CN103870657A - Method for achieving steel structure pre-assembling through computer simulation - Google Patents

Method for achieving steel structure pre-assembling through computer simulation Download PDF

Info

Publication number
CN103870657A
CN103870657A CN201410120659.0A CN201410120659A CN103870657A CN 103870657 A CN103870657 A CN 103870657A CN 201410120659 A CN201410120659 A CN 201410120659A CN 103870657 A CN103870657 A CN 103870657A
Authority
CN
China
Prior art keywords
theoretical
assembling
steel construction
dimensional coordinate
steel structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410120659.0A
Other languages
Chinese (zh)
Inventor
南东亚
刘鹏
侯兆新
吴明超
陈水荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central Research Institute of Building and Construction Co Ltd MCC Group
Original Assignee
Central Research Institute of Building and Construction Co Ltd MCC Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central Research Institute of Building and Construction Co Ltd MCC Group filed Critical Central Research Institute of Building and Construction Co Ltd MCC Group
Priority to CN201410120659.0A priority Critical patent/CN103870657A/en
Publication of CN103870657A publication Critical patent/CN103870657A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a method for achieving steel structure pre-assembling through computer simulation. The method includes the following steps: (1) obtaining assembled components according to a steel structure detail drawing model, and automatically compiling component splicing numbers, (2) extracting feature information of the assembled components in the detail drawing model, calculating actual coordinates of the assembled components according to extracted features, generating theoretical measurement and control point three-dimensional coordinates of the components, and automatically naming the numbers, (3) according to the theoretical measurement and control point numbers, positioning and marking the solid components, (4) conducting three-dimensional coordinate measurement on positioning marks through a three-dimensional coordinate measuring instrument, and obtaining actual measurement three-dimensional coordinates of positioning points, and (5) conducting contrastive analysis on theoretical coordinates and the actual measurement coordinates of control points, and providing a rectification report or a pre-assembling examining report according to national steel structure manufacturing technical regulations and technological requirements, the rectification report or the pre-assembling examining report serves as an evidence of the quality control link. The method has the advantages that the theoretical control points are intelligently and automatically generated, errors caused by manually drawing up the theoretical control points can be greatly reduced, and the machining and production efficiency is high.

Description

A kind of pre-assembled operating automation method of steel construction
Technical field
The present invention relates to the pre-assembling technique of steel construction field, relate in particular to a kind of pre-assembled operating automation method of steel construction.
Background technology
At present, in the pre-assembled field of steel construction, utilize computing machine to simulate preframed method and remain semi-artificial method.Two kinds of current methods, all cannot scale promote, and its drawback is:
(1) adopt the method based on laser scanning.Member in kind is formed to grating (point cloud model), grating is manually converted to solid model on computers, then compares with the model in computing machine, labor workload is huge, inefficiency, and human error is large.(2) method that adopts finger prosthesis to determine measuring control point.Artificial appointment reference mark in computing machine, then, with actual measurement contrast, same labor workload is very large, causes the situation of leak source, marked erroneous a lot, directly causes producing overstocked, inefficiency.
Summary of the invention
The object of this invention is to provide a kind of pre-assembled operating automation method of steel construction, to overcome currently available technology above shortcomings.
The object of the invention is to be achieved through the following technical solutions:
A kind of pre-assembled operating automation method of steel construction, comprises the following steps:
(1) according to three-dimensional steel construction detail drawing Software Create steel construction detail drawing model, obtain assembling members, and Organizational Parts splicing is numbered automatically;
(2) structure feature information of assembling members in detail drawing model is extracted, according to the feature of extracting, in database, search for the reference mark information of individual features needs and calculate its actual coordinate, finally generating the theoretical measuring control point three-dimensional coordinate of each member, and be automatically numbered;
(3) according to theoretical measuring control point numbering, the member corresponding site in kind producing is positioned to mark;
(4) utilize three-dimensional coordinate measuring instrument, each telltale mark is carried out to three-dimensional coordinate measurement, obtain each anchor point actual measurement three-dimensional coordinate; And
(5) by the theoretical coordinate at each reference mark and Measured Coordinates contrast and error statistics, analyze according to national manufacture of steel structure technical regulation and technological requirement etc., if find not tolerance, according to its orientation, modification report is proposed automatically, if all qualified, generate corresponding pre-assembled examining report, as the authority of Quality Control Links.
Further, in step (2), described structure feature information comprises cross-sectional geometry, connected mode and Type of Welding.
Further, described measuring control point detects by measuring control point intelligence generation software.
Preferably, described three-dimensional steel construction detail drawing software is Tekla Structures.
Preferably, described three-dimensional coordinate measuring instrument is total powerstation.
Beneficial effect of the present invention is: adopt the pre-assembled operating automation method of steel construction generating based on measuring control point intelligence.It can be according to the assembled feature of each assembling members, in database, search for the reference mark information of individual features needs and calculate its actual coordinate, automatically generative theory reference mark, contrast fast with actual measurement reference mark, complete fast and accurately the error-detecting of pre-assembled needs, improve detection efficiency and speed of production comprehensively.
Accompanying drawing explanation
With reference to the accompanying drawings the present invention is described in further detail below.
Fig. 1 is the process flow diagram of a kind of pre-assembled operating automation method of steel construction described in the embodiment of the present invention;
Fig. 2 is the structural representation of beam two ends described in the embodiment of the present invention and the splicing of post rigidity;
Fig. 3 is the splice point structure enlarged drawing of beam two ends described in the embodiment of the present invention and the splicing of post rigidity;
Fig. 4 is the position view of 16 measuring control points on the beam described in the embodiment of the present invention.
In figure:
1-16: measuring control point; 17, splice point; 18, beam; 19, post.
Embodiment
As Figure 1-4, be example by the be rigidly connected pre-assembled detection of central sill of beam column, illustrate the pre-assembled operating automation method of steel construction generating based on measuring control point intelligence of the present invention, specifically comprise the following steps:
(1) in three-dimensional steel construction detail drawing software Tekla Structures, design three-dimensional model: beam two ends and the splicing of post rigidity, post 19 is H type cross section with beam 18, web adopts high-strength bolt to connect, and the upper and lower edge of a wing adopts the groove welding of partial penetration, and this splice point 17 is shown in Fig. 2-3;
(2) measuring control point intelligence generates software and detects the H type cross section that the assembled section in beam left side is beam;
(3) according to the bolted feature in H type cross section, in database, searching for H type cross section bolt connects the reference mark information needing and is: four of left and right of top flange lower surface angle point (is shown in Fig. 41, 2 and 9, 10), four of left and right of lower flange lower surface angle point (is shown in Fig. 43, 4 and 11, 12), the home position of arranging up and down bolt hole in web surface (is supposed every web totally 4 centers of circle here, see in Fig. 45, 6, 7, 8 and 13, 14, 15, 16), and take out the computing formula of respective points, the height in the length of substitution beam and H type cross section, the information such as width are calculated its actual coordinate, like this, measuring control point intelligence generates software and just automatically calculates beam left side and beam right side totally 16 measuring control points,
(4) totally 16 measuring control points are carried out to automatic numbering, from 1-16, the three-dimensional coordinate calculating together with step (3), is kept at respectively connected node database and beam database;
(5) beam in kind factory being produced according to its numbering, reads orientation numbering and the coordinate of 8 points of 8 points and right sides in left side from database, and on beam in kind, mark is carried out in relevant position, totally 16 gauge points;
(6) utilize three-dimensional coordinate detecting instrument (total powerstation), 16 points are carried out to coordinate measurement;
(7), to the measured value of above-mentioned 16 with theoretical value contrasts and error statistics, according to manufacture of steel structure technical manual, to tolerance not, according to its orientation, modification report is proposed automatically;
(8) if all qualified, generate pre-assembled detection return on qualification, as this testing result, submit quality control department to.
The present invention directly extracts steel structure member from three-dimensional model, the features such as how much of member sections having according to these members, connection, welding, according to these features, in database, search for the reference mark information of individual features needs and calculate its actual coordinate, analyze judgement and reasonably detect reference mark, greatly shortened whole pre-assembled testing process.Adopt computer intelligence processing, reduced the error that artificial participation causes, greatly improved pre-assembled detection efficiency; Improve detection efficiency, solved the bottleneck of the production efficiency that manual intervention causes, can carry out large-scale promotion in the pre-assembled field of steel construction.
The present invention is not limited to above-mentioned preferred forms; anyone can draw other various forms of products under enlightenment of the present invention; no matter but do any variation in its shape or structure; every have identical with a application or akin technical scheme, within all dropping on protection scope of the present invention.

Claims (5)

1. the pre-assembled operating automation method of steel construction, is characterized in that, comprises the following steps:
(1) according to three-dimensional steel construction detail drawing Software Create steel construction detail drawing model, obtain assembling members, and Organizational Parts splicing is numbered automatically;
(2) structure feature information of assembling members in detail drawing model is extracted, according to the feature of extracting, in database, search for the reference mark information of individual features needs and calculate its actual coordinate, finally generating the theoretical measuring control point three-dimensional coordinate of each member, and be automatically numbered;
(3) according to theoretical measuring control point numbering, the member corresponding site in kind producing is positioned to mark;
(4) utilize three-dimensional coordinate measuring instrument, each telltale mark is carried out to three-dimensional coordinate measurement, obtain each anchor point actual measurement three-dimensional coordinate; And
(5) by the theoretical coordinate at each reference mark and Measured Coordinates contrast and error statistics, analyze according to national manufacture of steel structure technical regulation and technological requirement etc., if find not tolerance, according to its orientation, modification report is proposed automatically, if all qualified, generate corresponding pre-assembled examining report, as the authority of Quality Control Links.
2. the pre-assembled operating automation method of a kind of steel construction according to claim 1, is characterized in that: in step (2), described structure feature information comprises cross-sectional geometry, connected mode and Type of Welding.
3. the pre-assembled operating automation method of a kind of steel construction according to claim 2, is characterized in that: described measuring control point generates software by measuring control point intelligence and detects.
4. a kind of steel structure assembling operating automation method according to claim 3, is characterized in that: described three-dimensional steel construction detail drawing software is Tekla Structures.
5. a kind of steel structure assembling operating automation method according to claim 4, is characterized in that: described three-dimensional coordinate measuring instrument is total powerstation.
CN201410120659.0A 2014-03-27 2014-03-27 Method for achieving steel structure pre-assembling through computer simulation Pending CN103870657A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410120659.0A CN103870657A (en) 2014-03-27 2014-03-27 Method for achieving steel structure pre-assembling through computer simulation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410120659.0A CN103870657A (en) 2014-03-27 2014-03-27 Method for achieving steel structure pre-assembling through computer simulation

Publications (1)

Publication Number Publication Date
CN103870657A true CN103870657A (en) 2014-06-18

Family

ID=50909184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410120659.0A Pending CN103870657A (en) 2014-03-27 2014-03-27 Method for achieving steel structure pre-assembling through computer simulation

Country Status (1)

Country Link
CN (1) CN103870657A (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104376168A (en) * 2014-11-17 2015-02-25 博迈科海洋工程股份有限公司 Steel structure module characteristic information extracting and assembling method based on Tekla platform
CN104376185A (en) * 2014-12-02 2015-02-25 天津博迈科海洋工程有限公司 Large module welding quality tracking method based on Tekla software platform
CN104376170A (en) * 2014-11-17 2015-02-25 天津博迈科海洋工程有限公司 Large module welding visualization method based on Tekla software platform
CN104679516A (en) * 2015-03-10 2015-06-03 浙江精工钢结构集团有限公司 Virtual pre-assembly algorithm based on VB (visual basic) plug-in and application
CN105678464A (en) * 2016-01-13 2016-06-15 上海振华重工(集团)股份有限公司 Welding information management method
CN106354950A (en) * 2016-08-31 2017-01-25 华中科技大学 Steel structure pre-splicing method and system
CN106524902A (en) * 2016-08-31 2017-03-22 江苏中铁山桥重工有限公司 Real-time monitoring and measuring method for truss segment
CN106705848A (en) * 2017-01-20 2017-05-24 中冶建筑研究总院有限公司 Ball-link steel structure grid frame reverse modeling method
CN106844960A (en) * 2017-01-20 2017-06-13 中冶建筑研究总院有限公司 A kind of method of the reverse modeling of tubular weldment steel structure net rack
CN106971031A (en) * 2017-03-15 2017-07-21 上海森松制药设备工程有限公司 A kind of module assembled fit detecting system and method
CN107273607A (en) * 2017-06-13 2017-10-20 北京工业大学 A kind of steel-structure factory building pre-assembly method based on BIM
CN107784643A (en) * 2016-08-26 2018-03-09 上海宝冶集团有限公司 Pre-assembly method is digitized based on the steel construction with target 3-D scanning
CN109059889A (en) * 2018-10-26 2018-12-21 佛山市保利来建材实业有限公司 A kind of application method of total station in the processing of deformed steel structure
CN110512877A (en) * 2019-08-30 2019-11-29 中国二十二冶集团有限公司 Beam string installation detection control method
CN110515350A (en) * 2019-08-13 2019-11-29 北京城建道桥建设集团有限公司 The group's anchor centering of one population hole and error theory analysis method
CN111311735A (en) * 2020-02-26 2020-06-19 江南造船(集团)有限责任公司 Ship piping system welding line data management method and device, readable storage medium and terminal
CN112302171A (en) * 2020-10-28 2021-02-02 山东方大杭萧钢构科技有限公司 Steel structure pre-assembly method
CN113111464A (en) * 2021-04-21 2021-07-13 中交第三公路工程局有限公司工程总承包分公司 Steel arch bridge virtual pre-assembly method based on digital model

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104376170B (en) * 2014-11-17 2017-12-26 天津博迈科海洋工程有限公司 Heavy die block welding method for visualizing based on Tekla software platforms
CN104376170A (en) * 2014-11-17 2015-02-25 天津博迈科海洋工程有限公司 Large module welding visualization method based on Tekla software platform
CN104376168A (en) * 2014-11-17 2015-02-25 博迈科海洋工程股份有限公司 Steel structure module characteristic information extracting and assembling method based on Tekla platform
CN104376185A (en) * 2014-12-02 2015-02-25 天津博迈科海洋工程有限公司 Large module welding quality tracking method based on Tekla software platform
CN104679516A (en) * 2015-03-10 2015-06-03 浙江精工钢结构集团有限公司 Virtual pre-assembly algorithm based on VB (visual basic) plug-in and application
CN104679516B (en) * 2015-03-10 2018-02-06 浙江精工钢结构集团有限公司 A kind of virtual preassembling algorithm and application based on VB plug-in units
CN105678464A (en) * 2016-01-13 2016-06-15 上海振华重工(集团)股份有限公司 Welding information management method
CN107784643A (en) * 2016-08-26 2018-03-09 上海宝冶集团有限公司 Pre-assembly method is digitized based on the steel construction with target 3-D scanning
CN106524902A (en) * 2016-08-31 2017-03-22 江苏中铁山桥重工有限公司 Real-time monitoring and measuring method for truss segment
CN106354950B (en) * 2016-08-31 2020-02-21 华中科技大学 Steel structure pre-assembly method and system
CN106354950A (en) * 2016-08-31 2017-01-25 华中科技大学 Steel structure pre-splicing method and system
CN106844960A (en) * 2017-01-20 2017-06-13 中冶建筑研究总院有限公司 A kind of method of the reverse modeling of tubular weldment steel structure net rack
CN106705848A (en) * 2017-01-20 2017-05-24 中冶建筑研究总院有限公司 Ball-link steel structure grid frame reverse modeling method
CN106705848B (en) * 2017-01-20 2019-05-31 中冶建筑研究总院有限公司 A kind of method that ball chain connects the reverse modeling of steel structure net rack
CN106844960B (en) * 2017-01-20 2019-07-09 中冶建筑研究总院有限公司 A kind of method of the reverse modeling of tubular weldment steel structure net rack
CN106971031A (en) * 2017-03-15 2017-07-21 上海森松制药设备工程有限公司 A kind of module assembled fit detecting system and method
CN107273607A (en) * 2017-06-13 2017-10-20 北京工业大学 A kind of steel-structure factory building pre-assembly method based on BIM
CN109059889A (en) * 2018-10-26 2018-12-21 佛山市保利来建材实业有限公司 A kind of application method of total station in the processing of deformed steel structure
CN110515350B (en) * 2019-08-13 2020-10-16 北京城建道桥建设集团有限公司 Group hole group anchor centering and error theoretical analysis method
CN110515350A (en) * 2019-08-13 2019-11-29 北京城建道桥建设集团有限公司 The group's anchor centering of one population hole and error theory analysis method
CN110512877A (en) * 2019-08-30 2019-11-29 中国二十二冶集团有限公司 Beam string installation detection control method
CN111311735A (en) * 2020-02-26 2020-06-19 江南造船(集团)有限责任公司 Ship piping system welding line data management method and device, readable storage medium and terminal
CN111311735B (en) * 2020-02-26 2023-07-14 江南造船(集团)有限责任公司 Ship piping weld data management method and device, readable storage medium and terminal
CN112302171A (en) * 2020-10-28 2021-02-02 山东方大杭萧钢构科技有限公司 Steel structure pre-assembly method
CN112302171B (en) * 2020-10-28 2021-09-21 山东方大杭萧钢构科技有限公司 Steel structure pre-assembly method
CN113111464A (en) * 2021-04-21 2021-07-13 中交第三公路工程局有限公司工程总承包分公司 Steel arch bridge virtual pre-assembly method based on digital model

Similar Documents

Publication Publication Date Title
CN103870657A (en) Method for achieving steel structure pre-assembling through computer simulation
CN108388146B (en) Three-dimensional assembly process design system based on information physical fusion and operation method
CN111145236A (en) Product quasi-physical assembly model generation method based on digital twinning and implementation framework
CN109117602A (en) Large scale covering digitizing detection method based on laser tracker
CN104778488B (en) Steel building site based on BIM
CN111691679B (en) Digital twinning-based intelligent tensioning method for prestressed steel structure
CN103177149A (en) Steel structure welding deformation analytical method
CN107545080B (en) Steel bridge virtual pre-assembly method based on BIM model
CN106078359B (en) A kind of zero definition of more main shaft drilling building-block machines of planer-type and scaling method
CN111581804B (en) Method for generating minimum part repair scheme based on actual measurement model
CN101890638A (en) Assembling system of complex structural member
CN109145471A (en) Virtual assembly system and method based on CAD Yu the co-melting model of measured data
CN103522126A (en) Precise locating method for automatic assembly hole making
CN104006756A (en) Method for rapidly measuring deformation of assembled aircraft web part
CN104764415A (en) Steel bridge structure three-dimensional measurement and detection system and measurement method
CN106247931A (en) Guidance method is revised by the variance analysis of a kind of large complicated deformed steel member and factory
CN106647631A (en) Gantry hole making machine tool machining collision detection analysis method
CN114493549A (en) Building engineering cost evaluation management system based on big data analysis
CN104182569A (en) Three-dimensional visible simulation method for product error accumulation
CN117807659A (en) Building structure defect detection and correction method and system
CN105651202A (en) Three-dimensional scanning method and device used for measuring volume of mine
CN106248000B (en) The measurement method of part axially bored line
CN103324779B (en) Method for measuring plate incremental forming limit diagram
CN110222370B (en) Nuclear power station three-dimensional model repair control unit, system and method
CN104061897B (en) Large split type nut column coplanarity detection method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination