CN103803424B - Two-beam gantry crane with dual-spiral and self-defense structure - Google Patents

Two-beam gantry crane with dual-spiral and self-defense structure Download PDF

Info

Publication number
CN103803424B
CN103803424B CN201310682802.0A CN201310682802A CN103803424B CN 103803424 B CN103803424 B CN 103803424B CN 201310682802 A CN201310682802 A CN 201310682802A CN 103803424 B CN103803424 B CN 103803424B
Authority
CN
China
Prior art keywords
girder
fixed pulley
gantry crane
main beam
jacklift
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310682802.0A
Other languages
Chinese (zh)
Other versions
CN103803424A (en
Inventor
魏云平
许相柱
戴俊
吴娜
孙希跃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QIAN'AN JINNIU MINE MACHINERY PLANT
Tangshan University
Original Assignee
QIAN'AN JINNIU MINE MACHINERY PLANT
Tangshan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QIAN'AN JINNIU MINE MACHINERY PLANT, Tangshan University filed Critical QIAN'AN JINNIU MINE MACHINERY PLANT
Priority to CN201310682802.0A priority Critical patent/CN103803424B/en
Publication of CN103803424A publication Critical patent/CN103803424A/en
Application granted granted Critical
Publication of CN103803424B publication Critical patent/CN103803424B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a two-beam gantry crane with a dual-spiral and self-defense structure. The two-beam gantry crane comprises a main beam, support legs connected with the main beam to support the main beam, and a jacklift mechanism supported on the main beam, wherein the jacklift mechanism comprises a jacklift frame which is supported on the main beam through jacklift wheels and moves along the main beam under the drive of a running mechanism, and two sets of jack mechanisms which are arranged on the jacklift frame and used for hooking weight and completely have the same structure, a defense structure used for preventing the jacklift mechanism and the main beam from being eroded in a sun-scorched and rain-drenched way covers the main beam, and a drive structure of the jack mechanism is characterized in that the rotation directions of a winding drum and a fixed pulley shaft are opposite to each other. After the two-beam gantry crane is used, the jacklift and the main beam can be protected from being influenced by the climate such as the sun scorching and the rain drenching, so that the service life of the two-beam gantry crane can be prolonged; compared with the gantry crane with the same lifting weight, the two-beam gantry crane has the advantages that the mechanical property of the main beam can be obviously improved, and the stability and the safety can be obviously improved.

Description

A kind of have bispin and the double-beam gantry crane from defense structure
Technical field
The present invention relates to a kind of gantry.More particularly to a kind of have bispin and the double-beam gantry from defense structure Crane.
Background technology
Gantry is applied on outdoor yard, dock, power station, harbour and railway stock and other places, is carried and pacifies Pretend industry, operating environment is severe, and climate, ambient influnence are larger, the infringement that whole machine and each travelling mechanism are produced is larger.
The structure of box girder gantry is simple, is easy to manufacture, but front face area is big, running resistance is big, and conduct oneself with dignity Greatly, it is unfavorable for saving steel.Improve the structure of crane for this, mitigate deadweight, reduce construction weight, save process time, fall Low processing cost is a big target of current Development of Crane.
Content of the invention
The technical problem to be solved is to provide and a kind of can solve the problem that open work to each mechanism of trolley Damage, realize the tension and compression stress to girder from offsetting a part, to reduce there is bispin and certainly defending knot of the pressure to girder The double-beam gantry crane of structure.
The technical solution adopted in the present invention is: a kind of have bispin and the double-beam gantry crane from defense structure, bag Include girder, the supporting leg being connected for support girder with girder, it is supported on the trolley body on girder, described trolley body bag Include the trolley frame of the driving lower edge girder movement being supported on girder by trundle and in travelling mechanism, and be arranged on little Two groups of completely identical in structure jack machinisms of hook block weight are used on vehicle frame, described girder upper cover has for preventing dolly machine Structure and girder are subject to the defense structure of erosion of exposing to the sun and rain, and the drive mechanism of described jack machinism is reel and fixed pulley axis are in The drive mechanism of opposite direction rotation.
Described defense structure includes for the shape of a saddle cover taken shelter from rain that keeps out the wind to trolley body and girder, and is arranged on The reinforcement of the π shape structure for reinforcing shape of a saddle cover intensity inside shape of a saddle cover, described reinforcement is fixedly welded on institute On the girder stated, described shape of a saddle cover is fixedly connected with described girder by reinforcement.
Described reinforcement is provided with more than 2.
Described drive mechanism includes to be arranged on and is driven by the decelerator on the output shaft being connected to motor on trolley frame Dynamic reel, two ends are arranged on the fixed pulley axis on trolley frame, are fixed on being made up of the fixed pulley of more than 2 on fixed pulley axis Fixed pulley group, and be arranged on below fixed pulley group and by steel wire rope be connected with fixed pulley group by plural dynamic cunning The running block of wheel composition, the lower end of described running block is connected with suspension hook, and wherein, one end of described steel wire rope is fixing even It is connected on described trolley frame, the other end is fixedly connected on described reel.
The winding arrangement of described steel wire rope is: after one end of steel wire rope is fixed on trolley frame, with immediate dynamic cunning Wheel and fixed pulley axis start to be wound to successively after last movable pulley by the order of movable pulley, fixed pulley, movable pulley, fixed pulley It is fixed on described reel.
The a kind of of the present invention has bispin and the double-beam gantry crane from defense structure, by the lifting machine of upper and lower bispin Structure, realizes the tension and compression stress to girder from offsetting a part, to reduce the pressure to girder;By saddle type from defense structure, The infringement to each mechanism of trolley for the open work can be solved, also can improve the stress of girder, such that it is able to realize optimizing master Girder construction, reaches the purpose mitigating deadweight.Using the structure of the present invention, can effectively protect trolley and girder from day Solarization such as drenches with rain at the climatic effect, extends its service life;Compare with identical lifting capacity straddle truck, the stress performance of girder substantially changes It is apt to, stability and security performance are obviously improved.
Brief description
Fig. 1 is the external structure schematic diagram that girder of the present invention is covered with defense structure;
Fig. 2 is the structural representation that girder of the present invention removes the shape of a saddle cover in defense structure;
Fig. 3 is the top view of Fig. 2;
Fig. 4 is the side view of Fig. 1;
Fig. 5 is the top view of trolley body of the present invention;
Fig. 6 is the structural representation of trolley body of the present invention;
Fig. 7 is the structural representation of steel wire rope coiling in the present invention.
In figure
1: girder 2: defense structure
3: supporting leg 4: decelerator
5: reel 6: travelling mechanism
7: motor 8: shaft coupling
9: floating axle 10: steel wire rope
11: trolley frame 12: movable pulley
13: fixed pulley 14: fixed pulley axis
15: trundle 16: suspension hook
21: reinforcement 22: shape of a saddle cover
Specific embodiment
To a kind of of the present invention, there is bispin and the double-beam gantry lifting from defense structure with reference to embodiment and accompanying drawing Machine is described in detail.
As shown in Fig. 1~Fig. 6, a kind of of the present invention has bispin and the double-beam gantry crane from defense structure, including There is girder 1, the supporting leg 3 being connected for support girder 1 with girder 1, it is supported on the trolley body on girder 1, described dolly machine Structure includes the trolley frame 11 of driving lower edge girder 1 movement being supported on girder 1 and in travelling mechanism 6 by trundle 15, And it is arranged on two groups of completely identical in structure jack machinisms that hook block weight is used on trolley frame 11, described girder 1 upper cover Have for preventing trolley body and girder 1 to be subject to the defense structure 2 of erosion of exposing to the sun and rain, the drive mechanism of described jack machinism It is reel and the drive mechanism of fixed pulley axis rotation in opposite direction.
As shown in Figure 1, Figure 2, Figure 3, Figure 4, described defense structure 2 includes for keeping out the wind to trolley body and girder 1 The shape of a saddle cover 22 taken shelter from rain, and be arranged on the π shape structure for reinforcing shape of a saddle cover 22 intensity of shape of a saddle cover 22 inner side Reinforcement 21, described reinforcement 21 is fixedly welded on described girder 1, described shape of a saddle cover 22 pass through reinforcement 21 with Described girder 1 is fixedly connected.Described reinforcement 21 is provided with more than 2, and the present embodiment is provided with 3.
Defense structure 2 is welded on the outside of girder 1 by reinforcement 21, and shape of a saddle cover 22 is in the shape of a saddle, and the left and right sides can Think truss structure, for increasing the security and stability of structure, the uniform three reinforcement floors in inner side, described shape of a saddle cover 22 is Thin plate, acts primarily as and protects trolley and girder from the climatic effect such as expose to the sun and rain, extend the use of trolley and girder The effect in life-span.By doing force analysis to girder, it is understood that girder institute main inclusion two parts loaded, trolley is certainly Weight and lifting material weight, due to power application point not on girder so that girder is while bearing pressure, also can Acted on by moment of torsion, heterocoelous defense structure and Main Girder Welding are integrated, the mechanics mould of simply supported beam is changed from structure Type, improves the stress of girder, increased the stability that each mechanism runs.
As shown in Figure 5, Figure 6, described drive mechanism includes and is arranged on trolley frame 11 by being connected to the defeated of motor 7 The reel 5 that decelerator on shaft drives, two ends are arranged on the fixed pulley axis 14 on trolley frame 11, are fixed on fixed pulley axis 14 The fixed pulley group being made up of the fixed pulley 13 of more than 2, and be arranged on below fixed pulley group and by steel wire rope 10 with fixed The running block being made up of plural movable pulley 12 that assembly pulley connects, the lower end of described running block is connected with suspension hook 16, wherein, one end of described steel wire rope 10 is fixedly connected on described trolley frame 11, and the other end is fixedly connected on described volume On cylinder 5.
As shown in fig. 7, the winding arrangement of described steel wire rope 10 is: one end of steel wire rope 10 is fixed on trolley frame 11 Afterwards, with immediate movable pulley 12 and fixed pulley axis 14 start by movable pulley, fixed pulley, movable pulley, fixed pulley order successively It is fixed on after being wound to last movable pulley 12 on described reel 5.The winding structure of this steel wire rope can make reel 5 He Fixed pulley axis 14 realize opposite direction rotation so as to be cancelled each other a part by the inertia force that turning moment is formed, thus reduce right The pressure of girder 1.
In drive mechanism, motor 7 passes through decelerator 4, and band movable reel 5 rotates, and such as raising weight then makes steel wire rope 10 Around coiling 5, reel rotates counterclockwise, and as shown in Figure 6, Figure 7, steel wire rope 10 drives movable pulley 12 successively, fixed pulley 13, due to The other end of steel wire rope 10 is fixed on trolley frame 11, will be shifted up for this whole running block, under the drive of steel wire rope 10, fixed Pulley spindle 14 rotates clockwise.Reel 5 rotates counterclockwise the inertia force just phase rotating clockwise generation with fixed pulley axis 14 Instead it is possible to realize, from offsetting a part, thus the pressure to girder for the minimizing, strengthening the stability that mechanism runs.Under weight During fall, spool shaft rotates clockwise, and fixed pulley axis rotate counterclockwise, the inertia force also contrast of generation.So that girder Stress performance is obviously improved, and stability and security performance are obviously improved.

Claims (4)

1. a kind of have bispin and the double-beam gantry crane from defense structure, includes girder (1), is mutually used in conjunction with girder (1) In the supporting leg (3) of support girder (1), it is supported on the trolley body on girder (1), described trolley body includes by dolly Wheel (15) is supported on that girder (1) is upper and the trolley frame (11) of driving lower edge girder (1) movement in travelling mechanism (6), Yi Jishe Put in the upper two groups of completely identical in structure jack machinisms being used for hook block weight of trolley frame (11) it is characterised in that described master Beam (1) upper cover has for preventing trolley body and girder (1) to be subject to the defense structure (2) of erosion of exposing to the sun and rain, described lifting The drive mechanism that the drive mechanism of mechanism is reel and fixed pulley axis are in opposite direction rotation, described defense structure (2) includes For keeping out the wind the shape of a saddle cover (22) taken shelter from rain to trolley body and girder (1), and it is arranged on the use inside shape of a saddle cover (22) In the reinforcement (21) of the π shape structure reinforcing shape of a saddle cover (22) intensity, described reinforcement (21) is fixedly welded on described On girder (1), described shape of a saddle cover (22) is fixedly connected with described girder (1) by reinforcement (21).
2. according to claim 1 a kind of there is bispin and the double-beam gantry crane from defense structure it is characterised in that Described reinforcement (21) is provided with more than 2.
3. according to claim 1 a kind of there is bispin and the double-beam gantry crane from defense structure it is characterised in that Described drive mechanism includes to be arranged on and is driven by the decelerator on the output shaft being connected to motor (7) on trolley frame (11) Reel (5), two ends are arranged on the fixed pulley axis (14) on trolley frame (11), be fixed on fixed pulley axis (14) by 2 with On the fixed pulley group that forms of fixed pulley (13), and be arranged on below fixed pulley group and by steel wire rope (10) and fixed pulley group The running block being made up of plural movable pulley (12) connecting, the lower end of described running block is connected with suspension hook (16), wherein, one end of described steel wire rope (10) is fixedly connected on described trolley frame (11), and the other end is fixedly connected on On described reel (5).
4. according to claim 3 a kind of there is bispin and the double-beam gantry crane from defense structure it is characterised in that The winding arrangement of described steel wire rope (10) is: after one end of steel wire rope (10) is fixed on trolley frame (11), with immediate Movable pulley (12) and fixed pulley axis (14) start to be wound to successively finally by the order of movable pulley, fixed pulley, movable pulley, fixed pulley It is fixed on after one movable pulley (12) on described reel (5).
CN201310682802.0A 2013-12-12 2013-12-12 Two-beam gantry crane with dual-spiral and self-defense structure Expired - Fee Related CN103803424B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310682802.0A CN103803424B (en) 2013-12-12 2013-12-12 Two-beam gantry crane with dual-spiral and self-defense structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310682802.0A CN103803424B (en) 2013-12-12 2013-12-12 Two-beam gantry crane with dual-spiral and self-defense structure

Publications (2)

Publication Number Publication Date
CN103803424A CN103803424A (en) 2014-05-21
CN103803424B true CN103803424B (en) 2017-01-18

Family

ID=50700883

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310682802.0A Expired - Fee Related CN103803424B (en) 2013-12-12 2013-12-12 Two-beam gantry crane with dual-spiral and self-defense structure

Country Status (1)

Country Link
CN (1) CN103803424B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204057755U (en) * 2014-06-04 2014-12-31 国家电网公司 A kind of frame-type hanging device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201190085Y (en) * 2008-04-16 2009-02-04 张晓明 Bridge crane cart
CN201647885U (en) * 2010-04-22 2010-11-24 重庆宝井钢材加工配送有限公司 Trolly steel wire rope winding structure of double-beam bridge type traveling crane
CN201942435U (en) * 2011-03-07 2011-08-24 河南省盛华重型起重机有限公司 Special trolley for double-beam gantry crane
CN201952103U (en) * 2011-03-11 2011-08-31 中铁二十五局集团建筑安装工程有限公司 Steel-bar lifting frame
CN201961971U (en) * 2011-02-28 2011-09-07 天津起重设备有限公司 Large-tonnage dual-beam crane trolley
CN202046816U (en) * 2011-03-22 2011-11-23 大连大起产业开发有限公司 Portal crane with double beams and electric hoists
CN202766109U (en) * 2012-09-19 2013-03-06 河南卫华重型机械股份有限公司 Rain-proof cover and crane trolley using rain-proof cover
CN203667841U (en) * 2013-12-12 2014-06-25 唐山学院 Twin-beam gantry crane with bispin and self-defense structure

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1297469C (en) * 2003-07-30 2007-01-31 上海振华港口机械(集团)股份有限公司 Container crane capable of lifting dual 40 feet box
JP5169549B2 (en) * 2008-07-04 2013-03-27 株式会社日立プラントテクノロジー Large beam block lifting method and jack-up stage used for it

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201190085Y (en) * 2008-04-16 2009-02-04 张晓明 Bridge crane cart
CN201647885U (en) * 2010-04-22 2010-11-24 重庆宝井钢材加工配送有限公司 Trolly steel wire rope winding structure of double-beam bridge type traveling crane
CN201961971U (en) * 2011-02-28 2011-09-07 天津起重设备有限公司 Large-tonnage dual-beam crane trolley
CN201942435U (en) * 2011-03-07 2011-08-24 河南省盛华重型起重机有限公司 Special trolley for double-beam gantry crane
CN201952103U (en) * 2011-03-11 2011-08-31 中铁二十五局集团建筑安装工程有限公司 Steel-bar lifting frame
CN202046816U (en) * 2011-03-22 2011-11-23 大连大起产业开发有限公司 Portal crane with double beams and electric hoists
CN202766109U (en) * 2012-09-19 2013-03-06 河南卫华重型机械股份有限公司 Rain-proof cover and crane trolley using rain-proof cover
CN203667841U (en) * 2013-12-12 2014-06-25 唐山学院 Twin-beam gantry crane with bispin and self-defense structure

Also Published As

Publication number Publication date
CN103803424A (en) 2014-05-21

Similar Documents

Publication Publication Date Title
CN201647849U (en) Automatic balancing tower type crane
EP1731473A2 (en) Container transport vehicle
CN203295057U (en) Novel anti-rolling device for container spreaders
CN203667841U (en) Twin-beam gantry crane with bispin and self-defense structure
CN103803424B (en) Two-beam gantry crane with dual-spiral and self-defense structure
CN204714478U (en) A kind of Omni-mobile driving engine installation car
CN115676644A (en) Anti-swing outdoor portal crane
CN106144896A (en) A kind of pull-type carriage walking mechanism
CN205855466U (en) A kind of telescopic jib ship loader
CN110745715A (en) Automobile crane
CN102718155B (en) A kind of electric tyre crane
CN201801309U (en) Anti-shaking crane crab
CN212861207U (en) Connecting structure of carriage and automobile tail plate
CN202967917U (en) Gantry crane
CN203624705U (en) Welding wire pressing limiting device
CN206417802U (en) A kind of crane roll device
CN203223022U (en) Transmission device for lifting stereo garage car contained panel
CN103086280B (en) Automatic retractable sail
CN217458530U (en) Safety protection device of prestressed beam-making field beam-lifting machine
CN206051313U (en) A kind of road and bridge door machine vehicle structure
CN206051347U (en) A kind of double girder crane
CN205772937U (en) A kind of transfer device for cold lamination film volume
CN107572434A (en) Safe tackling system
CN202098964U (en) Crane hook device
CN219363003U (en) Gantry crane running gear

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170118

Termination date: 20171212

CF01 Termination of patent right due to non-payment of annual fee