment-friendly movable prefabricated track beam formwork system for straddle-type monorail traffic includes N steel frames, and the value of N is 10-30; the longitudinal distance between adjacent steel frames is 0.5-10m.

本发明的有益效果是:该轨道梁模板系统采用钢框架系统代替原有轨道梁模板系统中的混凝土基础和混凝土反力墙,大大降低了建造轨道梁模板系统混凝土的用量,从而降低了建筑垃圾的排放和对环境的污染。同时,实现了轨道梁模板系统可随线路架设地点进行移动、组拼和反复使用,减少轨道梁运输时通过桥梁、隧道和街道等的限制条件,缩短轨道梁的运输距离,降低运输成本;缩短制梁场的投产周期,提高轨道梁模板系统的使用效率,降低跨座式单轨交通土建工程的建设成本。The beneficial effects of the present invention are: the track beam formwork system uses a steel frame system to replace the concrete foundation and concrete reaction wall in the original track beam formwork system, which greatly reduces the amount of concrete used to build the track beam formwork system, thereby reducing construction waste emissions and environmental pollution. At the same time, the track beam formwork system can be moved, assembled and reused along with the line erection site, reducing the constraints of bridges, tunnels and streets when the track beam is transported, shortening the transport distance of the track beam, and reducing transportation costs; The commissioning cycle of the beam making yard is improved, the efficiency of the track beam formwork system is improved, and the construction cost of the straddle-type monorail traffic civil engineering is reduced.

附图说明Description of drawings

图1带斜撑带底梁的预制轨道梁模板系统的钢框架示意图。Fig. 1 Schematic diagram of the steel frame of the prefabricated track beam formwork system with diagonal braces and bottom beams.

图2无斜撑带底梁的预制轨道梁模板系统的钢框架示意图。Fig. 2 Schematic diagram of the steel frame of the prefabricated track beam formwork system without braces and bottom beams.

图3带斜撑无底梁的预制轨道梁模板系统的钢框架示意图。Fig. 3 Schematic diagram of the steel frame of the prefabricated track beam formwork system with diagonal braces and bottomless beams.

图4无斜撑无底梁的预制轨道梁模板系统的钢框架示意图。Figure 4 is a schematic diagram of the steel frame of the prefabricated track beam formwork system without diagonal braces and bottom beams.

图5带斜撑带底梁的预制轨道梁模板系统中的框架系统立面图。Figure 5 is the elevation view of the frame system in the prefabricated track beam formwork system with diagonal braces and bottom beams.

图6带斜撑带底梁的预制轨道梁模板系统制梁阶段立面图。Figure 6 is the elevation view of the beam-making stage of the prefabricated track beam formwork system with diagonal braces and bottom beams.

图7带斜撑带底梁的预制轨道梁模板系统组拼阶段立面图。Fig. 7 The elevation view of the assembly stage of the prefabricated track beam formwork system with diagonal braces and bottom beams.

图8图7中A-A截面图。Fig. 8 A-A sectional view in Fig. 7 .

图9带斜撑带底梁的预制轨道梁模板系统拆卸机械式千斤顶阶段立面图。Figure 9. Elevation of the stage of dismantling the mechanical jack of the prefabricated track beam formwork system with diagonal braces and bottom beams.

图中:钢支柱1、顶梁2、斜撑3、底梁4、上纵梁5-1、中间纵梁5-2、下纵梁5-3、底纵梁5-4、钢轨线路6、吊具7、侧模板8、机械式千斤顶9、底模板10、底模台车11。In the figure: steel pillar 1, top beam 2, diagonal brace 3, bottom beam 4, upper longitudinal beam 5-1, middle longitudinal beam 5-2, lower longitudinal beam 5-3, bottom longitudinal beam 5-4, rail line 6 , Spreader 7, side formwork 8, mechanical jack 9, bottom formwork 10, bottom formwork trolley 11.

具体实施方式detailed description

结合附图对本发明做进一步说明:The present invention will be further described in conjunction with accompanying drawing:

实施例一Embodiment one

跨座式单轨交通环保型活动式预制轨道梁模板系统,该模板系统包括:N榀钢框架、斜撑3、底梁4、上纵梁5-1、中间纵梁5-2、下纵梁5-3、底纵梁5-4、钢轨线路6、吊具7、侧模板8、机械式千斤顶9、底模板10、底模台车11。Environmentally friendly movable prefabricated track beam formwork system for straddle-type monorail traffic, the formwork system includes: N steel frame, diagonal brace 3, bottom beam 4, upper longitudinal beam 5-1, middle longitudinal beam 5-2, lower longitudinal beam 5-3, bottom longitudinal beam 5-4, rail line 6, spreader 7, side formwork 8, mechanical jack 9, bottom formwork 10, bottom formwork trolley 11.

一榀钢框架包括:一根顶梁2和两根钢支柱1;一根顶梁2的两端分别与两根钢支柱1的上端用焊接连接。A steel frame includes: a roof beam 2 and two steel pillars 1; the two ends of a roof beam 2 are respectively connected with the upper ends of the two steel pillars 1 by welding.

钢支柱1外侧与斜撑3上端焊接连接,钢支柱1和斜撑3的下端焊接在底梁4上。The outer side of the steel pillar 1 is welded to the upper end of the diagonal brace 3 , and the lower ends of the steel pillar 1 and the diagonal brace 3 are welded on the bottom beam 4 .

相邻钢框架之间通过上纵梁5-1、中间纵梁5-2、下纵梁5-3进行纵向螺栓连接,相邻底梁4通过底纵梁5-4进行纵向螺栓连接,如图1。The adjacent steel frames are longitudinally bolted through the upper longitudinal beam 5-1, the middle longitudinal beam 5-2, and the lower longitudinal beam 5-3, and the adjacent bottom beams 4 are longitudinally bolted through the bottom longitudinal beam 5-4, such as figure 1.

钢轨线路6铺设于两根钢支柱1之间的地面上。The rail line 6 is laid on the ground between the two steel pillars 1 .

底模台车11置于钢轨线路6上,底模板10置于底模台车11上。The bottom mold trolley 11 is placed on the rail line 6, and the bottom mold trolley 10 is placed on the bottom mold trolley 11.

吊具7安装在顶梁2上,每根钢支柱1上安装两个机械式千斤顶9,侧模板8吊在吊具7下,侧模板8的外侧与机械式千斤顶9连接。The spreader 7 is installed on the top beam 2, two mechanical jacks 9 are installed on each steel pillar 1, the side template 8 is hung under the spreader 7, and the outside of the side template 8 is connected with the mechanical jack 9.

根据轨道梁的长度和侧模板的受力特征来确定N的大小。The size of N is determined according to the length of the track beam and the force characteristics of the side formwork.

实施例二Embodiment two

跨座式单轨交通环保型活动式预制轨道梁模板系统,该模板系统包括:N榀钢框架、底梁4、上纵梁5-1、中间纵梁5-2、下纵梁5-3、钢轨线路6、吊具7、侧模板8、机械式千斤顶9、底模板10、底模台车11。Environmentally friendly movable prefabricated track beam formwork system for straddle-type monorail traffic. Rail line 6, spreader 7, side formwork 8, mechanical jack 9, bottom formwork 10, bottom formwork trolley 11.

一榀钢框架包括:一根顶梁2和两根钢支柱1;一根顶梁2的两端分别与两根钢支柱1上端进行焊接连接。A steel frame includes: a roof beam 2 and two steel pillars 1; both ends of a roof beam 2 are welded to the upper ends of the two steel pillars 1 respectively.

钢支柱1下端焊接在底梁4上。The lower end of the steel pillar 1 is welded on the bottom beam 4 .

