CN104018474B - 施工支洞回填改建检修支洞的方法 - Google Patents
施工支洞回填改建检修支洞的方法 Download PDFInfo
- Publication number
- CN104018474B CN104018474B CN201410281132.6A CN201410281132A CN104018474B CN 104018474 B CN104018474 B CN 104018474B CN 201410281132 A CN201410281132 A CN 201410281132A CN 104018474 B CN104018474 B CN 104018474B
- Authority
- CN
- China
- Prior art keywords
- hole
- access path
- tunnel
- working tunnel
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Abstract
本发明公开了一种施工支洞回填改建检修支洞的方法,首先将施工支洞与输水隧洞主洞连接处进行混凝土封堵;封堵时,在位于封堵段的施工支洞内留出第一检修通道,第一检修通道的纵坡为10%~12%;然后在靠近封堵段施工支洞的洞底用块石混凝土回填成沿施工支洞纵向呈“凸”字形曲线的第二检修通道;“凸”字形曲线洞底最高处为圆弧段,圆弧段两侧纵坡为10%~12%,位于封堵段一侧的纵坡与第一检修通道的纵坡相衔接;圆弧段洞底最高点的高程大于输水隧洞主洞正常运行水位线;最后在第二检修通道的洞底表面铺设0.2m厚的常态混凝土,作为混凝土防渗路面。本发明优点在于避免了增设检修闸门,降低了施工难度和工程投资,缩短了工期。
Description
技术领域
本发明涉及大、中型水利水电工程输水隧洞(明流洞)的建设方法,尤其是涉及施工支洞回填改建检修支洞的方法。
背景技术:
在大、中型水利水电工程输水隧洞(明流洞)建设过程中,特别是长距离、大直径、深埋输水隧洞,通常将施工期临时的施工支洞改建为检修支洞,以达到缩短工期、降低投资的目的。目前在改建中,通常是在施工支洞与输水隧洞主洞交叉连接段内设置金属检修闸门,通过控制金属检修闸门启闭达到输水隧洞主洞的运行和检修目的。此方法有两个弊端:一是增加金属检修闸门等相关结构,增加了工程投资;二是金属检修闸门本身存在维护及检修问题,当金属检修闸门因故障需要检修或定期维修时,必须放空整个输水隧洞主洞内的水。因此,通常的施工支洞改建检修支洞的方法,不仅增加工程投资、而且影响输水隧洞的正常运行、并存在一定的安全隐患。
发明内容
本发明目的在于提供一种施工支洞回填改建检修支洞的方法。
为实现上述目的,本发明采取下述技术方案:
本发明所述施工支洞回填改建检修支洞的方法,首先将施工支洞与输水隧洞主洞连接处进行混凝土封堵;封堵时,在位于封堵段的施工支洞内留出第一检修通道,所述第一检修通道的纵坡为10%~12%;然后在靠近所述封堵段施工支洞内的洞底用块石混凝土回填成沿施工支洞纵向呈“凸”字形曲线的第二检修通道;所述“凸”字形曲线的洞底最高处为圆弧段,所述圆弧段的两侧纵坡均为10%~12%,位于封堵段一侧的纵坡与第一检修通道的纵坡相衔接;圆弧段洞底最高点的高程大于输水隧洞主洞的正常运行水位线;最后在第二检修通道的洞底表面铺设0.1m-0.5m厚的常态混凝土,作为混凝土防渗路面。
当所述第二检修通道回填完成后的高度不能满足设计要求时,对第二检修通道的洞顶进行扩挖至满足设计要求即可。
本发明较传统施工支洞改建检修支洞方法优点在于避免了增设检修闸门,降低了施工难度和工程投资,经济易行且缩短了工期。本发明方法尤其适用于长距离、大直径、深埋输水隧洞(明流洞)的施工支洞回填改建检修支洞,该检修支洞还可兼作明流输水隧洞的通气洞。同时,检修支洞既可以在运行期挡水,又可以在检修期放空输水隧洞主洞的情况下对输水隧洞主洞进行检修。
附图说明:
图1是按照本发明方法实施的改建后施工支洞的结构示意图。
图2是图1的A-A向剖视结构示意图。
图3是图2的B部放大结构示意图。
具体实施方式
如图1-3所示,本发明所述施工支洞回填改建检修支洞的方法,在施工支洞1改建检修支洞时,按照下述步骤进行:
1、输水隧洞主洞2与施工支洞1钻爆开挖完成后,根据施工工期的安排开始进行检修支洞的改建;
2、将施工支洞1与输水隧洞主洞2连接处进行混凝土3的封堵,混凝土封堵段的长度根据设计要求取得。在混凝土3封堵的施工支洞1内留出第一检修通道4,第一检修通道4的高度、宽度、转弯半径根据检修需要按常规进行设计,第一检修通道4的纵坡为10%~12%;
3、在紧接混凝土封堵段的施工支洞1内,将其洞底用块石混凝土5沿纵向回填成纵向剖面呈“凸”字形曲线的第二检修通道6,所述“凸”字形曲线洞底7的最高处为圆弧段,所述圆弧段洞底的两侧纵坡均为10%~12%,位于混凝土封堵段一侧的纵坡与第一检修通道4的纵坡相衔接;圆弧段洞底最高点的高程大于输水隧洞主洞2的正常运行水位线8;最后在第二检修通道6的“凸”字形曲线洞底7表面铺设0.1m-0.5m厚的常态混凝土,作为混凝土防渗路面。
4、当第二检修通道6回填完成后的高度不能满足设计要求时,对第二检修通道6的洞顶进行扩挖至满足设计要求即可。
Claims (2)
1.一种施工支洞回填改建检修支洞的方法,其特征在于:首先将施工支洞与输水隧洞主洞连接处进行混凝土封堵;封堵时,在位于封堵段的施工支洞内留出第一检修通道,所述第一检修通道的纵坡为10%~12%;然后在靠近所述封堵段施工支洞内的洞底用块石混凝土回填成沿施工支洞纵向呈“凸”字形曲线的第二检修通道;所述“凸”字形曲线的洞底最高处为圆弧段,所述圆弧段的两侧纵坡均为10%~12%,位于封堵段一侧的纵坡与第一检修通道的纵坡相衔接;圆弧段洞底最高点的高程大于输水隧洞主洞的正常运行水位线;最后在第二检修通道的洞底表面铺设0.1m-0.5m厚的常态混凝土,作为混凝土防渗路面。
2.根据权利要求1所述施工支洞回填改建检修支洞的方法,其特征在于:当所述第二检修通道回填完成后的高度不能满足设计要求时,对第二检修通道的洞顶进行扩挖至满足设计要求即可。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410281132.6A CN104018474B (zh) | 2014-06-23 | 2014-06-23 | 施工支洞回填改建检修支洞的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410281132.6A CN104018474B (zh) | 2014-06-23 | 2014-06-23 | 施工支洞回填改建检修支洞的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104018474A CN104018474A (zh) | 2014-09-03 |
CN104018474B true CN104018474B (zh) | 2016-01-20 |
Family
ID=51435447
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410281132.6A Active CN104018474B (zh) | 2014-06-23 | 2014-06-23 | 施工支洞回填改建检修支洞的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104018474B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108951552B (zh) * | 2018-07-25 | 2023-10-20 | 中国电建集团北京勘测设计研究院有限公司 | 一种带通气口的无压隧洞检修通道 |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106968227B (zh) * | 2017-05-16 | 2023-07-25 | 中国电建集团成都勘测设计研究院有限公司 | 高拱坝导流洞永久堵头的检修布置结构及检修方法 |
CN109371914B (zh) * | 2018-12-25 | 2023-09-26 | 中国电建集团成都勘测设计研究院有限公司 | 一种便于后期改建的泄水渠结构 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09310329A (ja) * | 1997-02-14 | 1997-12-02 | Shimizu Corp | 水路式発電施設とその施工方法 |
CN201686965U (zh) * | 2010-05-19 | 2010-12-29 | 葛洲坝集团第一工程有限公司 | 导流隧洞现浇钢筋混凝土闸门 |
CN202117037U (zh) * | 2011-02-24 | 2012-01-18 | 中国水电顾问集团华东勘测设计研究院 | 便于引水隧洞空间弯管下部斜洞施工的结构 |
CN102505671A (zh) * | 2011-11-18 | 2012-06-20 | 中国水电顾问集团成都勘测设计研究院 | 用于多条引水隧洞的上跨式检修通道 |
CN202323897U (zh) * | 2011-11-18 | 2012-07-11 | 中国水电顾问集团成都勘测设计研究院 | 用于多条引水隧洞的检修通道 |
-
2014
- 2014-06-23 CN CN201410281132.6A patent/CN104018474B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09310329A (ja) * | 1997-02-14 | 1997-12-02 | Shimizu Corp | 水路式発電施設とその施工方法 |
CN201686965U (zh) * | 2010-05-19 | 2010-12-29 | 葛洲坝集团第一工程有限公司 | 导流隧洞现浇钢筋混凝土闸门 |
CN202117037U (zh) * | 2011-02-24 | 2012-01-18 | 中国水电顾问集团华东勘测设计研究院 | 便于引水隧洞空间弯管下部斜洞施工的结构 |
CN102505671A (zh) * | 2011-11-18 | 2012-06-20 | 中国水电顾问集团成都勘测设计研究院 | 用于多条引水隧洞的上跨式检修通道 |
CN202323897U (zh) * | 2011-11-18 | 2012-07-11 | 中国水电顾问集团成都勘测设计研究院 | 用于多条引水隧洞的检修通道 |
Non-Patent Citations (1)
Title |
---|
穿越坍方区及断层带的隧洞检修洞施工方案;王克丽;《岩土力学》;20040430;第25卷(第4期);第651-653页 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108951552B (zh) * | 2018-07-25 | 2023-10-20 | 中国电建集团北京勘测设计研究院有限公司 | 一种带通气口的无压隧洞检修通道 |
Also Published As
Publication number | Publication date |
---|---|
CN104018474A (zh) | 2014-09-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103775092B (zh) | 隧道浅埋暗挖预留核心土改良crd施工工法 | |
CN103306713B (zh) | 一种高突煤层穿层钻孔网络化加固方法 | |
CN103510957B (zh) | 一种组合式石门揭煤方法 | |
CN105134216B (zh) | 破碎顶板110工法巷旁防塌落结构 | |
CN104612698A (zh) | 一种浅埋暗挖隧道上台阶中隔壁施工方法 | |
CN103527219A (zh) | 用于大变形地层的隧道支护结构及其施工工法 | |
CN104533446A (zh) | 一种大断面软弱围岩隧道双层初期支护预防地质灾害发生的施工方法及其结构 | |
CN203515604U (zh) | 用于大变形地层的隧道支护结构 | |
CN102817621B (zh) | 一种适用于不良地质隧道控制拱墙脚沉降的综合施工方法 | |
CN104018474B (zh) | 施工支洞回填改建检修支洞的方法 | |
CN109707399A (zh) | 隧道出洞支护构造及其施工方法 | |
CN103993885A (zh) | 一种暗挖隧道侧向开洞支撑体系构建方法 | |
CN207111103U (zh) | 一种软弱围岩大断面隧道双侧壁导坑三台阶法开挖支护结构 | |
CN104989419A (zh) | 一种隧道初期支护侵限的处理方法及其施工配套设备 | |
CN102606173B (zh) | 一种处理隧道变形段、加快掘进的施工方法 | |
CN204327112U (zh) | 隧道出洞超前支护系统 | |
CN204783020U (zh) | 一种大跨度浅埋暗挖隧道施工设备 | |
CN203904947U (zh) | 施工支洞回填改建检修支洞的结构 | |
CN205677638U (zh) | 一种黄土隧道抗沉降支承结构 | |
CN104632228A (zh) | 横通道进入正线施工方法及横通道 | |
CN204199296U (zh) | 基于老旧地下室外墙结构的基坑支护结构 | |
CN103233742A (zh) | 长距离管道输煤不良地质段处理措施 | |
CN205116201U (zh) | 一种沉井施工装置 | |
CN203499692U (zh) | 在管线条件下地铁施工的异形竖井 | |
CN204386617U (zh) | 一种低水头引水隧洞的固结灌浆结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 450003 Jinshui Road 109, Zhengzhou City, Henan Province Patentee after: Yellow River Survey Planning and Design Research Institute Co., Ltd. Address before: 450003 Jinshui Road 109, Zhengzhou City, Henan Province Patentee before: Yellow River Engineering Consulting Co., Ltd. |