CN104074540A - Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section - Google Patents

Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section Download PDF

Info

Publication number
CN104074540A
CN104074540A CN201410307183.1A CN201410307183A CN104074540A CN 104074540 A CN104074540 A CN 104074540A CN 201410307183 A CN201410307183 A CN 201410307183A CN 104074540 A CN104074540 A CN 104074540A
Authority
CN
China
Prior art keywords
circular arc
section
trackless
tunnel cross
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410307183.1A
Other languages
Chinese (zh)
Inventor
万鹏
王立新
杨岳勤
孙世豪
张立青
李刚
章远方
王浩
张磊
王玲
王鹏
刘巍
贺春龙
吴敬蓬
孙振宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Railway No5 Institute Engineering Machinery Co Ltd
China Railway Fifth Survey and Design Institute Group Co Ltd
Original Assignee
Beijing Railway No5 Institute Engineering Machinery Co Ltd
China Railway Fifth Survey and Design Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Railway No5 Institute Engineering Machinery Co Ltd, China Railway Fifth Survey and Design Institute Group Co Ltd filed Critical Beijing Railway No5 Institute Engineering Machinery Co Ltd
Priority to CN201410307183.1A priority Critical patent/CN104074540A/en
Publication of CN104074540A publication Critical patent/CN104074540A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses trackless walking equipment for subsequent construction of a shield excavation circular arc-shaped tunnel cross section. The trackless walking equipment comprises a carrying system, wherein the lower part of the carrying system is provided with a walking system and a regulating system; walking wheels of the walking system are arranged on the inner surface of a circular arc-shaped tunnel; and all transportation equipment for logistics transportation, hanging, transferring and the like on the shield excavation circular arc-shaped tunnel cross section can realize the trackless transportation. The trackless walking equipment has the advantages that the structure is simple; the style is attractive; the construction is convenient; the arrangement of temporary support and tracks is not needed; and the general use in the circular arc-shaped tunnel cross section after the shield excavation can be realized.

Description

The follow-up construction trackless of shield tunneling circular arc tunnel cross-section walking arrangement
Technical field
The present invention relates to a kind of tunneling shield construction technology, relate in particular to the follow-up construction trackless of a kind of shield tunneling circular arc tunnel cross-section walking arrangement.
Background technology
At present, in tunneling shield excavation construction, its tunnel cross-section major part is circular section, and construction field relates to railway, subway and diversion tunnel.
Existing construction logistics transportation method, the transportation resources of most of employing rail is to adapt to the circular section after shield tunneling, and rail traffic requirements punches on section of jurisdiction, and temporary supporting and track are installed.
At least there is following shortcoming in above-mentioned prior art:
The broken endless tube chip architecture of punching on section of jurisdiction, punching work has increased workload, has dropped into a large amount of manpower and materials, and temporary supporting shakiness has the danger sliding down, and temporary supporting takes up room.
Summary of the invention
The object of this invention is to provide a kind of simple in structure, constructability, without the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that temporary supporting and track are set.
The object of the invention is to be achieved through the following technical solutions:
The follow-up construction trackless of shield tunneling circular arc tunnel cross-section of the present invention walking arrangement, comprises bearing system, and the bottom of described bearing system is provided with running gear, and the road wheel of described running gear is placed in the inner surface in circular arc tunnel.
As seen from the above technical solution provided by the invention, the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that the embodiment of the present invention provides, owing to comprising bearing system, the bottom of bearing system is provided with running gear, the road wheel of running gear is placed in the inner surface in circular arc tunnel, and all haulage devices are trackless transport can to realize shield tunneling circular section logistics transportation, lift, have bad luck etc.Simple in structure, pattern is attractive in appearance, constructability, without temporary supporting and track are set, can realize after shield tunneling general in circular arc tunnel cross-section.
Brief description of the drawings
The axle geodesic structure schematic diagram of the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that Fig. 1 provides for the embodiment of the present invention one;
The cross section structure schematic diagram of the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that Fig. 2 provides for the embodiment of the present invention one;
The axle geodesic structure schematic diagram of the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that Fig. 3 provides for the embodiment of the present invention two;
The cross section structure schematic diagram of the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement that Fig. 4 provides for the embodiment of the present invention two;
Fig. 5 is the structural representation of running gear in the embodiment of the present invention.
In figure:
1, connected system, 2, hanging device, 3, running gear, 4, adjustment System, 5, electrical system, 6, circular section, 7, haulage device.
Detailed description of the invention
To be described in further detail the embodiment of the present invention below.
The follow-up construction trackless of shield tunneling circular arc tunnel cross-section of the present invention walking arrangement, preferably detailed description of the invention is as shown in Figures 1 to 5 for it:
Comprise bearing system, the bottom of described bearing system is provided with running gear, and the road wheel of described running gear is placed in the inner surface in circular arc tunnel.
Between described running gear and described bearing system, be provided with adjustment System.
As shown in Figure 1 and Figure 2, described bearing system comprises hanging device, between described hanging device and described adjustment System, is connected by connected system.
As shown in Figure 3, Figure 4, described bearing system comprises haulage device.
Described bearing system comprises the equipment of having bad luck (not signal in detail, can be with reference to Fig. 3, Fig. 4).
Described circular arc tunnel cross-section is after shield tunneling or the section forming after pipe-plate lining.
The follow-up construction trackless of shield tunneling circular arc tunnel cross-section of the present invention walking arrangement, select trackless haulage device, can realize shield tunneling circular section logistics transportation, lift, have bad luck etc. comprises all means of transportation and is trackless transport, simple in structure, pattern is attractive in appearance, constructability, without temporary supporting and track are set, can realize after shield tunneling general in circular arc tunnel cross-section.
Handling appliance is simple in structure, pattern is attractive in appearance, constructability; Haulage device is for directly transporting material; The equipment of having bad luck is walked at circular section for vehicle.Can select the top equipment of difference in functionality according to form of construction work difference, running gear is walked on circular section, without walking track is set.Adjustment System can realize the conversion of running gear at rectangular cross section and circular section, has reduced and has laid the destruction of temporary track to tunnel duct piece, saves manpower, has greatly improved efficiency of construction, has reduced construction cost.
The present invention can be used as trackless transportation resources and construction equipment is applied to track traffic building field (railway, subway work all can relate to); be particularly useful for subway work; its advantage is simple in structure; pattern is attractive in appearance; constructability, without temporary supporting track is set, has effectively protected the integrality of shield duct piece; reduce construction cost, can realize after shield tunneling general in circular arc tunnel.
The above; only for preferably detailed description of the invention of the present invention, but protection scope of the present invention is not limited to this, is anyly familiar with in technical scope that those skilled in the art disclose in the present invention; the variation that can expect easily or replacement, within all should being encompassed in protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with the protection domain of claims.

Claims (6)

1. the follow-up construction trackless of a shield tunneling circular arc tunnel cross-section walking arrangement, is characterized in that, comprises bearing system, and the bottom of described bearing system is provided with running gear, and the road wheel of described running gear is placed in the inner surface in circular arc tunnel.
2. the follow-up construction trackless of shield tunneling circular arc tunnel cross-section according to claim 1 walking arrangement, is characterized in that, between described running gear and described bearing system, is provided with adjustment System.
3. the follow-up construction trackless of shield tunneling circular arc tunnel cross-section according to claim 2 walking arrangement, is characterized in that, described bearing system comprises hanging device, between described hanging device and described adjustment System, is connected by connected system.
4. the follow-up construction trackless of shield tunneling circular arc tunnel cross-section according to claim 2 walking arrangement, is characterized in that, described bearing system comprises haulage device.
5. the follow-up construction trackless of shield tunneling circular arc tunnel cross-section according to claim 2 walking arrangement, is characterized in that, described bearing system comprises the equipment of having bad luck.
6. according to the follow-up construction trackless of the shield tunneling circular arc tunnel cross-section walking arrangement described in claim 1 to 5 any one, it is characterized in that, described circular arc tunnel cross-section is after shield tunneling or the section forming after pipe-plate lining.
CN201410307183.1A 2014-06-30 2014-06-30 Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section Pending CN104074540A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410307183.1A CN104074540A (en) 2014-06-30 2014-06-30 Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410307183.1A CN104074540A (en) 2014-06-30 2014-06-30 Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section

Publications (1)

Publication Number Publication Date
CN104074540A true CN104074540A (en) 2014-10-01

Family

ID=51596106

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410307183.1A Pending CN104074540A (en) 2014-06-30 2014-06-30 Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section

Country Status (1)

Country Link
CN (1) CN104074540A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104743449A (en) * 2015-04-03 2015-07-01 中国水利水电第十工程局有限公司 Trackless portal crane applied in circular tunnel
CN105035102A (en) * 2015-06-18 2015-11-11 徐工集团凯宫重工南京有限公司 Anti-collision trailer for shield tunneling machine
CN106044552A (en) * 2016-08-08 2016-10-26 中铁工程机械研究设计院有限公司 Multi-leg rubber-tired track-laying crane and construction method thereof
CN107701195A (en) * 2017-11-16 2018-02-16 中铁建设投资集团有限公司 A kind of multi-functional running gear of TBM connecting bridges and its control method
CN108150204A (en) * 2018-02-01 2018-06-12 辽宁三三工业有限公司 A kind of shield machine fast discharging arm assembly suitable for small digging diameter
CN108678785A (en) * 2018-05-04 2018-10-19 中铁第五勘察设计院集团有限公司 A kind of box culvert loop wheel machine for the prefabricated inverted arch side box culvert lifting of railway tunnel
CN113701078A (en) * 2021-09-04 2021-11-26 交通运输部科学研究院 Tunnel construction lighting equipment

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104743449A (en) * 2015-04-03 2015-07-01 中国水利水电第十工程局有限公司 Trackless portal crane applied in circular tunnel
CN104743449B (en) * 2015-04-03 2016-06-29 中国水利水电第十工程局有限公司 It is applied to the railless door machine in circular hole
CN105035102A (en) * 2015-06-18 2015-11-11 徐工集团凯宫重工南京有限公司 Anti-collision trailer for shield tunneling machine
CN105035102B (en) * 2015-06-18 2017-07-07 徐工集团凯宫重工南京有限公司 A kind of crash-proof trailer for shield machine
CN106044552A (en) * 2016-08-08 2016-10-26 中铁工程机械研究设计院有限公司 Multi-leg rubber-tired track-laying crane and construction method thereof
CN106044552B (en) * 2016-08-08 2018-04-24 中铁工程机械研究设计院有限公司 A kind of more supporting leg rubber-tyred tracklaying cranes and construction method
CN107701195A (en) * 2017-11-16 2018-02-16 中铁建设投资集团有限公司 A kind of multi-functional running gear of TBM connecting bridges and its control method
CN108150204A (en) * 2018-02-01 2018-06-12 辽宁三三工业有限公司 A kind of shield machine fast discharging arm assembly suitable for small digging diameter
CN108678785A (en) * 2018-05-04 2018-10-19 中铁第五勘察设计院集团有限公司 A kind of box culvert loop wheel machine for the prefabricated inverted arch side box culvert lifting of railway tunnel
CN113701078A (en) * 2021-09-04 2021-11-26 交通运输部科学研究院 Tunnel construction lighting equipment

Similar Documents

Publication Publication Date Title
CN104074540A (en) Trackless walking equipment for subsequent construction of shield excavation circular arc-shaped tunnel cross section
CN103924527A (en) Highway girder fabrication yard arrangement structure which is environmentally friendly, saves resources and integrates frame fabrication and construction method thereof
CN103362546B (en) A kind of inclined shaft conveying device and haul method thereof
CN205802797U (en) A kind of monorail trolley
CN204777290U (en) Small -size railcar ring line operational system
CN203114336U (en) Device for transporting slag discharging vehicle in inclined shaft section and steep slope section
CN105274929A (en) All-in-one assembling machine for road construction
CN102979532A (en) Development method of transportation through auxiliary slope ramp matched with rubber belt inclined shaft
CN204020444U (en) A kind of railroad track sleeper conventional flat-panel car
CN204457797U (en) A kind of top longitudinal beam structure of subway station
CN104088665A (en) Steel pipe column construction process for underground excavated station
CN107829751A (en) A kind of supporting trolley device of shield machine for handling the interim dangerous situation of shield-tunneling construction
CN203430563U (en) Narrow and small deviated well bore space pipe conveying and hoisting device
CN203781688U (en) Novel miniature sling equipment
CN106927365A (en) Rail junction conversion equipment
CN104265304A (en) Metro circular-arc-shaped section reinforcing construction apparatus
CN204715128U (en) Railway track braced structures
CN204098916U (en) Subway circular section strengthening construction equipment
CN203284709U (en) Underground coal mine rubber-wheel vehicle main haulage roadway road pavement structure
CN202659279U (en) Turntable type flat parking lot for mine tunnel
CN102767384B (en) In construction hole, penstock installs rotating disk
CN202557552U (en) Squeezing car device
CN207727367U (en) Supporting member for metro shield tunneling battery truck walking rails
CN202176361U (en) Double-end type station for distributing movable escape capsules or movable escape capsule ranks
CN210829380U (en) Shield constructs quick-witted platform truck translation bracket

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20141001

RJ01 Rejection of invention patent application after publication