相邻钢框架之间通过上纵梁5-1、中间纵梁5-2、下纵梁5-3进行纵向螺栓连接,如图2。The adjacent steel frames are longitudinally bolted through the upper longitudinal beam 5-1, the middle longitudinal beam 5-2, and the lower longitudinal beam 5-3, as shown in Fig. 2 .

钢轨线路6铺设于两根钢支柱1之间的地面上。The rail line 6 is laid on the ground between the two steel pillars 1 .

底模台车11置于钢轨线路6上,底模板10置于底模台车11上。The bottom mold trolley 11 is placed on the rail line 6, and the bottom mold trolley 10 is placed on the bottom mold trolley 11.

吊具7安装在顶梁2上,每根钢支柱1上安装两个机械式千斤顶9,侧模板8吊在吊具7下,侧模板8的外侧与机械式千斤顶9连接。The spreader 7 is installed on the top beam 2, two mechanical jacks 9 are installed on each steel pillar 1, the side template 8 is hung under the spreader 7, and the outside of the side template 8 is connected with the mechanical jack 9.

根据轨道梁的长度和侧模板的受力特征来确定N的大小。The size of N is determined according to the length of the track beam and the force characteristics of the side formwork.

实施例三Embodiment three

跨座式单轨交通环保型活动式预制轨道梁模板系统,该模板系统包括:N榀钢框架、斜撑3、上纵梁5-1、中间纵梁5-2、下纵梁5-3、钢轨线路6、吊具7、侧模板8、机械式千斤顶9、底模板10、底模台车11。Environmentally friendly movable prefabricated track beam formwork system for straddle-type monorail traffic, the formwork system includes: N steel frame, diagonal brace 3, upper longitudinal beam 5-1, middle longitudinal beam 5-2, lower longitudinal beam 5-3, Rail line 6, spreader 7, side formwork 8, mechanical jack 9, bottom formwork 10, bottom formwork trolley 11.

一榀钢框架包括:一根顶梁2和两根钢支柱1;一根顶梁2的两端分别与两根钢支柱1的上端用焊接连接。A steel frame includes: a roof beam 2 and two steel pillars 1; the two ends of a roof beam 2 are respectively connected with the upper ends of the two steel pillars 1 by welding.

钢支柱1外侧与斜撑3上端焊接连接,钢支柱1和斜撑3的下端均固定在地面上。The outer side of the steel pillar 1 is welded to the upper end of the diagonal brace 3, and the lower ends of the steel pillar 1 and the diagonal brace 3 are fixed on the ground.

相邻钢框架之间通过上纵梁5-1、中间纵梁5-2、下纵梁5-3进行纵向螺栓连接,如图3。The adjacent steel frames are longitudinally bolted through the upper longitudinal beam 5-1, the middle longitudinal beam 5-2, and the lower longitudinal beam 5-3, as shown in Fig. 3 .

钢轨线路6铺设于两根钢支柱1之间的地面上。The rail line 6 is laid on the ground between the two steel pillars 1 .

底模台车11置于钢轨线路6上,底模板10置于底模台车11上。The bottom mold trolley 11 is placed on the rail line 6, and the bottom mold trolley 10 is placed on the bottom mold trolley 11.

吊具7安装在顶梁2上,每根钢支柱1上安装两个或三个机械式千斤顶9,侧模板8吊在吊具7下,侧模板8的外侧与机械式千斤顶9连接。The spreader 7 is installed on the top beam 2, two or three mechanical jacks 9 are installed on each steel pillar 1, the side template 8 is hung under the spreader 7, and the outside of the side template 8 is connected with the mechanical jack 9.

根据轨道梁的长度和侧模板的受力特征来确定N的大小。The size of N is determined according to the length of the track beam and the force characteristics of the side formwork.

实施例四Embodiment Four

跨座式单轨交通环保型活动式预制轨道梁模板系统,该模板系统包括:N榀钢框架、上纵梁5-1、中间纵梁5-2、下纵梁5-3、钢轨线路6、吊具7、侧模板8、机械式千斤顶9、底模板10、底模台车11。Environmentally friendly movable prefabricated track beam formwork system for straddle-type monorail traffic, the formwork system includes: N steel frame, upper longitudinal beam 5-1, middle longitudinal beam 5-2, lower longitudinal beam 5-3, rail line 6, Spreader 7, side formwork 8, mechanical jack 9, bottom formwork 10, bottom formwork trolley 11.

一榀钢框架包括:一根顶梁2和两根钢支柱1;一根顶梁2的两端分别与两根钢支柱1上端用焊接连接,钢支柱1下端固定在地面上。A steel frame includes: a roof beam 2 and two steel pillars 1; both ends of a roof beam 2 are respectively connected to the upper ends of the two steel pillars 1 by welding, and the lower ends of the steel pillars 1 are fixed on the ground.

相邻钢框架之间通过上纵梁5-1、中间纵梁5-2、下纵梁5-3进行纵向螺栓连接,如图4。The adjacent steel frames are longitudinally bolted through the upper longitudinal beam 5-1, the middle longitudinal beam 5-2, and the lower longitudinal beam 5-3, as shown in Fig. 4 .

钢轨线路6铺设于两根钢支柱1之间的地面上。The rail line 6 is laid on the ground between the two steel pillars 1 .

底模台车11置于钢轨线路6上,底模板10置于底模台车11上。The bottom mold trolley 11 is placed on the rail line 6, and the bottom mold trolley 10 is placed on the bottom mold trolley 11.

吊具7安装在顶梁2上,每根钢支柱1上安装两个机械式千斤顶9,侧模板8吊在吊具7下,侧模板8的外侧与机械式千斤顶9连接。The spreader 7 is installed on the top beam 2, two mechanical jacks 9 are installed on each steel pillar 1, the side template 8 is hung under the spreader 7, and the outside of the side template 8 is connected with the mechanical jack 9.

根据轨道梁的长度和侧模板的受力特征来确定N的大小。The size of N is determined according to the length of the track beam and the force characteristics of the side formwork.

跨座式单轨交通环保型活动式预制轨道梁模板系统的应用Application of environment-friendly movable prefabricated track beam formwork system for straddle monorail traffic

预制轨道梁的长度为24m,采用环保型活动式预制轨道梁模板系统进行预制。该体系包括19个钢框架及配套数量的底梁和斜撑,76个机械式千斤顶,2个侧模板、1底模板和1个底模台车。The length of the prefabricated track beam is 24m, and it is prefabricated with an environment-friendly movable prefabricated track beam formwork system. The system includes 19 steel frames and a matching number of bottom beams and braces, 76 mechanical jacks, 2 side formworks, 1 bottom formwork and 1 bottom formwork trolley.

1.组拼跨座式单轨交通环保型活动式预制轨道梁模板系统1. Assembling straddle-type monorail traffic environment-friendly movable prefabricated track beam formwork system

步骤一 一根顶梁2的两端分别与两根钢支柱1的上端进行焊接连接,构成一榀钢框架,钢支柱1外侧与斜撑3上端进行焊接连接,钢支柱1和斜撑3下端焊接在底梁4上,如图1。Step 1. The two ends of a top beam 2 are respectively welded and connected to the upper ends of two steel pillars 1 to form a steel frame. The outer side of the steel pillar 1 is welded to the upper end of the diagonal brace 3, and the lower ends of the steel pillar 1 and the diagonal brace 3 are connected. Welded on the bottom beam 4, as shown in Figure 1.

步骤二 相邻钢框架之间通过上纵梁5-1、中间纵梁5-2、下纵梁5-3进行纵向螺栓连接,相邻底梁4之间通过底纵梁5-4进行纵向螺栓连接,如图1。Step 2. Conduct longitudinal bolt connection between adjacent steel frames through the upper longitudinal beam 5-1, middle longitudinal beam 5-2, and lower longitudinal beam 5-3, and conduct longitudinal bolt connection between adjacent bottom beams 4 through the bottom longitudinal beam 5-4. Bolt connection, as shown in Figure 1.

步骤三 钢轨线路6铺设于两根钢支柱1之间的地面上,如图7。Step 3 The rail line 6 is laid on the ground between two steel pillars 1, as shown in Figure 7 .

步骤四 吊具7安装在顶梁2上,每根钢支柱1上安装两个机械式千斤顶9,侧模板8吊在吊具7下,侧模板8的外侧与机械式千斤顶9连接,如图7。Step 4: install the spreader 7 on the top beam 2, install two mechanical jacks 9 on each steel pillar 1, hang the side formwork 8 under the spreader 7, and connect the outer side of the side formwork 8 with the mechanical jack 9, as shown in the figure 7.

2.应用跨座式单轨交通环保型活动式预制轨道梁模板系统制梁2. Application of straddle-type monorail traffic environment-friendly movable prefabricated track beam formwork system to make beams

步骤一 底模台车11置于钢轨线路6上,底模板10放置在底模台车11上,如图6。Step 1 Place the bottom mold trolley 11 on the rail line 6, and the bottom formwork 10 is placed on the bottom mold trolley 11, as shown in Figure 6 .

步骤二 在底模板10上绑扎钢筋笼。Step 2 Bind the reinforcement cage on the bottom template 10.

步骤三 将底模台车11沿钢轨线路6推入钢模板系统内,如图6。Step 3 Push the bottom mold trolley 11 into the steel formwork system along the rail line 6, as shown in Figure 6.

步骤四 调整机械式千斤顶9,以使侧模板8满足轨道梁线形要求,如图8。Step 4 Adjust the mechanical jack 9 so that the side formwork 8 meets the linear requirements of the track beam, as shown in Figure 8.

步骤五 在两片侧模板8之间浇筑混凝土轨道梁;养护1天后,调整机械式千斤顶9,使侧模板8与轨道梁脱开,如图6;将初步养护后的轨道梁沿钢轨线路6通过底模台车11推出钢框架系统,如图7。Step 5 Concrete track beams are poured between the two side formworks 8; after one day of maintenance, adjust the mechanical jack 9 to disengage the side formwork 8 from the track beams, as shown in Figure 6; Roll out the steel frame system by the bottom mold trolley 11, as shown in Figure 7.

重复以上步骤,制造出所需数量的轨道梁。Repeat the above steps to produce the required number of track beams.

3.跨座式单轨交通环保型活动式预制轨道梁模板系统拆卸和移动3. Dismantling and moving of straddle-type monorail traffic environment-friendly movable prefabricated track beam formwork system

步骤一 拆除机械式千斤顶9。松开机械式千斤顶9与侧模板8的连接,从钢支柱1上将机械式千斤顶9拆卸下来,如图9。Step 1 Remove the mechanical jack 9. Loosen the connection between the mechanical jack 9 and the side template 8, and remove the mechanical jack 9 from the steel pillar 1, as shown in Figure 9.

步骤二 拆除侧模8。将侧模板8从吊具7拆卸下来,从顶梁2上将吊具7拆卸下来,如图5。Step 2 Remove the side form 8. Disassemble the side formwork 8 from the hanger 7, and disassemble the hanger 7 from the top beam 2, as shown in Figure 5.

步骤三 拆除钢框架。将连接钢框架之间的上纵梁5-1、中间纵梁5-2、下纵梁5-3、底纵梁5-4松开和拆卸下来,将铺设于钢框架内的钢轨线路6拆除。最后,拆除钢框架。Step 3 Remove the steel frame. Loosen and disassemble the upper longitudinal beam 5-1, middle longitudinal beam 5-2, lower longitudinal beam 5-3 and bottom longitudinal beam 5-4 connecting the steel frames, and lay the rail line 6 in the steel frame tear down. Finally, remove the steel frame.

步骤四 模板系统的移动。将以上拆卸的预制轨道梁模板系统运输到下一个工点进行安装或将其运输到仓库内进行保存以便以后制梁使用。Step 4 The movement of the template system. The prefabricated track beam formwork system dismantled above is transported to the next site for installation or transported to the warehouse for storage for future beam fabrication.

以上所述的具体实施方法,对本发明专利的目的、技术方案和有益效果进行了说明。所应强调的是,以上所述仅为本发明专利的具体实施例而已,并不能用于限制本发明的范围。凡在本发明的精神和原则之内,所做的任何修改、等同替换或改进等,均应包含在本发明的保护范围之内。The specific implementation method described above illustrates the purpose, technical solution and beneficial effects of the patent of the present invention. It should be emphasized that the above descriptions are only specific embodiments of the patent of the present invention, and should not be used to limit the scope of the present invention. Any modification, equivalent replacement or improvement made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

综上所述,本发明提供了一种用于跨座式单轨交通环保型活动式预制轨道梁模板系统,利用该模板系统,可以大大降低建筑垃圾的排放和对环境的污染。同时,该模板系统实现了可随线路架设地点进行移动、组拼和反复使用,减少轨道梁运输时通过桥梁、隧道和街道等的限制条件;缩短了制梁场的施工周期,降低单轨交通土建工程的建设成本。本发明具有新颖性、实用性,符合发明专利各要求,故依法提出发明专利申请。To sum up, the present invention provides an environment-friendly movable prefabricated track beam formwork system for straddle-type monorail traffic. The formwork system can greatly reduce the discharge of construction waste and the pollution to the environment. At the same time, the formwork system can be moved, assembled and reused along with the line erection site, reducing the restrictions on passing bridges, tunnels and streets during rail beam transportation; shortening the construction period of the beam making yard and reducing the cost of monorail traffic construction cost of the project. The present invention has novelty and practicability, and meets the requirements of the invention patent, so the application for the invention patent is filed according to law.

Claims (2)

1.跨座式单轨交通环保型活动式预制轨道梁模板系统,该模板系统包括:轨道梁运输系统和钢模板系统;轨道梁运输系统包括底模台车(11)、钢轨线路(6);钢模板系统包括侧模板(8)、底模板(10)、顶梁(2)、吊具(7)、机械式千斤顶(9);底模台车(11)置于钢轨线路(6)上,底模板(10)置于底模台车(11)上;吊具(7)安装在部分或全部顶梁(2)上;侧模板(8)吊在吊具(7)下,侧模板(8)的外侧与机械式千斤顶(9)连接;1. An environment-friendly movable prefabricated track beam formwork system for straddling monorail traffic. The formwork system includes: track beam transportation system and steel formwork system; the track beam transportation system includes bottom form trolley (11) and rail line (6); The steel formwork system includes side formwork (8), bottom formwork (10), top beam (2), spreader (7), mechanical jack (9); the bottom formwork trolley (11) is placed on the rail line (6) , the bottom formwork (10) is placed on the bottom formwork trolley (11); the spreader (7) is installed on part or all of the top beam (2); the side formwork (8) is hung under the spreader (7), and the side formwork The outside of (8) is connected with mechanical jack (9); 其特征是:Its characteristics are: 除轨道梁运输系统和钢模板系统外,还包括钢框架系统;In addition to rail beam transportation system and steel formwork system, it also includes steel frame system; 钢框架系统包括顶梁(2)、钢支柱(1)、纵梁,或顶梁(2)、钢支柱(1)、纵梁、底梁(4),或顶梁(2)、钢支柱(1)、纵梁、斜撑(3),或顶梁(2)、钢支柱(1)、纵梁、底梁(4)、斜撑(3);The steel frame system includes top beams (2), steel pillars (1), longitudinal beams, or top beams (2), steel pillars (1), longitudinal beams, bottom beams (4), or top beams (2), steel pillars (1), longitudinal beam, diagonal brace (3), or top beam (2), steel pillar (1), longitudinal beam, bottom beam (4), diagonal brace (3); 一榀钢框架包括一根顶梁(2)和两根钢支柱(1),顶梁(2)的两端分别与两根钢支柱(1)的上端进行连接;钢支柱(1)在其侧面用斜撑(3)支撑,或在其下端用底梁(4)连接,或在其侧面用斜撑(3)支撑并在其下端用底梁(4)连接;钢支柱(1)和斜撑(3)下端固定在地面上,或固定在底梁(4)上;相邻钢框架或相邻底梁(4)之间采用纵梁进行纵向连接;机械式千斤顶(9)固定在钢支柱(1)上;A steel frame comprises a top beam (2) and two steel pillars (1), and the two ends of the top beam (2) are respectively connected with the upper ends of the two steel pillars (1); The side is supported by a diagonal brace (3), or connected with a bottom beam (4) at its lower end, or supported by a diagonal brace (3) on its side and connected with a bottom beam (4) at its lower end; the steel pillar (1) and The lower end of the diagonal brace (3) is fixed on the ground or on the bottom beam (4); longitudinal beams are used to connect adjacent steel frames or adjacent bottom beams (4); the mechanical jack (9) is fixed on On the steel pillar (1); 纵梁包括上纵梁(5-1)、中间纵梁(5-2)、下纵梁(5-3)、底纵梁(5-4);The longitudinal beams include upper longitudinal beams (5-1), middle longitudinal beams (5-2), lower longitudinal beams (5-3), and bottom longitudinal beams (5-4); 顶梁(2)、钢支柱(1)、斜撑(3)、底梁(4)和纵梁之间的连接采用螺栓连接、焊接或销接;The connections among the top beam (2), steel pillar (1), diagonal brace (3), bottom beam (4) and longitudinal beam are bolted, welded or pinned; 钢框架、斜撑(3)、底梁(4)和纵梁均采用型钢或钢板加工制作。Steel frames, diagonal braces (3), bottom girders (4) and longitudinal girders are all manufactured by section steel or steel plates. 2.根据权利要求1所述的跨座式单轨交通环保型活动式预制轨道梁模板系统,其特征是:2. The environment-friendly movable prefabricated track beam formwork system for straddling monorail traffic according to claim 1, characterized in that: 所述跨座式单轨交通环保型活动式预制轨道梁模板系统包括N榀钢框架,N的取值为10~30;相邻钢框架之间的纵向间距为0.5~10m。The environment-friendly movable prefabricated track beam formwork system for straddle-type monorail traffic includes N steel frames, and the value of N is 10-30; the longitudinal distance between adjacent steel frames is 0.5-10m.
CN201410322613.7A 2014-07-08 2014-07-08 Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system Active CN104097253B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410322613.7A CN104097253B (en) 2014-07-08 2014-07-08 Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410322613.7A CN104097253B (en) 2014-07-08 2014-07-08 Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system

Publications (2)

Publication Number Publication Date
CN104097253A CN104097253A (en) 2014-10-15
CN104097253B true CN104097253B (en) 2017-07-18

Family

ID=51665993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410322613.7A Active CN104097253B (en) 2014-07-08 2014-07-08 Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system

Country Status (1)

Country Link
CN (1) CN104097253B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104999547A (en) * 2015-06-30 2015-10-28 中铁二十三局集团有限公司 Automatic template system for maglev curve track beam and use method of automatic template system
CN105643775A (en) * 2015-11-10 2016-06-08 北京交通大学 Formwork system for manufacturing suspension type monorail transit track beam and construction process
CN105666657A (en) * 2016-04-11 2016-06-15 北京交通大学 Automatic template system for suspension type monorail traffic track beams
CN105666658A (en) * 2016-04-11 2016-06-15 北京交通大学 Automatic template system for straddle-type single-rail traffic rail beam
CN106003391A (en) * 2016-07-04 2016-10-12 北京交通大学 Rapid assembling movable type template system of straddle type monorail transit rail beam
CN106003392B (en) * 2016-07-04 2024-08-16 北京交通大学 Fixed linear straddle type monorail traffic precast track beam template system
CN106626012B (en) * 2017-03-07 2022-06-03 中铁工程设计咨询集团有限公司 Integral shifting type straddle type monorail PC track beam template
CN108356968A (en) * 2018-01-25 2018-08-03 青岛德固特轨道装备有限公司 A kind of concrete track straight beam pours mould linkage die opening mechanism and straight beam depanning mode
CN108638297A (en) * 2018-05-09 2018-10-12 中国建筑第五工程局有限公司 Vertical shift trolley, adjusting part and application method for monorail track beam forms
CN108556122A (en) * 2018-06-26 2018-09-21 中铁四局集团第二工程有限公司 PC track beam mold
CN109808050A (en) * 2019-01-31 2019-05-28 中铁四局集团第二工程有限公司 A prefabricated construction method for curved PC track beams
CN111745791B (en) * 2019-03-29 2021-10-22 比亚迪股份有限公司 Side dies and dies for track beams
CN114182952A (en) * 2021-11-12 2022-03-15 江西志特新材料股份有限公司 Prefabricated part formwork system and operation method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007044956A (en) * 2005-08-09 2007-02-22 Oriental Construction Co Ltd Mold device for curved line beam
CN201633115U (en) * 2010-02-02 2010-11-17 中铁十一局集团第六工程有限公司 Track beam form
KR101212729B1 (en) * 2011-04-25 2012-12-14 유니슨이테크 주식회사 Apparatus for manufacturing curvilineal track beam for monorail in mold room
CN204109135U (en) * 2014-07-08 2015-01-21 北京交通大学 Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system

Also Published As

Publication number Publication date
CN104097253A (en) 2014-10-15

Similar Documents

Publication Publication Date Title
CN104097253B (en) Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system
CN204109135U (en) Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system
CN103485279B (en) For the wet seam of cross-saddle single-track traffic
KR101391637B1 (en) Constrution methoed for Prestressed Composite Truss girder using steel truss member
CN104499413B (en) Modularity punching block concrete combination arch bridge and suspension cable hanging construction method thereof
CN102154988B (en) Arch-after-girder construction method of large-span steel box tacked arch bridge
CN103981803B (en) The combined gate pier of precast assembly and construction method thereof
CN103924505A (en) Prefabricated steel-concrete combination T beam with corrugated steel web and construction method
CN103523665B (en) A kind of transport device and method of high pedestal jib crane
CN203229874U (en) Repeatedly used cast-in-place support system for simply-supported beam
CN207244447U (en) Movable hanging basket for steel-concrete composite bridge
CN100497833C (en) High-altitude framework type simple plate supporting machine
CN104594204A (en) Construction supporting system for hill type U beam of viaduct of urban light rail and construction method
CN104032967A (en) Hoisting construction method for prefabricated assembly-type frame structure members
CN105463997A (en) Erecting method for segmental beam
CN103850162B (en) Bridge-type combining structure pavement system and construction method thereof
CN204059179U (en) A kind of T-shaped plate girder precast segment unit based on steel truss and combined bridge deck
CN206635599U (en) A kind of road surface for caving in road, which is speedily carried out rescue work, fixes device
CN111851307A (en) Construction method of large-span prefabricated corrugated web composite box girder transport frame
CN203461693U (en) Bailey truss composite gantry crane super high steel outriggers
CN217027200U (en) Template operation trolley and operation system for construction of height-gradient retaining wall
CN107313628A (en) A kind of basic digging-free assembled tower-type space garage and its construction method
CN202989781U (en) Width widened cast-in-place box beam moving support
CN203878460U (en) Prefabricated assembly combined type portal pier
CN103850163B (en) Bridge-type steel plate pavement system and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant