CN104089269A - Load distribution method for main-pipeline unit boiler in power station - Google Patents

Load distribution method for main-pipeline unit boiler in power station Download PDF

Info

Publication number
CN104089269A
CN104089269A CN201410256878.1A CN201410256878A CN104089269A CN 104089269 A CN104089269 A CN 104089269A CN 201410256878 A CN201410256878 A CN 201410256878A CN 104089269 A CN104089269 A CN 104089269A
Authority
CN
China
Prior art keywords
boiler
unit
time
load power
parameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410256878.1A
Other languages
Chinese (zh)
Other versions
CN104089269B (en
Inventor
郭明奎
薛钢
申彦杰
刘峰
李红霞
张玉青
杨奇明
李柯
梁静
李文喆
徐永赪
习宝全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Huadian Shijiazhuang Thermoelectricity Co Ltd
Original Assignee
Hebei Huadian Shijiazhuang Thermoelectricity Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Huadian Shijiazhuang Thermoelectricity Co Ltd filed Critical Hebei Huadian Shijiazhuang Thermoelectricity Co Ltd
Priority to CN201410256878.1A priority Critical patent/CN104089269B/en
Publication of CN104089269A publication Critical patent/CN104089269A/en
Application granted granted Critical
Publication of CN104089269B publication Critical patent/CN104089269B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a load distribution method for a main-pipeline unit boiler in a power station. The method comprises the following steps: 1) acquiring data in real time and calculating boiler efficiency; 2) performing exhaustion calculation twice; carrying out the first-time exhaustion calculation for at most five times to properly adjust the boiler load and quickly respond the load change of a power grid; carrying out the second-time exhaustion calculation to adjust and further optimize the boiler load to achieve the optimal system efficiency. As a conventional exhaustion process is large in system calculation amount, long in load adjusting time, and cannot meet the requirements of the power grid, the conventional exhaustion process cannot be applied to the actual life; the load efficiency output when the total efficiency of two boilers is highest can be quickly and accurately found through the two-time exhaustion process.

