CN104037630A - 变电站门构架辅助放置安装系统 - Google Patents
变电站门构架辅助放置安装系统 Download PDFInfo
- Publication number
- CN104037630A CN104037630A CN201410262752.5A CN201410262752A CN104037630A CN 104037630 A CN104037630 A CN 104037630A CN 201410262752 A CN201410262752 A CN 201410262752A CN 104037630 A CN104037630 A CN 104037630A
- Authority
- CN
- China
- Prior art keywords
- door framework
- telescopic machine
- mounting panel
- framework
- ball
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了变电站门构架辅助放置安装系统,在支撑柱连接体上连接有工装支撑平台板,工装支撑平台板上安装有滚珠安装板,滚珠安装板上方设置有依次层叠的滚珠、伸缩机安装板、伸缩机,伸缩机的伸缩输出轴连接有U形门构架叉,门构架放置在U形门构架叉的凹槽内,滚珠安装板上面设置有锯齿条,伸缩机安装板侧面设置有齿轮,齿轮与直条式的锯齿条啮合,齿轮的移动路径与门构架轴线垂直。滚珠安装板、滚珠、锯齿条、齿轮、伸缩机安装板构成横向位移机构,实现门构架的横向位移,达到对准螺钉孔的目的。伸缩机作为上下位移装置,实现门构架的缓慢下落,实现低冲击放置操作。
Description
技术领域
本发明涉及电力设备中的变电站门构架辅助放置安装系统。
背景技术
在变电站中,门构架是作为主要输电线的支持结构,其体积庞大,架设位置高,现有门构架的架设方式是:采用吊装车将门构架吊装到门构架支撑柱上,一般存在2个V形的门构架支撑结构,门构架的两端分别放置在2个门构架支撑结构的顶端,在吊装时,需要对准螺钉孔,即门构架支撑结构的顶端的门构架平台板开设有螺钉孔,门构架的两端也设置有螺钉孔。2个螺钉孔要对准,现有技术吊装需要其他人员的检测,实时的报告方位给吊装车操作人员,同时需要人员爬到门构架支撑结构的顶端,手动推动门构架辅助对准螺钉孔,上述操作方式存在不安全的隐患,对辅助人员造成的维护比较大,若吊装车操作人员失误,则会使得门构架碰撞辅助人员,另外,需要远程的检测人员的实时报告方位,操作效率低下。
发明内容
本发明的目的在于提供一种变电站门构架辅助放置安装系统,可以提高安装效率,消除对辅助人员的安全隐患。
本发明的目的主要通过以下技术方案实现:变电站门构架辅助放置安装系统,包括2个门构架支撑柱,2个门构架支撑柱远离地面的一端同时连接有门构架平台板,2个门构架支撑柱之间设置有支撑柱连接体,在支撑柱连接体上连接有工装支撑平台板,工装支撑平台板上安装有滚珠安装板,滚珠安装板上方设置有依次层叠的滚珠、伸缩机安装板、伸缩机,伸缩机的伸缩输出轴连接有U形门构架叉,门构架放置在U形门构架叉的凹槽内,滚珠安装板上面设置有锯齿条,伸缩机安装板侧面设置有齿轮,齿轮与直条式的锯齿条啮合,齿轮的移动路径与门构架轴线垂直。
上述结构的作用原理为:施工时,2个门构架支撑柱组成门构架支撑结构,门构架支撑结构的顶端设置有门构架平台板,2个门构架支撑结构组成支撑系统,我们的目的是要将门构架放置到2个门构架支撑结构的顶端上,此时,我们先采用工装支撑平台板安装到支撑柱连接体上,构成支撑平台,辅助操作人员位于该支撑平台上进行辅助操作,然后将滚珠安装板、锯齿条、齿轮、伸缩机安装板、滚珠、U形门构架叉、伸缩机构成的上述工装放置到工装支撑平台板上,组装完成后,采用吊车将门构架吊装到U形门构架叉正上方,然后缓慢下降门构架,使得门构架落到U形门构架叉的凹槽内,此时吊装车不在作用,仅仅使用钢丝与门构架连接,防止意外发生,此时门构架的重力全部压在U形门构架叉下方的工装上,然后驱动齿轮,使得齿轮沿齿轮条移动,即伸缩机安装板横向移动,此时整个门构架做横向平移,使得门构架上的螺钉孔与门构架平台板上的螺钉孔对准后,停止驱动齿轮,然后驱动伸缩机,伸缩机的伸缩输出轴回收,门构架缓慢下移,当门构架落到门构架平台板上后,完成辅助放置操作。最后卸载上述工装结构。
优选的,所述伸缩机为气动伸缩机或液压伸缩机。
优选的,齿轮圆心处连接有手柄。
优选的,伸缩机安装板面向滚珠安装板的一面和滚珠安装板面向伸缩机安装板的一面均设置有滚珠凹槽,滚珠位于滚珠凹槽内,滚珠凹槽的走向与齿轮的移动路径平行。
本发明的优点在于:结构简单,操作简单,安全性能高,操作效率高。
附图说明
图1为本装置操作施工完成后门构架的放置俯视示意图。
图2为现有门构架支撑结构的示意图。
图3为门构架放置到U形门构架叉后的侧视示意图。
图4为门构架放置到U形门构架叉后的正视示意图。
图5为伸缩机安装板设置滚珠凹槽的示意图。
图中的附图标记分别表示为:1、门构架平台板;2、门构架;3、门构架支撑柱;4、工装支撑平台板;5、U形门构架叉;6、伸缩输出轴;7、伸缩机;8、伸缩机安装板;9、滚珠;10、滚珠安装板;11、齿轮;12、锯齿条;81、滚珠凹槽;41、支撑柱连接体。
具体实施方式
下面结合实施例及附图对本发明作进一步的详细说明,但本发明的实施方式不限于此。
实施例1:
如图1-图5所示。
变电站门构架辅助放置安装系统,包括2个门构架支撑柱3,2个门构架支撑柱3远离地面的一端同时连接有门构架平台板1,2个门构架支撑柱3之间设置有支撑柱连接体41,在支撑柱连接体41上连接有工装支撑平台板4,工装支撑平台板4上安装有滚珠安装板10,滚珠安装板10上方设置有依次层叠的滚珠9、伸缩机安装板8、伸缩机7,伸缩机7的伸缩输出轴连接有U形门构架叉5,门构架2放置在U形门构架叉5的凹槽内,滚珠安装板10上面设置有锯齿条12,伸缩机安装板8侧面设置有齿轮11,齿轮11与直条式的锯齿条12啮合,齿轮11的移动路径与门构架轴线垂直。
本发明中,滚珠安装板10、滚珠、锯齿条12、齿轮11、伸缩机安装板8构成横向位移机构,实现门构架的横向位移,达到对准螺钉孔的目的。伸缩机7作为上下位移装置,实现门构架的缓慢下落,实现低冲击的放置操作。
上述结构的作用原理为:施工时,2个门构架支撑柱3组成门构架支撑结构,门构架支撑结构的顶端设置有门构架平台板1,2个门构架支撑结构组成支撑系统,我们的目的是要将门构架放置到2个门构架支撑结构的顶端上,此时,我们先采用工装支撑平台板4安装到支撑柱连接体41上,构成支撑平台,辅助操作人员位于该支撑平台上进行辅助操作,然后将滚珠安装板10、锯齿条12、齿轮11、伸缩机安装板8、滚珠、U形门构架叉5、伸缩机7构成的上述工装放置到工装支撑平台板4上,组装完成后,采用吊车将门构架吊装到U形门构架叉5正上方,然后缓慢下降门构架,使得门构架落到U形门构架叉5的凹槽内,此时吊装车不在作用,仅仅使用钢丝与门构架连接,防止意外发生,此时门构架的重力全部压在U形门构架叉5下方的工装上,然后驱动齿轮,使得齿轮沿齿轮条移动,即伸缩机安装板8横向移动,此时整个门构架做横向平移,使得门构架上的螺钉孔与门构架平台板1上的螺钉孔对准后,停止驱动齿轮,然后驱动伸缩机,伸缩机的伸缩输出轴回收,门构架缓慢下移,当门构架落到门构架平台板1上后,完成辅助放置操作。最后卸载上述工装结构。
优选的,所述伸缩机7为气动伸缩机或液压伸缩机。
优选的,齿轮11圆心处连接有手柄。
优选的,伸缩机安装板面向滚珠安装板的一面和滚珠安装板面向伸缩机安装板的一面均设置有滚珠凹槽81,滚珠位于滚珠凹槽81内,滚珠凹槽81的走向与齿轮11的移动路径平行。
如上所述,则能很好的实现本发明。
Claims (4)
1.变电站门构架辅助放置安装系统,包括2个门构架支撑柱(3),2个门构架支撑柱(3)远离地面的一端同时连接有门构架平台板(1),2个门构架支撑柱(3)之间设置有支撑柱连接体(41),其特征在于:在支撑柱连接体(41)上连接有工装支撑平台板(4),工装支撑平台板(4)上安装有滚珠安装板(10),滚珠安装板(10)上方设置有依次层叠的滚珠(9)、伸缩机安装板(8)、伸缩机(7),伸缩机(7)的伸缩输出轴连接有U形门构架叉(5),门构架(2)放置在U形门构架叉(5)的凹槽内,滚珠安装板(10)上面设置有锯齿条(12),伸缩机安装板(8)侧面设置有齿轮(11),齿轮(11)与直条式的锯齿条(12)啮合,齿轮(11)的移动路径与门构架轴线垂直。
2.根据权利要求1所述的变电站门构架辅助放置安装系统,其特征在于:所述伸缩机(7)为气动伸缩机或液压伸缩机。
3.根据权利要求1所述的变电站门构架辅助放置安装系统,其特征在于:齿轮(11)圆心处连接有手柄。
4.根据权利要求1所述的变电站门构架辅助放置安装系统,其特征在于:伸缩机安装板面向滚珠安装板的一面和滚珠安装板面向伸缩机安装板的一面均设置有滚珠凹槽(81),滚珠位于滚珠凹槽(81)内,滚珠凹槽(81)的走向与齿轮(11)的移动路径平行。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410262752.5A CN104037630B (zh) | 2014-06-13 | 2014-06-13 | 变电站门构架辅助放置安装系统 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410262752.5A CN104037630B (zh) | 2014-06-13 | 2014-06-13 | 变电站门构架辅助放置安装系统 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104037630A true CN104037630A (zh) | 2014-09-10 |
CN104037630B CN104037630B (zh) | 2016-02-03 |
Family
ID=51468302
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410262752.5A Active CN104037630B (zh) | 2014-06-13 | 2014-06-13 | 变电站门构架辅助放置安装系统 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104037630B (zh) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3448511A (en) * | 1966-04-01 | 1969-06-10 | Strabag Bau Ag | Arrangement and method for constructing multispan bridges or the like |
GB1186687A (en) * | 1966-04-25 | 1970-04-02 | Plasser Bahnbaumasch Franz | Apparatus for Dismantling Railway Track Consisting of Rails and Sleepers |
AT310641B (de) * | 1971-02-20 | 1973-10-10 | Hebel Gasbetonwerk Gmbh | Verfahren und Anlage zur Herstellung von Baukörpern aus Porenbeton |
CN202248941U (zh) * | 2011-09-07 | 2012-05-30 | 福建二建建设集团公司 | 大型钢构件的整体提升就位安装装置 |
CN202745397U (zh) * | 2012-08-24 | 2013-02-20 | 中国建筑第六工程局有限公司 | 一种用于大跨空间网架的顶升装置 |
CN103806923A (zh) * | 2014-03-07 | 2014-05-21 | 陕西理工学院 | 钢模台车的平移机构 |
CN203871720U (zh) * | 2014-06-13 | 2014-10-08 | 国网四川省电力公司双流县供电分公司 | 变电站门构架辅助放置安装系统 |
-
2014
- 2014-06-13 CN CN201410262752.5A patent/CN104037630B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3448511A (en) * | 1966-04-01 | 1969-06-10 | Strabag Bau Ag | Arrangement and method for constructing multispan bridges or the like |
GB1186687A (en) * | 1966-04-25 | 1970-04-02 | Plasser Bahnbaumasch Franz | Apparatus for Dismantling Railway Track Consisting of Rails and Sleepers |
AT310641B (de) * | 1971-02-20 | 1973-10-10 | Hebel Gasbetonwerk Gmbh | Verfahren und Anlage zur Herstellung von Baukörpern aus Porenbeton |
CN202248941U (zh) * | 2011-09-07 | 2012-05-30 | 福建二建建设集团公司 | 大型钢构件的整体提升就位安装装置 |
CN202745397U (zh) * | 2012-08-24 | 2013-02-20 | 中国建筑第六工程局有限公司 | 一种用于大跨空间网架的顶升装置 |
CN103806923A (zh) * | 2014-03-07 | 2014-05-21 | 陕西理工学院 | 钢模台车的平移机构 |
CN203871720U (zh) * | 2014-06-13 | 2014-10-08 | 国网四川省电力公司双流县供电分公司 | 变电站门构架辅助放置安装系统 |
Also Published As
Publication number | Publication date |
---|---|
CN104037630B (zh) | 2016-02-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201991276U (zh) | 多排车位搬运器带横移机构垂直升降车库 | |
CN105281174B (zh) | 架空高压设备接地杆辅助装拆系统 | |
CN104563528A (zh) | 预制装配式建筑预制墙板快速就位装置及方法 | |
CN206219069U (zh) | 一种配电柜搬运吊装装置 | |
CN209412699U (zh) | 一种组装式行走悬挂小车施工平台 | |
CN205443975U (zh) | 一种用于箱型涵洞、通道施工的滑动模板装置 | |
CN203871720U (zh) | 变电站门构架辅助放置安装系统 | |
CN202880793U (zh) | 移动式单柱型高空作业平台 | |
CN103171970B (zh) | 一种高空作业轨道安装系统及其安装方法 | |
CN201473253U (zh) | 移动式轻型液压吊车 | |
CN203159151U (zh) | 盖板提升工具 | |
CN104037630A (zh) | 变电站门构架辅助放置安装系统 | |
CN202753951U (zh) | 副斜井施工平台车 | |
CN207063484U (zh) | 用于连廊施工的移动式操作平台 | |
CN202508723U (zh) | 一种新型施工升降机 | |
CN203867199U (zh) | 变电站二级门构架辅助放置系统 | |
CN204754246U (zh) | 预制装配式建筑预制墙板快速就位装置 | |
CN209481105U (zh) | 一种大型滚珠丝杠副装配用装置 | |
CN203304908U (zh) | 机床操作走台装置 | |
CN203555689U (zh) | 竖井电动吊篮 | |
CN203271210U (zh) | 升降式立体车库 | |
CN203871663U (zh) | 双导轨变电站二级门构架辅助放置系统 | |
CN201981489U (zh) | 一种单导梁伸缩式架桥机 | |
CN104064961B (zh) | 双导轨变电站二级门构架辅助放置系统 | |
CN104386610A (zh) | 摆动门运输就位设备 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |