CN104047421A - 成品组装式塑料组合周转模板施工方法 - Google Patents
成品组装式塑料组合周转模板施工方法 Download PDFInfo
- Publication number
- CN104047421A CN104047421A CN201410228756.1A CN201410228756A CN104047421A CN 104047421 A CN104047421 A CN 104047421A CN 201410228756 A CN201410228756 A CN 201410228756A CN 104047421 A CN104047421 A CN 104047421A
- Authority
- CN
- China
- Prior art keywords
- finished product
- assembly type
- product assembly
- type plastics
- template
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明公开了成品组装式塑料组合周转模板施工方法,其具体技术方案为:确定成品组装式塑料组合周转模板的长宽尺寸比例及组配模数,采用工厂车间批量生产模板;模板的质量监测;模板按照规格尺寸分别码放;模板的安装;模板的拆除。本发明所提出的成品组装式塑料组合周转模板施工方法,降低了工程施工模板措施成本的投入,降低了作业人员的劳动强度,提高了作业效率、提高质量、减少周转材料消耗和摊销、减少了作业人员的投入,增加了工程利润效益。
Description
技术领域
本发明属于土建施工技术领域,具体的是成品组装式塑料组合周转模板的施工方法。
背景技术
目前国家提倡节能、环保、低碳的建筑施工要求,传统建筑模板施工,结构工序施工技术繁琐,需要大量的人力、物力、财力,施工效率不高,过程中产生大量废旧模板,造成大量资源的浪费,对工程的质量也不能提高和有效控制。
发明内容
本发明所要解决的技术问题是提供成品组装式塑料组合周转模板施工方法,降低了工程施工模板措施成本的投入,降低了作业人员的劳动强度,提高了作业效率、提高质量、减少周转材料消耗和摊销、减少了作业人员的投入,增加了工程利润效益。
为实现上述目的,本发明成品组装式塑料组合周转模板施工方法,其具体技术方案为:
一、测量现场建筑实物,再结合一般建筑图纸中梁、板、柱、剪力墙的通常尺寸,确定成品组装式塑料组合周转模板的长宽尺寸比例及组配模数,采用工厂车间批量生产模板;
二、出厂前成品组装式塑料组合周转模板的质量监测:保证模板无裂缝、无缺损;凡不符合质量要求的不得使用;根据组装图纸核对规格型号以及标号编码,按照组装的先后顺序对每块成品组装式塑料组合周转模板编制出场序号;
三、成品组装式塑料组合周转模板根据不同板号按照规格尺寸应分别码放,上下对齐、对正、垫平、垫实,不允许不同板号重叠堆放,以方便组装需要;
四、根据建筑实体混凝土结构的几何尺寸,选择相应的成品组装式塑料组合周转模板,在复核标高及轴线无误后,先搭设成品组装式塑料组合周转模板的支撑系统,再铺设安装成品组装式塑料组合周转模板,所述的支撑系统包括可调钢支撑架、三脚架和支撑方木,支撑方木上部顶住成品组装式塑料组合周转模板,下部设置在可调钢支撑架上,可调钢支撑架与三脚架间可活动连接,铺设模板时,相邻两块模板间采用专用螺栓链接固定,并与支撑木方及支撑杆着力服帖,支撑木方未起到作用的,应立即调节可调钢支撑架,使成品组装式塑料组合周转模板贴紧直接传给支撑木方和可调钢支撑架;
五、成品组装式塑料组合周转模板的拆除,待上一楼层顶板混凝土浇筑完毕,且混凝土的强度应达到混凝土设计强度的75%以上,跨度大于8m或悬挑结构的,支撑应在混凝土达到设计强度的100%后方可除,支撑系统根部的三角支架是组合可分离部件,楼板混凝土浇注完毕后,即可先行拆除三角支架,待混凝土强度要求满足后,依据拆模的原则,先支后拆,后支先拆,调节螺旋丝扣,使支撑系统脱离方木,拆除成品组装式塑料组合周转模板。
所述的支撑系统竖向连续支撑层数不少于2层且上下层支撑应在同一直线上,边支撑距离墙、柱、梁边的净距不大于0.5米,上层铺设若干80×180mm的方木承托成品组装式塑料组合周转模板,每层支撑方木间距不大于1.5米。
成品组装式塑料组合周转模板铺设完毕后,在其表面粘贴一层保护膜,保护膜有两种作用,一是防止浇筑的混凝土漏浆。二是粘贴在成品组装 式塑料组合周转模板上,防止成品组装式塑料组合周转模板与混凝土结构粘接过牢,支撑系统拆除时,难以拆除,或强行拆除时损坏成品组装式塑料组合周转模板,降低其周转使用寿命。
本发明所提出的成品组装式塑料组合周转模板施工方法,降低了工程施工模板措施成本的投入,降低了作业人员的劳动强度,提高了作业效率、提高质量、减少周转材料消耗和摊销、减少了作业人员的投入,增加了工程利润效益。
附图说明
图1是本发明所提出的成品组装式塑料组合周转模板施工结构示意图。
图2是图1的左视图(去掉混凝土和模板后的支撑系统的左视图)。
具体实施方式
参见附图,成品组装式塑料组合周转模板施工方法,其具体技术方案为:
一、测量现场建筑实物,再结合一般建筑图纸中梁、板、柱、剪力墙的通常尺寸,确定成品组装式塑料组合周转模板2的长宽尺寸比例及组配模数,采用工厂车间批量生产模板;
二、出厂前成品组装式塑料组合周转模板的质量监测:保证模板无裂缝、无缺损;凡不符合质量要求的不得使用;根据组装图纸核对规格型号以及标号编码,按照组装的先后顺序对每块成品组装式塑料组合周转模板编制出场序号;
三、成品组装式塑料组合周转模板根据不同板号按照规格尺寸应分别码放,上下对齐、对正、垫平、垫实,不允许不同板号重叠堆放,以方便组装需要;
四、根据建筑实体混凝土结构的几何尺寸,选择相应的成品组装式塑料组合周转模板,在复核标高及轴线无误后,先搭设成品组装式塑料组合周转模板的支撑系统,再铺设安装成品组装式塑料组合周转模板,所述 的支撑系统包括可调钢支撑架4、三脚架5和支撑方木3,支撑方木上部顶住成品组装式塑料组合周转模板,下部设置在可调钢支撑架上,可调钢支撑架与三脚架间可活动连接,铺设模板时,相邻两块模板间采用专用螺栓6链接固定,并与支撑木方及支撑杆着力服帖,支撑木方未起到作用的,应立即调节可调钢支撑架,使成品组装式塑料组合周转模板贴紧直接传给支撑木方和可调钢支撑架;
五、成品组装式塑料组合周转模板的拆除,待上一楼层顶板混凝土1浇筑完毕,且混凝土的强度应达到混凝土设计强度的75%以上,跨度大于8m或悬挑结构的,支撑应在混凝土达到设计强度的100%后方可除,支撑系统根部的三角支架是组合可分离部件,楼板混凝土浇注完毕后,即可先行拆除三角支架,待混凝土强度要求满足后,依据拆模的原则,先支后拆,后支先拆,调节螺旋丝扣,使支撑系统脱离方木,拆除成品组装式塑料组合周转模板。
所述的支撑系统竖向连续支撑层数不少于2层且上下层支撑应在同一直线上,边支撑距离墙、柱、梁边的净距不大于0.5米,上层铺设若干80×180mm的方木承托成品组装式塑料组合周转模板,每层支撑方木间距不大于1.5米。
成品组装式塑料组合周转模板铺设完毕后,在其表面粘贴一层保护膜,保护膜有两种作用,一是防止浇筑的混凝土漏浆。二是粘贴在成品组装式塑料组合周转模板上,防止成品组装式塑料组合周转模板与混凝土结构粘接过牢,支撑系统拆除时,难以拆除,或强行拆除时损坏成品组装式塑料组合周转模板,降低其周转使用寿命。
本发明所提出的成品组装式塑料组合周转模板施工方法,降低了工程施工模板措施成本的投入,降低了作业人员的劳动强度,提高了作业效率、提高质量、减少周转材料消耗和摊销、减少了作业人员的投入,增加了工程利润效益。
Claims (3)
1.成品组装式塑料组合周转模板施工方法,其具体技术方案为:
一、测量现场建筑实物,再结合一般建筑图纸中梁、板、柱、剪力墙的通常尺寸,确定成品组装式塑料组合周转模板的长宽尺寸比例及组配模数,采用工厂车间批量生产模板;
二、出厂前成品组装式塑料组合周转模板的质量监测:保证模板无裂缝、无缺损;凡不符合质量要求的不得使用;根据组装图纸核对规格型号以及标号编码,按照组装的先后顺序对每块成品组装式塑料组合周转模板编制出场序号;
三、成品组装式塑料组合周转模板根据不同板号按照规格尺寸分别码放,上下对齐、对正、垫平、垫实,不允许不同板号重叠堆放,以方便组装需要;
四、根据建筑实体混凝土结构的几何尺寸,选择相应的成品组装式塑料组合周转模板,在复核标高及轴线无误后,先搭设成品组装式塑料组合周转模板的支撑系统,再铺设安装成品组装式塑料组合周转模板,所述的支撑系统包括可调钢支撑架、三脚架和支撑方木,支撑方木上部顶住成品组装式塑料组合周转模板,下部设置在可调钢支撑架上,可调钢支撑架与三脚架间可活动连接,铺设模板时,相邻两块模板间采用专用螺栓链接固定,并与支撑木方及支撑杆着力服帖,支撑木方未起到作用的,应立即调节可调钢支撑架,使成品组装式塑料组合周转模板贴紧直接传给支撑木方和可调钢支撑架;
五、成品组装式塑料组合周转模板的拆除,待上一楼层顶板混凝土浇筑完毕,且混凝土的强度应达到混凝土设计强度的75%以上,跨度大于8m或悬挑结构的,支撑应在混凝土达到设计强度的100%后方可除,支撑系统根部的三角支架是组合可分离部件,楼板混凝土浇注完毕后,即可先行拆除三角支架,待混凝土强度要求满足后,依据拆模的原则,先支后拆,后支先拆,调节螺旋丝扣,使支撑系统脱离方木,拆除成品组装式塑料组合周转模板。
2.根据权利要求1所述的成品组装式塑料组合周转模板施工方法,其特征在于所述的支撑系统竖向连续支撑层数不少于2层且上下层支撑应在同一直线上,边支撑距离墙、柱、梁边的净距不大于0.5米,上层铺设若干80×180mm的方木承托成品组装式塑料组合周转模板,每层支撑方木间距不大于1.5米。
3.根据权利要求1所述的成品组装式塑料组合周转模板施工方法,其特征在于成品组装式塑料组合周转模板铺设完毕后,在其表面粘贴一层保护膜。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410228756.1A CN104047421B (zh) | 2014-05-27 | 2014-05-27 | 成品组装式塑料组合周转模板施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410228756.1A CN104047421B (zh) | 2014-05-27 | 2014-05-27 | 成品组装式塑料组合周转模板施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104047421A true CN104047421A (zh) | 2014-09-17 |
CN104047421B CN104047421B (zh) | 2016-03-23 |
Family
ID=51500787
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410228756.1A Active CN104047421B (zh) | 2014-05-27 | 2014-05-27 | 成品组装式塑料组合周转模板施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104047421B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106703399A (zh) * | 2016-12-14 | 2017-05-24 | 山东电力建设第工程公司 | 可重复使用的高平整度混凝土模板及施工方法 |
CN113756565A (zh) * | 2021-09-28 | 2021-12-07 | 北京怡泰盛达技术发展有限责任公司 | 一种建筑专用模板安装与拆卸体系 |
CN113775171A (zh) * | 2021-09-28 | 2021-12-10 | 北京怡泰盛达技术发展有限责任公司 | 一种建筑专用模板循环使用方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1991109A (zh) * | 2005-12-30 | 2007-07-04 | 上海宝冶建设有限公司 | 组合胶合板模板的工艺方法 |
KR20110004777A (ko) * | 2009-07-08 | 2011-01-14 | 해밀턴 선드스트랜드 코포레이션 | 권선 계자 발전기용 겹쳐진 여자기 및 주 발전기 스테이지 |
CN202194379U (zh) * | 2011-07-16 | 2012-04-18 | 中国十七冶集团有限公司 | 楼层模板钢管支撑立杆用垫块 |
CN203320944U (zh) * | 2013-06-19 | 2013-12-04 | 泰兴市第一建筑安装工程有限公司 | 组合整体木模板 |
-
2014
- 2014-05-27 CN CN201410228756.1A patent/CN104047421B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1991109A (zh) * | 2005-12-30 | 2007-07-04 | 上海宝冶建设有限公司 | 组合胶合板模板的工艺方法 |
KR20110004777A (ko) * | 2009-07-08 | 2011-01-14 | 해밀턴 선드스트랜드 코포레이션 | 권선 계자 발전기용 겹쳐진 여자기 및 주 발전기 스테이지 |
CN202194379U (zh) * | 2011-07-16 | 2012-04-18 | 中国十七冶集团有限公司 | 楼层模板钢管支撑立杆用垫块 |
CN203320944U (zh) * | 2013-06-19 | 2013-12-04 | 泰兴市第一建筑安装工程有限公司 | 组合整体木模板 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106703399A (zh) * | 2016-12-14 | 2017-05-24 | 山东电力建设第工程公司 | 可重复使用的高平整度混凝土模板及施工方法 |
CN113756565A (zh) * | 2021-09-28 | 2021-12-07 | 北京怡泰盛达技术发展有限责任公司 | 一种建筑专用模板安装与拆卸体系 |
CN113775171A (zh) * | 2021-09-28 | 2021-12-10 | 北京怡泰盛达技术发展有限责任公司 | 一种建筑专用模板循环使用方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104047421B (zh) | 2016-03-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202706536U (zh) | 适用于后浇带或施工缝的侧支模 | |
CN104047421B (zh) | 成品组装式塑料组合周转模板施工方法 | |
CN106285001B (zh) | 一种小面积分段快速交叉流水施工方法 | |
CN109252879A (zh) | 一种公路隧道排水沟内衬工具式模板及施工方法 | |
CN106088579B (zh) | 钢筋混凝土墙体模板的搭设方法 | |
CN113152893A (zh) | 一种建筑施工用模板及使用方法 | |
CN102912977A (zh) | 一种用于浇筑定型楼梯的模具 | |
CN104074354A (zh) | 一种插板式现浇楼梯模板及其使用方法 | |
CN202108006U (zh) | 易拆除防护墙断缝模板 | |
CN207999071U (zh) | 一种墙柱根部混凝土封堵工具 | |
CN104453235B (zh) | 换流站防火墙施工工艺 | |
CN106522544A (zh) | 一种模板的防烂根补偿装置 | |
CN104131635B (zh) | 一种预制楼梯间周边剪力墙施工方法及施工平台 | |
CN204875544U (zh) | 一种t型梁翼板钢筋胎膜 | |
CN103883119A (zh) | 早拆体系使用的建筑模板安装方法 | |
CN216042665U (zh) | 一种建筑施工用模板 | |
CN205476468U (zh) | 一种非定型、可周转模板体系预制楼梯梯段模板 | |
CN208396295U (zh) | 一种明挖车站施工用楼梯支模结构 | |
CN212428077U (zh) | 楼梯踏步模板施工结构 | |
CN205035732U (zh) | 复合式桥梁临时支座 | |
CN209163831U (zh) | 一种公路隧道排水沟内衬工具式模板 | |
CN204040457U (zh) | 木框塑料模板体系 | |
CN104032892B (zh) | 一种再生混凝土分段梁及其施工方法 | |
CN204081482U (zh) | V型圆柱交叉段混凝土浇筑模具 | |
CN205822778U (zh) | 一种劲性巨柱无螺杆式铝合金模板体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |