CN103899133A - 一种变电站用固定式可伸缩安全围栏 - Google Patents

一种变电站用固定式可伸缩安全围栏 Download PDF

Info

Publication number
CN103899133A
CN103899133A CN201410138316.7A CN201410138316A CN103899133A CN 103899133 A CN103899133 A CN 103899133A CN 201410138316 A CN201410138316 A CN 201410138316A CN 103899133 A CN103899133 A CN 103899133A
Authority
CN
China
Prior art keywords
fence
turning cylinder
safety
transformer station
safety fence
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410138316.7A
Other languages
English (en)
Inventor
张继龙
顾凌伟
李开夏
李吉兰
吕广臣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HEGANG POWER SUPPLY COMPANY STATE GRID HEILONGJIANG ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Original Assignee
HEGANG POWER SUPPLY COMPANY STATE GRID HEILONGJIANG ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HEGANG POWER SUPPLY COMPANY STATE GRID HEILONGJIANG ELECTRIC POWER Co Ltd, State Grid Corp of China SGCC filed Critical HEGANG POWER SUPPLY COMPANY STATE GRID HEILONGJIANG ELECTRIC POWER Co Ltd
Priority to CN201410138316.7A priority Critical patent/CN103899133A/zh
Publication of CN103899133A publication Critical patent/CN103899133A/zh
Pending legal-status Critical Current

Links

Images

Abstract

一种变电站用固定式可伸缩安全围栏。本发明属于一种安全围栏,具体涉及一种变电站用固定式可伸缩安全围栏。本发明为解决现有电力检修作业时,运维人员布置现场安全措施的工作量大,效率低,且很难达到规范化和标准化,容易出现安全漏洞,威胁人身安全的问题。一种变电站用固定式可伸缩安全围栏包括可伸缩式围栏桩和旋转式围栏,可伸缩式围栏桩是由多节直径从小到大的中空杆套叠构成,底节中空杆竖直插装在地面,顶节中空杆的顶端设有围栏杆头,围栏杆头的两侧分别各设有一个围栏网挂钩,旋转式围栏包括转动轴、围栏网和预埋管,围栏网卷绕在转动轴上,转动轴的底端竖直插装在预埋管内。本发明主要用于电力检修作业。

Description

一种变电站用固定式可伸缩安全围栏
技术领域
本发明涉及一种安全围栏,具体涉及一种变电站用固定式可伸缩安全围栏。
背景技术
随着“三集五大”改革的深入,各供电公司的变电站,包括大中型的220千伏变电站均实现了无人值班。这些变电站往往电场面积都很大,部分大中型变电站电场总面积达到10000平方米以上,有检修作业时,运维人员布置现场安全措施的工作量非常大,据实际统计某变电站布置电场内“I段母线检修作业”的安全措施,4名运维人员需工作2-2.5小时,收措施需1小左右,由于运行人员使用的大都是移动式的,现布置、现搬运,不但费时、费力,而且布置的措施很难达到规范化和标准化,同时还容易出现安全漏洞,威胁作业人员的人身安全。
另外,各供电公司的运维站都存在人员不足的情况,比如,一个巡维站往往负责几个或十几个变电站,每班5-6个人,当多座变电站现场有作业时,加之设备异常时有发生,经常出现人员不足的情况,影响安全生产工作的顺利开展。
发明内容
本发明为解决现有电力检修作业时,运维人员布置现场安全措施的工作量大,效率低,且很难达到规范化和标准化,容易出现安全漏洞,威胁人身安全的问题,进而提出一种变电站用固定式可伸缩安全围栏。
本发明为解决上述问题采取技术方案是:本发明包括可伸缩式围栏桩和旋转式围栏,可伸缩式围栏桩是由多节直径从小到大的中空杆套叠构成,底节中空杆竖直插装在地面,顶节中空杆的顶端设有围栏杆头,围栏杆头的两侧分别各设有一个围栏网挂钩,旋转式围栏包括转动轴、围栏网和预埋管,围栏网的末端与转动轴固接,围栏网卷绕在转动轴上,转动轴的两端分别设有上挡板和下挡板,预埋管竖直插装在地面,转动轴的底端竖直插装在预埋管内,预埋管上转动轴的末端位置设有定位销。
本发明的有益效果是:本发明可以有效提高变电站作业时现场安全措施布置的标准化与规范化,降低变电站各项检修作业的安全风险,同时不用频繁搬运围栏,从而极大地减轻了巡维人员在安全措施布置工作中的劳动强度和工作量,工作效率提高90%以上。
附图说明
图1是本发明可伸缩式围栏桩1和旋转式围栏2的连接示意图;图2是可伸缩式围栏桩1的结构示意图;图3是旋转式围栏2的结构示意图;图4是可伸缩式围栏桩1和旋转式围栏2的布置示意图;图5是电路检修时可伸缩式围栏桩1和旋转式围栏2的连接示意图。
具体实施方式
具体实施方式一:如图1-5所示,本实施方式所述一种变电站用固定式可伸缩安全围栏包括可伸缩式围栏桩1和旋转式围栏2,可伸缩式围栏桩1是由多节直径从小到大的中空杆套叠构成,底节中空杆1-1竖直插装在地面,顶节中空杆1-2的顶端设有围栏杆头1-3,围栏杆头1-3的两侧分别各设有一个围栏网挂钩1-4,旋转式围栏2包括转动轴2-1、围栏网2-2和预埋管2-3,围栏网2-2的末端与转动轴2-1固接,围栏网2-2卷绕在转动轴2-1上,转动轴2-1的两端分别设有上挡板2-5和下挡板2-6,预埋管2-3竖直插装在地面,转动轴2-1的底端竖直插装在预埋管2-3内,预埋管2-3上转动轴2-1的末端位置设有定位销2-4。
如此设计可伸缩式围栏桩1由多节绝缘材料制成,不用时缩回地面,缩回地面时,仅留围栏杆头1-3在地面上,距地面8cm-10cm,使用时从地面拉出,可伸缩式围栏桩1的高度为80cm-90cm,在围栏杆头1-3的两侧分别各设有一个围栏网挂钩1-4,用于挂围栏网,开口较小设计,可防止围栏脱出;围栏网2-2可设计成15米、20米或25米三种,使用时可以拉出,不用时可以旋转收回。
具体实施方式二:如图1-5所示,本实施方式所述上挡板2-5通过紧固螺栓2-7与转动轴2-1固接,上挡板2-5上沿轴向方向设有锁止销2-8。其它组成和连接关系与具体实施方式一相同。如此设计在拉出围栏网2-2时,先将紧固螺栓2-7旋开,根据需要将围栏网2-2拉出任意长度,然后旋紧紧固螺栓2-7,将剩余围栏网2-2固定,通过锁止销2-8将围栏网2-2定位。
具体实施方式三:如图1-5所示,本实施方式所述可伸缩式围栏桩1是绝缘材料制作的可伸缩式围栏桩1。其它组成和连接关系与具体实施方式一相同。
具体实施方式四:如图1-5所示,本实施方式所述旋转式围栏2的外侧设有防护罩2-9。其它组成和连接关系与具体实施方式一相同。如此设计可以将围栏网2-2有效的进行防护,防止围栏网长年日晒雨淋,延长使用寿命。
具体实施方式五:如图1-5所示,本实施方式所述防护罩2-9是绝缘材料制作的防护罩2-9。其它组成和连接关系与具体实施方式四相同。
工作原理
如图4和5所示,在电场内合理布置可伸缩式围栏桩和旋转式围栏的位置,每个间隔设有4个围栏、12个围栏桩,一般在每个间隔的入口处和间隔内的两台设备之间,便于两台设备用围栏网分隔,在确定好的位置上挖深40cm-50cm、边长为20cm-30cm的坑,用混凝土将旋转式围栏的预埋管与可伸缩式围栏桩固定其中。当开关检修作业时,打开围栏网,将需要检修作业的甲I刀闸及开关与其设备隔离,从而将作业区与带电区分隔开,此项安全措施布置,两名运维人员可以轻松在几分钟内完成。

Claims (5)

1.一种变电站用固定式可伸缩安全围栏,其特征在于:所述一种变电站用固定式可伸缩安全围栏包括可伸缩式围栏桩(1)和旋转式围栏(2),可伸缩式围栏桩(1)是由多节直径从小到大的中空杆套叠构成,底节中空杆(1-1)竖直插装在地面,顶节中空杆(1-2)的顶端设有围栏杆头(1-3),围栏杆头(1-3)的两侧分别各设有一个围栏网挂钩(1-4),旋转式围栏(2)包括转动轴(2-1)、围栏网(2-2)和预埋管(2-3),围栏网(2-2)的末端与转动轴(2-1)固接,围栏网(2-2)卷绕在转动轴(2-1)上,转动轴(2-1)的两端分别设有上挡板(2-5)和下挡板(2-6),预埋管(2-3)竖直插装在地面,转动轴(2-1)的底端竖直插装在预埋管(2-3)内,预埋管(2-3)上转动轴(2-1)的末端位置设有定位销(2-4)。
2.根据权利要求1所述一种变电站用固定式可伸缩安全围栏,其特征在于:所述上挡板(2-5)通过紧固螺栓(2-7)与转动轴(2-1)固接,上挡板(2-5)上沿轴向方向设有锁止销(2-8)。
3.根据权利要求1所述一种变电站用固定式可伸缩安全围栏,其特征在于:所述可伸缩式围栏桩(1)是绝缘材料制作的可伸缩式围栏桩(1)。
4.根据权利要求1所述一种变电站用固定式可伸缩安全围栏,其特征在于:所述旋转式围栏(2)的外侧设有防护罩(2-9)。
5.根据权利要求4所述一种变电站用固定式可伸缩安全围栏,其特征在于:所述防护罩(2-9)是绝缘材料制作的防护罩(2-9)。
CN201410138316.7A 2014-04-08 2014-04-08 一种变电站用固定式可伸缩安全围栏 Pending CN103899133A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410138316.7A CN103899133A (zh) 2014-04-08 2014-04-08 一种变电站用固定式可伸缩安全围栏

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410138316.7A CN103899133A (zh) 2014-04-08 2014-04-08 一种变电站用固定式可伸缩安全围栏

Publications (1)

Publication Number Publication Date
CN103899133A true CN103899133A (zh) 2014-07-02

Family

ID=50990682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410138316.7A Pending CN103899133A (zh) 2014-04-08 2014-04-08 一种变电站用固定式可伸缩安全围栏

Country Status (1)

Country Link
CN (1) CN103899133A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401280A (zh) * 2016-10-18 2017-02-15 成都绿迪科技有限公司 建筑施工隔离护栏
CN107313357A (zh) * 2017-08-30 2017-11-03 云南工程建设总承包公司 一种桥梁上部施工安全防护栏
CN110107146A (zh) * 2019-05-24 2019-08-09 国家电网有限公司 变电站便接式围栏网
CN110439357A (zh) * 2019-07-26 2019-11-12 国网江苏省电力有限公司灌南县供电分公司 一种变电站固定升降式安全围栏网架装置
CN110670947A (zh) * 2019-11-19 2020-01-10 国网四川省电力公司凉山供电公司 一种预埋式围栏杆及其安装方法
CN115370231A (zh) * 2022-08-02 2022-11-22 广西电网有限责任公司北海供电局 一种用收高效的安全围栏及其使用方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050098770A1 (en) * 2003-11-08 2005-05-12 Schell Ronald A. Retractable safety net barricade
CN2931746Y (zh) * 2006-07-26 2007-08-08 郑州绪鑫电力装备有限公司 旋转开启式安全围网
CN203129705U (zh) * 2012-12-12 2013-08-14 刘洪超 固定式伸缩防护围栏
CN203296467U (zh) * 2013-04-18 2013-11-20 国家电网公司 预埋式安全围网伸缩插杆
CN203452455U (zh) * 2013-09-03 2014-02-26 国家电网公司 一种围网收纳杆
CN203755793U (zh) * 2014-04-08 2014-08-06 国家电网公司 一种变电站用固定式可伸缩安全围栏

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050098770A1 (en) * 2003-11-08 2005-05-12 Schell Ronald A. Retractable safety net barricade
CN2931746Y (zh) * 2006-07-26 2007-08-08 郑州绪鑫电力装备有限公司 旋转开启式安全围网
CN203129705U (zh) * 2012-12-12 2013-08-14 刘洪超 固定式伸缩防护围栏
CN203296467U (zh) * 2013-04-18 2013-11-20 国家电网公司 预埋式安全围网伸缩插杆
CN203452455U (zh) * 2013-09-03 2014-02-26 国家电网公司 一种围网收纳杆
CN203755793U (zh) * 2014-04-08 2014-08-06 国家电网公司 一种变电站用固定式可伸缩安全围栏

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401280A (zh) * 2016-10-18 2017-02-15 成都绿迪科技有限公司 建筑施工隔离护栏
CN107313357A (zh) * 2017-08-30 2017-11-03 云南工程建设总承包公司 一种桥梁上部施工安全防护栏
CN110107146A (zh) * 2019-05-24 2019-08-09 国家电网有限公司 变电站便接式围栏网
CN110439357A (zh) * 2019-07-26 2019-11-12 国网江苏省电力有限公司灌南县供电分公司 一种变电站固定升降式安全围栏网架装置
CN110670947A (zh) * 2019-11-19 2020-01-10 国网四川省电力公司凉山供电公司 一种预埋式围栏杆及其安装方法
CN115370231A (zh) * 2022-08-02 2022-11-22 广西电网有限责任公司北海供电局 一种用收高效的安全围栏及其使用方法

Similar Documents

Publication Publication Date Title
CN103899133A (zh) 一种变电站用固定式可伸缩安全围栏
CN107965201B (zh) 带闭锁功能的可控安全围网
CN208010043U (zh) 带闭锁功能的可控安全围网
CN104265067B (zh) 多功能安全围栏
CN201635487U (zh) 绝缘式安全围栏
CN203755793U (zh) 一种变电站用固定式可伸缩安全围栏
CN103613032B (zh) 变电站可移动式电缆盖板起重小车
CN206707400U (zh) 一种变电站安全围栏装置
CN201883761U (zh) 变电站室内标准化安全围栏
CN204186137U (zh) 多功能安全围栏
CN203654877U (zh) 一种变压器护栏
CN203593574U (zh) 变电站可移动式电缆盖板起重小车
CN205046943U (zh) 预埋式检修安全警示伸缩围栏
CN210316809U (zh) 一种红外线感应报警电力作业围栏
CN201959439U (zh) 绝缘安全带挂杆
CN203574322U (zh) 铁道信号控制电缆分向盒
CN203977994U (zh) 安全警示遮拦
CN206942319U (zh) 一种适用于室内变配电站使用的快速围网
CN206672738U (zh) 一种油浸式变压器安全防护机构
CN213573367U (zh) 一种风电场箱变安全防护围栏
CN204840723U (zh) 变压器维修用安全带悬挂装置
CN201867436U (zh) 综合配电防窃电电能计量箱
CN206053414U (zh) 建筑施工用配电箱防护棚
CN205421081U (zh) 一种伸缩地杆
CN203867258U (zh) 一种110kV格构式复合材料杆塔

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140702