CN104074331B - The construction method of sightseeing elevator structure finishing factory operation - Google Patents

The construction method of sightseeing elevator structure finishing factory operation Download PDF

Info

Publication number
CN104074331B
CN104074331B CN201410290802.0A CN201410290802A CN104074331B CN 104074331 B CN104074331 B CN 104074331B CN 201410290802 A CN201410290802 A CN 201410290802A CN 104074331 B CN104074331 B CN 104074331B
Authority
CN
China
Prior art keywords
construction
factory
sightseeing elevator
aluminum veneer
agent structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410290802.0A
Other languages
Chinese (zh)
Other versions
CN104074331A (en
Inventor
方继
李荣浩
牙马忠
刘瑜
方源
史纲
李国华
于向涛
刘果
张士宝
杨兴武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Steel Structure Construction Co Ltd of CTCE Group
Original Assignee
STEEL STRUCTURE Co Ltd OF CHINA TIESIJU CIVIL ENGINEERING GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by STEEL STRUCTURE Co Ltd OF CHINA TIESIJU CIVIL ENGINEERING GROUP filed Critical STEEL STRUCTURE Co Ltd OF CHINA TIESIJU CIVIL ENGINEERING GROUP
Priority to CN201410290802.0A priority Critical patent/CN104074331B/en
Publication of CN104074331A publication Critical patent/CN104074331A/en
Application granted granted Critical
Publication of CN104074331B publication Critical patent/CN104074331B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses the construction method of sightseeing elevator structure finishing factory operation, include following construction procedure: main body steel construction is integrated with segmentation in extraneous adornment factory to be manufactured, the segmented whole Transporting of sections, integral hoisting, last on-the-spot standardization carries out the construction of embedding benefit region.The present invention provides the construction method of a kind of sightseeing elevator structure finishing factory operation, achieve erecting bed welding operation in sightseeing elevator is constructed, reduce amount of high-altitude operation, construction standardization, efficient, convenient, reach effective reduction construction cost, shortened the construction period, ensure the target of construction quality safety.

Description

The construction method of sightseeing elevator structure finishing factory operation
Technical field
Present invention relates particularly to sightseeing elevator structure finishing factory operation method, be particularly well-suited to sightseeing elevator, similar sightseeing elevator rectangular configuration building or structures, belong to room and build structure and decoration construction technical field.
Background technology
Sightseeing elevator is a kind of vertical conveyor with motor as power, equipped with box like gondola, takes advantage of people or carrying goods for tier building, serves the fixed type lifting equipment of regulation floor.Agent structure mainly uses xoncrete structure or steel construction, is mainly installed on hotel, market, office tower occasion.
The form of construction work of sightseeing elevator routine is, after main structure construction completes, to carry out decorations construction, is primarily present not enough:
1, amount of high-altitude operation is big, safe pressure is big;
2, finishing keel welding node is many, welds the most reliable, it is difficult to check comprehensively;
3, the construction period is longer;
4, taking relevant interim measure more, cost puts into relatively can be increased.
Summary of the invention
It is an object of the invention to provide the construction method of a kind of structure finishing factory operation simply, efficiently and not affecting architectural effect, it is achieved solution sightseeing elevator rapidly and efficiently, the construction difficult problem in the similar field such as sightseeing elevator rectangular configuration building or structures.
The present invention solve technical problem provide following scheme:
The construction method of sightseeing elevator structure finishing factory operation, includes following construction procedure:
A, go sightseeing electricity and the integrated manufacture of segmentation in ladder main body steel construction extraneous adornment factory:
(1), according to arranging construction moulding bed in design drawing factory, agent structure integral construction is carried out;
(2), agent structure machines, and carries out coating decoration;
(3), setting level by agent structure is segmented, install decoration main joist, main joist is heat insulative fire-proof composite plate keel;
(4), heat insulative fire-proof composite plate is installed;
(5), installing secondary joist, secondary joist is outer aluminum veneer keel;
(6), aluminum veneer is installed;
B, by sections transport to on-the-spot, after on-the-spot segmental hoisting ring flange bolts firm acceptance(check), then the exterior decoration in embedding benefit section region is installed, fills up all aluminum veneer plates seam clay;
Embedding benefit regional structure, decoration construction between c, sections:
(1), flange bolt between agent structure sections;
(2), factory's embedded benefit region by standard size reserve, decorative scene keel use corner brace self threading pin be connected with agent structure, be subsequently mounted heat insulative fire-proof composite plate, aluminum veneer;
D, embedding benefit seam crossing aluminum veneer plate seam gluing.
Compared with prior art, the Advantageous Effects of the present invention:
1, minimum on architectural effect impact;
2, amount of high-altitude operation greatly reduces;
3, factory operation structure, decoration size Control precision guarantee;
4, on-the-spot embedding benefit portion structure, decoration are installed and are not got angry, and security is high;
5, easy construction, work efficiency is high, it is highly beneficial to reduce cost;
6, erecting bed only needs embedding benefit local nacelle construction, and construction safety risk is low;
7, safe and reliable, economical rationality, there is bigger promotional value.
Accompanying drawing explanation
Fig. 1 agent structure batch production processing and stepwise schematic views.
Fig. 2 fitment operation batch production machining sketch chart.
Schematic diagram after the interior decoration operation of Fig. 3 sections factory.
The transport of Fig. 4 sections, lifting stepwise schematic views.
Fig. 5 embedding benefit region construction schematic diagram.
Fig. 6 embedding benefit regional structure node connection diagram.
Fig. 7 embedding benefit region keel node connection diagram.
Detailed description of the invention
See accompanying drawing, the construction method of sightseeing elevator structure finishing factory operation, include following construction procedure:
A, go sightseeing electricity and the integrated manufacture of segmentation in ladder main body steel construction extraneous adornment factory:
(1), according to arranging construction moulding bed 1 in design drawing factory, agent structure integral construction is carried out;
(2), agent structure 2 machine, and carry out coating decoration, weld main purlin purlin and drag 3, main purlin 4 is installed;
(3), setting level by agent structure 2 is segmented, install decoration main joist, main joist is heat insulative fire-proof composite plate keel;
(4), heat insulative fire-proof composite plate 5, welding time purlin 6 are installed;
(5), installing secondary joist, secondary joist is outer aluminum veneer keel;
(6), aluminum veneer 7 is installed;
B, by sections transport to on-the-spot, after on-the-spot segmental hoisting ring flange bolts firm acceptance(check), then the exterior decoration in embedding benefit section region is installed, fills up all aluminum veneer plates seam clay;
Embedding benefit regional structure, decoration construction between c, sections:
(1), between agent structure sections, flange 9 bolts;
(2), factory's embedded benefit region by standard size reserve, decorative scene keel use corner brace 10 self threading pin 11 be connected with agent structure 2, be subsequently mounted heat insulative fire-proof composite plate 5, aluminum veneer 7;
D, embedding benefit seam crossing aluminum veneer plate seam gluing.

Claims (1)

1. the construction method of sightseeing elevator structure finishing factory operation, it is characterised in that include following construction procedure:
In a, sightseeing elevator main body steel construction extraneous adornment factory, segmentation integration manufactures:
(1), according to arranging construction moulding bed in design drawing factory, agent structure integral construction is carried out;
(2), agent structure machines, and carries out coating decoration;
(3), setting level by agent structure is segmented, install decoration main joist, main joist is heat insulative fire-proof composite plate keel;
(4), heat insulative fire-proof composite plate is installed;
(5), installing secondary joist, secondary joist is outer aluminum veneer keel;
(6), aluminum veneer is installed;
B, by sections transport to on-the-spot, after on-the-spot segmental hoisting ring flange bolts firm acceptance(check), then the exterior decoration in embedding benefit section region is installed, fills up all aluminum veneer plates seam clay;
Embedding benefit regional structure, decoration construction between c, sections:
(1), flange bolt between agent structure sections;
(2), factory's embedded benefit region by standard size reserve, decorative scene keel use corner brace self threading pin be connected with agent structure, be subsequently mounted heat insulative fire-proof composite plate, aluminum veneer;
D, embedding benefit seam crossing aluminum veneer plate seam gluing.
CN201410290802.0A 2014-06-24 2014-06-24 The construction method of sightseeing elevator structure finishing factory operation Active CN104074331B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410290802.0A CN104074331B (en) 2014-06-24 2014-06-24 The construction method of sightseeing elevator structure finishing factory operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410290802.0A CN104074331B (en) 2014-06-24 2014-06-24 The construction method of sightseeing elevator structure finishing factory operation

Publications (2)

Publication Number Publication Date
CN104074331A CN104074331A (en) 2014-10-01
CN104074331B true CN104074331B (en) 2016-08-24

Family

ID=51595902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410290802.0A Active CN104074331B (en) 2014-06-24 2014-06-24 The construction method of sightseeing elevator structure finishing factory operation

Country Status (1)

Country Link
CN (1) CN104074331B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104340813B (en) * 2014-10-30 2016-09-14 中国建筑股份有限公司 A kind of installation construction method for elevator

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2862451B2 (en) * 1993-02-02 1999-03-03 積水化成品工業株式会社 Thermal insulation wall material made of foamed resin and its construction method
CN101759079B (en) * 2009-12-30 2012-05-30 山西四建集团有限公司 Method for integrally assembling and installing steel structure elevator derrick on the ground
CN102180395B (en) * 2011-05-30 2014-03-26 张凡 Integrated sightseeing lift with steel-structured hoistway

Also Published As

Publication number Publication date
CN104074331A (en) 2014-10-01

Similar Documents

Publication Publication Date Title
CN103982038B (en) A kind of for solar energy separate house modularization rapid-assembling construction method
CN108033367B (en) Synchronous lifting device and lifting method for steel column and cylinder frame alternately supported steel platform and tower crane
CN204782005U (en) On --spot installation dolly of transporting of wallboard
CN106245779A (en) Integral prefabricated modular architectural construction technology based on UHPC material and system
CN204686104U (en) A kind of lift furred ceiling card punch
CN103898977A (en) Modularized integrated house
CN106044651A (en) Aerial operation basket
CN104074331B (en) The construction method of sightseeing elevator structure finishing factory operation
CN102808521B (en) High-altitude butting method and high-altitude butting device for heavy structures
CN201099982Y (en) Rotating arc stairway joist assembly model
CN201687218U (en) Installation device of steel shaft well
CN204456816U (en) One can promote supporting leg type elevator hoistway construction platform
CN205116390U (en) Balcony combination outer wall
CN105350651A (en) Long-span steel truss-concrete composition roofing integral lifting method
CN203905436U (en) Steel chimney annular installation platform
CN102817467A (en) Operating platform for high-altitude installation of steel structure
CN104806001B (en) The sliding safe operation platform of elevator guide rail and construction method
CN203729562U (en) Lifting and efficient working platform
CN102733518B (en) A kind of cell curtain wall top rail
CN203924695U (en) A kind of indirect cool tower mould-lifting device
CN206536942U (en) Plate aluminum coated steel device
CN204626927U (en) The sliding safe operation platform of elevator shaft guide rail
CN204850441U (en) Vertical member aluminium frame template
CN205712655U (en) A kind of movable roof
CN206438749U (en) Construction operation platform in turnover type elevator

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 230022 China Railway Fourth Bureau Group Steel Structure Co., Ltd. No. 388 Huanhu East Road, Hefei City, Anhui Province

Patentee after: Steel structure building Co., Ltd. of the four Bureau of China Railway

Address before: 230022 China Railway Fourth Bureau Group Steel Structure Co., Ltd. No. 388 Huanhu East Road, Hefei City, Anhui Province

Patentee before: Steel Structure Co., Ltd. of China Tiesiju Civil Engineering Group

CP01 Change in the name or title of a patent holder