CN103869213A - Power line electrical on-off testing device - Google Patents

Power line electrical on-off testing device Download PDF

Info

Publication number
CN103869213A
CN103869213A CN201410127059.7A CN201410127059A CN103869213A CN 103869213 A CN103869213 A CN 103869213A CN 201410127059 A CN201410127059 A CN 201410127059A CN 103869213 A CN103869213 A CN 103869213A
Authority
CN
China
Prior art keywords
power lead
operational amplifier
power line
circuit
electric
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410127059.7A
Other languages
Chinese (zh)
Other versions
CN103869213B (en
Inventor
姜清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huizhou Pu'an Electronics Co ltd
Original Assignee
Changzhou Vocational Institute of Mechatronic Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changzhou Vocational Institute of Mechatronic Technology filed Critical Changzhou Vocational Institute of Mechatronic Technology
Priority to CN201410127059.7A priority Critical patent/CN103869213B/en
Publication of CN103869213A publication Critical patent/CN103869213A/en
Application granted granted Critical
Publication of CN103869213B publication Critical patent/CN103869213B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Measurement Of Current Or Voltage (AREA)

Abstract

The invention relates to a power line electrical on-off testing device, which comprises two operational amplifiers; the non-inverting input end of the first operational amplifier is respectively connected with a resistor and a first capacitor; the three components form a signal generator; a current limiting resistor and two voltage stabilizing tubes are connected between the inverting input end and the output end of the operational amplifier; the non-inverting input end of the second operational amplifier is connected in series with an adjustable resistor and a second capacitor; the power line to be tested is connected between the adjustable resistor and the current limiting resistor; the tested power line and the second capacitor form a proportional voltage division circuit; the output end of the second operational amplifier is connected with a rectifying circuit, and the output end of the rectifying circuit is connected with a voltmeter; the output end of the voltmeter is connected with a time base circuit; the output end of the time base circuit is connected with the two light emitting diodes. The invention adopts the basic principle that the capacitance exists between the two parallel leads, can test the on-off condition of the power line only by testing the power line plug, and is quick and convenient.

Description

The electric on off test device of a kind of power lead
Technical field
The present invention relates to a kind of proving installation, especially a kind of device of quick test power lead break-make.
Background technology
Power lead is the electric wire of transmission current, must carry out aborning high-potting, insulation measurement, on off test etc.; Conventionally, when testing power supply line break-make, as to run into one end be the plug other end while being wire, conventionally conductor wire end pressed on copper wire scrubbing brush, measures plug end with multimeter; See whether the information such as voltage that multimeter shows judges break-make; As when running into the other end and being a certain connector, with corresponding connector short circuit it, measure plug end with multimeter, this method of testing speed is slower and very inconvenient.
Summary of the invention
The technical problem to be solved in the present invention is: propose a kind of device that can fast detecting power lead break-make.
The technical solution adopted in the present invention is: the electric on off test device of a kind of power lead, comprises two operational amplifiers; Wherein the in-phase input end of the first operational amplifier connects respectively a resistance and the first electric capacity; Described three forms a signal generator; Between inverting input and the output terminal of operational amplifier, be connected with current-limiting resistance and two stabilivolts; The in-phase input end of the second described operational amplifier is in series with an adjustable resistance and the second electric capacity; Between described adjustable resistance and current-limiting resistance, be connected tested power lead; Described tested power lead and the second electric capacity form proportion divider circuit; The output terminal of the second described operational amplifier connects rectification circuit, and rectification circuit output end connects voltage table; The output terminal of described voltage table is connected with time base circuit; The output terminal of described time base circuit connects two light emitting diodes.
Further, two stabilivolts of the present invention are for restricting signal amplitude, and its voltage is 3.0~3.5V.
Because tested power lead often there will be short circuit phenomenon, for anti-voltage table burns, the present invention is provided with a diode between described rectification circuit and voltage table.
Time base circuit of the present invention is 555 time base circuits.
Two operational amplifiers of the present invention be no more than ± 15V of supply voltage, its common mode inhibition is higher.
The invention has the beneficial effects as follows: adopt the ultimate principle that has electric capacity between two parallel wires, only need testing power supply line plug just can test out power lead break-make situation, quick and convenient.
Brief description of the drawings
Below in conjunction with drawings and Examples, the present invention is further described.
Fig. 1 is circuit theory diagrams of the present invention.
Embodiment
The present invention is further detailed explanation with preferred embodiment by reference to the accompanying drawings now.These accompanying drawings are the schematic diagram of simplification, and basic structure of the present invention is only described in a schematic way, and therefore it only shows the formation relevant with the present invention.
As shown in Figure 1, IC1, IC2 adopt the higher operational amplifier of common mode inhibition all can, be no more than ± 15V of supply voltage, IC1 and R1, C1 form the signal generator of a 10KHz, R2 is current-limiting resistance, and DW1-2 is that the stabilivolt of 2 3.3V is for restricting signal amplitude.
P1, P2 connect with black, the red table rod of multimeter respectively, when test, access power lead between them, and power lead is an electric capacity, and it and C2 form proportion divider circuit, and measured signal is carried out linearity by IC2 and amplified after W1 decay.
IC2 output signal is by D1~D4 full-bridge rectification, and gained direct current signal voltage supplied table is read, because tested power lead often there will be short circuit phenomenon, therefore establish D6 in case voltage table burns.
Because needing a stabilization process, voltage table instruction affects test speed, therefore show fast with IC3 time base circuit NE555 again.NE555 is arranged on 3 pin noble potentials (when red) while test, and while having the setting voltage of exceeding signal, 6 pin trigger upset, make 3 pin become electronegative potential (green light).
Before test, first carry out tester debugging:
Select a good power lead, plug is separately fixed on P1, P2, adjustment is located at the W1 on panel, makes red light just be converted to green light, unclamps P1, P2, green light should become red light about 0.5 second, otherwise, adjust R6 or C4, repeat above-mentioned adjustment process, until time delay 0.5 second, then adjusting W2, to make voltage table reading be 4/5 place (4/5FULL) of full scale.
When test:
Select the shortest (standard minus deviation) good power lead (line-transect), plug is separately fixed to P1, P2 upper, adjust the W1 being located on panel, make red light just be converted to green light.When test, the wire connecting on P1, P2 must not lean on too closely, more must not be wound around.Per hour must correction once with line-transect, in case circuit drift causes error.
If power lead is three utmost point power leads, only need be just passable in two pairs of different inserted sheets tests respectively, the power lead that is connector for the other end, point two ends are tested, by that analogy.
If voltage table pointer reaches maximum range, on tested power lead, there is short circuit; If pointer less than still light yellow of 4/5FULL, red light, in tested power lead, may have open circuit or line too short; In other end test, still like this, certainly on tested power lead, there are open circuit or line too short.
Just the specific embodiment of the present invention of describing in above instructions, various not illustrating is construed as limiting flesh and blood of the present invention, person of an ordinary skill in the technical field read after instructions can to before described embodiment make an amendment or be out of shape, and do not deviate from essence of an invention and scope.

Claims (5)

1. the electric on off test device of power lead, is characterized in that: comprise two operational amplifiers; Wherein the in-phase input end of the first operational amplifier connects respectively a resistance and the first electric capacity; Described three forms a signal generator; Between inverting input and the output terminal of operational amplifier, be connected with current-limiting resistance and two stabilivolts;
The in-phase input end of the second described operational amplifier is in series with an adjustable resistance and the second electric capacity; Between described adjustable resistance and current-limiting resistance, be connected tested power lead; Described tested power lead and the second electric capacity form proportion divider circuit;
The output terminal of the second described operational amplifier connects rectification circuit, and rectification circuit output end connects voltage table; The output terminal of described voltage table is connected with time base circuit; The output terminal of described time base circuit connects two light emitting diodes.
2. the electric on off test device of a kind of power lead as claimed in claim 1, is characterized in that: the voltage of two described stabilivolts is 3.0~3.5V.
3. the electric on off test device of a kind of power lead as claimed in claim 1, is characterized in that: between described rectification circuit and voltage table, be provided with a diode.
4. the electric on off test device of a kind of power lead as claimed in claim 1, is characterized in that: described time base circuit is 555 time base circuits.
5. the electric on off test device of a kind of power lead as claimed in claim 1, is characterized in that: two described operational amplifiers be no more than ± 15V of supply voltage.
CN201410127059.7A 2014-03-31 2014-03-31 Power line electrical on-off testing device Active CN103869213B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410127059.7A CN103869213B (en) 2014-03-31 2014-03-31 Power line electrical on-off testing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410127059.7A CN103869213B (en) 2014-03-31 2014-03-31 Power line electrical on-off testing device

Publications (2)

Publication Number Publication Date
CN103869213A true CN103869213A (en) 2014-06-18
CN103869213B CN103869213B (en) 2016-05-04

Family

ID=50907959

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410127059.7A Active CN103869213B (en) 2014-03-31 2014-03-31 Power line electrical on-off testing device

Country Status (1)

Country Link
CN (1) CN103869213B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3800214A (en) * 1972-01-31 1974-03-26 Flynn J O Apparatus for testing energized and non-energized electrical circuits
CN2099982U (en) * 1991-08-10 1992-03-25 南通县水表厂 Multifunctional power supply line detector
CN2529262Y (en) * 2001-06-08 2003-01-01 缪国军 Alarm device for charging line cut-off
JP3817555B2 (en) * 2004-01-19 2006-09-06 株式会社エネゲート Distribution line short circuit detector
CN200965561Y (en) * 2006-11-09 2007-10-24 崔双喜 Power line leakage, broken and short circuit tester
CN102243279A (en) * 2010-04-30 2011-11-16 Ls产电株式会社 Apparatus for monitoring fault current in power system
CN102545178A (en) * 2012-03-02 2012-07-04 哈尔滨理工大学 RS485 line status monitor and monitoring method
CN202633687U (en) * 2012-06-20 2012-12-26 傅碧辉 Comprehensive protection socket
CN203786239U (en) * 2014-03-31 2014-08-20 常州机电职业技术学院 Power line electrical on-off testing device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3800214A (en) * 1972-01-31 1974-03-26 Flynn J O Apparatus for testing energized and non-energized electrical circuits
CN2099982U (en) * 1991-08-10 1992-03-25 南通县水表厂 Multifunctional power supply line detector
CN2529262Y (en) * 2001-06-08 2003-01-01 缪国军 Alarm device for charging line cut-off
JP3817555B2 (en) * 2004-01-19 2006-09-06 株式会社エネゲート Distribution line short circuit detector
CN200965561Y (en) * 2006-11-09 2007-10-24 崔双喜 Power line leakage, broken and short circuit tester
CN102243279A (en) * 2010-04-30 2011-11-16 Ls产电株式会社 Apparatus for monitoring fault current in power system
CN102545178A (en) * 2012-03-02 2012-07-04 哈尔滨理工大学 RS485 line status monitor and monitoring method
CN202633687U (en) * 2012-06-20 2012-12-26 傅碧辉 Comprehensive protection socket
CN203786239U (en) * 2014-03-31 2014-08-20 常州机电职业技术学院 Power line electrical on-off testing device

Also Published As

Publication number Publication date
CN103869213B (en) 2016-05-04

Similar Documents

Publication Publication Date Title
JP2004294437A (en) Electronic battery tester
CN204287245U (en) A kind of power supply ripple test connector
CN203786239U (en) Power line electrical on-off testing device
CN203672961U (en) Broadband 0-200Hz current detection circuit
CN219016553U (en) Three-phase misconnection prevention detection circuit and air conditioner
CN103869213B (en) Power line electrical on-off testing device
CN207380122U (en) MOSFET hourglass source electrode resistance test circuits
TWI418828B (en) Transformer test system
CN208125876U (en) A kind of triode Kelvin test suite
CN106772003A (en) A kind of load switch of transformer test system and method
CN211528540U (en) Portable primary equipment electrical connector contact resistance detection device
TW201443446A (en) Negative voltage detector
CN104111398A (en) Short-circuit detection device
CN103207356A (en) High-voltage lossless dielectric strength tester
CN112485530A (en) System and method for testing resistance value of high-voltage arm of direct-current voltage transformer
CN110895290A (en) Picoampere-level low-current test circuit suitable for ATE test
WO2023026839A1 (en) Impedance measuring device
CN106124865A (en) The measuring method of the capacitance of differential capacitance and device
CN207148277U (en) Optocoupler CTR test devices
CN201845072U (en) Portable wide-range detection device for voltage-regulating value of voltage-regulator tube
CN205786847U (en) There is the watt-hour meter device of optical flare function
JP6608234B2 (en) Contact determination device and measurement device
CN106970267B (en) Measurement method, controller and the control system of conductor insulation against ground resistance
CN203084059U (en) High-voltage testing apparatus based on semiconductor discrete device testing system
CN103293386A (en) Test device and method of insulating resistance

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20181227

Address after: 516032 Third Floor of No. 76 Qiaoxing Road, Tongqiao Town, Huizhou City, Guangdong Province

Patentee after: HUIZHOU PU'AN ELECTRONICS Co.,Ltd.

Address before: 213164 No. 6 Mingxin East Road, Wujin District, Changzhou City, Jiangsu Province

Patentee before: CHANGZHOU VOCATIONAL INSTITUTE OF MECHATRONIC TECHNOLOGY

TR01 Transfer of patent right