CN104074540A - Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section - Google Patents
Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section Download PDFInfo
- Publication number
- CN104074540A CN104074540A CN201410307183.1A CN201410307183A CN104074540A CN 104074540 A CN104074540 A CN 104074540A CN 201410307183 A CN201410307183 A CN 201410307183A CN 104074540 A CN104074540 A CN 104074540A
- Authority
- CN
- China
- Prior art keywords
- circular arc
- section
- trackless
- tunnel cross
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The invention discloses trackless walking equipment for subsequent construction of a shield excavation circular arc-shaped tunnel cross section. The trackless walking equipment comprises a carrying system, wherein the lower part of the carrying system is provided with a walking system and a regulating system; walking wheels of the walking system are arranged on the inner surface of a circular arc-shaped tunnel; and all transportation equipment for logistics transportation, hanging, transferring and the like on the shield excavation circular arc-shaped tunnel cross section can realize the trackless transportation. The trackless walking equipment has the advantages that the structure is simple; the style is attractive; the construction is convenient; the arrangement of temporary support and tracks is not needed; and the general use in the circular arc-shaped tunnel cross section after the shield excavation can be realized.
Description
Technical field
The present invention relates to a kind of tunneling shield construction technology, relate in particular to the follow-up construction trackless of a kind of shield tunneling circular arc tunnel cross-section walking arrangement.
Background technology
At present, in tunneling shield excavation construction, its tunnel cross-section major part is circular section, and construction field relates to railway, subway and diversion tunnel.
Existing construction logistics transportation method, the transportation resources of most of employing rail is to adapt to the circular section after shield tunneling, and rail traffic requirements punches on section of jurisdiction, and temporary supporting and track are installed.
At least there is following shortcoming in above-mentioned prior art:
The broken endless tube chip architecture of punching on section of jurisdiction, punching work has increased workload, has dropped into a large amount of manpower and materials, and temporary supporting shakiness has the danger sliding down, and temporary supporting takes up room.
Summary of the invention
The object of this invention is to provide a kind of simple in structure, constructability, without the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that temporary supporting and track are set.
The object of the invention is to be achieved through the following technical solutions:
The follow-up construction trackless of shield tunneling circular arc tunnel cross-section of the present invention walking arrangement, comprises bearing system, and the bottom of described bearing system is provided with running gear, and the road wheel of described running gear is placed in the inner surface in circular arc tunnel.
As seen from the above technical solution provided by the invention, the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that the embodiment of the present invention provides, owing to comprising bearing system, the bottom of bearing system is provided with running gear, the road wheel of running gear is placed in the inner surface in circular arc tunnel, and all haulage devices are trackless transport can to realize shield tunneling circular section logistics transportation, lift, have bad luck etc.Simple in structure, pattern is attractive in appearance, constructability, without temporary supporting and track are set, can realize after shield tunneling general in circular arc tunnel cross-section.
Brief description of the drawings
The axle geodesic structure schematic diagram of the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that Fig. 1 provides for the embodiment of the present invention one;
The cross section structure schematic diagram of the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that Fig. 2 provides for the embodiment of the present invention one;
The axle geodesic structure schematic diagram of the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that Fig. 3 provides for the embodiment of the present invention two;
The cross section structure schematic diagram of the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that Fig. 4 provides for the embodiment of the present invention two;
Fig. 5 is the structural representation of running gear in the embodiment of the present invention.
In figure:
1, connected system, 2, hanging device, 3, running gear, 4, adjustment System, 5, electrical system, 6, circular section, 7, haulage device.
Detailed description of the invention
To be described in further detail the embodiment of the present invention below.
The follow-up construction trackless of shield tunneling circular arc tunnel cross-section of the present invention walking arrangement, preferably detailed description of the invention is as shown in Figures 1 to 5 for it:
Comprise bearing system, the bottom of described bearing system is provided with running gear, and the road wheel of described running gear is placed in the inner surface in circular arc tunnel.
Between described running gear and described bearing system, be provided with adjustment System.
As shown in Figure 1 and Figure 2, described bearing system comprises hanging device, between described hanging device and described adjustment System, is connected by connected system.
As shown in Figure 3, Figure 4, described bearing system comprises haulage device.
Described bearing system comprises the equipment of having bad luck (not signal in detail, can be with reference to Fig. 3, Fig. 4).
Described circular arc tunnel cross-section is after shield tunneling or the section forming after pipe-plate lining.
The follow-up construction trackless of shield tunneling circular arc tunnel cross-section of the present invention walking arrangement, select trackless haulage device, can realize shield tunneling circular section logistics transportation, lift, have bad luck etc. comprises all means of transportation and is trackless transport, simple in structure, pattern is attractive in appearance, constructability, without temporary supporting and track are set, can realize after shield tunneling general in circular arc tunnel cross-section.
Handling appliance is simple in structure, pattern is attractive in appearance, constructability; Haulage device is for directly transporting material; The equipment of having bad luck is walked at circular section for vehicle.Can select the top equipment of difference in functionality according to form of construction work difference, running gear is walked on circular section, without walking track is set.Adjustment System can realize the conversion of running gear at rectangular cross section and circular section, has reduced and has laid the destruction of temporary track to tunnel duct piece, saves manpower, has greatly improved efficiency of construction, has reduced construction cost.
The present invention can be used as trackless transportation resources and construction equipment is applied to track traffic building field (railway, subway work all can relate to); be particularly useful for subway work; its advantage is simple in structure; pattern is attractive in appearance; constructability, without temporary supporting track is set, has effectively protected the integrality of shield duct piece; reduce construction cost, can realize after shield tunneling general in circular arc tunnel.
The above; only for preferably detailed description of the invention of the present invention, but protection scope of the present invention is not limited to this, is anyly familiar with in technical scope that those skilled in the art disclose in the present invention; the variation that can expect easily or replacement, within all should being encompassed in protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with the protection domain of claims.
Claims (6)
1. the follow-up construction trackless of a shield tunneling circular arc tunnel cross-section walking arrangement, is characterized in that, comprises bearing system, and the bottom of described bearing system is provided with running gear, and the road wheel of described running gear is placed in the inner surface in circular arc tunnel.
2. the follow-up construction trackless of shield tunneling circular arc tunnel cross-section according to claim 1 walking arrangement, is characterized in that, between described running gear and described bearing system, is provided with adjustment System.
3. the follow-up construction trackless of shield tunneling circular arc tunnel cross-section according to claim 2 walking arrangement, is characterized in that, described bearing system comprises hanging device, between described hanging device and described adjustment System, is connected by connected system.
4. the follow-up construction trackless of shield tunneling circular arc tunnel cross-section according to claim 2 walking arrangement, is characterized in that, described bearing system comprises haulage device.
5. the follow-up construction trackless of shield tunneling circular arc tunnel cross-section according to claim 2 walking arrangement, is characterized in that, described bearing system comprises the equipment of having bad luck.
6. according to the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement described in claim 1 to 5 any one, it is characterized in that, described circular arc tunnel cross-section is after shield tunneling or the section forming after pipe-plate lining.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410307183.1A CN104074540A (en) | 2014-06-30 | 2014-06-30 | Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410307183.1A CN104074540A (en) | 2014-06-30 | 2014-06-30 | Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104074540A true CN104074540A (en) | 2014-10-01 |
Family
ID=51596106
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410307183.1A Pending CN104074540A (en) | 2014-06-30 | 2014-06-30 | Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104074540A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104743449A (en) * | 2015-04-03 | 2015-07-01 | 中国水利水电第十工程局有限公司 | Trackless portal crane applied in circular tunnel |
CN105035102A (en) * | 2015-06-18 | 2015-11-11 | 徐工集团凯宫重工南京有限公司 | Anti-collision trailer for shield tunneling machine |
CN106044552A (en) * | 2016-08-08 | 2016-10-26 | 中铁工程机械研究设计院有限公司 | Multi-leg rubber-tired track-laying crane and construction method thereof |
CN107701195A (en) * | 2017-11-16 | 2018-02-16 | 中铁建设投资集团有限公司 | A kind of multi-functional running gear of TBM connecting bridges and its control method |
CN108150204A (en) * | 2018-02-01 | 2018-06-12 | 辽宁三三工业有限公司 | A kind of shield machine fast discharging arm assembly suitable for small digging diameter |
CN108678785A (en) * | 2018-05-04 | 2018-10-19 | 中铁第五勘察设计院集团有限公司 | A kind of box culvert loop wheel machine for the prefabricated inverted arch side box culvert lifting of railway tunnel |
CN113701078A (en) * | 2021-09-04 | 2021-11-26 | 交通运输部科学研究院 | Tunnel construction lighting equipment |
-
2014
- 2014-06-30 CN CN201410307183.1A patent/CN104074540A/en active Pending
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104743449A (en) * | 2015-04-03 | 2015-07-01 | 中国水利水电第十工程局有限公司 | Trackless portal crane applied in circular tunnel |
CN104743449B (en) * | 2015-04-03 | 2016-06-29 | 中国水利水电第十工程局有限公司 | It is applied to the railless door machine in circular hole |
CN105035102A (en) * | 2015-06-18 | 2015-11-11 | 徐工集团凯宫重工南京有限公司 | Anti-collision trailer for shield tunneling machine |
CN105035102B (en) * | 2015-06-18 | 2017-07-07 | 徐工集团凯宫重工南京有限公司 | A kind of crash-proof trailer for shield machine |
CN106044552A (en) * | 2016-08-08 | 2016-10-26 | 中铁工程机械研究设计院有限公司 | Multi-leg rubber-tired track-laying crane and construction method thereof |
CN106044552B (en) * | 2016-08-08 | 2018-04-24 | 中铁工程机械研究设计院有限公司 | A kind of more supporting leg rubber-tyred tracklaying cranes and construction method |
CN107701195A (en) * | 2017-11-16 | 2018-02-16 | 中铁建设投资集团有限公司 | A kind of multi-functional running gear of TBM connecting bridges and its control method |
CN108150204A (en) * | 2018-02-01 | 2018-06-12 | 辽宁三三工业有限公司 | A kind of shield machine fast discharging arm assembly suitable for small digging diameter |
CN108678785A (en) * | 2018-05-04 | 2018-10-19 | 中铁第五勘察设计院集团有限公司 | A kind of box culvert loop wheel machine for the prefabricated inverted arch side box culvert lifting of railway tunnel |
CN113701078A (en) * | 2021-09-04 | 2021-11-26 | 交通运输部科学研究院 | Tunnel construction lighting equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104074540A (en) | Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section | |
CN103924527A (en) | Highway girder fabrication yard arrangement structure which is environmentally friendly, saves resources and integrates frame fabrication and construction method thereof | |
CN103362546B (en) | A kind of inclined shaft conveying device and haul method thereof | |
CN205802797U (en) | A kind of monorail trolley | |
CN204777290U (en) | Small -size railcar ring line operational system | |
CN203114336U (en) | Device for transporting slag discharging vehicle in inclined shaft section and steep slope section | |
CN105274929A (en) | All-in-one assembling machine for road construction | |
CN102979532A (en) | Development method of transportation through auxiliary slope ramp matched with rubber belt inclined shaft | |
CN204020444U (en) | A kind of railroad track sleeper conventional flat-panel car | |
CN204457797U (en) | A kind of top longitudinal beam structure of subway station | |
CN104088665A (en) | Steel pipe column construction process for underground excavated station | |
CN107829751A (en) | A kind of supporting trolley device of shield machine for handling the interim dangerous situation of shield-tunneling construction | |
CN203430563U (en) | Narrow and small deviated well bore space pipe conveying and hoisting device | |
CN203781688U (en) | Novel miniature sling equipment | |
CN106927365A (en) | Rail junction conversion equipment | |
CN104265304A (en) | Metro circular-arc-shaped section reinforcing construction apparatus | |
CN204715128U (en) | Railway track braced structures | |
CN204098916U (en) | Subway circular section strengthening construction equipment | |
CN203284709U (en) | Underground coal mine rubber-wheel vehicle main haulage roadway road pavement structure | |
CN202659279U (en) | Turntable type flat parking lot for mine tunnel | |
CN102767384B (en) | In construction hole, penstock installs rotating disk | |
CN202557552U (en) | Squeezing car device | |
CN207727367U (en) | Supporting member for metro shield tunneling battery truck walking rails | |
CN202176361U (en) | Double-end type station for distributing movable escape capsules or movable escape capsule ranks | |
CN210829380U (en) | Shield constructs quick-witted platform truck translation bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20141001 |
|
RJ01 | Rejection of invention patent application after publication |