Description

A kind of power station piping-main scheme unit boiler load distribution method
Technical field
The present invention relates to a kind of power station piping-main scheme unit boiler load distribution method, be particularly useful for piping-main scheme unit boiler load in the time dropping into the automatic control of AGC load and, by efficiency smart allocation, belong to load optimizing distribution method.
Background technology
12 propose ten thousand yuan of GDP energy consumptions drops to 0.869 ton of standard coal, declines 16% than 1.034 tons of standard coals of 2010, and along with the reduction of energy-saving and emission-reduction marginal utility, the five-year country will be growing on and on to the dynamics of energy-saving and emission-reduction.CFBB has been realized strict disposal of pollutants index as a kind of clean coal combustion technology low cost, uses inferior fuel, has comprehensive advantage at the aspect such as load adaptability and ash comprehensive utilization, has been widely used in power industry.In actual motion, for better adapting to the requirement of intelligent grid to fired power generating unit, grid-connected fired power generating unit need to respond fast to load variations.But what adopt micro-gaining rate load distribution method such as is more, from Functional Analysis, if consumption function is not convexity, by etc. the total coal consumption of system of micro-principle distribution load gained be not minimum but greatly; If adopt the general method of exhaustion to look for successively the ratio of distribution load, waste time and energy, amount of calculation is possibility too greatly hardly, and consumes the plenty of time, affects boiler load and adjusts in time according to actual needs, causes huge energy waste.
Summary of the invention
The technical problem to be solved in the present invention is to provide the power station piping-main scheme unit boiler load distribution method of a kind of precise and high efficiency, fast energy-saving, and this method is to be based upon on AGC load automatic control system based on twice method of exhaustion to realize the quick responsive electricity grid load variations of boiler load and reach the method for system effectiveness optimum.
The technical solution used in the present invention is as follows:
A kind of power station piping-main scheme unit boiler load distribution method, comprises the steps:
Step 1: real-time data collection, calculates boiler efficiency:
Image data comprises feedwater parameter, steam parameter, primary air flow F1 and secondary air flow F2;
Described feedwater parameter comprises feed temperature Tgs (DEG C) and feedwater flow Dgs(t/h);
Described steam parameter comprises boiler capacity D(t/h), steam pressure P (MPa) and vapor (steam) temperature t (DEG C);
Calculate real-time coal supply gross calorific value N(kJ/h by following formula (1)):
N=Y1×Q (1)
Wherein, N is real-time coal supply gross calorific value, and unit is kJ/h;
Y1 is the amount of making charcoal, and unit is kg/h;
Q is the directly calorific value of burning of carbon, and unit is kJ/kg;
According to carbon oxygen combustion reaction formula C+ O 2 cO 2, establishing the Y1 representative amount of making charcoal, X1 represents total oxygen demand (kg/h), tries to achieve Y1=12 × X1/32; Wherein 12 and 32 mass fractions that represent respectively carbon and oxygen;
Described total oxygen demand meets formula: X1=F × K;
Wherein, F is total blast volume, the primary air flow F1 recording and secondary air flow F2 sum, and its unit is m3/h; K is oxygen quality in 1m3 air, and unit is kg;
Calculate boiler export steam enthalpy h by following formula (2):
(2)
Wherein, h is boiler export steam enthalpy, and unit is kj/kg;
T=t+273.15, i.e. vapor (steam) temperature, unit is K;
P is steam pressure, and unit is MPa;
Calculate boiler feedwater enthalpy h1 by following formula (3):
h1=Tgs*C (3)
Wherein, h1 is boiler feedwater enthalpy, and unit is kj/kg;
C is water specific heat capacity, C=4.18J/(kg DEG C);
Tgs is feed temperature, and unit is DEG C;
Calculate boiler efficiency E (%) by following formula (4);
E=1000(h*D-h1*Dgs)/N*100% (4)
Wherein, E is boiler efficiency;
N is real-time coal supply gross calorific value, and unit is kJ/h;
H is boiler export steam enthalpy, and unit is kj/kg;
H1 is boiler feedwater enthalpy, and unit is kj/kg;
D is boiler capacity, and unit is t/h;
Dgs is feedwater flow, and unit is t/h;
Described boiler is piping-main scheme unit boiler, and it comprises boiler A and boiler B, utilizes formula (1) ~ (4) to calculate respectively its A, B boiler efficiency, and note is E1 and E2;
Step 2: adopt the secondary method of exhaustion to find boiler efficiency maximum point, complete sharing of load:
(1) exhaustive computations for the first time:
A. according to the variable quantity △ Z of network load power, determine step-length a, step-length a meets following formula (5):
a=v*△Z (5)
Wherein, a is step-length, and unit is MW;
V is for adjusting parameter, and span is 10% ~ 15%;
△ Z is the variable quantity of network load power, and unit is MW;
B. load power Z1 and the Z2 of boiler A and boiler B adjusted in circulation:
△ Z is resolved into △ Z1 and △ Z2, i.e. △ Z=△ Z1+ △ Z2, the span of △ Z1 is 0 ~ △ Z, the span of △ Z2 is 0 ~ △ Z;
According to step-length a,, utilize following formula (6) to calculate reduced parameter Kn:
Kn=(Z1+△Z1+n*a)* E1+ (Z2+△Z2- n*a)* E2 (6)
Wherein, n is the adjustment parameter in exhaustive computations for the first time, and value is 0 ~ N, N≤5;
Kn is for adjusting the corresponding reduced parameter of parameter n in exhaustive computations for the first time, and unit is MW;
Z1 is the current load power of boiler 1, and unit is MW;
Z2 is the current load power of boiler 2, and unit is MW;
△ Z1 is the variable quantity of the load power of boiler 1, and unit is MW;
△ Z2 is the variable quantity of the load power of boiler 2, and unit is MW;
E1 is the boiler efficiency (%) of boiler 1;
E2 is the boiler efficiency (%) of boiler 2;
Adjustment parameter n in described exhaustive computations for the first time gets 0 ~ N successively, N≤5, obtain successively K0, KN, select K0, maximum in KN, takes out and now adjusts (Z1+ △ Z1+n*a) that parameter n is corresponding load power Z1 ' as boiler 1, and (Z2+ △ Z2-n*a) is as the load power Z2 ' of boiler 2;
The plane curve forming due to Kn and n only has a crest, therefore as long as in the time that the previous value Kn-1 of Kn and a rear value Kn+1 are all less than Kn, can determine that Kn is maximum;
(2) exhaustive computations for the second time:
Step-length lower limit is a min, more described step-length a and step-length lower limit a minsize:
A. when step-length a is greater than step-length lower limit a mintime, make a=a min, the step B in exhaustive computations for the first time described in employing, substitution step-length lower limit a minas a, utilize following formula (7) new load power Z1 ' and Z2 ' that further refining-circulation is adjusted boiler A and boiler B, try to achieve the Optimal Load power after boiler 1 and boiler 2 refinements:
Km=( Z1’+m*a)* E1+ (Z2’-m*a)* E2 (7)
Wherein, m is the adjustment parameter m in exhaustive computations for the second time, and value is positive integer;
Km is for adjusting the corresponding reduced parameter of parameter m in exhaustive computations for the second time, and unit is MW;
The load power that the exhaustive computations for the first time that Z1 ' is boiler 1 obtains, unit is MW;
The load power that the exhaustive computations for the first time that Z2 ' is boiler 2 obtains, unit is MW;
E1 is the boiler efficiency (%) of boiler 1;
E2 is the boiler efficiency (%) of boiler 2;
Adjustment parameter m in described exhaustive computations is for the second time got positive integer successively, in the Km obtaining successively, select maximum, take out and now adjust the load power Z1 of parameter m corresponding (Z1 '+m*a) as boiler 1 ", (Z2 '-m*a) is as the load power Z2 of boiler 2 ";
The plane curve forming due to Km and m only has a crest, therefore as long as in the time that the previous value Km-1 of Km and a rear value Km+1 are all less than Km, can determine that Km is maximum;
B. when step-length a is less than or equal to step-length lower limit a mintime, no longer calculate, directly output (Z1+ △ Z1+n*a) is as the load power Z1 ' of boiler 1, and (Z2+ △ Z2-n*a) is as the load power Z2 ' of boiler 2.
The invention has the beneficial effects as follows: the load power of output while finding fast and accurately two boilers to make gross efficiency maximum by the secondary method of exhaustion, because of conventional method of exhaustion system-computed amount large, the load adjustment time is long, can not meet electrical network requirement, therefore the conventional method of exhaustion cannot be applied in practice, and this method adopts the secondary method of exhaustion, maximum 5 times of exhaustive computations for the first time, boiler load is adjusted to the right place, fast responsive electricity grid load variations; Exhaustive computations is adjusted to boiler load and is further optimized for the second time, reaches system effectiveness optimum.
Brief description of the drawings
Accompanying drawing 1 is method flow diagram of the present invention.
Detailed description of the invention
Following examples are used for illustrating the present invention, but are not used for limiting the scope of the invention.
Embodiment: taking No. 21 units of Hua electricity Shijiazhuang, Hebei Thermal Power Co., Ltd as example, adopt following steps to carry out power station piping-main scheme unit boiler sharing of load:
Step 1: real-time data collection, calculates boiler efficiency:
Image data comprises feedwater parameter, steam parameter, primary air flow F1 and secondary air flow F2;
Described feedwater parameter comprises feed temperature Tgs (DEG C) and feedwater flow Dgs(t/h);
Described steam parameter comprises boiler capacity D(t/h), steam pressure P (MPa) and vapor (steam) temperature t (DEG C);
Calculate real-time coal supply gross calorific value N(kJ/h by following formula (1)):
N=Y1×Q (1)
Wherein, N is real-time coal supply gross calorific value, and unit is kJ/h;
Y1 is the amount of making charcoal, and unit is kg/h;
Q is the directly calorific value of burning of carbon, and unit is kJ/kg;
According to carbon oxygen combustion reaction formula C+ O 2 cO 2, establishing the Y1 representative amount of making charcoal, X1 represents total oxygen demand (kg/h), tries to achieve Y1=12 × X1/32; Wherein 12 and 32 mass fractions that represent respectively carbon and oxygen;
Described total oxygen demand meets formula: X1=F × K;
Wherein, F is total blast volume, the primary air flow F1 recording and secondary air flow F2 sum, and its unit is m3/h; K is oxygen quality in 1m3 air, and unit is kg; Air molal weight is 0.029kg/mol, and 20 DEG C, under the condition of a standard atmospheric pressure, the volume of air of 1mol is about 0.023m3, and atmospheric density is 1.260kg/m3, and in air, oxygen quality mark is 20%, so oxygen quality is about 0.252kg in 1m3 air;
Calculate boiler export steam enthalpy h by following formula (2):
(2)
Wherein, h is boiler export steam enthalpy, and unit is kj/kg;
T=t+273.15, i.e. vapor (steam) temperature, unit is K;
P is steam pressure, and unit is MPa;
Calculate boiler feedwater enthalpy h1 by following formula (3):
h1=Tgs*C (3)
Wherein, h1 is boiler feedwater enthalpy, and unit is kj/kg;
C is water specific heat capacity, C=4.18J/(kg DEG C);
Tgs is feed temperature, and unit is DEG C;
Calculate boiler efficiency E (%) by following formula (4);
E=1000(h*D-h1*Dgs)/N*100% (4)
Wherein, E is boiler efficiency;
N is real-time coal supply gross calorific value, and unit is kJ/h;
H is boiler export steam enthalpy, and unit is kj/kg;
H1 is boiler feedwater enthalpy, and unit is kj/kg;
D is boiler capacity, and unit is t/h;
Dgs is feedwater flow, and unit is t/h;
Described boiler is piping-main scheme unit boiler, and it comprises boiler A and boiler B, utilizes formula (1) ~ (4) to calculate respectively its A, B boiler efficiency, and note is E1 and E2;
Step 2: adopt the secondary method of exhaustion to find boiler efficiency maximum point, complete sharing of load:
(1) exhaustive computations for the first time:
A. according to the variable quantity △ Z of network load power, determine step-length a, step-length a meets following formula (5):
a=v*△Z (5)
Wherein, a is step-length, and unit is MW;
V is for adjusting parameter, and span is 10% ~ 15%;
△ Z is the variable quantity of network load power, and unit is MW;
B. load power Z1 and the Z2 of boiler A and boiler B adjusted in circulation:
△ Z is resolved into △ Z1 and △ Z2, i.e. △ Z=△ Z1+ △ Z2, the span of △ Z1 is 0 ~ △ Z, the span of △ Z2 is 0 ~ △ Z;
According to step-length a,, utilize following formula to calculate reduced parameter Kn:
In the time of n=0, K0=Z1* E1+ (Z2+ △ Z) * E2
In the time of n=1, K1=(Z1+a) * E1+ (Z2+ △ Z-a) * E2
In the time of n=2, K2=(Z1+2*a) * E1+ (Z2+ △ Z-2*a) * E2
In the time of n=3, K3=(Z1+3*a) * E1+ (Z2+ △ Z-3*a) * E2
In the time of n=4, K4=(Z1+4*a) * E1+ (Z2+ △ Z-4*a) * E2
In the time of n=5, K5=(Z1+5*a) * E1+ (Z2+ △ Z-5*a) * E2
Increase progressively and analogize successively from n=0, by big or small the value of the Kn obtaining, for example, in the time calculating K4, find that K2 is less than K3, when K4 is less than K3, can judge the maximum that K3 is reduced parameter Kn, because the plane curve that Kn and n form only has a crest, once occur that downward opening flex point finds the maximum under this sampling condition, as long as in the time that the previous value Kn-1 of Kn and a rear value Kn+1 are all less than Kn, can determine that Kn is maximum; Therefore usually can find the maximum in reduced parameter Kn without the value that calculates the corresponding Kn of a lot of n, can calculate for maximum 5 times under normal circumstances.
Take out and now adjust (Z1+ △ Z1+n*a) that parameter n is corresponding load power Z1 ' as boiler 1, (Z2+ △ Z2-n*a) is as the load power Z2 ' of boiler 2;
Wherein, n is the adjustment parameter in exhaustive computations for the first time, and value is 0 ~ N, N≤5;
Kn is for adjusting the corresponding reduced parameter of parameter n in exhaustive computations for the first time, and unit is MW;
Z1 is the current load power of boiler 1, and unit is MW;
Z2 is the current load power of boiler 2, and unit is MW;
△ Z1 is the variable quantity of the load power of boiler 1, and unit is MW;
△ Z2 is the variable quantity of the load power of boiler 2, and unit is MW;
E1 is the boiler efficiency (%) of boiler 1;
E2 is the boiler efficiency (%) of boiler 2;
(2) exhaustive computations for the second time:
Step-length lower limit is a min, more described step-length a and step-length lower limit a minsize:
A. when step-length a is greater than step-length lower limit a mintime, make a=a min, the step B in exhaustive computations for the first time described in employing, substitution step-length lower limit a minas a, utilize following formula (7) new load power Z1 ' and Z2 ' that further refining-circulation is adjusted boiler A and boiler B, try to achieve the Optimal Load power after boiler 1 and boiler 2 refinements:
Km=(Z1’+m*a)* E1+ (Z2’-m*a)* E2 (7)
Wherein, m is the adjustment parameter m in exhaustive computations for the second time, and value is positive integer;
Km is for adjusting the corresponding reduced parameter of parameter m in exhaustive computations for the second time, and unit is MW;
The load power that the exhaustive computations for the first time that Z1 ' is boiler 1 obtains, unit is MW;
The load power that the exhaustive computations for the first time that Z2 ' is boiler 2 obtains, unit is MW;
E1 is the boiler efficiency (%) of boiler 1;
E2 is the boiler efficiency (%) of boiler 2;
Adjustment parameter m in described exhaustive computations is for the second time got positive integer successively, in the Km obtaining successively, select maximum, take out and now adjust the load power Z1 of parameter m corresponding (Z1 '+m*a) as boiler 1 ", (Z2 '-m*a) is as the load power Z2 of boiler 2 ";
The plane curve forming due to Km and m only has a crest, therefore as long as in the time that the previous value Km-1 of Km and a rear value Km+1 are all less than Km, can determine that Km is maximum;
B. when step-length a is less than or equal to step-length lower limit a mintime, no longer calculate, directly output (Z1+ △ Z1+n*a) is as the load power Z1 ' of boiler 1, and (Z2+ △ Z2-n*a) is as the load power Z2 ' of boiler 2.
The present invention utilizes the senior calculation function that control system is powerful, by to a large amount of soft instrument amounts in line computation, measuring and calculating boiler thermal output and coal supply phosphorus content in real time, the load of every boiler is carried out to on-line optimization distribution, the operating states of the units that calculates in real time, adjusts, make unit efficiency in responsive electricity grid load variations the moment in optimum state.
Although content of the present invention has been done detailed introduction by above preferred embodiment, will be appreciated that above-mentioned description should not be considered to limitation of the present invention.Those skilled in the art have read after foregoing, for multiple amendment of the present invention and substitute will be all apparent.

