CN104037707B - 海上风电导管架基础处海缆敷设保护装置及安装方法 - Google Patents
海上风电导管架基础处海缆敷设保护装置及安装方法 Download PDFInfo
- Publication number
- CN104037707B CN104037707B CN201410245543.XA CN201410245543A CN104037707B CN 104037707 B CN104037707 B CN 104037707B CN 201410245543 A CN201410245543 A CN 201410245543A CN 104037707 B CN104037707 B CN 104037707B
- Authority
- CN
- China
- Prior art keywords
- sleeve pipe
- protection sleeve
- extra large
- large cable
- protection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 16
- 238000009434 installation Methods 0.000 title claims abstract description 15
- 238000010276 construction Methods 0.000 claims abstract description 6
- 230000001681 protective effect Effects 0.000 claims description 6
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 239000000725 suspension Substances 0.000 claims description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 3
- 239000007787 solid Substances 0.000 claims description 2
- 239000003653 coastal water Substances 0.000 abstract description 5
- 230000005684 electric field Effects 0.000 abstract description 3
- 238000005452 bending Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 1
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
- Wind Motors (AREA)
Abstract
本发明公开了一种海上风电导管架基础处海缆敷设保护装置及安装方法,包括第一保护套管、第二保护套管和第三保护套管;所述第三保护套管套装在海缆的一端;所述第二保护套管由多个通过螺栓紧固在一起的小组件组装而成;所述第一保护套管和第二保护套管均固定在风电机组导管架基础上;所述海缆的另一端从第二保套管的底端依次穿过第二保护套管和第一保护套管接入海上风电机组内的塔底变压器。本发明解决了近海、潮间带海上风电场风机导管架基础海缆敷设的问题,缩短了施工工期,简化了施工工序,大大降低了施工成本,优化了海缆敷设工艺。
Description
技术领域
本发明涉及海洋工程领域,尤其涉及近海、潮间带海上风电导管架基础处海缆敷设保护装置及安装方法。
背景技术
海上风电场风机导管架基础处海缆一般通过J型管装置保护海缆,海缆终端敷设作业困难,费用高,危险性大,敷设时间长。因此,需要针对海缆敷设的上述特性,专门开发海缆保护装置及方法。
发明内容
本发明的目的是提供一种近海、潮间带海上风电导管架基础处海缆敷设保护装置及安装方法,以解决近海、潮间带海域风电机组海缆敷设的问题。
为实现上述目的,本发明提供如下技术方案:
海上风电导管架基础处海缆敷设保护装置,包括第一保护套管、第二保护套管和第三保护套管;所述第三保护套管套装在海缆的一端;所述第二保护套管由多个通过螺栓紧固在一起的小组件组装而成;所述第一保护套管和第二保护套管均固定在风电机组导管架基础上;所述海缆的另一端从第二保套管的底端依次穿过第二保护套管和第一保护套管接入海上风电机组内的塔底变压器,海上风电导管架基础处海缆敷设保护装置的安装方法,包括以下步骤:
(1)将第一保护套管和第二保护套管固定在风电机组导管架基础上;
(2)在岸上预先将第三保护套管套装至待敷设的海缆上,并在海缆终端预留出大于第一保护套管和第二保护套管总长的未保护段;
(3)第三保护套管安装完成后,通过施工船到码头装有电缆,利用缆绳牵引施工船到风电机组终端附近,将装置在施工船上的导扭架放入水中;
(4)启动装在施工船上的吊装装置,将悬挂在吊钩上的牵引钢丝绳从第一保护套管的上端引下,从第二保护套管的末端引出,并将引出第二保护套管的钢丝绳装上钢丝网套与海缆终端处连接;
(5)完成连接固定后吊机启动吊缆,最终将海缆引至海上风电机组内部并接入塔底变压器。
作为本发明的进一步方案,所述小组件的长度为248~380mm,对海缆的弯曲半径进行限制,确保海缆实际弯曲半径大于其允许的最小弯曲半径。
作为本发明的进一步方案,所述第一保护套管和第二保护套管均由多个通过螺栓紧固在一起的小组件组装而成。
本发明与以往技术相比,具有以下优点:
本发明解决了近海、潮间带海上风电场风机导管架基础海缆敷设的问题,缩短了施工工期,简化了施工工序,大大降低了施工成本,优化了海缆敷设工艺。
说明书附图
图1为本发明安装示意图;
图2为本发明所述第二保护套管的结构示意图。
图中数字所代表的结构分别为:1-第一保护套管,2-第二保护套管,3-第三保护套管,4-固定连接装置,5-连接点,6-导扭架,7-施工船,8-吊钩,海缆,10-海平面,11-海床,12-小组件
具体实施方式
下面将结合本发明实施例,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
实施例
海上风电导管架基础处海缆敷设保护装置及安装方法,包括第一保护套管1、第二保护套管2和第三保护套管3;将第一保护套管1和第二保护套管2预先通过固定连接装置4固定在风电机组导管架基础上,在岸上先将第三保护套管3套装至待敷设的海缆9上,并在海缆终端预留出稍大于第一保护套管1和第二保护套管2总长的未保护段;第三保护套管3安装完成后,通过施工船7到码头将套有第三保护套管3的海缆9进行装运,利用缆绳牵引施工船7到风电机组终端附近,将装置在施工船7上的导扭架6放入水中,启动装在施工船7上的吊装装置,将悬挂在吊钩8上的牵引钢丝绳从第一保护套管1的上端引下,从第二保护套管2的末端引出,并将引出第二保护套管2的钢丝绳装上钢丝网套与海缆终端处连接;第一保护套管1和第二保护套管2替代现有技术中的J型管,第二保护套管2由多个通过螺栓紧固在一起的小组件12组装而成,小组件12的长度均在248~380mm范围内,可对海缆9的弯曲半径进行限制,确保海缆实际弯曲半径大于其允许的最小弯曲半径,如图2所示;完成连接固定后吊机启动吊缆,最终将海缆引至海上风电机组内部并接入塔底变压器。
对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其他的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。
此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。
Claims (3)
1.海上风电导管架基础处海缆敷设保护装置的安装方法,其特征是,包括第一保护套管、第二保护套管和第三保护套管;所述第三保护套管套装在海缆的一端;所述第二保护套管由多个通过螺栓紧固在一起的小组件组装而成;所述第一保护套管和第二保护套管均固定在风电机组导管架基础上;所述海缆的另一端从第二保套管的底端依次穿过第二保护套管和第一保护套管接入海上风电机组内的塔底变压器,海上风电导管架基础处海缆敷设保护装置的安装方法,包括以下步骤:
(1)将第一保护套管和第二保护套管固定在风电机组导管架基础上;
(2)在岸上预先将第三保护套管套装至待敷设的海缆上,并在海缆终端预留出大于第一保护套管和第二保护套管总长的未保护段;
(3)第三保护套管安装完成后,通过施工船到码头装有电缆,利用缆绳牵引施工船到风电机组终端附近,将装置在施工船上的导扭架放入水中;
(4)启动装在施工船上的吊装装置,将悬挂在吊钩上的牵引钢丝绳从第一保护套管的上端引下,从第二保护套管的末端引出,并将引出第二保护套管的钢丝绳装上钢丝网套与海缆终端处连接;
(5)完成连接固定后吊机启动吊缆,最终将海缆引至海上风电机组内部并接入塔底变压器。
2.根据权利要求1所述的海上风电导管架基础处海缆敷设保护装置的安装方法,其特征是,所述小组件的长度为248~380mm。
3.根据权利要求1所述的海上风电导管架基础处海缆敷设保护装置的安装方法,其特征是,所述第一保护套管和第二保护套管均由多个通过螺栓紧固在一起的小组件组装而成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410245543.XA CN104037707B (zh) | 2014-06-05 | 2014-06-05 | 海上风电导管架基础处海缆敷设保护装置及安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410245543.XA CN104037707B (zh) | 2014-06-05 | 2014-06-05 | 海上风电导管架基础处海缆敷设保护装置及安装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104037707A CN104037707A (zh) | 2014-09-10 |
CN104037707B true CN104037707B (zh) | 2017-10-10 |
Family
ID=51468373
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410245543.XA Active CN104037707B (zh) | 2014-06-05 | 2014-06-05 | 海上风电导管架基础处海缆敷设保护装置及安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104037707B (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106159846B (zh) * | 2016-07-12 | 2017-09-15 | 中交第三航务工程局有限公司 | 外海风机j型海缆保护管和iccp导线钢管的安装工艺 |
CN108488485B (zh) * | 2018-04-03 | 2020-01-03 | 航天晨光股份有限公司 | 一种舰船大管径输水软管悬挂装置及其安装方法 |
CN108808568A (zh) * | 2018-08-02 | 2018-11-13 | 江苏海上龙源风力发电有限公司 | 一种海上风机浮式基础输出动态海缆安装工艺 |
WO2022171257A1 (en) * | 2021-02-11 | 2022-08-18 | National Oilwell Varco Denmark I/S | A protection system for installing a flexible member |
CN114389226B (zh) * | 2022-01-14 | 2023-07-25 | 宁波东方电缆股份有限公司 | 基于导管架平台的附着式管缆系统及设计方法 |
CN117477446B (zh) * | 2023-11-16 | 2024-07-09 | 宁波东方电缆股份有限公司 | 一种海缆敷设的施工方法 |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA872007A (en) * | 1968-11-29 | 1971-06-01 | W. W. Pfeiffer Frank | Cable fairing improvements |
IT1186157B (it) * | 1985-12-20 | 1987-11-18 | Pirelli Cavi Spa | Dispositivo per limitare la curvatura di una porzione di cavo sottomarino |
JPH0576115A (ja) * | 1991-09-12 | 1993-03-26 | Nec Corp | 海底ケーブルの防護管取付工法 |
GB0709274D0 (en) * | 2007-05-15 | 2007-06-20 | Featherstone Jeremy J R | Devices for deploying underwater cables and methods of deployment thereof |
KR20100020469A (ko) * | 2007-06-11 | 2010-02-22 | 베스타스 윈드 시스템스 에이/에스 | 해상 시설물용 배관 구조물 |
CN102332695B (zh) * | 2011-08-31 | 2013-10-09 | 中国海洋石油总公司 | 登陆平台的海底电缆终端的提升方法 |
EP2597738A1 (en) * | 2011-11-22 | 2013-05-29 | Seven Eighty X Limited | Method for mounting electrical cable and cable protection apparatus to support |
EP2696123A1 (en) * | 2012-08-06 | 2014-02-12 | Siemens Aktiengesellschaft | Cable hang-off arrangement |
CN103762538B (zh) * | 2014-01-22 | 2016-08-24 | 钢铁研究总院青岛海洋腐蚀研究所 | 一种水下电缆抗弯曲护管及其使用方法 |
CN203911431U (zh) * | 2014-06-05 | 2014-10-29 | 龙源电力集团股份有限公司 | 海上风电导管架基础处海缆敷设保护装置 |
-
2014
- 2014-06-05 CN CN201410245543.XA patent/CN104037707B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN104037707A (zh) | 2014-09-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104037707B (zh) | 海上风电导管架基础处海缆敷设保护装置及安装方法 | |
KR101283790B1 (ko) | 풍력 발전 장치 및 그것에 사용되는 케이블 지지 구조 | |
ITTO20070666A1 (it) | Sistema di conversione di energia eolica offshore per acque profonde | |
CN206706811U (zh) | 一种海上风机单桩基础 | |
CN204538629U (zh) | 一种海上风机电缆保护系统 | |
CN103758705A (zh) | 一种双体浮式海上风力机系统 | |
CN205744309U (zh) | 风力发电机组的涡激振动防护装置及风力发电机组 | |
PH12018500779A1 (en) | A system and method for raising and lowering a component of a wind turbine | |
Schnepf et al. | Feasibility study on suspended inter-array power cables between two spar-type offshore wind turbines | |
Ahmad et al. | An optimisation methodology for suspended inter-array power cable configurations between two floating offshore wind turbines | |
CN203911431U (zh) | 海上风电导管架基础处海缆敷设保护装置 | |
CN107201991A (zh) | 一种新型海上风力机浮式平台 | |
WO2015071679A1 (en) | Cable installation and/or protection system | |
EP3384574B1 (en) | Bend limiting device for a cable connected to a floating marine installation or vessel | |
CN204809816U (zh) | 岩基海床减震玻璃钢保护管覆盖砼块褥垫的海缆保护装置 | |
NO20071361L (no) | Kraftkabel. | |
CN208684100U (zh) | 一种圆盘牵引机 | |
KR20200094575A (ko) | 풍력타워의 tp영역 내 해저케이블의 횡배열 정리방법 | |
CN205622148U (zh) | 一种动态复合电缆牵引保护头 | |
CN106159846B (zh) | 外海风机j型海缆保护管和iccp导线钢管的安装工艺 | |
CN205173726U (zh) | 一种钻井平台穿舱件的密封结构 | |
CN207596369U (zh) | 一种适用于海上运维的起吊装置 | |
CN206640281U (zh) | 一种海洋工程设备之间整束活动电缆连接的工装 | |
CN204138197U (zh) | 一种可移动式输缆装置 | |
CN107026422A (zh) | 一种海洋工程设备之间整束活动电缆连接的工装 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |