CN103822019B - 水中悬浮输送管道及其施工方法 - Google Patents
水中悬浮输送管道及其施工方法 Download PDFInfo
- Publication number
- CN103822019B CN103822019B CN201410087263.0A CN201410087263A CN103822019B CN 103822019 B CN103822019 B CN 103822019B CN 201410087263 A CN201410087263 A CN 201410087263A CN 103822019 B CN103822019 B CN 103822019B
- Authority
- CN
- China
- Prior art keywords
- steel
- pipeline
- pipe
- water
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 82
- 238000010276 construction Methods 0.000 title claims abstract description 26
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 100
- 239000010959 steel Substances 0.000 claims abstract description 100
- 239000004567 concrete Substances 0.000 claims abstract description 62
- 239000002131 composite material Substances 0.000 claims abstract description 43
- 239000000725 suspension Substances 0.000 claims abstract description 28
- 238000000034 method Methods 0.000 claims abstract description 18
- 239000004575 stone Substances 0.000 claims abstract description 18
- 238000007667 floating Methods 0.000 claims abstract description 12
- 239000007921 spray Substances 0.000 claims description 17
- 230000000903 blocking effect Effects 0.000 claims description 16
- 230000009189 diving Effects 0.000 claims description 2
- 238000012423 maintenance Methods 0.000 abstract description 4
- 238000001514 detection method Methods 0.000 abstract description 3
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000012544 monitoring process Methods 0.000 abstract description 3
- 238000005188 flotation Methods 0.000 abstract description 2
- 238000005507 spraying Methods 0.000 abstract 1
- 230000007613 environmental effect Effects 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 230000009286 beneficial effect Effects 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 239000007789 gas Substances 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000002195 synergetic effect Effects 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/12—Laying or reclaiming pipes on or under water
- F16L1/14—Laying or reclaiming pipes on or under water between the surface and the bottom
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/12—Laying or reclaiming pipes on or under water
- F16L1/20—Accessories therefor, e.g. floats or weights
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L9/00—Rigid pipes
- F16L9/14—Compound tubes, i.e. made of materials not wholly covered by any one of the preceding groups
- F16L9/153—Compound tubes, i.e. made of materials not wholly covered by any one of the preceding groups comprising only layers of metal and concrete with or without reinforcement
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410087263.0A CN103822019B (zh) | 2014-03-11 | 2014-03-11 | 水中悬浮输送管道及其施工方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410087263.0A CN103822019B (zh) | 2014-03-11 | 2014-03-11 | 水中悬浮输送管道及其施工方法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103822019A CN103822019A (zh) | 2014-05-28 |
| CN103822019B true CN103822019B (zh) | 2015-12-09 |
Family
ID=50757223
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410087263.0A Active CN103822019B (zh) | 2014-03-11 | 2014-03-11 | 水中悬浮输送管道及其施工方法 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103822019B (zh) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105952967B (zh) * | 2016-06-01 | 2018-09-14 | 天津市城安热电有限公司 | 一种利用浮球沉放管道的沉管作业方法 |
| CN108253205B (zh) * | 2016-12-28 | 2024-05-14 | 北京市水利规划设计研究院 | 管道及其组件 |
| CN106895214A (zh) * | 2017-05-05 | 2017-06-27 | 俞扬池 | 一种智能化钢管 |
| CN107237924A (zh) * | 2017-07-06 | 2017-10-10 | 中化二建集团有限公司 | 一种沿沟渠周边敷设的长输管道的安装施工方法 |
| CN111597611B (zh) * | 2020-05-06 | 2021-03-09 | 中铁(天津)隧道工程勘察设计有限公司 | 一种隧道在水中悬浮状态受水动力分析方法 |
| CN112127315A (zh) * | 2020-09-09 | 2020-12-25 | 中国市政工程中南设计研究总院有限公司 | 过丘陵地区河涌的原水管道敷设系统及其敷设方法 |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5615977A (en) * | 1993-09-07 | 1997-04-01 | Continental Emsco Company | Flexible/rigid riser system |
| CN1246619C (zh) * | 2002-12-10 | 2006-03-22 | 胜利油田胜利石油化工建设有限责任公司 | 海底管道固定施工方法及装置 |
| AU2009243413A1 (en) * | 2009-03-27 | 2010-10-14 | Berhad, Bumi Armada | Riser Support System |
| CN201636454U (zh) * | 2010-04-21 | 2010-11-17 | 中铁隧道集团二处有限公司 | 双层耐磨管 |
| CN102221128B (zh) * | 2011-06-09 | 2015-05-13 | 浙江大学 | 一种基于锚墩固定的海底输油输气软管管线 |
| CN102269328B (zh) * | 2011-08-18 | 2013-01-02 | 浙江大学 | 一种海上输油输气柔性立管管线 |
-
2014
- 2014-03-11 CN CN201410087263.0A patent/CN103822019B/zh active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN103822019A (zh) | 2014-05-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103822019B (zh) | 水中悬浮输送管道及其施工方法 | |
| CN106988346B (zh) | 沉管隧道最终接头及预制方法、安装方法 | |
| CN109506044B (zh) | 一种海底输油管道施工工艺 | |
| CN102877484B (zh) | 一种钢混复合筒型基础结构及其施工方法 | |
| CN103556655A (zh) | 一种悬索钢-混组合结构水中悬浮隧道及其施工方法 | |
| CN101798815A (zh) | 一种钢混组合结构的海上风电机组地基基础 | |
| CN108661081A (zh) | 一种反张式锚索体系支撑悬浮隧道结构 | |
| CN106759430B (zh) | 一种三个筒型基础与混凝土支撑结构的风电整机施工方法 | |
| CN104060522B (zh) | 一种应用双层钢管混凝土柔性桩的整体式桥台无缝桥梁 | |
| CN103953036A (zh) | 一种滨海盐渍土输电线路桩基接桩用防腐护套施工方法 | |
| CN106836265A (zh) | 一种带裙板的重力式筒型基础及其施工方法 | |
| CN206234474U (zh) | 一种海底hdpe管道压重块 | |
| CN207015550U (zh) | 实现系泊风向标的深海系泊柱 | |
| CN113389222B (zh) | 一种悬浮隧道结构 | |
| CN205875197U (zh) | 一种多边形海上风电筒型基础 | |
| CN115787728A (zh) | 一种组合式的水中悬浮隧道 | |
| CN107794972A (zh) | 一种海上取水口施工方法 | |
| CN100432343C (zh) | 横跨并保护海底管线的筒型基础海堤结构及安装方法 | |
| CN103195080B (zh) | 一种重力式基础的拖航方法 | |
| CN204510256U (zh) | 海上风机的钢筒型基础结构 | |
| CN207523892U (zh) | 随水位升沉向波性海流发电机搭载器 | |
| CN201678202U (zh) | 一种置于深海海底的圆柱体储油装置 | |
| CN103423514B (zh) | 一种带基座的焊接式海底管道止屈器 | |
| CN211922691U (zh) | 一种可迁移预制海上风电筒型基础的设备 | |
| CN103741724B (zh) | 一种预制预应力地下连续墙接头 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB03 | Change of inventor or designer information |
Inventor after: Lu Zhaohong Inventor after: Zhang Wenfu Inventor after: Xue Yihan Inventor after: Xue Jinghong Inventor after: Wang Shuwei Inventor after: Ji Jing Inventor before: Lu Zhaohong Inventor before: Zhang Wenfu Inventor before: Xue Jinghong Inventor before: Zhang Guangming Inventor before: Wang Shuwei Inventor before: Ji Jing |
|
| COR | Change of bibliographic data | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20191211 Address after: Bai Bu Zhen Heng Gang Cun, Haiyan County, Jiaxing City, Zhejiang Province Patentee after: Haiyan Jinchao Regeneration Technology Co.,Ltd. Address before: 163319 No. 199, development road, hi tech Development Zone, Heilongjiang, Daqing Patentee before: Northeast Petroleum University |
|
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20201116 Address after: 233000 Room 102 north, No.11, No.2 building, liukm Huayuan commercial building, Changqing Township, Yuhui District, Bengbu City, Anhui Province Patentee after: Anhui Licha Information Technology Co.,Ltd. Address before: Bai Bu Zhen Heng Gang Cun, Haiyan County, Jiaxing City, Zhejiang Province Patentee before: Haiyan Jinchao Regeneration Technology Co.,Ltd. |
|
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20240807 Address after: No. 1701, Unit 1, Building 6, Chamber of Commerce Building, Jinlong Avenue, Enshi Tujia and Miao Autonomous Prefecture, Hubei Province, 445000 Patentee after: Hubei Anyue Construction Engineering Co.,Ltd. Country or region after: China Address before: 233000 Room 102 north, No.11, No.2 building, liukm Huayuan commercial building, Changqing Township, Yuhui District, Bengbu City, Anhui Province Patentee before: Anhui Licha Information Technology Co.,Ltd. Country or region before: China |