CN104074388A - 一种组合式高压线路抢修塔用单元体 - Google Patents
一种组合式高压线路抢修塔用单元体 Download PDFInfo
- Publication number
- CN104074388A CN104074388A CN201310103959.3A CN201310103959A CN104074388A CN 104074388 A CN104074388 A CN 104074388A CN 201310103959 A CN201310103959 A CN 201310103959A CN 104074388 A CN104074388 A CN 104074388A
- Authority
- CN
- China
- Prior art keywords
- tower
- voltage line
- cell cube
- emergent repairing
- rush repair
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Electric Cable Installation (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
一种组合式高压线路抢修塔用单元体,用于现场组装为高压线路铁塔的立柱式抢修塔,其特征在于:所述抢修塔单元体为框架式方体,所述抢修塔单元体多个上下叠置后以螺栓固定连接,即成为高压线路铁塔的立柱式抢修塔。根据本发明的组合式高压线路抢修塔用单元体,使得组合式高压线路铁塔立柱式抢修塔的安装方法简单,操作方便,省力,稳定性好,到位准确。另外,所述组合式高压线路抢修塔用单元体可重复使用,大大提高成本,使得铁塔及其输电线路的抢修及时完成,及时解除灾害影响,使得生产、安全可及时恢复,以减少延误和损失。
Description
技术领域
本发明涉及一种输电线路的维修施工领域,更具体地,本发明涉及一种高压输电线路铁塔抢修用的组合式抢修塔用单元体。
背景技术
在输电线路,例如220kv或以上的超高压输电线路等遇狂风暴雨、地震等风灾、雨灾、雪灾、地震等极端恶劣的自然灾害时,常会引起超高压输电线路铁塔的倒塌。由此,又会导致倒塌的铁塔及其支架的高压输电线路段危及其附近的交通设施,例如,高速公路、铁路等设施,以及各种民用设施及厂矿企业生产设备,导致严重的生产及安全事故的发生。如在位于城市地区的超高压输电线路铁塔的倒塌,则其危害更加严重。
以往,遇到所述超高压输电线路铁塔,通常是在事故现场紧急抢险,临时搭起超高压输电线路支撑用铁塔,同时,重新新建新的超高压输电线路铁塔。待所述新铁塔完成之后,在拆除该临时搭建的超高压输电线路支撑用铁塔。
或者,此时,导致倒塌的铁塔及其支架的高压输电线路段附近有交通设施,例如,高速公路、铁路等设施,所述输电线路维修、施工用的跨越架通常为30-40多公尺高。为使输电线需跨越于某些特殊交通设施路段的上方,又通常在所述跨越路段二侧分别竖立,安装跨越架专用立柱,以便将跨越架支撑。所述跨越架专用立柱通常与该跨越架连接一体,因此,其重量很大,其竖立、提升、接长和加固非常麻烦,费力。
另外,如上所述,由于倒塌的铁塔及其支架的高压输电线路段为超高电压,铁塔高度很大,且立柱重量很大,其竖立、提升、接长和加固非常麻烦,费力。因此,以往临时搭建的超高压输电线路支撑用铁塔的施工本身也非常麻烦,费时,费力,由此,使得倒塌的铁塔及其支架的高压输电线路的抢修也非常麻烦,费时,费力,给铁塔及其输电线路的抢修、灾害的及时解除和生产、安全的及时回复带来延误和损失。
发明内容
为解决上述问题,本发明的目的之一在于:提供一种组合式高压线路抢修塔用单元体。所述组合式高压线路抢修塔用单元体可在极短的时间内完成高压输电线路铁塔抢修用的立柱式抢修塔,大大有利于重新新建新的超高压输电线路铁塔。待所述新铁塔完成之后,可方便拆除该临时搭建的超高压输电线路支撑用铁塔。由此,使得倒塌的铁塔及其支架的高压输电线路的抢修也方便,快捷。另外,所述组合式高压线路抢修塔用单元体可重复使用,大大提高成本,使得铁塔及其输电线路的抢修及时完成,及时解除灾害影响,使得生产、安全可及时恢复,以减少延误和损失。
为解决上述问题,本发明的组合式高压线路抢修塔用单元体的技术方案如下:
一种组合式高压线路抢修塔用单元体,用于现场组装为高压线路抢修用的立柱式抢修塔,其特征在于:
所述抢修塔单元体3为框架式方体,所述抢修塔单元体3多个上下叠置后以螺栓固定连接,即成为高压线路铁塔的立柱式抢修塔。
根据本发明所述的一种组合式高压线路抢修塔用单元体,其特征在于:上下叠置、固定的二个抢修塔单元体3之间设置有定位销。
根据本发明所述的一种组合式高压线路抢修塔用单元体,其特征在于:所述抢修塔单元体由杆件构成长方体框架结构,所述抢修塔单元体为240-300mm见方、高300-500mm的长方体框架结构。
根据本发明所述的一种组合式高压线路抢修塔用单元体,其特征在于:所述抢修塔单元体3的长方体框架结构用于形成高压线路铁塔的立柱式抢修塔的各侧边框架的夹角处设置有连接所述框架边的加强连接板5。
根据本发明所述的一种组合式高压线路抢修塔用单元体,其特征在于,所述加强连接板5为扇形连接板。
根据本发明所述的一种组合式高压线路抢修塔用单元体,其特征在于:所述组合式高压线路抢修塔用单元体还用于形成组合式高压线路铁塔立柱式抢修塔上端、用于挂接导线的水平杆2。
由此,根据本发明的组合式高压线路抢修塔用单元体,使得组合式高压线路铁塔立柱式抢修塔的安装方法简单,操作方便,省力,稳定性好,到位准确。另外,所述组合式高压线路抢修塔用单元体可重复使用,大大提高成本,使得铁塔及其输电线路的抢修及时完成,及时解除灾害影响,使得生产、安全可及时恢复,以减少延误和损失。
附图说明
图1为本发明的组合式高压线路铁塔抢修塔单元体用于抢修铁塔示意图。
图2A为本发明的组合式高压线路铁塔抢修塔单元体示意图。
图中,三单元体连接一起。
图2B为本发明的组合式高压线路铁塔抢修塔单元体俯视图。
具体实施方式
下面结合附图和具体实施方式对本发明的组合式高压线路抢修塔用单元体作进一步说明。
实施例1
一种组合式高压线路抢修塔用单元体,用于现场组装为高压线路铁塔抢修用的立柱式抢修塔,所述抢修塔单元体3为框架式长方体,所述抢修塔单元体3多个上下叠置后以螺栓固定连接,即成为高压线路铁塔的立柱式抢修塔。
所述上下叠置、固定的二个抢修塔单元体3之间设置有定位销。先上下叠置,用定位销定位后,再螺栓固定所述二个抢修塔单元体3。
另外,在所述抢修塔单元体3的长方体框架结构用于形成高压线路铁塔的立柱式抢修塔的各侧边框架的夹角处设置有连接所述框架边的扇形加强连接板5。
所述抢修塔单元体为240mm见方、高300mm的长方形框架式单元体,所述长方形框架式单元体由铝合金制的杆件构成单元体外周六面支柱。构成所述长方形框架式单元体的单元体外周各面支柱之间设置有加强用铝合金制连接杆件。
本实施例的抢修塔用单元体构成高约32m的组合式高压线路铁塔单立柱式抢修塔。
除了形成高压线路抢修塔主体立柱,所述组合式高压线路抢修塔用单元体还用于形成组合式高压线路铁塔立柱式抢修塔上端、用于挂接导线的水平杆2。
实施例2
除了以下不同之处外,其他如同实施例1,构成组合式高压线路铁塔立柱式抢修塔:所述抢修塔单元体为260mm见方、高400mm的长方形框架式单元体,,构成高约45m的组合式高压线路铁塔双立柱式抢修塔。构成高约45m的组合式高压线路铁塔双立柱式抢修塔、由单元体构成的二个立柱顶端以杆件螺栓固定。
实施例3
除了以下不同之处外,其他如同实施例1,构成组合式高压线路铁塔立柱式抢修塔:所述抢修塔单元体为300mm见方、高450mm的长方形框架式单元体,构成高约60m的组合式高压线路铁塔四立柱式抢修塔。构成高约60m的组合式高压线路铁塔四立柱式抢修塔、由单元体构成的四个立柱顶端以杆件螺栓固定。
由此,根据本发明的组合式高压线路抢修塔用单元体,使得组合式高压线路铁塔立柱式抢修塔的安装方法简单,操作方便,省力,稳定性好,到位准确。另外,所述组合式高压线路抢修塔用单元体可重复使用,大大提高成本,使得铁塔及其输电线路的抢修及时完成,及时解除灾害影响,使得生产、安全可及时恢复,以减少延误和损失。
Claims (6)
1.一种组合式高压线路抢修塔用单元体,用于现场组装为高压线路抢修用的立柱式抢修塔,其特征在于:
所述抢修塔单元体为框架式方体,所述抢修塔单元体多个上下叠置后以螺栓固定连接,即成为高压线路铁塔的立柱式抢修塔。
2.如权利要求1所述的一种组合式高压线路抢修塔用单元体,其特征在于:上下叠置、固定的二个抢修塔单元体之间设置有定位销。
3.如权利要求1所述的一种组合式高压线路抢修塔用单元体,其特征在于:所述抢修塔单元体由杆件构成长方体框架结构,所述抢修塔单元体为240-300mm见方、高300-500mm的长方体框架结构。
4.如权利要求1所述的一种组合式高压线路抢修塔用单元体,其特征在于:所述抢修塔单元体的长方体框架结构用于形成高压线路铁塔的立柱式抢修塔的各侧边框架的夹角处设置有连接所述框架边的加强连接板。
5.如权利要求1所述的一种组合式高压线路抢修塔用单元体,其特征在于,所述加强连接板为扇形连接板。
6.如权利要求1所述的一种组合式高压线路抢修塔用单元体,其特征在于:所述组合式高压线路抢修塔用单元体还用于形成组合式高压线路铁塔立柱式抢修塔上端、用于挂接导线的水平杆。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310103959.3A CN104074388A (zh) | 2013-03-28 | 2013-03-28 | 一种组合式高压线路抢修塔用单元体 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310103959.3A CN104074388A (zh) | 2013-03-28 | 2013-03-28 | 一种组合式高压线路抢修塔用单元体 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104074388A true CN104074388A (zh) | 2014-10-01 |
Family
ID=51595958
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310103959.3A Pending CN104074388A (zh) | 2013-03-28 | 2013-03-28 | 一种组合式高压线路抢修塔用单元体 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104074388A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106121341A (zh) * | 2016-08-09 | 2016-11-16 | 国网上海市电力公司 | 一种超高压输电线路应急抢修用耐张杆塔 |
CN106150176A (zh) * | 2016-08-09 | 2016-11-23 | 国网上海市电力公司 | 一种超高压输电线路应急抢修用耐张杆塔立柱模块 |
WO2016192392A1 (zh) * | 2015-05-29 | 2016-12-08 | 王勇 | 一种单元组合式通信塔 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0389214A2 (en) * | 1989-03-21 | 1990-09-26 | Owen Brown Group Ltd | Composite beam, connector and construction |
CN201372599Y (zh) * | 2008-12-25 | 2009-12-30 | 广东和发输变电安装有限公司 | 一种输电线路快速抢修系统 |
CN101736935A (zh) * | 2010-03-01 | 2010-06-16 | 国网电力科学研究院武汉南瑞有限责任公司 | 一种便于运输的电力事故抢修塔 |
CN101736936A (zh) * | 2010-03-04 | 2010-06-16 | 国网电力科学研究院武汉南瑞有限责任公司 | 新型模块化应急抢修塔 |
CN101824932A (zh) * | 2010-03-23 | 2010-09-08 | 宁波天弘电力器具有限公司 | 抢修塔的塔段 |
CN202578108U (zh) * | 2012-04-27 | 2012-12-05 | 陕西秦能电力科技有限公司 | 一种用于抢修塔立柱与横担之间的铰接式连接构件 |
CN203223035U (zh) * | 2013-03-28 | 2013-10-02 | 国家电网公司 | 一种组合式高压线路抢修塔用单元体 |
-
2013
- 2013-03-28 CN CN201310103959.3A patent/CN104074388A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0389214A2 (en) * | 1989-03-21 | 1990-09-26 | Owen Brown Group Ltd | Composite beam, connector and construction |
CN201372599Y (zh) * | 2008-12-25 | 2009-12-30 | 广东和发输变电安装有限公司 | 一种输电线路快速抢修系统 |
CN101736935A (zh) * | 2010-03-01 | 2010-06-16 | 国网电力科学研究院武汉南瑞有限责任公司 | 一种便于运输的电力事故抢修塔 |
CN101736936A (zh) * | 2010-03-04 | 2010-06-16 | 国网电力科学研究院武汉南瑞有限责任公司 | 新型模块化应急抢修塔 |
CN101824932A (zh) * | 2010-03-23 | 2010-09-08 | 宁波天弘电力器具有限公司 | 抢修塔的塔段 |
CN202578108U (zh) * | 2012-04-27 | 2012-12-05 | 陕西秦能电力科技有限公司 | 一种用于抢修塔立柱与横担之间的铰接式连接构件 |
CN203223035U (zh) * | 2013-03-28 | 2013-10-02 | 国家电网公司 | 一种组合式高压线路抢修塔用单元体 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016192392A1 (zh) * | 2015-05-29 | 2016-12-08 | 王勇 | 一种单元组合式通信塔 |
CN106121341A (zh) * | 2016-08-09 | 2016-11-16 | 国网上海市电力公司 | 一种超高压输电线路应急抢修用耐张杆塔 |
CN106150176A (zh) * | 2016-08-09 | 2016-11-23 | 国网上海市电力公司 | 一种超高压输电线路应急抢修用耐张杆塔立柱模块 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9366456B2 (en) | Concentrated solar tower assembly and method | |
CN203223035U (zh) | 一种组合式高压线路抢修塔用单元体 | |
CN104074388A (zh) | 一种组合式高压线路抢修塔用单元体 | |
CN104532850A (zh) | 基坑支撑系统 | |
CN204266124U (zh) | 大节段钢箱梁预拼装胎架 | |
CN203938346U (zh) | 自动扶梯桁架连接结构 | |
CN103532048B (zh) | 一种快速组合的大型格构式跨越架 | |
CN202785351U (zh) | 塔式起重机附着操作平台 | |
CN204645793U (zh) | 一种输电线路的抢修塔 | |
CN104074389A (zh) | 一种组合式高压线路铁塔立柱式抢修塔 | |
CN104863407A (zh) | 一种输电线路的抢修塔 | |
CN203145547U (zh) | 一种组合式高压线路铁塔四立柱式抢修塔 | |
CN203097390U (zh) | 一种组合式高压线路铁塔单立柱式抢修塔 | |
CN203097399U (zh) | 一种组合式高压线路铁塔双立柱式抢修塔 | |
CN106121341B (zh) | 超高压输电线路应急抢修用耐张杆塔 | |
CN205742523U (zh) | 一种防连续倒塌转换框架结构 | |
CN103982076A (zh) | 一种单回110kV/35拉线型铝合金抢修塔 | |
CN204850517U (zh) | 组拼式高度可调钢结构防砸系统 | |
CN204590410U (zh) | 一种户外变电构架悬挑钢梁 | |
CN103397638A (zh) | 高刚度整体预应力装配式基坑支护内支撑系统用的拉杆 | |
CN207568333U (zh) | 一种经济环保、可重复倒用的装配式钢制围挡及围挡组件 | |
CN106150176B (zh) | 超高压输电线路应急抢修用耐张杆塔立柱模块 | |
CN202627194U (zh) | 一种大型消能减震空间结构体系 | |
CN202990386U (zh) | 一种外挂脚手架 | |
CN204919363U (zh) | 一种抗强风高墩拼装式劲性骨架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20141001 |