Claims (1)

1. a power station piping-main scheme unit boiler load distribution method, is characterized in that comprising the steps:
Step 1: real-time data collection, calculates boiler efficiency:
Image data comprises feedwater parameter, steam parameter, primary air flow F1 and secondary air flow F2;
Described feedwater parameter comprises feed temperature Tgs (DEG C) and feedwater flow Dgs(t/h);
Described steam parameter comprises boiler capacity D(t/h), steam pressure P (MPa) and vapor (steam) temperature t (DEG C);
Calculate real-time coal supply gross calorific value N(kJ/h by following formula (1)):
N=Y1×Q (1)
Wherein, N is real-time coal supply gross calorific value, and unit is kJ/h;
Y1 is the amount of making charcoal, and unit is kg/h;
Q is the directly calorific value of burning of carbon, and unit is kJ/kg;
According to carbon oxygen combustion reaction formula C+ O 2 cO 2, establishing the Y1 representative amount of making charcoal, X1 represents total oxygen demand (kg/h), tries to achieve Y1=12 × X1/32; Wherein 12 and 32 mass fractions that represent respectively carbon and oxygen;
Described total oxygen demand meets formula: X1=F × K;
Wherein, F is total blast volume, the primary air flow F1 recording and secondary air flow F2 sum, and its unit is m3/h; K is oxygen quality in 1m3 air, and unit is kg;
Calculate boiler export steam enthalpy h by following formula (2):
(2)
Wherein, h is boiler export steam enthalpy, and unit is kj/kg;
T=t+273.15, i.e. vapor (steam) temperature, unit is K;
P is steam pressure, and unit is MPa;
Calculate boiler feedwater enthalpy h1 by following formula (3):
h1=Tgs*C (3)
Wherein, h1 is boiler feedwater enthalpy, and unit is kj/kg;
C is water specific heat capacity, C=4.18J/(kg DEG C);
Tgs is feed temperature, and unit is DEG C;
Calculate boiler efficiency E (%) by following formula (4);
E=1000(h*D-h1*Dgs)/N*100% (4)
Wherein, E is boiler efficiency;
N is real-time coal supply gross calorific value, and unit is kJ/h;
H is boiler export steam enthalpy, and unit is kJ/kg;
H1 is boiler feedwater enthalpy, and unit is kJ/kg;
D is boiler capacity, and unit is t/h;
Dgs is feedwater flow, and unit is t/h;
Described boiler is piping-main scheme unit boiler, and it comprises boiler A and boiler B, utilizes formula (1) ~ (4) to calculate respectively its A, B boiler efficiency, and note is E1 and E2;
Step 2: adopt the secondary method of exhaustion to find boiler efficiency maximum point, complete sharing of load:
(1) exhaustive computations for the first time:
A. according to the variable quantity △ Z of network load power, determine step-length a, step-length a meets following formula (5):
a=v*△Z (5)
Wherein, a is step-length, and unit is MW;
V is for adjusting parameter, and span is 10% ~ 15%;
△ Z is the variable quantity of network load power, and unit is MW;
B. load power Z1 and the Z2 of boiler A and boiler B adjusted in circulation:
△ Z is resolved into △ Z1 and △ Z2, i.e. △ Z=△ Z1+ △ Z2, the span of △ Z1 is 0 ~ △ Z, the span of △ Z2 is 0 ~ △ Z;
According to step-length a,, utilize following formula (6) to calculate reduced parameter Kn:
Kn=(Z1+△Z1+n*a)* E1+ (Z2+△Z2- n*a)* E2 (6)
Wherein, n is the adjustment parameter in exhaustive computations for the first time, and value is 0 ~ N, N≤5;
Kn is for adjusting the corresponding reduced parameter of parameter n in exhaustive computations for the first time, and unit is MW;
Z1 is the current load power of boiler 1, and unit is MW;
Z2 is the current load power of boiler 2, and unit is MW;
△ Z1 is the variable quantity of the load power of boiler 1, and unit is MW;
△ Z2 is the variable quantity of the load power of boiler 2, and unit is MW;
E1 is the boiler efficiency (%) of boiler 1;
E2 is the boiler efficiency (%) of boiler 2;
Adjustment parameter n in described exhaustive computations for the first time gets 0 ~ N successively, N≤5, obtain successively K0, KN, select K0, maximum in KN, takes out and now adjusts (Z1+ △ Z1+n*a) that parameter n is corresponding load power Z1 ' as boiler 1, and (Z2+ △ Z2-n*a) is as the load power Z2 ' of boiler 2;
The plane curve forming due to Kn and n only has a crest, therefore as long as in the time that the previous value Kn-1 of Kn and a rear value Kn+1 are all less than Kn, can determine that Kn is maximum;
(2) exhaustive computations for the second time:
Step-length lower limit is a min, more described step-length a and step-length lower limit a minsize:
A. when step-length a is greater than step-length lower limit a mintime, make a=a min, the step B in exhaustive computations for the first time described in employing, substitution step-length lower limit a minas a, utilize following formula (7) new load power Z1 ' and Z2 ' that further refining-circulation is adjusted boiler A and boiler B, try to achieve the Optimal Load power after boiler 1 and boiler 2 refinements:
Km=( Z1’+m*a)* E1+ (Z2’—m*a)* E2 (7)
Wherein, m is the adjustment parameter m in exhaustive computations for the second time, and value is positive integer;
Km is for adjusting the corresponding reduced parameter of parameter m in exhaustive computations for the second time, and unit is MW;
The load power that the exhaustive computations for the first time that Z1 ' is boiler 1 obtains, unit is MW;
The load power that the exhaustive computations for the first time that Z2 ' is boiler 2 obtains, unit is MW;
E1 is the boiler efficiency (%) of boiler 1;
E2 is the boiler efficiency (%) of boiler 2;
Adjustment parameter m in described exhaustive computations is for the second time got positive integer successively, in the Km obtaining successively, select maximum, take out and now adjust the load power Z1 of parameter m corresponding (Z1 '+m*a) as boiler 1 ", (Z2 '-m*a) is as the load power Z2 of boiler 2 ";
The plane curve forming due to Km and m only has a crest, therefore as long as in the time that the previous value Km-1 of Km and a rear value Km+1 are all less than Km, can determine that Km is maximum;
B. when step-length a is less than or equal to step-length lower limit a mintime, no longer calculate, directly output (Z1+ △ Z1+n*a) is as the load power Z1 ' of boiler 1, and (Z2+ △ Z2-n*a) is as the load power Z2 ' of boiler 2.
CN201410256878.1A 2014-06-11 2014-06-11 A kind of power station piping-main scheme unit boiler load distribution method Active CN104089269B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410256878.1A CN104089269B (en) 2014-06-11 2014-06-11 A kind of power station piping-main scheme unit boiler load distribution method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410256878.1A CN104089269B (en) 2014-06-11 2014-06-11 A kind of power station piping-main scheme unit boiler load distribution method

Publications (2)

Publication Number Publication Date
CN104089269A true CN104089269A (en) 2014-10-08
CN104089269B CN104089269B (en) 2016-02-03

Family

ID=51637009

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410256878.1A Active CN104089269B (en) 2014-06-11 2014-06-11 A kind of power station piping-main scheme unit boiler load distribution method

Country Status (1)

Country Link
CN (1) CN104089269B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108613247A (en) * 2018-04-02 2018-10-02 上海航天智慧能源技术有限公司 A kind of Load Distribution method of steam-water dual-purpose gas fired-boiler group

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1486569A (en) * 1974-09-03 1977-09-21 Babcock & Wilcox Co Control system for a power producing unit
CN101093075A (en) * 2007-06-25 2007-12-26 周振华 Distribution control method for automatic balancing pressures in mother pipes of boilers run parallelly
CN202032548U (en) * 2011-04-02 2011-11-09 中国石油化工股份有限公司 Automatic load distribution control system for boiler using main pipe system operation mode
CN102799778A (en) * 2012-07-16 2012-11-28 杭州电子科技大学 Method for optimizing load distribution of boiler
CN103512021A (en) * 2013-10-23 2014-01-15 北京和隆优化科技股份有限公司 Method for precisely regulating and adjusting load of main-pipe furnace

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1486569A (en) * 1974-09-03 1977-09-21 Babcock & Wilcox Co Control system for a power producing unit
CN101093075A (en) * 2007-06-25 2007-12-26 周振华 Distribution control method for automatic balancing pressures in mother pipes of boilers run parallelly
CN202032548U (en) * 2011-04-02 2011-11-09 中国石油化工股份有限公司 Automatic load distribution control system for boiler using main pipe system operation mode
CN102799778A (en) * 2012-07-16 2012-11-28 杭州电子科技大学 Method for optimizing load distribution of boiler
CN103512021A (en) * 2013-10-23 2014-01-15 北京和隆优化科技股份有限公司 Method for precisely regulating and adjusting load of main-pipe furnace

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙艳 等: "母管制机组的炉机负荷分配运算与协调控制", 《自动化仪表》 *
张宇 等: "一种适用于电力系统中长期稳定仿真的汽轮机模型", 《电气开关》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108613247A (en) * 2018-04-02 2018-10-02 上海航天智慧能源技术有限公司 A kind of Load Distribution method of steam-water dual-purpose gas fired-boiler group
CN108613247B (en) * 2018-04-02 2022-09-20 上海航天智慧能源技术有限公司 Heat load distribution method of steam-water dual-purpose gas boiler group

Also Published As

Publication number Publication date
CN104089269B (en) 2016-02-03

Similar Documents

Publication Publication Date Title
Zhang et al. Conventional and energy level based exergoeconomic analysis of biomass and natural gas fired polygeneration system integrated with ground source heat pump and PEM electrolyzer
CN109943373B (en) Energy conversion and storage method based on electric gas production technology
Zhou et al. Decrease of energy demand for bioethanol-based polygeneration system through case study
CN104633765A (en) Energy-conservation control system and method
CN107355262A (en) A kind of thermal power plant's peaking generation system and electricity-generating control method
Nie et al. Clean and low-carbon heating in the building sector of China: 10-Year development review and policy implications
CN104089269A (en) Load distribution method for main-pipeline unit boiler in power station
CN113343490A (en) Industrial steam supply power station operation optimization method and system coupled with molten salt heat storage
CN103983841B (en) The determination method that power is affected by the economy of cogeneration units
CN206094975U (en) Utilize device of aluminium cell cogeneration
Yan et al. China's present situation of coal consumption and future coal demand forecast
CN104965984A (en) Calculation method for carbon dioxide emission reduction amount of natural gas distributed energy system
CN207094629U (en) Biomass centralized power generation device
CN212777602U (en) Biomass boiler and wind power clean heat supply and gas supply power supply system
CN201706900U (en) Device utilizing smoke of economizer to heat condensation water for waste heat generation
CN104178234A (en) Method and system for preparing natural gas from coke oven gas and generator gas and utilizing waste heat
CN202304454U (en) Double-pressure waste heat recovery system for flue gas acid making in copper smelting
CN220852108U (en) Oil field steam injection system with fossil energy and clean energy coupled
CN104614197A (en) Thermal efficient on-line monitoring method for furnace with multi-fuel combustion of pulverized coal and blast-furnace gas
CN112146887B (en) Method and system for calculating minimum stable combustion load of coal-fired unit in real time
FAQS What is US electricity generation by energy source?
CN111585311B (en) Method for adjusting biomass gasification power generation rate in real time
CN211502740U (en) Natural gas boiler flue gas condensate water and waste heat recovery utilize system
CN102766562A (en) Heat pump-assisted electric boiler heat-accumulated heating and brewing distillation system
CN202092210U (en) Photo-thermal solar energy and cogeneration machine set combined heating system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant