CN103825214A - Novel guide rope laying one-pull-seven construction method - Google Patents
Novel guide rope laying one-pull-seven construction method Download PDFInfo
- Publication number
- CN103825214A CN103825214A CN201310474732.XA CN201310474732A CN103825214A CN 103825214 A CN103825214 A CN 103825214A CN 201310474732 A CN201310474732 A CN 201310474732A CN 103825214 A CN103825214 A CN 103825214A
- Authority
- CN
- China
- Prior art keywords
- rope
- rotary connector
- coaster
- ropes
- steel wire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
A novel guide rope laying one-pull-seven construction method relates to a guide rope laying method. At present, the guide rope laying mainly has the disadvantages that back-and-forth traction laying process is tedious; a plurality of high-altitude rope moving is needed in the whole process and the high-altitude construction amount is large; and the process is tedious and is time consuming. The novel guide rope laying one-pull-seven construction method comprises the following step: 1) pulling and laying ropes: a powered parachute aerially lays a [phi]2 Deenyma rope serving as a primary guide rope for construction, and the Deenyma ropes are dragged and laid manually in the order of [phi]2 Deenyma rope-[phi]4 Deenyma rope-[phi]8 Deenyma rope; the ropes are in tension laying in the order of [phi]8 Deenyma rope-[phi] 15 anti-twisting steel wire rope-[phi]25 steel wire rope; during tension laying, a large tractor and two large tension machines are utilized to carry out guide rope one-pull-seven tension laying, wherein one large tension machine lays three ropes and the other large tension machine lays four ropes; and 2) moving plate passing through a pulley and rope branching. With the technical scheme, the labour intensity is low and the construction efficiency is high.
Description
Technical field
The present invention relates to a kind of messenger unfolding method.
Background technology
Along with social progress, the development of power grid construction, also there is variation with rapid changepl. never-ending changes and improvements in transmission line construction.Lead wire and earth wire erection construction, from original artificial unfolding, develops into tension stringing gradually; From artificial spreading guiding rope to passing through the high technology equipment unfolding preliminary Di Nima messengers such as propeller-parachuting, remote control airship, RC Goblin, helicopter, speedboat, new equipment, new technology, a large amount of introducing of new material, for the high new development of transmission line construction is laid a good foundation.
The densely covered region in project of transmitting and converting electricity work transmission line construction passage or the network of waterways or no man's land, high mountain high hill, have inconvenient traffic, and affected by the factor such as landform, traffic larger.If adopt conventional artificial pilot rope laying mode, there is certain difficulty in pull rope unfolding, brings certain difficulty also to the processing of engineering policy simultaneously.For fully reducing the impact of passage in circuit stringing construction, accelerate payingoff speed, current most Poling Constructions all adopt the construction method of the flight equipment pilot rope layings such as propeller-parachuting, make messenger unfolding overall process face sky.
Conventional spreading lead wire and earth wire construction process is as Fig. 2, in construction, guide rope unfolds main existent defect and is: it is loaded down with trivial details that (1) tracts operation back and forth, need to be from original φ 2 enlightening Nima → φ 4 enlightening Nima → φ 8 enlightening Nima → 9 steel wire ropes (or 2 φ 8 enlightening Nimas, rope is moved in high-altitude again) → 15( 13) steel wire rope → 18 steel wire ropes (or 49 steel wire ropes, then rope is moved in high-altitude) → 25( 28) steel wire rope → mono-leads four wires; (2) in whole process, need repeatedly high-altitude to move rope, amount of high-altitude operation is very large; (3) double door releasing pulley quantity required is many; (4) operation is loaded down with trivial details, elapsed time.
Summary of the invention
The technical assignment of the technical problem to be solved in the present invention and proposition is that prior art scheme is improved and improved, and provides new-type messenger unfolding one to lead seven construction methods, to reach the object that improves Poling Construction efficiency.For this reason, the present invention takes following technical scheme.
New-type messenger unfolding one is led seven construction methods, it is characterized in that it comprises the following steps:
1) rope is put in traction
A. propeller-parachuting unfolds φ 2 enlightening Nima ropes in the air as working elementary messenger, and by the order of Φ 2 enlightening Nima rope → Φ 4 enlightening Nima rope → Φ 8 enlightening Nima ropes, manpower traction unfolds Di Nima rope;
B. by the anti-steel wire rope → 25 steel wire rope order showing and placing of the tension of turning round of Ф 8 enlightening Nima rope → 15; When showing and placing of the tension, utilize a large traction machine and two hightension machines to carry out leading seven showing and placing of the tension guide ropes, wherein a hightension machine unfolds 3,4 of another hightension machine unfoldings, totally 7 15 steel wire ropes;
2) coaster and point rope are crossed in limp
A. lead slowly 7 15 guide ropes of traction of seven limps by one, the releasing pulley of 7 corresponding shaft tower one sides of 15 guide ropes is respectively: be arranged in first coaster failing to agree, be positioned at second coaster failing to agree, the 3rd coaster failing to agree under being positioned at, be positioned at the 4th coaster for ground wire unfolding at top, be positioned at the 5th right mutually coaster, be positioned at lower the 6th coaster on the right side mutually, be arranged in the 7th right mutually coaster, first, second, the 3rd, the 4th, the 5th, the 6th, the 7th 7 15 guide ropes corresponding to coaster are respectively first, second, the 3rd, the 4th, the 5th, the 6th, No. seven rope,
B. when limp at a slow speed by middle phase guide rope behind the corresponding about 60-70m of coaster position large traction machine stop, hightension mechanism is moving, controls second, third, the bending resistance of the 4th, the 5th, No. six rope or rotary connector be near near coaster;
C. utilize in advance colligation is good on cross-arm node separately 5 anchoring ropes by second, third, the 4th, the 5th, No. six rope all face anchor; Face anchor line and adopt Ф 13 steel wire covers, length is 20-30m;
D. after facing anchor line and arranging, large traction machine slack rope at a slow speed, first, No. seven rope be according to guide rope sag situation on circuit, operation tensioner slowly reclaims; Note observing coaster place second, No. six rope, avoid second, the 6th rope and first, No. seven rope friction, collision or be wound around;
E. after all anchoring ropes are stressed, stop hauling machine and tensioner, check confirm to face anchor system effectively stressed after, slack rope and first, No. seven rope slowly reclaim at a slow speed to continue operation large traction machine;
F. until limp to approaching after coaster, stop hauling machine and tensioner braking, by second, third, the 4th, the 5th, the 6th, No. seven rope carry after pine, remove successively the rotary connector being connected with limp, then climb over respectively separately and be again connected with limp again after coaster, connect after intact and open tensioner brake, slowly operate large traction machine and draw;
G. anchor line to be faced and 15 guide rope junctions are walked near coaster, suspend traction, by hauling machine and tensioner braking, remove and face anchor system, then continue traction, complete a side messenger unfolding job of a base double.
As the further of technique scheme improved and supplemented, the present invention also comprises following additional technical feature.
Limp comprises trapezoidal body, be located at first rotary connector of body head, be located at seven the second rotary connectors of body bottom, wears 25 steel wire ropes in the first rotary connector; In the second described rotary connector, wear 15 steel wire ropes, seven the second rotary connectors divide two rows to be arranged on the tail end of limp.
Described limp tail end connects the second rotary connector, anti-steel wire cover, moment connection device, anti-steel wire cover, the 3rd rotary connector turned round turned round successively.
The first described rotary connector adopts 250kN rotary connector; The second described rotary connector adopts 50kN or 80kN rotary connector; The 3rd described rotary connector adopts 50kN rotary connector.
With second, the second rotary connector of being connected of the 4th, No. six rope is located at first row, with first, the 3rd, the 5th, No. seven the second rotary connector being connected of restricting be located at second row; The second rotary connector that is positioned at first row adopts 50kN rotary connector; The second rotary connector that is positioned at second row adopts 80kN rotary connector.
Beneficial effect: the technical program adopts one to lead seven construction method for spreading, has greatly alleviated labour intensity, has improved efficiency of construction.Through practice test, it is smooth that coaster is crossed in limp, it is fast that guide rope divides coaster to penetrate, work high above the ground is light, many guide rope unfoldings are without mutual wrapping phenomena, and the guide rope entirety unfolding time shortens greatly, increases work efficiency comparatively obvious, by originally within required 10-12 days, foreshortening to 3-5 days, for similar engineering construction is offered reference.
Accompanying drawing explanation
Fig. 1 is steel tower coaster hanging structure schematic diagram of the present invention.
Fig. 2 is existing construction process figure.
Fig. 3 is construction process figure of the present invention.
Fig. 4 is floor plan of the present invention.
Fig. 5 is that 15 guide ropes of the present invention divide rope schematic diagram.
Fig. 6 is limp connection layout of the present invention.
In figure: first coaster of 1-, second coaster of 2-, the 3rd coaster of 3-, the 4th coaster of 4-, the 5th coaster of 5-, the 6th coaster of 6-, the 7th coaster of 7-; 11-number one rope, No. second rope of 12-, No. three rope of 13-, No. four rope of 14-, No. five rope of 15-, No. six rope of 16-, No. seven rope of 17-; 21-the 3rd rotary connector; The anti-steel wire cover of turning round of 22-; 23-moment connection device; The anti-steel wire cover of turning round of 24-; 25-the second rotary connector; 26-the second rotary connector; 27-the first rotary connector; 28-25 steel wire ropes; 29-limp.
Embodiment
Below in conjunction with Figure of description, technical scheme of the present invention is described in further detail.
As shown in Fig. 1,3,4,5,
The technical program construction method comprises the following steps:
1) rope is put in traction
A. propeller-parachuting unfolds φ 2 enlightening Nima ropes in the air as working elementary messenger, and by the order of Φ 2 enlightening Nima rope → Φ 4 enlightening Nima rope → Φ 8 enlightening Nima ropes, manpower traction unfolds Di Nima rope;
B. by the anti-steel wire rope → 25 steel wire rope 28 order showing and placing of the tension of turning round of Ф 8 enlightening Nima rope → 15; When showing and placing of the tension, utilize a large traction machine and two hightension machines to carry out leading seven showing and placing of the tension guide ropes, wherein a hightension machine unfolds 3,4 of another hightension machine unfoldings, totally 7 15 steel wire ropes;
2) coaster and point rope are crossed in limp 29
A. lead slowly 7 15 guide ropes of traction of seven limps 29 by one, the releasing pulley of 7 corresponding shaft tower one sides of 15 guide ropes is respectively: be arranged in first coaster 1 failing to agree, be positioned at second coaster 2 failing to agree, the 3rd coaster 3 failing to agree under being positioned at, be positioned at the 4th coaster 4 for ground wire unfolding at top, be positioned at the 5th right mutually coaster 5, be positioned at lower the 6th coaster 6 on the right side mutually, be arranged in the 7th right mutually coaster 7, first, second, the 3rd, the 4th, the 5th, the 6th, the 7th takes turns coaster 1, 2, 3, 4, 5, 6, 7 15 guide ropes of 7 correspondences are respectively first, second, the 3rd, the 4th, the 5th, the 6th, No. seven rope 11, 12, 13, 14, 15, 16, 17,
B. when limp 29 at a slow speed by middle phase conductor rope behind the corresponding about 60-70m of coaster position large traction machine stop, hightension mechanism is moving, controls second, third, the bending resistance of the 4th, the 5th, No. six rope 12,13,14,15,16 or rotary connector be near near coaster;
C. utilize in advance colligation is good on cross-arm node separately 5 anchoring ropes by second, third, the 4th, the 5th, No. six rope 12,13,14,15,16 all face anchor; Face anchor line and adopt Ф 13 steel wire covers, length is 20-30m;
D. after facing anchor line and arranging, large traction machine slack rope at a slow speed, first, 11,17, No. seven rope be according to guide rope sag situation on circuit, operation tensioner slowly reclaims; Note observing coaster place second, No. six rope 13,16, avoid second, the 6th rope 13,16 and first, No. seven rope 11,17 friction, collision or winding;
E. after all anchoring ropes are stressed, stop hauling machine and tensioner, check confirm to face anchor system effectively stressed after, slack rope and first, No. seven rope 11,17 slowly reclaim at a slow speed to continue operation large traction machine;
F. until limp 29 to approaching after coaster, stop hauling machine and tensioner braking, by second, third, the 4th, the 5th, the 6th, No. seven rope 12,13,14,15,16,17 carry after pine, remove successively the rotary connector being connected with limp 29, then climb over respectively separately and again couple together with limp 29 again after coaster, connect after intact and open tensioner brake, slowly operate large traction machine and draw;
G. anchor line to be faced and 15 guide rope junctions are walked near coaster, suspend traction, by hauling machine and tensioner braking, remove and face anchor system, then continue traction, complete a side messenger unfolding job of a base double.
As shown in Figure 6, limp 29 comprise trapezoidal body, be located at body head first rotary connector 27, be located in seven the second rotary connector 25,26, the first rotary connectors 27 of body bottom and wear 25 steel wire ropes 28; In the second described rotary connector 25,26, wear 15 steel wire ropes, 25,26 points of two rows of seven the second rotary connectors are arranged on the tail end of limp 29.Described limp 29 tail ends connect the second rotary connector 25,26, anti-steel wire cover 24,5t bending resistance part 23, anti-steel wire cover 22, the 3rd rotary connector 21 turned round of 30m* 15 turned round of 40m* 15 successively.Wherein, the first rotary connector 27 adopts 250kn rotary connector; The second described rotary connector 25,26 adopts 50kN or 80kN rotary connector; The 3rd described rotary connector adopts 50kN rotary connector; With second, the 4th, No. six rope 12,14,16 the second rotary connectors 26 that are connected are located at first row, with first, the 3rd, the 5th, No. seven 11,13,15,17 the second rotary connectors 25 that are connected of restricting are located at second row; The second rotary connector 26 that is positioned at first row adopts 50kN rotary connector; The second rotary connector 25 that is positioned at second row adopts 80kN rotary connector.
It is instantiations of the present invention that new-type messenger unfolding one shown in above Fig. 1,3,4,5,6 is led seven construction methods; substantive distinguishing features of the present invention and progress are embodied; can be according to actual use needs; under enlightenment of the present invention; it is carried out to the equivalent modifications of the aspects such as shape, structure, all at the row of the protection range of this programme.
Claims (5)
1. new-type messenger unfolding one is led seven construction methods, it is characterized in that it comprises the following steps:
1) rope is put in traction
A. propeller-parachuting unfolds φ 2 enlightening Nima ropes in the air as working elementary messenger, and by the order of Φ 2 enlightening Nima rope → Φ 4 enlightening Nima rope → Φ 8 enlightening Nima ropes, manpower traction unfolds Di Nima rope;
B. by anti-steel wire rope → 25 steel wire ropes (28) order showing and placing of the tension of turning round of Ф 8 enlightening Nima rope → 15; When showing and placing of the tension, utilize a large traction machine and two hightension machines to carry out leading seven showing and placing of the tension guide ropes, wherein a hightension machine unfolds 3,4 of another hightension machine unfoldings, totally 7 15 steel wire ropes;
2) coaster and point rope are crossed in limp
A. lead slowly 7 15 guide ropes of traction of seven limps by one, the releasing pulley of 7 corresponding shaft tower one sides of 15 guide ropes is respectively: be arranged in first coaster (1) failing to agree, be positioned at second coaster (2) failing to agree, the 3rd coaster (3) failing to agree under being positioned at, be positioned at the 4th coaster (4) for ground wire unfolding at top, be positioned at right mutually the 5th coaster (5), be positioned at lower the 6th coaster (6) on the right side mutually, be arranged in right mutually the 7th coaster (7), first, second, the 3rd, the 4th, the 5th, the 6th, the 7th coaster (1, 2, 3, 4, 5, 6, 7) 7 corresponding 15 guide ropes are respectively first, second, the 3rd, the 4th, the 5th, the 6th, No. seven rope (11, 12, 13, 14, 15, 16, 17),
B. when limp at a slow speed by middle phase guide rope behind the corresponding about 60-70m of coaster position large traction machine shut down, hightension mechanism is moving, controls second, third, the bending resistance of the 4th, the 5th, No. six rope (12,13,14,15,16) or rotary connector be near near coaster;
C. utilize in advance colligation is good on cross-arm node separately 5 anchoring ropes by second, third, the 4th, the 5th, No. six rope (12,13,14,15,16) all face anchor; Face anchor line and adopt Ф 13 steel wire covers, length is 20-30m;
D. after facing anchor line and arranging, large traction machine slack rope at a slow speed, first, No. seven rope (11,17) be according to guide rope sag situation on circuit, operation tensioner slowly reclaims; Note observing coaster place second, No. six rope (12,16), avoid second, the 6th rope (12,16) and first, No. seven rope (11,17) friction, collision or winding;
E. after all anchoring ropes are stressed, stop hauling machine and tensioner, check confirm to face anchor system effectively stressed after, continue operation large traction machine slack rope at a slow speed, and slowly reclaim first, No. seven rope (11,17);
F. until limp to approaching after coaster, stop hauling machine and tensioner braking, by second, third, the 4th, the 5th, the 6th, No. seven rope ((11,12,13,14,15,16,17)) carry after pine, remove successively the rotary connector being connected with limp, then climb over respectively separately and be again connected with limp again after coaster, connect after intact and open tensioner brake, slowly operate large traction machine and draw;
G. draw near coaster time wait facing anchor line and 15 guide rope tie points, suspend traction, by hauling machine and tensioner braking, remove and face anchor system, then continue traction, complete a side messenger unfolding job of a base double.
2. new-type messenger unfolding one according to claim 1 is led seven construction methods, it is characterized in that: limp (29) comprises trapezoidal body, be located at first rotary connector (27) of body head, be located at seven second rotary connectors (25,26) of body bottom, wears 25 steel wire ropes (28) in the first rotary connector (27); In described the second rotary connector (25,26), wear 15 steel wire ropes, seven the second rotary connectors (25,26) point two rows are arranged on the tail end of limp (29).
3. new-type messenger unfolding one according to claim 2 is led seven construction methods, it is characterized in that: described limp (29) tail end connects the second rotary connector (25,26), anti-steel wire cover (24), moment connection device (23), anti-steel wire cover (22), the 3rd rotary connector (21) turned round turned round successively.
4. new-type messenger unfolding one according to claim 3 is led seven construction methods, it is characterized in that: described the first rotary connector (27) adopts 250kN rotary connector; Described the second rotary connector (25,26) adopts 50kN or 80kN rotary connector; The 3rd described rotary connector adopts 50kN rotary connector.
5. new-type messenger unfolding one according to claim 4 is led seven construction methods, it is characterized in that: with second, the second rotary connector (26) of being connected of the 4th, No. six rope (12,14,16) is located at first row, with first, the 3rd, the 5th, No. seven restrict (11,13,15,17) second rotary connector (25) of being connected is located at second row; The second rotary connector (26) that is positioned at first row adopts 50kN rotary connector; The second rotary connector (25) that is positioned at second row adopts 80kN rotary connector.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310474732.XA CN103825214A (en) | 2013-10-12 | 2013-10-12 | Novel guide rope laying one-pull-seven construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310474732.XA CN103825214A (en) | 2013-10-12 | 2013-10-12 | Novel guide rope laying one-pull-seven construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103825214A true CN103825214A (en) | 2014-05-28 |
Family
ID=50760139
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310474732.XA Pending CN103825214A (en) | 2013-10-12 | 2013-10-12 | Novel guide rope laying one-pull-seven construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103825214A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105390977A (en) * | 2015-11-10 | 2016-03-09 | 国网浙江省电力公司湖州供电公司 | Pay-off apparatus for electric power distribution network |
CN113629581A (en) * | 2021-08-16 | 2021-11-09 | 安徽宏源电力设计咨询有限责任公司 | Net sealing structure on temporary cross arm and net rope threading method thereof |
CN114221289A (en) * | 2021-12-01 | 2022-03-22 | 浙江省送变电工程有限公司 | Construction method for gap type self-damping wire large-span overhead line |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06276634A (en) * | 1993-03-15 | 1994-09-30 | Niida Densetsu Kk | Wire extension method for stringing messenger wire of aerial wire and device thereof |
JP2004282984A (en) * | 2003-02-24 | 2004-10-07 | Himeno Corp | Electric cable laying method |
CN101582572A (en) * | 2009-06-23 | 2009-11-18 | 湖南省送变电建设公司 | Method of extra-high voltage tension stringing |
CN102354926A (en) * | 2011-09-06 | 2012-02-15 | 湖北省输变电工程公司 | Large-section conductor tension stringing construction method |
-
2013
- 2013-10-12 CN CN201310474732.XA patent/CN103825214A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06276634A (en) * | 1993-03-15 | 1994-09-30 | Niida Densetsu Kk | Wire extension method for stringing messenger wire of aerial wire and device thereof |
JP2004282984A (en) * | 2003-02-24 | 2004-10-07 | Himeno Corp | Electric cable laying method |
CN101582572A (en) * | 2009-06-23 | 2009-11-18 | 湖南省送变电建设公司 | Method of extra-high voltage tension stringing |
CN102354926A (en) * | 2011-09-06 | 2012-02-15 | 湖北省输变电工程公司 | Large-section conductor tension stringing construction method |
Non-Patent Citations (1)
Title |
---|
鲍庆等: ""特高压架线新型导引绳一牵七展放施工技术研究与应用"", 《第四届全国架空输电线路技术交流研讨会论文集》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105390977A (en) * | 2015-11-10 | 2016-03-09 | 国网浙江省电力公司湖州供电公司 | Pay-off apparatus for electric power distribution network |
CN113629581A (en) * | 2021-08-16 | 2021-11-09 | 安徽宏源电力设计咨询有限责任公司 | Net sealing structure on temporary cross arm and net rope threading method thereof |
CN114221289A (en) * | 2021-12-01 | 2022-03-22 | 浙江省送变电工程有限公司 | Construction method for gap type self-damping wire large-span overhead line |
CN114221289B (en) * | 2021-12-01 | 2024-03-19 | 浙江省送变电工程有限公司 | Construction method for gap type self-damping wire long-span overhead line |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102064493B (en) | Method for paying off overhead transmission line by unmanned helicopter | |
CN100440660C (en) | Mechanical laying method for overlength large section cable | |
CN102290742B (en) | Tension stringing construction technology | |
CN102354926A (en) | Large-section conductor tension stringing construction method | |
CN103825214A (en) | Novel guide rope laying one-pull-seven construction method | |
CN104134950A (en) | Method for releasing guide rope of aircraft | |
CN102392418A (en) | Span-division erection construction method of construction catwalk of multi-tower suspension bridge | |
CN102780178A (en) | Obstacle bridging construction method for power line wiring and wiring pulleys | |
CN105672138A (en) | Through type stayed cable installation circulation system and cable threading construction method thereof | |
CN212025936U (en) | Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge | |
CN207612011U (en) | Cable wears ditch device | |
CN108149932B (en) | Beam penetrating device and beam penetrating method for prestress steel strand | |
CN207782294U (en) | Cable dragging device | |
CN107023310A (en) | The separate zone production quick lapping technique of large area | |
CN102593759B (en) | One-pulling-two expansion and construction process of large-section lead | |
CN203481710U (en) | Novel one-drag-seven construction apparatus for pulling rope laying | |
CN204707748U (en) | Dam formula fish lift is crossed on inclined-plane | |
CN107324231B (en) | Endless rope winch wire rope distributing technique | |
CN105923548B (en) | One kind realizing cable logging device based on digging machine | |
CN104682268A (en) | Method for constructing compact double-loop overhead line by adoption of flying powered parachute | |
CN205985949U (en) | Tension formula transmission line protection system | |
CN111636372B (en) | Construction method for laying interlocking block soft mattress in high-beach shallow water area under low water level | |
CN205901187U (en) | Crane span structure threading draw gear | |
CN107178044A (en) | A kind of method that I-shaped gooseneck is worn under during jacking bridge and culvert track strengthening | |
CN214993148U (en) | Integral penetrating device for long-distance steel strand |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20140528 |