KR20120079259A - Manufacturing method of modular mobile buildings with insulation structure and mobile buildings using them - Google Patents

Manufacturing method of modular mobile buildings with insulation structure and mobile buildings using them Download PDF

Info

Publication number
KR20120079259A
KR20120079259A KR1020110000461A KR20110000461A KR20120079259A KR 20120079259 A KR20120079259 A KR 20120079259A KR 1020110000461 A KR1020110000461 A KR 1020110000461A KR 20110000461 A KR20110000461 A KR 20110000461A KR 20120079259 A KR20120079259 A KR 20120079259A
Authority
KR
South Korea
Prior art keywords
insulating material
building
horizontal frame
module structure
frame
Prior art date
Application number
KR1020110000461A
Other languages
Korean (ko)
Inventor
강용욱
Original Assignee
강용욱
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 강용욱 filed Critical 강용욱
Priority to KR1020110000461A priority Critical patent/KR20120079259A/en
Publication of KR20120079259A publication Critical patent/KR20120079259A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34815Elements not integrated in a skeleton
    • E04B1/3483Elements not integrated in a skeleton the supporting structure consisting of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34384Assembling details for foldable, separable, collapsible or retractable structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/7604Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only fillings for cavity walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Acoustics & Sound (AREA)
  • Building Environments (AREA)

Abstract

PURPOSE: A manufacturing method of a modulated transportable building equipped with the thermal insulation structure is provided to reduce build period and costs while securing sealing performance, thermal insulation performance, and strength. CONSTITUTION: A manufacturing method of a modulated transportable building equipped with the thermal insulation structure is as follows. The skeleton of a module structure is formed into intended structure of building by using an insulation injection port(50) horizontal frame(2) having an insulation discharge hole, a vertical frame(1), and a support member(4). A slab, a floor, electric wires, and water pipes are installed in the installed module structure. All gaps in the module are sealed. Insulating material(6) is injected into the module structure. Windows and doors are formed in the module structure having clotted insulating material.

Description

단열구조를 구비하는 모듈화된 이동식 건축물의 제조 방법과 이를 이용한 이동식 건축물{.}Manufacturing Method of Modular Mobile Building with Insulating Structure and Mobile Building Using Them {.}

본 발명은 조립식 건축물에 관한 것으로, 보다 구체적으로는 수직 프레임과 수평 프레임을 기초로 하는 골조에 바닥, 천장 슬래브 및 내부 시설물들을 설치하고, 창문과 출입문 등을 구획하여 내장재가 되는 합판을 설치한 모듈 구조체를 시공한 다음, 상기 모듈 구조체의 온도를 일정 이상 상승시키고, 골조와 합판 사이에 형성되는 공간 내부에 발포성 중합체 및 황토를 포함하는 단열재를 주입하여 상기 내부 시설물들이 매설되어 건축물의 기능이 일체로 모듈화 되도록 구성함으로써 시공 기간을 단축하면서 시공경비를 절감할 수 있고, 아울러 향상된 기밀성에 의한 단열구조를 구비하여 이동 가능하도록 공장에서 완성된 상태의 건축물로 제공되어 현장에 운반하여 배치될 수 있는 단열 구조를 구비하는 모듈화된 이동식 건축물의 제조 방법과 이를 이용한 이동식 건축물에 관한 것이다.
The present invention relates to a prefabricated building, and more specifically, to install a floor, a ceiling slab and internal facilities in a frame based on a vertical frame and a horizontal frame, and install a plywood that is a interior material by partitioning windows and doors, etc. After constructing the structure, the temperature of the module structure is raised to a certain level, and the interior facilities are buried by injecting an insulating material containing effervescent polymer and loess into the space formed between the frame and the plywood to integrally function the building. The modular construction reduces the construction cost while shortening the construction period, and also provides a heat-insulated structure that can be transported to the site and provided as a building completed in the factory so as to be movable with an insulating structure with improved airtightness. Method of manufacturing a modular mobile building having a It relates to the mobile building used.

종래에 건설되고 있는 대부분의 건축물은 콘크리트 구조이거나, 또는 철골구조를 바탕으로 한 콘크리트 구조물이다. 이러한 건축물들은 대부분의 공정과 시설물 들이 현장에서 서로 결합시키고 파이프 및 소요되는 다른 부품들을 연결시키는 기능 인력 및 장비에 의존하는 현장 시공으로 이루어지고 있다.Most buildings conventionally constructed are concrete structures or concrete structures based on steel structures. These buildings consist of field construction, in which most processes and facilities rely on functional personnel and equipment to join each other and connect pipes and other components in the field.

이러한 건축물의 현장 시공은 착공 및 기초공사에서 부터 기둥이나 벽쌓기, 슬래브, 단열, 내외장, 창호, 부대시설 공사로 이루어지는데 필요한 자재와 부품을 조달하거나 일일이 제작하여 시공하여야 하기 때문에 시공후 정밀도에 의한 하자가 발생될 가능성이 높고, 많은 양의 자재가 손실되는 문제점이 있었다.On-site construction of these buildings requires the procurement of materials and parts necessary for the construction of pillars, wall stacking, slabs, insulation, interior and exterior, windows, and auxiliary facilities from construction and foundation work. Defects are likely to occur, there was a problem that a large amount of material is lost.

따라서 상기 현장 시공의 경우에는 기능 인력의 숙련도와 현장의 환경 조건, 기후 변화, 자재 수급 현황, 감독자의 역량 등 여러 가지 요인에 의해 영향을 받게 되므로, 현장마다 시공 품질이나 공사 기간 등에 차이가 발생하게 된다.Therefore, in the case of the site construction is affected by a number of factors, such as skill level of skilled personnel, environmental conditions of the site, climate change, material supply and demand, supervisor capacity, such as the construction quality and construction period for each site do.

또한, 건축물의 시공이 장기화 되고, 작업이 고도화 될수록 그에 따른 안전사고의 위험이 증가하게 되며, 오랜 숙련을 거친 전문 인력을 고용함에 따라 인건비가 필연적으로 증가되고 있다.In addition, the longer the construction of the building, the more advanced the work, the risk of safety accidents, and the labor costs are inevitably increased by hiring skilled workers.

한편 컨테이너와 같이 이동 설치가 가능하고, 공장에서 제작하여 현장에서 조립할 수 있는 건축물의 개발 및 적용이 본격화 되고 있으나, 현장에서 상하수도용 배관과 전기 시설 및 배선 공사를 별도로 수행하는 기존의 건축 방법이 적용됨에 따라 현장 시공의 범주를 벗어날 수 없었다.On the other hand, the development and application of buildings that can be moved and installed like containers and can be manufactured at the factory and assembled at the site are in full swing, but existing construction methods that separately carry out water and sewage piping, electrical facilities, and wiring work are applied. Depending on the field construction could not escape.

모듈러 공법(Modular Framing)은 공장에서 제작하여 조립된 3차원적인 상자형의 유닛 부품군을 현장으로 운반하여 조립 시공하는 방법으로서, 유닛 부품에 들어가는 전기 및 기계설비, 창호를 포함한 내외장재, 바닥재, 천장재, 화장실이나 부엌의 기기설치 등 건축물의 90% 이상이 공장에서 완성되는 것으로 모듈러 공법을 적용한 모듈러 건축물은 상자형으로서 공간 유닛 부품을 상하, 전후, 좌우로 조합하여 건축물을 구성하므로 단독주택, 집합주택으로도 사용 가능하다.Modular Framing is a method of assembling and constructing a three-dimensional box-shaped unit component group that is manufactured and assembled at the factory.It is an electrical and mechanical equipment that enters the unit parts, interior and exterior materials including windows, flooring and ceiling materials. More than 90% of the buildings, such as the installation of toilets and kitchens, are completed at the factory. The modular construction method is a box type. Can also be used as

모듈러 건축물의 일예로서 스틸 하우스(Steel House)는 건물의 골조를 경량 형강으로 구성한 것으로, 기본 구조는 기둥과 같은 벽체 부재와 벽면 상하의 트랙 부재, 바닥이나 천장을 받쳐주는 조이스트로 이루어진다.Steel House (Steel House) is an example of a modular building is composed of a lightweight frame steel frame, the basic structure is composed of a wall member such as a column and track members above and below the wall, the joist supporting the floor or ceiling.

상기와 같이 모듈화 되는 건축물은 이전의 시공 방법 보다 시공성을 향상시키고 품질을 높이기 위해 공장에서 박스 형태의 모듈로 제작하고, 현장에서는 이를 적층하여 건물을 건립하는 현장 패널 공법이나 공장 패널 공법으로 시공되고 있다. The modular building as described above is manufactured in a box-shaped module at the factory in order to improve the constructability and quality than the previous construction method, and in the field, it is being constructed by a field panel method or a factory panel method in which a building is constructed. .

이러한 모듈러 건축물은 제작된 스틸 스터드를 현장에서 절단하여 패널 형태로 제작하고, 각각의 패널을 현장에서 조립하여 벽체와 박스 형태의 방을 구성하여야 하므로 현장에서 소음이 발생하고, 패널 제작상의 오차가 발생하여 시공성이 떨어질 수 있으며, 현장 주변에서 일반인들과 차량의 통행에 불편함을 주고, 안전성을 저해시키는 문제점이 여전히 남아있게 된다.These modular buildings must be manufactured in the form of panels by cutting the manufactured steel studs in the field, and each panel must be assembled in the field to form a wall and a box-shaped room, resulting in noise in the field and errors in panel production. The construction may be degraded, giving inconvenience to the general public and the traffic of the vehicle around the site, and the problem of impairing safety still remains.

모듈화된 건물은 구조적 안정성이 보장되는 조립 상태를 유지해야 되는 것은 물론이고, 일반적인 건축물의 구비 조건과 같이 친환경적 건축물로서 냉난방시 과도한 에너지의 소모를 방지할 수 있도록 단열성이 확보되어야 한다.
Modular buildings must be assembled to ensure structural stability, as well as to be insulated to prevent excessive energy consumption during heating and cooling.

현재 건설되고 있는 모듈화 건축물은 현장 패널 공법이나 공장 패널 공법으로 건립되고 있으나, 보다 시공성과 안전성을 향상시키고 품질을 높이기 위해 공장에서 조립이 완료된 완전한 박스 형태의 모듈로 제작하고, 현장에서는 단지 운반되어진 모듈화 건축물을 배치하는 것만으로 완료할 수 있는 공법에 의한 모듈화 건축물을 공급하는 것이 시공자나 수요자의 입장에서 보다 유리할 것이다.The modular building currently being constructed is being constructed by on-site panel construction or factory panel construction.However, in order to improve construction and safety and improve quality, the modular building is manufactured as a complete box-shaped module that has been assembled at the factory, and only transported in the field. It would be more advantageous from the point of view of the contractor or consumer to supply a modular building by a construction method that can be completed simply by arranging the building.

본 발명은 조립식 건축물이 설치되어야 하는 건설 현장의 공간에 적합한 크기로서 골조를 이루는 프레임과, 각종 건축 시설물과 세라믹, 기공성 재료, 기포성 재료 및 중합체를 포함하는 단열재가 일체로 이루어져서 완전한 건축물의 형태를 갖추게 되는 모듈화된 구조로 제작되어 현장에 운반하여 설치함으로써 현장에서 건축 시공 작업을 하지 않고서도 완성된 건축물을 제공할 수 있는 모듈화된 구조의 이동식 건축물을 제안한다.
The present invention is a frame suitable for the space of the construction site where the prefabricated building is to be installed, and the frame constituting the frame, and various building facilities and a heat insulating material including ceramic, porous material, foam material and polymer are integrally formed to form a complete building form. It proposes a modular structure that is made of modular structure that can be transported to the site and installed to provide a completed structure without the construction work in the field.

본 발명의 단열 구조를 구비하는 모듈화된 이동식 건축물의 제조 방법은 단열재 투입구과 단열재 배출공이 구비된 수평 프레임과 수직 프레임 및 지지부재를 이용하여 의도하는 건축물 형상으로 되는 모듈 구조체의 골조를 설치하는 제1단계;Method for manufacturing a modular mobile building having a heat insulating structure of the present invention is a first step of installing a frame of a modular structure of the intended structure using a horizontal frame and a vertical frame and a support member provided with a heat insulating material inlet and a heat insulating material discharge hole ;

상기 제1단계에 의하여 완성된 모듈 구조체의 골조에 마감재에 의하여 창문과 출입문이 설치되는 공간 구조를 구비하는 외벽과 슬래브 및 바닥을 설치하는 제2단계; A second step of installing an outer wall, a slab, and a floor having a space structure in which windows and doors are installed by finishing materials in the framework of the module structure completed by the first step;

상기 제2단계에 의한 모듈 구조체에 전기 배선과 상하수도 및 냉난방 시설을 하기 위한 배관설비를 시공하는 제3단계;A third step of constructing plumbing facilities for electric wiring, water and sewage, and heating and cooling facilities in the module structure according to the second step;

상기 제2단계 및 상기 제3단계에 의하여 시공된 외벽과 슬래브 및 바닥 연결부의 틈새를 밀폐시키는 제4단계;A fourth step of sealing a gap between the outer wall, the slab, and the bottom connection part constructed by the second and third steps;

상기 제4단계에 의한 모듈 구조체에 상기 제1단계에 의하여 형성된 단열재 투입구을 통하여 단열재를 주입하는 제5단계;A fifth step of injecting the insulating material into the module structure according to the fourth step through the insulating material inlet formed by the first step;

상기 제5단계에서 모듈 구조체에 주입된 단열재를 응고시키는 제6단계;A sixth step of solidifying the insulating material injected into the module structure in the fifth step;

상기 제6단계에 의하여 단열재가 응고된 모듈 구조체에 창문과 출입문을 시공하는 제7단계를 포함하는 것이다.
And a seventh step of constructing windows and doors in the module structure in which the insulation is solidified by the sixth step.

상기한 단계별 시골 과정에서 건축물 형상의 골조를 설치하는 제1단계와 단열재를 주입하는 제5단계의 공정 사이에서 건축물 형상의 골조를 지지하기 위한 기초 콘크리트 작업을 더 포함할 수도 있다.
The above-described rural process may further include a basic concrete work for supporting the frame of the building shape between the first step of installing the frame of the building shape and the fifth step of injecting insulation.

상기 제5단계에서 단열재는 발포성 합성중합체, 구체적으로는 발포 우레탄이 적용될 수 있고, 볏짚 스티로폴 알갱이와 같은 다공체가 혼합된 황토, 콘크리트, 바람직하게는 경량 기포 콘크리트, 또는 기타 세라믹 재료로부터 선택될 수 있다.In the fifth step, the insulation may be applied to a foamed synthetic polymer, specifically, urethane foam, and may be selected from ocher, concrete, preferably lightweight foamed concrete, or other ceramic material mixed with porous bodies such as rice straw styropol grains. .

상기 제6단계에서 단열재를 응고시키는 방법은 모듈 구조체를 가열로 내에서 일정 온도 이상으로 가온한 상태에서 이루어지거나 자연 건조 상태로 건조시키는 방법에서 선택될 수 있다.
The method of solidifying the heat insulating material in the sixth step may be selected from a method in which the module structure is heated to a predetermined temperature or more in a heating furnace or dried in a natural dry state.

이와 같이 모듈화된 이동식 건축물의 제조 방법은 건물의 벽체 내에 설치되는 전기 시설물과 상하수도 및 냉난방 설비와 같은 내부 시설물들의 배열이 일치되도록 기포성 합성 중합체로 되는 단열재, 또는 세라믹 단열재 내부에 파묻히게 되어 내부 시설물들의 위치에 균일성이 제공되고, 향상된 기밀성에 의한 단열구조와 현장에서 전선 및 배관을 설치하는 노동력이 필요 없게 되는 경제적인 구조와 방법을 제공한다.
The method of manufacturing a modular mobile building is embedded in an insulating material made of a foamable synthetic polymer or a ceramic insulating material so that the arrangement of the electrical facilities installed in the wall of the building and the internal facilities such as water and sewage and heating and cooling facilities are embedded. It provides a uniform structure in the location, an economical structure and a method which eliminates the need for labor to install wires and pipes in the field, and a heat insulation structure with improved airtightness.

본 발명의 단열구조를 구비하는 모듈화된 이동식 건축물의 기술적인 특징은 제1 기부의 양쪽 단부로부터 나란하게 형성되는 제1 고정단부에 보울트와 너트 같은 체결구가 체결되는 체결공이 일정한 간격을 두고 연속적으로 형성되는 수직 프레임;The technical feature of the modular mobile building having a heat insulating structure of the present invention is that the fastening holes, such as bolts and nuts, are fastened to a first fixed end formed side by side from both ends of the first base at regular intervals. Vertical frame formed;

상기 수직 프레임이 마주보며 놓여지는 제1 기부의 접촉면에 개입되어 수평 프레임을 결합시키는 연결부재;A connecting member which engages with the contact surface of the first base on which the vertical frame faces and engages the horizontal frame;

상기 수직 프레임에 결합될 수 있도록 제2 기부의 양쪽 단부로부터 나란하게 형성되는 제2고정단부가 상기 수평 프레임의 제1고정단부 사이에 형성되는 공간에 삽입되는 폭으로 형성되면서 보울트와 너트 같은 체결구가 체결되는 체결공이 일정한 간격을 두고 연속적으로 형성되어 상기 수평 프레임과 상기 연결부재에 선택적으로 결합되는 수평 프레임; Fasteners, such as bolts and nuts, having a second fixed end formed side by side from both ends of the second base so as to be coupled to the vertical frame and having a width inserted into a space formed between the first fixed end of the horizontal frame. A fastening hole to which the fastening holes are continuously formed at regular intervals and selectively coupled to the horizontal frame and the connection member;

상기 수평 프레임에 결합되기 위하여 보울트와 너트 같은 체결구가 체결되는 체결공이 일정한 간격을 두고 연속적으로 형성되어 상기 수평 프레임에 결합되는 지지부재;A support member coupled to the horizontal frame by successively forming fastening holes for fastening fasteners such as bolts and nuts to be coupled to the horizontal frame at regular intervals;

상기 지지부재에 고정되어 단열재를 충진하기 위한 거푸집을 형성하면서 상부에 단열재가 투입되는 공간을 형성하는 외장재를 포함하는 것을 특징으로 한다.
It is fixed to the support member characterized in that it comprises a housing for forming a form for filling the heat insulating material to form a space in which the heat insulating material is put in the upper portion.

이와 같은 본 발명의 단열구조를 구비하는 모듈화된 이동식 건축물은 수직 프레임과 수평 프레임 및 지지부재가 장방형, 정방형, 또는 기타 의도하는 형상으로 되는 격자상의 프레임 구조를 이루면서 외장재에 의하여 단열재가 충진되는 공간을 형성하게 되고, 상기 공간에 후속적으로 충진되는 단열재에 의하여 일체로 모듈화된 건축 구조물을 제공한다.
The modular mobile building having a heat insulating structure according to the present invention has a lattice frame structure in which the vertical frame, the horizontal frame, and the supporting member have a rectangular, square, or other intended shape, and the space filled with the heat insulating material by the exterior material. It provides a building structure that is integrally modular by a heat insulating material that is formed and subsequently filled in the space.

본 발명에 의하여 내부 단열구조로서 세라믹, 황토 및 폴리우레탄과 같은 기포성 합성수지로 되는 단열구조가 일체로 형성된 모듈화된 건축 구조물은 공장에서 이동 가능하게 완성된 건축물로 제공되면서, 뛰어난 기밀성에 의한 단열성과 만족할 수 있는 강도를 가진다.According to the present invention, a modular building structure in which a heat insulating structure made of a foamable synthetic resin such as ceramic, ocher and polyurethane as an internal heat insulating structure is integrally provided as a completed building to be movable in a factory, satisfying heat insulating property due to excellent airtightness. Has the strength to

또한 각 모듈들을 제작하고 현장에 운반한 다음 현장에서 조립 시공을 하였던 종래의 모듈화 건축물과는 달리 단열 구조와 전기시설, 냉난방용 배관 및 상하수도용 배관을 포함하는 각종 시설물이 완비되어 완성된 모듈화 구조의 건축물을 단지 현장에 공급하여 내려놓기만 하면 되므로 현장에서의 조립 시공 작업이 필요 없게 되어 건축 시간이 단축되고, 위험한 작업 여건이 줄어들어 안전성이 높아지며, 건설비용을 절감할 수 있게 된다.
In addition, unlike the conventional modular building that manufactured and transported each module to the site and then assembled and assembled on site, the modular structure of the completed modular structure is fully equipped with various facilities including insulation structure, electric facility, heating and cooling pipe, and water and sewage pipe. As the building only needs to be supplied to the site, it is not necessary to assemble and perform construction work on site, which shortens the construction time, reduces dangerous working conditions, increases safety, and reduces construction cost.

도 1은 본 발명 실시예의 공정순서를 나타낸 순서도
도 2는 본 발명 실시예의 프레임 구조를 나타낸 사시도
도 3은 본 발명 실시예에서 프레임 구조의 일부를 분해한 사시도
도 4는 본 발명 실시예의 단면도
도 5는 도 3의 A부 확대도
도 6은 도 3의 A부가 조립된 상태의 평단면도
도 7은 도 3의 B부 확대도
도 8은 도 3의 B부가 조립된 상태의 평단면도
도 9는 본 발명의 실시예에서 단열재가 충진된 상태를 나타낸 단면도
도 10은 본 발명의 실시예에서 기초 콘크리트가 시공된 상태를 나타낸 단면도
1 is a flow chart showing the process sequence of the embodiment of the present invention
Figure 2 is a perspective view showing a frame structure of the embodiment of the present invention
Figure 3 is an exploded perspective view of a part of the frame structure in the embodiment of the present invention
4 is a cross-sectional view of an embodiment of the present invention.
5 is an enlarged view of a portion A of FIG.
FIG. 6 is a cross-sectional plan view of a state in which the portion A of FIG. 3 is assembled.
7 is an enlarged view of a portion B of FIG.
8 is a cross-sectional plan view of the assembled state B of FIG.
Figure 9 is a cross-sectional view showing a state in which the insulation is filled in an embodiment of the present invention
10 is a cross-sectional view showing a state in which the concrete foundation in the embodiment of the present invention

본 발명의 특징과 장점은 첨부된 도면에 의하여 설명되는 실시예에 의하여 더욱 명확하게 될 것이다. The features and advantages of the present invention will become more apparent from the embodiments described by the accompanying drawings.

다음에서 본 발명의 실시예를 설명한다.Hereinafter, embodiments of the present invention will be described.

본 발명의 단열 구조를 구비하는 모듈화된 이동식 건축물은 단열 구조를 구비하는 모듈화된 이동식 건축물의 제조 방법은 도 1에서 보는 바와 같이 단열재 투입구과 단열재 배출공이 구비된 수평 프레임과 수직 프레임 및 지지부재를 이용하여 의도하는 건축물 형상으로 되는 모듈 구조체의 골조를 설치하는 제1단계(S1);Modular portable building having a heat insulating structure of the present invention is a method of manufacturing a modular mobile building having a heat insulating structure as shown in Figure 1 using a horizontal frame and a vertical frame and a support member provided with a heat insulating material inlet and a heat insulating material discharge hole A first step (S1) of installing a framework of a modular structure having an intended building shape;

설치된 골조에 마감재에 의하여 창문과 출입문이 설치되는 공간 구조를 구비하는 외벽과 슬래브 및 바닥을 설치하는 제2단계(S2); A second step (S2) of installing an outer wall, a slab, and a floor having a space structure in which windows and doors are installed by finishing materials in the installed framework;

모듈 구조체에 전기 배선과 상하수도 및 냉난방 시설을 하기 위한 배관설비를 시공하는 제3단계(S3);A third step (S3) of constructing plumbing equipment for electric wiring and water and sewage and heating and cooling facilities in the module structure;

앞서 시공된 외벽과 슬래브 및 바닥 연결부의 틈새를 밀폐시키는 시일링 작업을 수행하는 제4단계(S4);A fourth step (S4) of performing a sealing operation for sealing a gap between the outer wall, the slab, and the bottom connection part, which has been previously constructed;

시일링 작업이 완료된 모듈 구조체에 단열재 투입구을 통하여 단열재를 주입하는 제5단계(S5);A fifth step (S5) of insulating the insulating material through the insulating material inlet to the module structure in which the sealing operation is completed;

모듈 구조체에 주입된 단열재를 응고시키는 제6단계(S6);A sixth step (S6) of solidifying the insulating material injected into the module structure;

단열재가 응고된 모듈 구조체에 창문과 출입문을 시공하는 제7단계(S7)에 의하여 구현된다.
Insulating material is implemented by the seventh step (S7) for constructing the windows and doors to the solidified module structure.

제1단계(S1)에 따라 설치되는 모듈 구조체를 도 2에 나타내고 있다. 모듈 구조체는 다양한 크기로 제작될 수 있으며, 도 2에 예시된 모듈 구조체는 본 발명에 의하여 구현될 수 있는 다양한 형태 중에서 하나의 일례를 보여주는 것이다.The module structure installed in accordance with the first step S1 is shown in FIG. The module structure may be manufactured in various sizes, and the module structure illustrated in FIG. 2 illustrates one example of various forms that may be implemented by the present invention.

이 도면에서 참조되는 바와 같이 본 발명에 따르는 단열 구조를 구비하는 모듈화된 이동식 건축물의 모듈 구조체는 수직 프레임(1), 수평 프레임(2), 연결부재(3), 지지부재(4), 외장재(5) 및 단열재(6)로 구성된다.As referred to in this figure, the modular structure of a modular mobile building having an insulating structure according to the present invention is a vertical frame (1), horizontal frame (2), connecting member (3), support member (4), exterior material ( 5) and heat insulating material (6).

상기한 각각의 구성 요소들은 완성되는 건축물의 규모에 따르는 크기로 직접 제조되거나, 기성품으로부터 절단되어 사용된다. Each of the above components is either manufactured directly to a size that corresponds to the scale of the finished building, or cut from a ready-made product.

도 3 및 도 4는 수직 프레임(1), 수평 프레임(2), 연결부재(3), 지지부재(4), 외장재(5)가 결합되는 관계를 나타낸 도면이다.3 and 4 are views illustrating a relationship in which the vertical frame 1, the horizontal frame 2, the connection member 3, the support member 4, and the exterior member 5 are coupled to each other.

이 도면에서 참조되는 바와 같이 수직 프레임(1)은 제1기부(10)의 양쪽 단부로부터 나란하게 형성되는 고정단부(11)가 형성되면서 보울트(100)와 너트(101) 같은 체결구가 체결되는 체결공(12,13)이 제1기부(10)와 고정단부(11)에 일정한 간격을 두고 연속적으로 형성되어 있다.
As referred to in this figure, the vertical frame 1 is formed with a fixed end 11 formed side by side from both ends of the first base 10 is fastened to the fasteners such as the bolt 100 and the nut 101 The fastening holes 12 and 13 are continuously formed at regular intervals on the first base 10 and the fixed end 11.

수평 프레임(2)은 상기 수직 프레임(1)에 결합될 수 있도록 기부(20)의 양쪽 단부로부터 나란하게 형성되는 고정단부(21)가 상기 수평 프레임(1)의 고정단부(11) 사이에 형성되는 공간에 삽입되는 폭으로 형성되면서 보울트(100a)와 너트(101a) 같은 체결구가 체결되는 체결공(22,23)이 기부(20)와 고정단부(21)에 일정한 간격을 두고 연속적으로 형성되어 있다. 이러한 구조에 의하여 수평 프레임(2)은 상기 수직 프레임(1)과 연결부재(3)에 선택적으로 결합될 수 있게 된다.
The horizontal frame 2 has a fixed end portion 21 formed side by side from both ends of the base 20 so as to be coupled to the vertical frame 1 between the fixed end portions 11 of the horizontal frame 1. The fastening holes 22 and 23 to which the fasteners, such as the bolt 100a and the nut 101a, are fastened while being formed to have a width inserted into the space, are continuously formed at regular intervals at the base 20 and the fixed end portion 21. It is. By this structure, the horizontal frame 2 can be selectively coupled to the vertical frame 1 and the connecting member (3).

연결부재(3)는 체결공(30)이 형성되어 상기 수직 프레임(1)이 한 쌍으로 조합되어 마주보며 놓여지는 기부(10) 사이의 공간에 개입되어 수평 프레임(2)을 결합시킬 수 있게 된다.
The connecting member 3 has a fastening hole 30 formed therein so that the vertical frame 1 can be engaged in a space between the bases 10 on which the vertical frames 1 are combined to face each other so as to engage the horizontal frame 2. do.

도 5 내지 도 8은 수직 프레임(1)과 수평 프레임(2)이 결합되는 부위의 일부를 확대한 사시도와 단면도를 각각 나타내고 있다.5 to 8 show an enlarged perspective view and a cross-sectional view of a part of the portion where the vertical frame 1 and the horizontal frame 2 are coupled, respectively.

여기서 도 5 및 도 6은 모서리부(A)의 결합 상태를 보여주고 있다.5 and 6 show the coupling state of the corner portion (A).

이 도면들을 참조하여 상기한 수직 프레임(1)과 수평 프레임(2)이 연결부재(3)에 의하여 결합되는 상태를 구체적으로 설명하면, 2개가 1조가 되어 수직 방향으로 입설되는 수직 프레임(1,1a)는 기부(10)가 서로 마주보는 상태에서 양쪽 기부(10) 사이의 공간에 연결부재(3)가 개입되어 체결공(12,30)을 관통하는 보울트(100)와 이 보울트(100)에 체결되는 너트(101)에 의하여 양쪽의 수직 프레임(1,1a)과 연결부재(3)가 결합된다.The state in which the vertical frame 1 and the horizontal frame 2 are coupled to each other by the connecting member 3 will be described in detail with reference to the drawings. 1a) the bolt 100 and the bolt 100 penetrating the fastening holes 12 and 30 through the connecting member 3 in the space between the two base 10 in the state that the base 10 is facing each other. Both vertical frames 1 and 1a and the connecting member 3 are coupled to each other by a nut 101 fastened thereto.

이때 연결부재(3)의 한쪽편은 수직 프레임(1,1a)의 측면으로 노출되는데, 이렇게 노출되는 연결부재(3)의 단부(C)에는 수평 프레임(2,2a)의 체결공(22)과 연결부재(3)의 체결공(30)에 보울트(100a)와 너트(101a)가 체결된다.At this time, one side of the connecting member (3) is exposed to the side of the vertical frame (1, 1a), the end of the connection member (3) exposed so that the fastening hole 22 of the horizontal frame (2, 2a) The bolt 100a and the nut 101a are fastened to the fastening hole 30 of the connection member 3.

즉, 수평 프레임(2)은 2개가 1조로 되어 기부(20)가 마주보는 상태에서 양쪽 기부(20) 사이의 공간에 노출된 연결부재(3)의 단부(C)가 개입되어 체결공(22,30)을 관통하는 보울트(100a)와 이 보울트(100a)에 체결되는 너트(101a)에 의하여 양쪽의 수평 프레임(2)과 연결부재(3)가 결합됨으로써, 연결부재(3)를 매개체로 하여 수직 프레임(1)과 수평 프레임(2)이 결합되는 상태를 유지하게 된다. That is, two horizontal frames 2 are formed in one set, and the end C of the connecting member 3 exposed in the space between the two bases 20 in the state where the bases 20 face each other is interposed with the fastening hole 22. The horizontal frame 2 and the connecting member 3 are coupled to each other by the bolt 100a penetrating through the 30 and the nut 101a fastened to the bolt 100a, thereby connecting the connecting member 3 to the medium. Thus, the vertical frame 1 and the horizontal frame 2 are maintained in a coupled state.

한편 수평 프레임(2b)는 수직 프레임(1a)의 고정단부(11) 사이의 공간에 삽입되어 보울트(100b)와 너트(101b)에 의하여 체결된다.
Meanwhile, the horizontal frame 2b is inserted into the space between the fixed ends 11 of the vertical frame 1a and fastened by the bolt 100b and the nut 101b.

도 7 및 도 8은 벽체부(B)의 결합 상태를 보여주고 있다.7 and 8 show the coupling state of the wall portion (B).

이 도면들을 참조하여 상기한 수직 프레임(1)과 수평 프레임(2)이 연결부재(3)에 의하여 결합되는 상태를 구체적으로 설명하면, 2개가 1조가 되어 수직 방향으로 입설되는 수직 프레임(1b,1c)는 기부(10)가 서로 마주보는 상태에서 양쪽 기부(10) 사이의 공간에 연결부재(3a)가 개입되어 체결공(12,30)을 관통하는 보울트(100b)와 이 보울트(100b)에 체결되는 너트(101b)에 의하여 양쪽의 수직 프레임(1b,1c)과 연결부재(3a)가 결합된다.The state in which the vertical frame 1 and the horizontal frame 2 are coupled to each other by the connecting member 3 will be described in detail with reference to the drawings. 1c is the bolt 100b and the bolt 100b penetrating the fastening holes 12 and 30 through the connecting member 3a in the space between the two bases 10 while the base 10 faces each other. Both vertical frames 1b and 1c and the connecting member 3a are coupled to each other by a nut 101b fastened thereto.

이때 연결부재(3a)의 한쪽편은 수직 프레임(1b,1c)의 측면으로 노출되는데, 이렇게 노출되는 연결부재(3a)의 단부(D)에는 수평 프레임(2c,2d)의 체결공(22)과 연결부재(3a)의 체결공(30)에 보울트(100c)와 너트(101c)가 체결된다.At this time, one side of the connecting member (3a) is exposed to the side of the vertical frame (1b, 1c), the fastening hole 22 of the horizontal frame (2c, 2d) to the end (D) of the connecting member (3a) is exposed in this way The bolt 100c and the nut 101c are fastened to the fastening hole 30 of the connection member 3a.

즉, 수평 프레임(2b,2c)은 2개가 1조로 되어 기부(20)가 마주보는 상태에서 양쪽 기부(20) 사이의 공간에 노출된 연결부재(3a)의 단부(D)가 개입되어 체결공(22,30)을 관통하는 보울트(100c)와 이 보울트(100c)에 체결되는 너트(101c)에 의하여 양쪽의 수평 프레임(2b,2c)과 연결부재(3a)가 결합됨으로써, 연결부재(3a)를 매개체로 하여 수직 프레임(1b,1c)과 수평 프레임(2c,2d)이 결합되는 상태를 유지하게 된다.That is, two horizontal frames (2b, 2c) is a set of two fastening holes through the end (D) of the connecting member (3a) exposed to the space between the two base 20 in the state that the base 20 is facing each other Both horizontal frames 2b and 2c and the connecting member 3a are joined by the bolt 100c penetrating the 22 and 30 and the nut 101c fastened to the bolt 100c, thereby connecting the connecting member 3a. ), The vertical frames 1b and 1c and the horizontal frames 2c and 2d are coupled to each other.

한편 수직 프레임(1b,1c)의 고정단부(11) 사이의 공간에는 수평 프레임(2d,2e)이 삽입되어 체결공(13,23)을 관통하는 보울트(100d)와 이 보울트(100d)에 체결되는 너트(101d)에 의하여 수직 프레임(1b,1c)와 수평 프레임(2d,2e)이 결합된다. <제1단계, S1>On the other hand, in the space between the fixed ends 11 of the vertical frames 1b and 1c, horizontal frames 2d and 2e are inserted and fastened to the bolt 100d and the bolt 100d passing through the fastening holes 13 and 23. The vertical frame 1b, 1c and the horizontal frame 2d, 2e are coupled by the nut 101d. <Step 1, S1>

이러한 프레임 구조는 수직 프레임(1,1a,1b,1c)이 건축물의 모서리 부위와 모서리 부위 사이에서 적정한 간격을 두고 설치되면서, 수평 프레임(2,2a,2b,2c,2d,2e)이 수직 프레임(1,1a,1b,1c)의 기립 조건을 유지하면서 지붕의 형상을 가지는 골조를 완성할 수 있게 된다.This frame structure is a vertical frame (1, 1a, 1b, 1c) is installed at an appropriate interval between the corner portion and the corner portion of the building, the horizontal frame (2, 2a, 2b, 2c, 2d, 2e) is a vertical frame It is possible to complete a frame having a roof shape while maintaining the standing conditions of (1, 1a, 1b, 1c).

수평 프레임(2)은 통상적인 프레임 구조와 같이 적정한 간격을 두고 다단계로 설치되어 창문틀과 출입문 등을 구성할 수 있게 된다.
The horizontal frame 2 is installed in multiple stages at appropriate intervals as in a conventional frame structure, so that the window frame and the door can be configured.

지지부재(4)는 기부(40)의 양쪽 단부로부터 나란하게 형성되는 연장부(41)와 상기 연장부(41)로부터 기부(40)와 나란한 방향으로 절곡되어 형성되는 고정단부(42)가 형성되어 있다.The support member 4 is formed with an extended portion 41 formed side by side from both ends of the base 40 and a fixed end portion 42 formed by bending in a direction parallel to the base 40 from the extended portion 41. It is.

상기 기부(40)에는 외장재(5)를 고정시키기 위하여 나사(102)와 같은 체결구가 체결되는 체결공(43)이 일정한 간격을 두고 연속적으로 형성되어 고, 고정단부(42)에는 상기 수직 프레임(1)과 수평 프레임(2)에 결합될 수 있도록 보울트(100c)와 너트(101c)와 같은 체결구가 체결되는 체결공(44)이 일정한 간격을 두고 연속적으로 형성되어 있다.In the base 40, fastening holes 43 to which fasteners, such as screws 102 are fastened, are continuously formed at regular intervals in order to fix the exterior material 5, and the fixed end 42 has the vertical frame. Fastening holes 44 to which fasteners such as bolts 100c and nuts 101c are fastened so as to be coupled to (1) and the horizontal frame 2 are continuously formed at regular intervals.

이러한 지지부재(4)는 수직 프레임(1)의 고정단부(11)사이에 삽입되어 보울트(100d)와 너트(101d)로 체결되는 고정편(7)에 양쪽 단부가 보울트(100e)와 너트(101e)로 고정되어 벽면을 구성하는 외장재(5)를 설치할 수 있게 된다.The support member 4 is inserted between the fixed end 11 of the vertical frame 1, and both ends thereof are fixed to the bolt 100d and the nut 101d, and the bolt 100e and the nut ( It is possible to install the exterior member 5 which is fixed to 101e) and constitutes the wall surface.

도면에 도시된 예에서는 벽체를 구성하는 지지부재(4)가 수평 상태로 고정되는 것을 나타내었으나, 수직 상태로 고정될 수도 있음은 물론이다.In the example illustrated in the drawings, the supporting member 4 constituting the wall is fixed in a horizontal state, but may also be fixed in a vertical state.

또한 지지부재(4)는 수평 프레임(2)의 상부와 하부에서 고정단부(21)의 체결공(23)에 보울트와 너트로 고정되어 바닥과 슬래브를 구성하는 외장재(5)를 설치할 수 있게 된다.
In addition, the support member 4 is fixed to the fastening hole 23 of the fixed end portion 21 in the upper and lower portions of the horizontal frame (2) by bolts and nuts to be able to install the exterior material (5) constituting the floor and the slab. .

외장재(5)는 수직 프레임(1)에 고정되는 지지부재(4)의 기부(40)에 형성되어 있는 있는 체결공(43)에 나사(102)로 고정되어 벽체를 구성하고, 수평 프레임(2)에 고정되는 지지부재(4)에 형성되어 있는 체결공(43)에 나사(102a)로 고정되어 바닥과 슬래브를 구성할 수 있게 된다.The exterior material 5 is fixed to the fastening hole 43 formed in the base 40 of the support member 4 fixed to the vertical frame 1 by screws 102 to form a wall, and the horizontal frame 2 The screw 102a is fixed to the fastening hole 43 formed in the support member 4 which is fixed to the bottom surface, and thus the floor and the slab can be configured.

외장재(6)는 상기 지지부재(4)에 고정되어 단열재(6)를 충진하기 위한 거푸집을 형성하게 되고, 상부에는 단열재(5)가 투입되는 투입구(50)를 형성한다. <제2단계, S2>The exterior member 6 is fixed to the support member 4 to form a mold for filling the thermal insulator 6, and forms an inlet 50 through which the thermal insulator 5 is inserted. <Step 2, S2>

이렇게 외장재(5)의 설치가 완료되면 상하수도 및 공기조화 설비를 포함한 각종 배관 공사와 전기 배선 공사가 이루어진다. When the installation of the exterior material 5 is completed in this way, various plumbing and electrical wiring works including water and sewage and air conditioning facilities are performed.

이러한 시설물 공사는 도면에 도시되지는 아니하였지만 외장재(5)가 설치된 공간 내부에서 각각의 시설 구조물에 적합하게 마련되는 고정수단에 의하여 결합된다.<제3단계, S3>
Although not shown in the drawings, such facility construction is combined by fixing means that are suitably provided for each facility structure in the space in which the exterior material 5 is installed.

배관 및 배선 설비가 완료된 모듈 구조체에는 외장재(5)에 의하여 형성되는 내부 공간에 단열재(6)가 투입되는데, 단열재(6)의 누출을 방지하기 위하여 단열재(6)를 투입하기 전에 시일링 공사를 수행하게 된다.Insulating material 6 is injected into the inner space formed by the exterior material 5 in the modular structure in which the piping and wiring facilities are completed. In order to prevent leakage of the insulating material 6, sealing work is performed before the thermal insulation material 6 is introduced. Will perform.

시일링 공사는 외장재(5)가 접촉하는 사이의 공간과 수직 프레임(1)과 수평 프레임(2)의 단부에 삽입되는 마감캡(8)과의 틈새에 대하여 이루어진다.<제4단계, S4>
The sealing construction is made with respect to the space between the contact of the exterior material 5 and the clearance between the vertical frame 1 and the finishing cap 8 inserted into the end of the horizontal frame 2. <Fourth Step, S4>

시일링이 이루어진 모듈 구조체는 상부에 형성되어 있는 투입구(50)를 통하여 단열재(6)가 투입된다. <제5단계, S5> In the module structure in which the sealing is made, the heat insulating material 6 is injected through the inlet 50 formed on the upper portion. <Step 5, S5>

단열재(6)는 볏짚, 스티로폴 알갱이와 같은 다공체가 혼합된 황토, 콘크리트, 경량 기포 콘크리트, 기타 세라믹 재료, 바람직하게는 발포 우레탄이 적용될 수 있다.The heat insulating material 6 may be applied ocher, concrete, lightweight foamed concrete, other ceramic materials, preferably foamed urethane, in which porous bodies such as rice straw and styropol grains are mixed.

투입되는 단열재(6)는 외장재(5)가 형성하는 공간 내에서 수직 프레임(1)과 수평 프레임(2) 사이의 공간과 단열재 배출공의 역할을 하는 체결공(12,13,22,23,30,44)을 통하여 외장재(5)가 형성하는 공간 내부에 고르게 분포될 수 있다.The insulator 6 to be injected is a space between the vertical frame 1 and the horizontal frame 2 and the fastening holes 12, 13, 22, 23, which serve as the insulator discharge holes in the space formed by the exterior member 5. Through the 30, 44 may be evenly distributed in the space formed by the packaging material (5).

단열재(6)가 투입된 모듈 구조체는 오븐, 또는 가열로와 같은 가열수단에 의하여 발포되거나 응고된다.<제6단계, S6> The module structure into which the heat insulating material 6 is injected is foamed or solidified by a heating means such as an oven or a heating furnace.

이와 같은 단열재의 발포 및 응고에 의하여 단열재(6)는 외장재(5)에 의하여 벽체와 바닥 및 천장 슬래브를 이루는 내부 공간을 채우면서 배관 및 배선 설비물 들을 견고하게 고정시키게 된다.By the foaming and solidification of the heat insulating material, the heat insulating material 6 is firmly fixed to the piping and wiring fixtures while filling the internal space constituting the wall and the floor and ceiling slab by the exterior material (5).

발포성 폴리우레탄을 포함하는 단열재는 가격이 저렴하면서도 뛰어난 단열성과 만족할 만한 강도를 가지며 내부 시설물 들이 설치된 상태를 견고하게 유지할 수 있게 되어 시설물들의 고정 작업을 매우 편리하게 수행할 수 있다.Insulation including foamed polyurethane is inexpensive, has excellent insulation and satisfactory strength, and it is possible to maintain the installation of the internal installations firmly, thus making it very convenient to fix the installations.

단열재(6)가 응고되면 투입구(50)를 제거하고, 외부로 새어나와서 노출된 단열재를 절단하여 제거한다. When the heat insulating material 6 is solidified, the inlet 50 is removed and leaks to the outside to cut and remove the exposed heat insulating material.

단열재(6)가 응고된 모듈 구조체는 창문과 출입문을 시공하여 완성되며,<제7단계, S7> 외장재(5)의 표면에는 통상적인 방법과 같이 기타 다양한 형태의 단열재, 또는 마감재를 시공하면 된다.The module structure in which the heat insulating material 6 is solidified is completed by constructing windows and doors. <Seventh Step S7> The surface of the external material 5 may be provided with various types of heat insulating material or finishing materials as usual. .

상기한 모듈 구조체의 제작 과정에서 단열재(6)가 투입되기 전에 도 10에서 보는 바와 같은 콘크리트 구조물(9)에 의한 기초공사가 선택적으로 수행될 수 있다. Before the heat insulator 6 is introduced in the manufacturing process of the module structure, the foundation work by the concrete structure 9 as shown in FIG. 10 may be selectively performed.

이러한 기초공사는 본 발명의 모듈 구조체가 다독 건축물의 형태로 제공될 때에 적합하며, 다층 구조의 건물에 조립식 모듈로 적용될 때에는 생략될 수도 있다.
Such foundation works are suitable when the module structure of the present invention is provided in the form of an extensive building, and may be omitted when applied as a prefabricated module to a multi-storey building.

1 : 수직 프레임 2 : 수평 프레임
3 : 연결부재 4 : 지지부재
5 : 외장재 6 : 단열재
7 : 고정편 8 : 마감캡
9 : 콘크리트 구조물 10 : 기부
11 : 고정단부 12, 13 : 체결공
20 : 기부 21 : 고정단부
22, 23 : 체결공 40 : 기부
41 : 연장부 42 : 고정단부
43, 44 : 체결공
1: vertical frame 2: horizontal frame
3: connecting member 4: supporting member
5: exterior material 6: insulation material
7: fixing piece 8: closing cap
9: concrete structure 10: base
11: fixed end 12, 13: fastening hole
20: donation 21: fixed end
22, 23 fastener 40: donation
41: extension part 42: fixed end
43, 44 fasteners

Claims (5)

단열재 투입구과 단열재 배출공이 구비된 수평 프레임과 수직 프레임및 지지부재를 이용하여 의도하는 건축물 형상으로 되는 모듈 구조체의 골조를 설치하는 제1단계;
상기 제1단계에 의하여 완성된 모듈 구조체의 골조에 마감재에 의하여 창문과 출입문이 설치되는 공간 구조를 구비하는 외벽과 슬래브 및 바닥을 설치하는 제2단계;
상기 제2단계에 의한 모듈 구조체에 전기 배선과 상하수도 및 냉난방 시설을 하기 위한 배관설비를 시공하는 제3단계;
상기 제2단계 및 상기 제3단계에 의하여 시공된 외벽과 슬래브 및 바닥 연결부의 틈새를 밀폐시키는 제4단계;
상기 제4단계에 의한 모듈 구조체에 상기 제1단계에 의하여 형성된 단열재 투입구을 통하여 단열재를 주입하는 제5단계;
상기 제5단계에서 모듈 구조체에 주입된 단열재를 응고시키는 제6단계;
상기 제6단계에 의하여 단열재가 응고된 모듈 구조체에 창문과 출입문을 시공하는 제7단계를 포함하여 이동 가능하게 완성된 건축물로 제공되는 것을 특징으로 하는 단열구조를 구비하는 모듈화된 이동식 건축물의 제조 방법.
A first step of installing a framework of a modular structure having an intended building shape by using a horizontal frame, a vertical frame, and a supporting member provided with an insulation material inlet and an insulation material discharge hole;
A second step of installing an outer wall, a slab, and a floor having a space structure in which windows and doors are installed by finishing materials in the framework of the module structure completed by the first step;
A third step of constructing plumbing facilities for electric wiring, water and sewage, and heating and cooling facilities in the module structure according to the second step;
A fourth step of sealing a gap between the outer wall, the slab, and the bottom connection part constructed by the second and third steps;
A fifth step of injecting the insulating material into the module structure according to the fourth step through the insulating material inlet formed by the first step;
A sixth step of solidifying the insulating material injected into the module structure in the fifth step;
Method of manufacturing a modular mobile building having a thermal insulation structure characterized in that provided in the building completed to be movable, including the seventh step of constructing windows and doors to the module structure in which the insulation is solidified by the sixth step. .
제 1 항에 있어서, 건축물 형상의 골조를 설치하는 제1단계와 단열재를 주입하는 제5단계의 공정 사이에 기초 콘크리트 작업을 더 포함하는 것을 특징으로 하는 단열구조를 구비하는 모듈화된 이동식 건축물의 제조 방법.
2. The method of claim 1, further comprising a foundation concrete work between the first step of installing the framework of the building shape and the fifth step of injecting the insulation. Way.
제 1 항 또는 제 2 항 중 어느 한 항에 있어서, 단열재를 응고시키는 방법이 모듈 구조체를 가열로 내에서 일정 온도 이상으로 가온한 상태에서 이루어지거나 자연 건조 상태로 건조시키는 방법에서 선택되는 것을 특징으로 하는 단열구조를 구비하는 모듈화된 이동식 건축물의 제조 방법.
The method of claim 1, wherein the method of solidifying the heat insulating material is selected from a method in which the module structure is heated in a heating furnace at a predetermined temperature or higher, or dried in a natural dry state. Method of manufacturing a modular mobile building having a thermal insulation structure.
제 1 기부의 양쪽 단부로부터 나란하게 형성되는 제1고정단부에 보울트와 너트 같은 체결구가 체결되는 체결공이 일정한 간격을 두고 연속적으로 형성되는 수직 프레임;
상기 수직 프레임이 마주보며 놓여지는 제1기부의 접촉면에 개입되어 수평 프레임을 결합시키는 연결부재;
상기 수직 프레임에 결합될 수 있도록 제2기부의 양쪽 단부로부터 나란하게 형성되는 제2고정단부가 상기 수평 프레임의 제1고정단부 사이에 형성되는 공간에 삽입되는 폭으로 형성되면서 보울트와 너트 같은 체결구가 체결되는 체결공이 일정한 간격을 두고 연속적으로 형성되어 상기 수평 프레임과 상기 연결부재에 선택적으로 결합되는 수평 프레임;
상기 수평 프레임에 결합되기 위하여 보울트와 너트 같은 체결구가 체결되는 체결공이 일정한 간격을 두고 연속적으로 형성되어 상기 수평 프레임에 결합되는 지지부재;
상기 지지부재에 고정되어 단열재를 충진하기 위한 거푸집을 형성하면서 상부에 단열재가 투입되는 공간을 형성하는 외장재를 포함하는 것을 특징으로 하는 단열구조를 구비하는 모듈화된 이동식 건축물.
A vertical frame in which fastening holes for fastening fasteners, such as bolts and nuts, are fastened to a first fixed end formed side by side from both ends of the first base and are continuously formed at regular intervals;
A connecting member for engaging the horizontal frame through the contact surface of the first base on which the vertical frame is placed facing each other;
Fasteners, such as bolts and nuts, having a second fixed end formed side by side from both ends of the second base so as to be coupled to the vertical frame and inserted into a space formed between the first fixed end of the horizontal frame. A fastening hole to which the fastening holes are continuously formed at regular intervals and selectively coupled to the horizontal frame and the connection member;
A support member coupled to the horizontal frame by successively forming fastening holes for fastening fasteners such as bolts and nuts to be coupled to the horizontal frame at regular intervals;
Modular mobile building having a heat insulating structure, characterized in that it comprises a sheath fixed to the support member to form a form for filling the heat insulating material to form a space into which the heat insulating material is put in the upper portion.
제 4 항에 있어서, 단열재가 발포성 합성 중합체, 세라믹, 황토에서 선택되는 어느 하나인 것을 특징으로 하는 단열구조를 구비하는 모듈화된 이동식 건축물.5. The modular mobile building of claim 4 wherein the thermal insulator is any one selected from foamable synthetic polymers, ceramics, and loess.
KR1020110000461A 2011-01-04 2011-01-04 Manufacturing method of modular mobile buildings with insulation structure and mobile buildings using them KR20120079259A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110000461A KR20120079259A (en) 2011-01-04 2011-01-04 Manufacturing method of modular mobile buildings with insulation structure and mobile buildings using them

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110000461A KR20120079259A (en) 2011-01-04 2011-01-04 Manufacturing method of modular mobile buildings with insulation structure and mobile buildings using them

Publications (1)

Publication Number Publication Date
KR20120079259A true KR20120079259A (en) 2012-07-12

Family

ID=46712264

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110000461A KR20120079259A (en) 2011-01-04 2011-01-04 Manufacturing method of modular mobile buildings with insulation structure and mobile buildings using them

Country Status (1)

Country Link
KR (1) KR20120079259A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016093578A1 (en) * 2014-12-11 2016-06-16 (주)세이크 Diy (do-it-yourself) house using cube-shaped blocks, and method of constructing same
KR20190085023A (en) * 2016-11-15 2019-07-17 베르크 아인스 게엠베하 Manufacture of residential block and insulation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016093578A1 (en) * 2014-12-11 2016-06-16 (주)세이크 Diy (do-it-yourself) house using cube-shaped blocks, and method of constructing same
KR20160071154A (en) * 2014-12-11 2016-06-21 (주) 세이크 A self-assembly house building it myself using block of cube type and thereof construction method
KR20190085023A (en) * 2016-11-15 2019-07-17 베르크 아인스 게엠베하 Manufacture of residential block and insulation

Similar Documents

Publication Publication Date Title
US9151053B2 (en) Modular building panel with frame
CA2832991C (en) System for forming an insulated concrete thermal mass wall
US4813193A (en) Modular building panel
US4674250A (en) Modular building panel
US10724228B2 (en) Building assemblies and methods for constructing a building using pre-assembled floor-ceiling panels and walls
US20100024323A1 (en) Energy Saving House
US9797137B2 (en) Fully assembled, fully cast-in-place, composite-type house and construction method thereof
EP3258021A1 (en) Construction module and modular construction system comprising one or more of said construction modules
HU220484B1 (en) Building panel, method of making building panel, building structure foundation member, foundation for building structure, method of securing architectural covering element to a surface formed by a castable material, building structure, multistorey ...
US20140338283A1 (en) House constructed from finished product components and constructing method thereof
EP3889374A1 (en) Method for constructing buildings
US20090113814A1 (en) Monolithic module structure to build constructions and method for its manufacture
EP2175088B1 (en) Method of installation on site of a prefabricated semi-resistant module for construction
EP3971356A1 (en) Sandwich panel and building module
RU2538573C1 (en) Method of prefabricated building construction
AU2013332012B2 (en) Building system, particularly a residential building
US20090049776A1 (en) Stable and efficient building system
KR20120079259A (en) Manufacturing method of modular mobile buildings with insulation structure and mobile buildings using them
US20210396002A1 (en) Modular construction system
CN205171730U (en) Building structure and outer wall body thereof
FI69674B (en) SEAT ATT RESA EN BYGGNAD SAMT ANORDNING FOER UTFOERANDE AV SATTET
CN113550424A (en) Prefabricated building system
CN104631858A (en) Method for mounting prefabricated residence
US20060283119A1 (en) Building unit and method of constructing buildings therewith
KR20090006687U (en) Prefabricated adiabatic panel

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application