CN104060635A - 封闭的地下结构抗浮力施工方法 - Google Patents

封闭的地下结构抗浮力施工方法 Download PDF

Info

Publication number
CN104060635A
CN104060635A CN201310089964.3A CN201310089964A CN104060635A CN 104060635 A CN104060635 A CN 104060635A CN 201310089964 A CN201310089964 A CN 201310089964A CN 104060635 A CN104060635 A CN 104060635A
Authority
CN
China
Prior art keywords
floating
pipe well
well
underground
underground water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310089964.3A
Other languages
English (en)
Other versions
CN104060635B (zh
Inventor
杨前
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201310089964.3A priority Critical patent/CN104060635B/zh
Publication of CN104060635A publication Critical patent/CN104060635A/zh
Application granted granted Critical
Publication of CN104060635B publication Critical patent/CN104060635B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明涉及地下结构施工。一种封闭的地下结构抗浮力施工方法,它包括:步骤一,在结构封底混凝土施工前在结构底部当中设置抗浮管井,管井上口安装蝶阀;步骤二,设置抗浮管井后浇筑封底混凝土,在封底混凝土上部进行内部构筑物钢筋帮扎及其他工序时,如外围降水管井出现问题,就开启所述抗浮管井的蝶阀,将进入抗浮管井的地下水引入已施工好的舱体结构内,使其重量与浮力平衡,当降水井恢复运转后,随着地下水位的降低,结构内的地下水会通过抗浮管井流出,结构内部地下水流出后,关闭抗浮管井蝶阀;步骤三,继续结构内构筑物的施工,浇筑内部构筑物混凝土。本发明使结构内部构筑物砼浇筑后,结构重量与地下水浮托力平衡,可使结构处于稳定状态。

Description

封闭的地下结构抗浮力施工方法
技术领域
本发明涉及地下结构施工,尤其涉及一种封闭的地下结构施工方法。
背景技术
在地下水丰富区域进行各种形状的舱体或盒状的地下结构施工时,当地下结构外围封闭后,封闭的结构就会形成一个象船一样可以漂浮的完整结构体,在结构体内部的其它构筑物未施工之前,因为结构体的总体重量小于地下水的浮托力,就会出现上浮现象,尤其是在超深基坑结构施工及沉井结构封底阶段这种可能性的出现几率就会越大,一般超深基坑或深度较大的沉井施工会在外围设置降水管井,将地下水位降至安全高度,但如果降水井供电或其他方面出现问题导致降水井停止一段时间,随着地下水位的快速回升,施工好的地下结构就会出现上浮现象,一旦施工好的地下结构出现上浮,恢复的可能性极小,会使前面已经完成的基坑地下结构工程前功尽弃。
发明内容
本发明旨在克服现有技术的缺陷,提供一种封闭的地下结构抗浮力施工方法。本发明使结构内部构筑物砼浇筑后,结构重量与地下水浮托力平衡,可使结构处于稳定状态。
为了解决上述技术问题,本发明一种封闭的地下结构抗浮力施工方法,它包括:
步骤一,在结构封底混凝土施工前在结构底部当中设置抗浮管井,抗浮管井的直径与数量根据土层渗透系数及地下水位高度确定,管井上口安装蝶阀;
步骤二,设置抗浮管井后浇筑封底混凝土,在封底混凝土上部进行内部构筑物钢筋帮扎及其他工序时,如果外围降水管井出现问题,就立即开启位于基坑内底部抗浮管井的蝶阀,将进入抗浮管井的地下水引入已施工好的舱体结构内,使其重量与浮力平衡,当降水井恢复运转后,随着地下水位的降低,结构内的地下水会通过抗浮管井流出,结构内部地下水流出后,关闭抗浮管井蝶阀;
步骤三,继续结构内构筑物的施工,浇筑内部构筑物混凝土。
所述的封闭的地下结构抗浮力施工方法,所述步骤一的蝶阀开启装置向上设置。
所述的封闭的地下结构抗浮力施工方法,所述抗浮管井下部连接过滤管。
本发明在封底混凝土上部进行内部构筑物钢筋帮扎及其他工序时,如果外围降水管井出现问题,就立即开启位于基坑内底部抗浮管井的蝶阀,将进入抗浮管井的地下水引入已施工好的舱体结构内,使其重量与浮力平衡,当降水井恢复运转后,随着地下水位的降低,结构内的地下水会通过抗浮管井流出,结构内部地下水流出后,关闭抗浮管井蝶阀,继续结构内构筑物的施工,待浇筑内部构筑物混凝土后,由于地下结构重量的增加,就会同地下水产生的浮托力相平衡,使超深基坑的结构稳定。
本发明的抗浮管井的结构形式按照降水管井进行制作,在制作降水管井时可同时进行;降水与土方开挖期间安装抗浮管井,操作简单,容易控制;蝶阀的控制开关方向向上,易于开启,绑扎钢筋后可将开启装置加长,可随时对蝶阀进行开关操作。
具体实施方式
下面,结合具体实施方式对本发明作进一步的说明:
本发明一种封闭的地下结构抗浮力施工方法,它包括:
步骤一,在结构封底混凝土施工前在结构底部当中设置抗浮管井,抗浮管井的直径与数量根据土层渗透系数及地下水位高度确定,管井上口安装蝶阀;
步骤二,设置抗浮管井后浇筑封底混凝土,在封底混凝土上部进行内部构筑物钢筋帮扎及其他工序时,如果外围降水管井出现问题,就立即开启位于基坑内底部抗浮管井的蝶阀,将进入抗浮管井的地下水引入已施工好的舱体结构内,使其重量与浮力平衡,当降水井恢复运转后,随着地下水位的降低,结构内的地下水会通过抗浮管井流出,结构内部地下水流出后,关闭抗浮管井蝶阀;
步骤三,继续结构内构筑物的施工,浇筑内部构筑物混凝土。
所述的封闭的地下结构抗浮力施工方法,所述步骤一的蝶阀开启装置向上设置。
所述的封闭的地下结构抗浮力施工方法,所述抗浮管井下部连接过滤管。

Claims (3)

1.一种封闭的地下结构抗浮力施工方法,其特征在于,它包括:
步骤一,在结构封底混凝土施工前在结构底部当中设置抗浮管井,抗浮管井的直径与数量根据土层渗透系数及地下水位高度确定,管井上口安装蝶阀;
步骤二,设置抗浮管井后浇筑封底混凝土,在封底混凝土上部进行内部构筑物钢筋帮扎及其他工序时,如果外围降水管井出现问题,就立即开启位于基坑内底部抗浮管井的蝶阀,将进入抗浮管井的地下水引入已施工好的舱体结构内,使其重量与浮力平衡,当降水井恢复运转后,随着地下水位的降低,结构内的地下水会通过抗浮管井流出,结构内部地下水流出后,关闭抗浮管井蝶阀;
步骤三,继续结构内构筑物的施工,浇筑内部构筑物混凝土。
2.根据权利要求1所述的封闭的地下结构抗浮力施工方法,其特征在于,所述步骤一的蝶阀开启装置向上设置。
3.根据权利要求1所述的封闭的地下结构抗浮力施工方法,其特征在于,所述抗浮管井下部连接过滤管。
CN201310089964.3A 2013-03-20 2013-03-20 封闭的地下结构抗浮力施工方法 Active CN104060635B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310089964.3A CN104060635B (zh) 2013-03-20 2013-03-20 封闭的地下结构抗浮力施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310089964.3A CN104060635B (zh) 2013-03-20 2013-03-20 封闭的地下结构抗浮力施工方法

Publications (2)

Publication Number Publication Date
CN104060635A true CN104060635A (zh) 2014-09-24
CN104060635B CN104060635B (zh) 2016-08-10

Family

ID=51548549

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310089964.3A Active CN104060635B (zh) 2013-03-20 2013-03-20 封闭的地下结构抗浮力施工方法

Country Status (1)

Country Link
CN (1) CN104060635B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013265A (zh) * 2016-07-15 2016-10-12 宁波建工工程集团有限公司 地下室应急抗浮结构及其施工方法
CN109797760A (zh) * 2017-11-17 2019-05-24 李文 深基坑降水浮力平衡作业法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19521986A1 (de) * 1995-06-16 1996-12-19 Wiemer & Trachte Ag Verfahren zur Herstellung einer trockenen, unter dem Grundwasserspiegel liegenden Baugruben-Sohle für ein Tiefbauwerk
KR20060114664A (ko) * 2006-09-04 2006-11-07 홍종인 지하수 배수장치
CN101096852A (zh) * 2007-06-11 2008-01-02 袁奕 一种地下建筑物抗浮的方法
CN101851935A (zh) * 2010-06-02 2010-10-06 中国市政工程西北设计研究院有限公司 压差式自动安全抗浮装置
CN201762733U (zh) * 2010-08-26 2011-03-16 中国京冶工程技术有限公司 一种建筑基底可控减压排水抗浮结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19521986A1 (de) * 1995-06-16 1996-12-19 Wiemer & Trachte Ag Verfahren zur Herstellung einer trockenen, unter dem Grundwasserspiegel liegenden Baugruben-Sohle für ein Tiefbauwerk
KR20060114664A (ko) * 2006-09-04 2006-11-07 홍종인 지하수 배수장치
CN101139841A (zh) * 2006-09-04 2008-03-12 洪钟堙 地下水排水装置
CN101096852A (zh) * 2007-06-11 2008-01-02 袁奕 一种地下建筑物抗浮的方法
CN101851935A (zh) * 2010-06-02 2010-10-06 中国市政工程西北设计研究院有限公司 压差式自动安全抗浮装置
CN201762733U (zh) * 2010-08-26 2011-03-16 中国京冶工程技术有限公司 一种建筑基底可控减压排水抗浮结构

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013265A (zh) * 2016-07-15 2016-10-12 宁波建工工程集团有限公司 地下室应急抗浮结构及其施工方法
CN109797760A (zh) * 2017-11-17 2019-05-24 李文 深基坑降水浮力平衡作业法

Also Published As

Publication number Publication date
CN104060635B (zh) 2016-08-10

Similar Documents

Publication Publication Date Title
CN202401429U (zh) 自动启闭防洪闸门
CN105625483B (zh) 一种地下工程用水压控制方法
CN103590415A (zh) 适于跨海桥梁大直径管柱基础的预制承台及其施工方法
WO2013075407A1 (zh) 一种箱体衬砌式泥石流排导槽及其应用和施工方法
CN207268004U (zh) 卫生间防漏系统
CN106836313B (zh) 一种地下室水浮力泄压自动保护装置
CN104060635A (zh) 封闭的地下结构抗浮力施工方法
CN107642100B (zh) 用于最终接头接合腔排水的装置和方法
CN100557173C (zh) 大容量地下储油库
CN105649096A (zh) 基坑降水备用兼观测井
CN104831682B (zh) 一种增大城市河道蓄水量的蓄洪防涝装置
CN202450504U (zh) 新型高坝船闸
CN101967447A (zh) 沼气池
CN206956916U (zh) 一种超大筒体的地埋式一体化预制雨水泵站
CN110056069A (zh) 一种高压防洪下水道排水系统
CN205171386U (zh) 一种适用于桥梁架设的水中临时墩
CN204715287U (zh) 一种适用于城市中小型河道的调蓄装置
CN208395840U (zh) 一种地下室集水井预防性泄水装置
CN210345509U (zh) 带有自动加水阀的煤气站烟道水封
CN205387711U (zh) 基坑降水备用兼观测井
CN101538865B (zh) 张力腿平台附带抗压储水舱的整体式基础及其沉贯方法
CN202202358U (zh) 一种设在湿陷性黄土上的水池结构
CN205077463U (zh) 用于发电厂的山体引水隧道结构
CN103437380B (zh) 防水池漂浮泄压装置和方法
CN205935169U (zh) 溢流装置及蓄水池

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant