CN104074194A - 深基坑反向对接结构平衡稳固施工方法 - Google Patents
深基坑反向对接结构平衡稳固施工方法 Download PDFInfo
- Publication number
- CN104074194A CN104074194A CN201310098204.9A CN201310098204A CN104074194A CN 104074194 A CN104074194 A CN 104074194A CN 201310098204 A CN201310098204 A CN 201310098204A CN 104074194 A CN104074194 A CN 104074194A
- Authority
- CN
- China
- Prior art keywords
- concrete
- foundation ditch
- construction
- foundation pit
- superstructure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Road Paving Structures (AREA)
- Foundations (AREA)
Abstract
本发明涉及深基坑建筑结构施工;其特征是:它包括六道砼稳固平衡支撑梁结构,还包括下述施工方法:将土方开挖至岩石层,此开挖层面为基坑上部结构;在基坑上部结构下方爆破开挖的岩石层上建立砼填充找平层;在砼填充找平层的基础上按砼结构外径支模并浇筑填充混凝土,在砼结构外模的基础上进行上部砼结构施工;在上部砼结构的顶部外围均匀布设总共六道的砼稳固平衡支撑梁,待基坑上部结构施工完毕后,进行土方回填作业,基坑上部结构下方岩石层爆破施工,基坑土方开挖至基坑整体设计深度;基坑下部结构施工,基坑作业完成。本发明上部砼结构不会因爆破岩层松动出现位移,保证了整体结构位置精度及对接施工的顺利进行。
Description
技术领域
本发明涉及土木建筑施工领域,具体涉及深基坑建筑结构施工。
背景技术
深基坑施工遇到上半部为土层下半部为岩石层的地质条件时,上半部采取土方开挖,下半部采岩石层需采取爆破,爆破工程从方案编制、审批、公安部门审查、爆破材料的选取等各项工作周期相对比较长,而爆破时产生的振动会影响上半部开挖基坑土方边坡的稳定,按照常规施工结构需待基坑开挖到底部时,由下向上施工,按此方法进行施工会出现施工周期长、施工环境安全系数小等缺点;为解决此问题,提供了一种深基坑反向施工方法,该方法先将岩石层上部的土方进行开挖,开挖后将岩石层上部的结构施工好,之后在结构底边设计一圈反梁,该反梁用以稳固上部结构以及与下部结构对接,之后将土方进行回填,回填后进行爆破施工,爆破开挖至基坑底部后再进行下部结构施工,施工至上部结构底部反梁进行对接;此种方法遇到下部为松散岩层或强度不均匀的岩层时,进行岩层爆破期间,松散岩层结构会因震动出现变形致使上部已经施工好的结构出现位移,给反向对接施工带来影响。
发明内容
本发明的目的在于提供一种上部结构不会因爆破岩层松动出现位移,保证整体结构位置精度及对接施工的深基坑反向对接结构平衡稳固施工方法。
为了达到上述目的,本发明是这样实现的:
一种深基坑反向对接结构平衡稳固施工方法,它包括围绕基坑上部结构均匀分布的至少六道砼稳固平衡支撑梁结构,还包括下述施工方法:
步骤1、将土方开挖至岩石层,此开挖层面为基坑上部结构;
步骤2、将基坑上部结构下方岩石层向下爆破开挖2米,爆破开挖直径大于砼结构直径200mm以上;
步骤3、在基坑上部结构下方爆破开挖的岩石层上建立砼填充找平层;
步骤4、在砼填充找平层的基础上按砼结构外径支模并浇筑填充混凝土,待其凝固后形成砼结构的外模;
步骤5、在砼结构外模底部设置横向打入岩石层平面内的反梁,所述反梁底部布设于周边岩石层牢固链接的外圈锚固钢筋以及反梁内圈结构预留钢筋;锚固钢筋用以在爆破期间与基坑下部爆破开挖后的稳固作用,内圈预留钢筋为与下部结构施工时的对接作用;
步骤6、在砼结构外模的基础上进行上部砼结构施工;
步骤7、在上部砼结构的顶部外围均匀布设总共六道的砼稳固平衡支撑梁,如此,形成基坑上部结构;
步骤8、待基坑上部结构施工完毕后,进行土方回填作业,土方回填时应当对称回填并分层夯实;
步骤9、基坑上部结构下方岩石层爆破施工,爆破深度达到基坑整体深度设计要求;
步骤10、基坑土方开挖至基坑整体设计深度;
步骤11、基坑下部结构施工,并与反梁内圈的预留钢筋进行对接作业;
如此,基坑作业完成。
本发明采用上述设计,施工好的上部结构插入下部岩层内一部分,周围有六道平衡稳固结构进行支撑,回填夯实后的土方对上部结构起到挤实稳定作用,上部结构稳固后,进行下部岩石层爆破施工,进行爆破施工期间即使岩石层部位有松散现象,经过上述几项平衡稳固措施后,上部砼结构不会因爆破岩层松动出现位移,保证了整体结构位置精度及对接施工的顺利进行。
附图说明
图1为本发明基坑上部结构施工示意图。
图2为本发明基坑下部结构施工示意图。
图3为本发明基坑俯视图。
具体实施方式
如图1、图2和图3所示,一种深基坑反向对接结构平衡稳固施工方法,它包括围绕基坑上部结构均匀分布的六道砼稳固平衡支撑梁结构5,还包括下述施工方法:
步骤1、将土方3开挖至岩石层,此开挖层面为基坑上部结构;
步骤2、将基坑上部结构下方岩石层向下爆破开挖2米,爆破开挖直径大于砼结构直径200mm以上;
步骤3、在基坑上部结构下方爆破开挖的岩石层上建立砼填充找平层2;
步骤4、在砼填充找平层2的基础上按砼结构外径支模并浇筑填充混凝土,待其凝固后形成砼结构的外模1;
步骤5、在砼结构外模1底部设置横向打入岩石层平面内的反梁4,所述反梁4底部布设于周边岩石层牢固链接的外圈锚固钢筋以及反梁内圈结构预留钢筋;锚固钢筋用以在爆破期间与基坑下部爆破开挖后的稳固作用,内圈预留钢筋为与下部结构施工时的对接作用;
步骤6、在砼结构外模1的基础上进行上部砼结构施工;
步骤7、在上部砼结构的顶部外围均匀布设总共六道的砼稳固平衡支撑梁5,如此,形成基坑上部结构;
步骤8、待基坑上部结构施工完毕后,进行土方3回填作业,土方3回填时应当对称回填分层夯实;
步骤9、基坑上部结构下方岩石层爆破施工,爆破深度达到基坑整体深度设计要求;
步骤10、基坑土方开挖至基坑整体设计深度;
步骤11、基坑下部结构6施工,并与反梁4内圈的预留钢筋进行对接作业;
如此,基坑作业完成。
本发明采用上述设计,施工好的上部结构插入下部岩层内一部分,周围有六道平衡稳固结构进行支撑,回填夯实后的土方对上部结构起到挤实稳定作用,上部结构稳固后,进行下部岩石层爆破施工,进行爆破施工期间即使岩石层部位有松散现象,经过上述几项平衡稳固措施后,上部砼结构不会因爆破岩层松动出现位移,保证了整体结构位置精度及对接施工的顺利进行。
Claims (1)
1. 一种深基坑反向对接结构平衡稳固施工方法,其特征是:它包括围绕基坑上部结构均匀分布的至少六道砼稳固平衡支撑梁结构,还包括下述施工方法:
步骤1、将土方开挖至岩石层,此开挖层面为基坑上部结构;
步骤2、将基坑上部结构下方岩石层向下爆破开挖2米,爆破开挖直径大于砼结构直径200mm以上;
步骤3、在基坑上部结构下方爆破开挖的岩石层上建立砼填充找平层;
步骤4、在砼填充找平层的基础上按砼结构外径支模并浇筑填充混凝土,待其凝固后形成砼结构的外模;
步骤5、在砼结构外模底部设置横向打入岩石层平面内的反梁,所述反梁底部布设于周边岩石层牢固链接的外圈锚固钢筋以及反梁内圈结构预留钢筋;锚固钢筋用以在爆破期间与基坑下部爆破开挖后的稳固作用,内圈预留钢筋为与下部结构施工时的对接作用;
步骤6、在砼结构外模的基础上进行上部砼结构施工;
步骤7、在上部砼结构的顶部外围均匀布设总共六道的砼稳固平衡支撑梁,如此,形成基坑上部结构;
步骤8、待基坑上部结构施工完毕后,进行土方回填作业,土方回填时应当对称回填分层夯实;
步骤9、基坑上部结构下方岩石层爆破施工,爆破深度达到基坑整体深度设计要求;
步骤10、基坑土方开挖至基坑整体设计深度;
步骤11、基坑下部结构施工,并与反梁内圈的预留钢筋进行对接作业;
如此,基坑作业完成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310098204.9A CN104074194B (zh) | 2013-03-26 | 2013-03-26 | 深基坑反向对接结构平衡稳固施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310098204.9A CN104074194B (zh) | 2013-03-26 | 2013-03-26 | 深基坑反向对接结构平衡稳固施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104074194A true CN104074194A (zh) | 2014-10-01 |
CN104074194B CN104074194B (zh) | 2016-08-10 |
Family
ID=51595770
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310098204.9A Active CN104074194B (zh) | 2013-03-26 | 2013-03-26 | 深基坑反向对接结构平衡稳固施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104074194B (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003278160A (ja) * | 2002-03-27 | 2003-10-02 | Goko Kensetsu Kk | 簡易山留め工法 |
KR20060001203A (ko) * | 2004-06-30 | 2006-01-06 | 박길석 | 지하 연속벽 시공방법 및 톱니형 합벽 지하 연속벽 구조 |
CN102002952A (zh) * | 2009-09-03 | 2011-04-06 | 中国二十冶集团有限公司 | 土岩结合地域的旋流池基坑防护施工方法 |
CN102409683A (zh) * | 2011-08-12 | 2012-04-11 | 天津二十冶建设有限公司 | 漩流井半逆作施工方法 |
CN102979026A (zh) * | 2012-06-11 | 2013-03-20 | 有利华建筑预制件有限公司 | 带顶盖的人行道及其半预制建造方法 |
-
2013
- 2013-03-26 CN CN201310098204.9A patent/CN104074194B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003278160A (ja) * | 2002-03-27 | 2003-10-02 | Goko Kensetsu Kk | 簡易山留め工法 |
KR20060001203A (ko) * | 2004-06-30 | 2006-01-06 | 박길석 | 지하 연속벽 시공방법 및 톱니형 합벽 지하 연속벽 구조 |
CN102002952A (zh) * | 2009-09-03 | 2011-04-06 | 中国二十冶集团有限公司 | 土岩结合地域的旋流池基坑防护施工方法 |
CN102409683A (zh) * | 2011-08-12 | 2012-04-11 | 天津二十冶建设有限公司 | 漩流井半逆作施工方法 |
CN102979026A (zh) * | 2012-06-11 | 2013-03-20 | 有利华建筑预制件有限公司 | 带顶盖的人行道及其半预制建造方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104074194B (zh) | 2016-08-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105840207B (zh) | 一种穿越浅埋偏压松散堆积体大跨度隧道综合进洞结构施工方法 | |
CN107330194B (zh) | 盾构隧道开挖对邻近群桩基础影响的数值模拟分析方法 | |
CN103774675B (zh) | 组合双排桩联合竖向预应力锚杆支护体系的施工方法 | |
CN104695963B (zh) | 碎裂岩层中地铁隧道穿越建筑物的施工方法 | |
CN110318770A (zh) | 一种公路隧道半明半暗进洞施工方法 | |
CN103696784B (zh) | 一种浅埋大跨隧道下穿建构筑物的大直径长管幕施工方法 | |
CN106930321B (zh) | 一种大直径顶管结合洞桩修建地下结构的施工方法 | |
CN104264688A (zh) | 人工挖孔变截面桩支护施工工艺 | |
CN107142926B (zh) | 浅水河床厚漂石覆盖层上的钢栈桥钢管桩抗冲刷施工方法 | |
CN214530750U (zh) | 一种适用于岩质陡坡的桥梁桩基结构 | |
CN103321234B (zh) | 建于高边坡或地质复杂区域上的承重结构的施工方法 | |
CN102817372A (zh) | 地下深基础混凝土反模施工方法 | |
CN104532868A (zh) | 高陡变形斜坡区桥梁锚拉式高承台群桩基础修建方法 | |
CN109853399A (zh) | 用于拱桥的大截面倾斜隧道式拱座结构及其施工方法 | |
CN110821500B (zh) | 穿越土石分界地层的大断面隧道开挖及支护施工方法 | |
CN103485347A (zh) | 一种建筑基坑支护用斜桩及其施工方法 | |
KR101746654B1 (ko) | 광산 대규모 채굴공동 보강을 위한 골재 그라우트 기둥 시공 방법 | |
CN110700860A (zh) | 一种穿越黄土沟谷的土石分界隧道施工方法 | |
CN203729309U (zh) | 组合双排桩联合竖向预应力锚杆支护体系 | |
CN204000848U (zh) | 一种用于水下施工的嵌岩桩 | |
CN102966109A (zh) | 软土地基带状深基坑封底施工方法 | |
CN210195766U (zh) | 一种拱盖暗挖顺筑地下结构 | |
CN201406687Y (zh) | 深基坑支护结构 | |
CN113847062B (zh) | 一种小直径顶管结合双层六洞桩的地铁车站施工方法 | |
CN210507517U (zh) | 一种适用于挡土墙加高的组合构件 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |