- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Building Environments (AREA)
- Refrigerator Housings (AREA)
Abstract
The invention discloses a method for transforming old factory buildings into fresh keeping storehouses, and belongs to the field of technologies for transforming old factory buildings. By the aid of the method for transforming the old factory buildings, the old factory buildings can be reused. The technical scheme for solving technical problems includes that the method for transforming the old factory buildings into the fresh keeping storehouses is characterized by comprising a wall cleaning procedure (1), a refrigeration equipment mounting procedure (2), a wall cleaning procedure (3), a foam wall manufacturing procedure (4) and a refrigeration pipeline arranging procedure (5). The method has the advantages that embedded parts not only can be used as mounting components for refrigeration pipelines, but also can be used as support parts for foam walls, accordingly, the foam walls can be prevented from being separated from solid brick walls, equipment in the factory buildings can be reasonably utilized, spaces can be saved, and the manufacturing cost can be reduced.
Description
Technical field
A kind of old old factory rehabilitation of the present invention becomes the method for fresh-keeping warehouse, belongs to old old factory rehabilitation technical field.
Background technology
For original old production department, due to the needs of technological innovation and industrial development, old factory building in the past just can not meet the needs of production, but the structure of these old factory buildings is also very complete, other purposes can be made, if directly remove, the waste of resource can be caused, and rebuild other production houses and can drop into larger fund, be faced with the shortcomings such as construction works amount is large, the construction period is long, construction investment is high.In addition, these old factory buildings also need not be removed sometimes, leave unused also without his use, and the resource free time is just equivalent to the wasting of resources, has brought economic loss to producer.
Summary of the invention
The present invention overcomes the deficiency that prior art exists, and technical problem to be solved is for providing a kind of by the remodeling method of old factory building recycling.
In order to solve the problems of the technologies described above, the technical solution used in the present invention is: a kind of old old factory rehabilitation becomes the method for fresh-keeping warehouse, carries out according to following operation:
Body of wall cleaning: when to old old factory rehabilitation, retain body of wall and the roof of original factory building, remove coating and the wall paint of old Brick wall endosexine, until expose the entity part of brick wall, the window of old factory building is removed, and stifled real with fragment of brick and cement, then entity brick wall is cleared up, coating and the cement on entity brick wall top layer are cleaned out;
Chiller plant is installed: according to actual factory building layout needs, perforate on body of wall, in hole, be coated with and be connected with compressor import and export and form the refrigerator pipes of refrigerating circuit, and compressor is arranged on to old factory building outside, design the installation site of refrigeration piping according to the topology layout of old factory building inside, in the inner perforating of body of wall, the built-in fitting for supporting pipeline is also installed, it is 35 ~ 55cm that built-in fitting stretches out body of wall length;
The cleaning of body of wall: clear up the dust on entity brick wall endosexine, and clean the endosexine of entity brick wall, at room temperature naturally dry;
Make foam wall: PEPA is mixed according to the proportioning of 1:0.9 ~ 1:1.2 with vulcabond, generation has the foam of insulation effect, foam is linearity molecular structure, foam wall forms space network, the foam density making is 30 ~ 40kg/m3, then foam is evenly sprayed on entity brick wall, form the foam wall of 5 ~ 25cm, foam wall and built-in fitting tight bond, and in the hole of body of wall filled and process, ensure the sealing of body of wall entirety, then under the environment of 20 ~ 30 DEG C, dry, flash-off time is 1 ~ 2 day;
Arrange refrigeration piping operation: on the built-in fitting of installing in chiller plant operation, refrigeration piping is installed, in installation process, will be avoided destroying foam wall.
As preferably, described built-in fitting is fastened on entity brick wall by high-strength expansion bolt.
As preferably, the density of described foam is 33 ~ 35 kg/m3.
As preferably, the density of described foam is 34 kg/m3.
As preferably, the thickness of described foam wall is 10 ~ 20cm.
As preferably, the thickness of described foam wall is 15cm.
As preferably, described built-in fitting stretches out the large 25 ~ 35cm of thickness of body of wall Length Ratio foam wall.
As preferably, described built-in fitting stretches out the large 30cm of thickness of body of wall Length Ratio foam wall.
As preferably, described PEPA mixes according to the proportioning of 1:1 with vulcabond.
The present invention compared with prior art has following beneficial effect.
One, the present invention effectively utilizes the former factory building of haveing been friends in the past to be transformed into fresh-keeping warehouse, has reduced building removal rubbish, has shortened the duration and has reduced initial investment, for producer has saved cost of production, has also brought economic well-being of workers and staff simultaneously.
Two, the present invention utilizes solid netted froth bed as insulated wall, Stability Analysis of Structures, and high insulating effect, quality is light, and has good fire performance, can meet security against fire demand.
Three, built-in fitting of the present invention is the installing component of refrigeration piping, is again the support member of foam wall, and foam wall can not separate with entity brick wall, rationally utilizes the equipment in factory building, and conserve space, has shortened manufacturing cost.
Detailed description of the invention
Below in conjunction with specific embodiment, the invention will be further described.
Embodiment mono-
Old old factory rehabilitation becomes a method for fresh-keeping warehouse, carries out according to following operation:
Body of wall cleaning: when to old old factory rehabilitation, retain body of wall and the roof of original factory building, remove coating and the wall paint of old Brick wall endosexine, until expose the entity part of brick wall, the window of old factory building is removed, and stifled real with fragment of brick and cement, then entity brick wall is cleared up, coating and the cement on entity brick wall top layer are cleaned out;
Chiller plant is installed: according to actual factory building layout needs, perforate on body of wall, in hole, be coated with and be connected with compressor import and export and form the refrigerator pipes of refrigerating circuit, and compressor is arranged on to old factory building outside, design the installation site of refrigeration piping according to the topology layout of old factory building inside, in the inner perforating of body of wall, the built-in fitting for supporting pipeline is also installed, it is 35cm that built-in fitting stretches out body of wall length;
The cleaning of body of wall: clear up the dust on entity brick wall endosexine, and clean the endosexine of entity brick wall, at room temperature naturally dry;
Make foam wall: PEPA is mixed according to the proportioning of 1:0.9 with vulcabond, generation has the foam of insulation effect, foam is linearity molecular structure, foam wall forms space network, the foam density making is 30kg/m3, then foam is evenly sprayed on entity brick wall, form the foam wall of 5cm, foam wall and built-in fitting tight bond, and in the hole of body of wall filled and process, ensure the sealing of body of wall entirety, then under the environment of 20 DEG C, dry, flash-off time is 1 day, and foam is fire proofing material, can meet fire-fighting needs;
Arrange refrigeration piping operation: on the built-in fitting of installing in chiller plant operation, refrigeration piping is installed, in installation process, will be avoided destroying foam wall.
Built-in fitting of the present invention is the installing component of refrigeration piping, is again the support member of foam wall, and foam wall can not separate with entity brick wall, rationally utilizes the equipment in factory building, and conserve space, has shortened manufacturing cost.
Embodiment bis-
Old old factory rehabilitation becomes a method for fresh-keeping warehouse, carries out according to following operation:
Body of wall cleaning: when to old old factory rehabilitation, retain body of wall and the roof of original factory building, remove coating and the wall paint of old Brick wall endosexine, until expose the entity part of brick wall, the window of old factory building is removed, and stifled real with fragment of brick and cement, then entity brick wall is cleared up, coating and the cement on entity brick wall top layer are cleaned out;
Chiller plant is installed: according to actual factory building layout needs, perforate on body of wall, in hole, be coated with and be connected with compressor import and export and form the refrigerator pipes of refrigerating circuit, and compressor is arranged on to old factory building outside, design the installation site of refrigeration piping according to the topology layout of old factory building inside, in the inner perforating of body of wall, the built-in fitting for supporting pipeline is also installed, it is 40cm that built-in fitting stretches out body of wall length;
The cleaning of body of wall: clear up the dust on entity brick wall endosexine, and clean the endosexine of entity brick wall, at room temperature naturally dry;
Make foam wall: PEPA is mixed according to the proportioning of 1:1 with vulcabond, generation has the foam of insulation effect, foam is linearity molecular structure, foam wall forms space network, the foam density making is 33kg/m3, then foam is evenly sprayed on entity brick wall, form the foam wall of 10cm, foam wall and built-in fitting tight bond, and in the hole of body of wall filled and process, ensure the sealing of body of wall entirety, then under the environment of 23 DEG C, dry, flash-off time is 1.5 days, and foam is fire proofing material, can meet fire-fighting needs;
Arrange refrigeration piping operation: on the built-in fitting of installing in chiller plant operation, refrigeration piping is installed, in installation process, will be avoided destroying foam wall.
Embodiment tri-
Old old factory rehabilitation becomes a method for fresh-keeping warehouse, carries out according to following operation:
Body of wall cleaning: when to old old factory rehabilitation, retain body of wall and the roof of original factory building, remove coating and the wall paint of old Brick wall endosexine, until expose the entity part of brick wall, the window of old factory building is removed, and stifled real with fragment of brick and cement, then entity brick wall is cleared up, coating and the cement on entity brick wall top layer are cleaned out;
Chiller plant is installed: according to actual factory building layout needs, perforate on body of wall, in hole, be coated with and be connected with compressor import and export and form the refrigerator pipes of refrigerating circuit, and compressor is arranged on to old factory building outside, design the installation site of refrigeration piping according to the topology layout of old factory building inside, in the inner perforating of body of wall, the built-in fitting for supporting pipeline is also installed, it is 45cm that built-in fitting stretches out body of wall length;
The cleaning of body of wall: clear up the dust on entity brick wall endosexine, and clean the endosexine of entity brick wall, at room temperature naturally dry;
Make foam wall: PEPA is mixed according to the proportioning of 1:1.1 with vulcabond, generation has the foam of insulation effect, foam is linearity molecular structure, foam wall forms space network, the foam density making is 35kg/m3, then foam is evenly sprayed on entity brick wall, form the foam wall of 15cm, foam wall and built-in fitting tight bond, and in the hole of body of wall filled and process, ensure the sealing of body of wall entirety, then under the environment of 26 DEG C, dry, flash-off time is 1.5 days, and foam is fire proofing material, can meet fire-fighting needs;
Arrange refrigeration piping operation: on the built-in fitting of installing in chiller plant operation, refrigeration piping is installed, in installation process, will be avoided destroying foam wall.
Embodiment tetra-
Old old factory rehabilitation becomes a method for fresh-keeping warehouse, carries out according to following operation:
Body of wall cleaning: when to old old factory rehabilitation, retain body of wall and the roof of original factory building, remove coating and the wall paint of old Brick wall endosexine, until expose the entity part of brick wall, the window of old factory building is removed, and stifled real with fragment of brick and cement, then entity brick wall is cleared up, coating and the cement on entity brick wall top layer are cleaned out;
Chiller plant is installed: according to actual factory building layout needs, perforate on body of wall, in hole, be coated with and be connected with compressor import and export and form the refrigerator pipes of refrigerating circuit, and compressor is arranged on to old factory building outside, design the installation site of refrigeration piping according to the topology layout of old factory building inside, in the inner perforating of body of wall, the built-in fitting for supporting pipeline is also installed, it is 55cm that built-in fitting stretches out body of wall length;
The cleaning of body of wall: clear up the dust on entity brick wall endosexine, and clean the endosexine of entity brick wall, at room temperature naturally dry;
Make foam wall: PEPA is mixed according to the proportioning of 1:1.2 with vulcabond, generation has the foam of insulation effect, foam is linearity molecular structure, foam wall forms space network, the foam density making is 40kg/m3, then foam is evenly sprayed on entity brick wall, form the foam wall of 25cm, foam wall and built-in fitting tight bond, and in the hole of body of wall filled and process, ensure the sealing of body of wall entirety, then under the environment of 30 DEG C, dry, flash-off time is 2 days, and foam is fire proofing material, can meet fire-fighting needs;
Arrange refrigeration piping operation: on the built-in fitting of installing in chiller plant operation, refrigeration piping is installed, in installation process, will be avoided destroying foam wall.
The present invention can summarize with other the concrete form without prejudice to spirit of the present invention or principal character.Therefore, no matter from that, above-mentioned embodiment of the present invention all can only think explanation of the present invention can not limit invention, claims have been pointed out scope of the present invention, and scope of the present invention is not pointed out in above-mentioned explanation, therefore, any variation in implication and the scope suitable with claims of the present invention, all should think to be included in the scope of claims.
Claims (9)
1. old old factory rehabilitation becomes a method for fresh-keeping warehouse, it is characterized in that, carries out according to following operation:
Body of wall cleaning: when to old old factory rehabilitation, retain body of wall and the roof of original factory building, remove coating and the wall paint of old Brick wall endosexine, until expose the entity part of brick wall, the window of old factory building is removed, and stifled real with fragment of brick and cement, then entity brick wall is cleared up, coating and the cement on entity brick wall top layer are cleaned out;
Chiller plant is installed: according to actual factory building layout needs, perforate on body of wall, in hole, be coated with and be connected with compressor import and export and form the refrigerator pipes of refrigerating circuit, and compressor is arranged on to old factory building outside, design the installation site of refrigeration piping according to the topology layout of old factory building inside, in the inner perforating of body of wall, the built-in fitting for supporting pipeline is also installed, it is 35 ~ 55cm that built-in fitting stretches out body of wall length;
The cleaning of body of wall: clear up the dust on entity brick wall endosexine, and clean the endosexine of entity brick wall, at room temperature naturally dry;
Make foam wall: PEPA is mixed according to the proportioning of 1:0.9 ~ 1:1.2 with vulcabond, generation has the foam of insulation effect, foam is linearity molecular structure, foam wall forms space network, the foam density making is 30 ~ 40kg/m3, then foam is evenly sprayed on entity brick wall, form the foam wall of 5 ~ 25cm, foam wall and built-in fitting tight bond, and in the hole of body of wall filled and process, ensure the sealing of body of wall entirety, then under the environment of 20 ~ 30 DEG C, dry, flash-off time is 1 ~ 2 day;
Arrange refrigeration piping operation: on the built-in fitting of installing in chiller plant operation, refrigeration piping is installed, in installation process, will be avoided destroying foam wall.
2. a kind of old old factory rehabilitation according to claim 1 becomes the method for fresh-keeping warehouse, it is characterized in that, described built-in fitting is fastened on entity brick wall by high-strength expansion bolt.
3. a kind of old old factory rehabilitation according to claim 1 becomes the method for fresh-keeping warehouse, it is characterized in that, the density of described foam is 33 ~ 35 kg/m3.
4. a kind of old old factory rehabilitation according to claim 3 becomes the method for fresh-keeping warehouse, it is characterized in that, the density of described foam is 34 kg/m3.
5. a kind of old old factory rehabilitation according to claim 1 becomes the method for fresh-keeping warehouse, it is characterized in that, the thickness of described foam wall is 10 ~ 20cm.
6. a kind of old old factory rehabilitation according to claim 5 becomes the method for fresh-keeping warehouse, it is characterized in that, the thickness of described foam wall is 15cm.
7. a kind of old old factory rehabilitation according to claim 1 becomes the method for fresh-keeping warehouse, it is characterized in that, described built-in fitting stretches out the large 25 ~ 35cm of thickness of body of wall Length Ratio foam wall.
8. a kind of old old factory rehabilitation according to claim 1 becomes the method for fresh-keeping warehouse, it is characterized in that, described built-in fitting stretches out the large 30cm of thickness of body of wall Length Ratio foam wall.
9. a kind of old old factory rehabilitation according to claim 1 becomes the method for fresh-keeping warehouse, it is characterized in that, described PEPA mixes according to the proportioning of 1:1 with vulcabond.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410147469.8A CN103924790B (en) | 2014-04-14 | 2014-04-14 | A kind of old old factory rehabilitation becomes the method for fresh-keeping warehouse |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410147469.8A CN103924790B (en) | 2014-04-14 | 2014-04-14 | A kind of old old factory rehabilitation becomes the method for fresh-keeping warehouse |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103924790A true CN103924790A (en) | 2014-07-16 |
CN103924790B CN103924790B (en) | 2016-04-06 |
Family
ID=51143167
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410147469.8A Active CN103924790B (en) | 2014-04-14 | 2014-04-14 | A kind of old old factory rehabilitation becomes the method for fresh-keeping warehouse |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103924790B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106152688A (en) * | 2015-03-26 | 2016-11-23 | 郑州大学 | A kind of air-regulation type freezer encapsulating method |
CN109057388A (en) * | 2018-08-16 | 2018-12-21 | 中国十七冶集团有限公司 | A kind of gear hinders the medium pipeline remodeling method for steel column installation of extending a factory building |
CN109356398A (en) * | 2018-11-22 | 2019-02-19 | 中国十七冶集团有限公司 | It is a kind of to keep off the remodeling method for hindering steel column install medium pipeline of extending a factory building |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1632265A (en) * | 2004-11-07 | 2005-06-29 | 戴卫东 | Fresh-keeping warehouse and refrigeration house construction technology |
JP2007170773A (en) * | 2005-12-26 | 2007-07-05 | Sharp Corp | Refrigerator |
CN101669001A (en) * | 2007-04-26 | 2010-03-10 | 松下电器产业株式会社 | refrigerator |
WO2010029728A1 (en) * | 2008-09-12 | 2010-03-18 | パナソニック株式会社 | Refrigerator |
CN201527147U (en) * | 2009-11-12 | 2010-07-14 | 国家农产品保鲜工程技术研究中心(天津) | Fresh keeping storage in micro difference pressing jack type |
CN103216106A (en) * | 2013-04-24 | 2013-07-24 | 启东建筑集团有限公司 | Construction method of electronic workshop low-temperature cold store |
-
2014
- 2014-04-14 CN CN201410147469.8A patent/CN103924790B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1632265A (en) * | 2004-11-07 | 2005-06-29 | 戴卫东 | Fresh-keeping warehouse and refrigeration house construction technology |
JP2007170773A (en) * | 2005-12-26 | 2007-07-05 | Sharp Corp | Refrigerator |
CN101669001A (en) * | 2007-04-26 | 2010-03-10 | 松下电器产业株式会社 | refrigerator |
WO2010029728A1 (en) * | 2008-09-12 | 2010-03-18 | パナソニック株式会社 | Refrigerator |
CN201527147U (en) * | 2009-11-12 | 2010-07-14 | 国家农产品保鲜工程技术研究中心(天津) | Fresh keeping storage in micro difference pressing jack type |
CN103216106A (en) * | 2013-04-24 | 2013-07-24 | 启东建筑集团有限公司 | Construction method of electronic workshop low-temperature cold store |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106152688A (en) * | 2015-03-26 | 2016-11-23 | 郑州大学 | A kind of air-regulation type freezer encapsulating method |
CN109057388A (en) * | 2018-08-16 | 2018-12-21 | 中国十七冶集团有限公司 | A kind of gear hinders the medium pipeline remodeling method for steel column installation of extending a factory building |
CN109057388B (en) * | 2018-08-16 | 2020-06-05 | 中国十七冶集团有限公司 | Medium pipeline transformation method for obstructing installation of steel column of expanded plant |
CN109356398A (en) * | 2018-11-22 | 2019-02-19 | 中国十七冶集团有限公司 | It is a kind of to keep off the remodeling method for hindering steel column install medium pipeline of extending a factory building |
CN109356398B (en) * | 2018-11-22 | 2020-01-10 | 中国十七冶集团有限公司 | Transformation method for obstructing installation medium pipeline of steel column of expanded plant |
Also Published As
Publication number | Publication date |
---|---|
CN103924790B (en) | 2016-04-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102659351B (en) | Thermal-insulation loading recycled concrete | |
CN103924790B (en) | A kind of old old factory rehabilitation becomes the method for fresh-keeping warehouse | |
CN203783198U (en) | Clean room for semiconductor plant | |
JP3218531U (en) | Blocked partition wall | |
CN102731903A (en) | Composite material of imitated glass reinforced plastic, its manufacture method and its application | |
CN103978547A (en) | Long-wall structure concrete curing device and curing method thereof | |
CN101275704A (en) | Steel face type phenolic aldehyde heat preserving composite board and manufacturing method and application thereof | |
CN111608293A (en) | Wall body of spray-built gypsum double-layer heat-insulation composite double-layer outer wall structure and preparation method | |
CN103570300A (en) | Recycled concrete tile and preparation method thereof | |
CN104975676A (en) | Lightweight high-strength composite partition batten, and production method thereof | |
JP2007247372A (en) | Panel for building such as house and panel for refrigerator | |
KR101656029B1 (en) | Multy insulation construction being composed of urethane layer and nonflammable natural fibrous material layer | |
CN205159818U (en) | Have box -type substation waterproof and sealed function concurrently | |
CN104060791B (en) | Flexible decorative face polyurethane thermal insulation and decoration integrated board and preparation method thereof | |
CN107382234A (en) | A kind of assembled lightgage steel joist lightweight heat-proof machine spray inserts and its construction method | |
CN202596042U (en) | Roof waterproof, heat preservation and heat insulation integrated system | |
CN111962715A (en) | Hollow outer wall body structure and preparation method thereof | |
CN209082824U (en) | A kind of light lath | |
Sun et al. | Applications and Analysis of the Composite wall on Construction in Heilongjiang Province | |
CN203145306U (en) | Aerated concrete self-insulation compound building block | |
CN111593834A (en) | Spray-built gypsum three-layer heat-preservation composite double-layer outer wall and preparation method thereof | |
CN204523340U (en) | A kind of building castoff process spraying humidifier | |
KR20120079259A (en) | Manufacturing method of modular mobile buildings with insulation structure and mobile buildings using them | |
CN212427653U (en) | Spray-built gypsum heat-insulation composite double-layer outer wall structure | |
CN103452194B (en) | Interval shielding adiabatic module and manufacture method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |