CN103797216A - Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same - Google Patents

Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same Download PDF

Info

Publication number
CN103797216A
CN103797216A CN201280044802.1A CN201280044802A CN103797216A CN 103797216 A CN103797216 A CN 103797216A CN 201280044802 A CN201280044802 A CN 201280044802A CN 103797216 A CN103797216 A CN 103797216A
Authority
CN
China
Prior art keywords
row
jurisdiction
section
twisted wire
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201280044802.1A
Other languages
Chinese (zh)
Other versions
CN103797216B (en
Inventor
马相准
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Korea Lnstitute Of Construction Technology
Original Assignee
Korea Lnstitute Of Construction Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Korea Lnstitute Of Construction Technology filed Critical Korea Lnstitute Of Construction Technology
Publication of CN103797216A publication Critical patent/CN103797216A/en
Application granted granted Critical
Publication of CN103797216B publication Critical patent/CN103797216B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention enables each segment, in which two center through-paths and two end through-paths are formed, to be sequentially and adjacently arranged at each column in a vertical direction, wherein: horizontal segments at four columns are set as one unit such that strands are inserted, strained, and settled therein; only one strand is settled in each segment such that only the corresponding segment is settled and fixed; the segments, by the remaining three strands, located at the other columns are sequentially settled and fixed in the same manner as above via through-paths, thereby forming a foundation reaction wall through which all the four strands pass, and at the same time, segments at the other columns are also sequentially and easily settled and fixed by the remaining three strands with respect to structurally-stabilized foundation reaction wall; and the foundation reaction wall of the segments is formed and the other columns in accordance with the foundation reaction wall are sequentially settled and fixed together with a drilling operation by repeating the above steps. Thus, through said features, the invention allows the segments to be assembled in an efficient and economical manner.

Description

There is the tunnel segment structure of longitudinal twisted wire and transverse shearing force key and the method for building shield tunnel by described structure
Technical field
The present invention relates to have the tunnel segment structure of longitudinal twisted wire and transverse shearing force key and the method for building shield tunnel by described structure, and more particularly, forming two central authorities penetrates the section of jurisdiction that path and two ends penetrate path and sequentially arranges in column, so that contiguous in a longitudinal direction, twisted wire inserts take longitudinal section of jurisdiction as unit, prestretching (prestress) and being anchored in four row, only single twisted wire is anchored in each section of jurisdiction, to make only described section of jurisdiction be anchored and fix, three residue twisted wires penetrate path and allow to carry out sequentially grappling and be fixed in the section of jurisdiction in other row by above method, form basis, the section of jurisdiction adjacency test wall that all four twisted wires all penetrate, and simultaneously by structurally stable basis in abutting connection with the easily sequentially grappling and fix the section of jurisdiction in other row of test wall three remaining twisted wires around, and in the time repeating this process, the grappling of basis, section of jurisdiction gained in other row in abutting connection with test wall is sequentially carried out together with boring with fixing.
Because the assembling of section of jurisdiction is efficient and economical, so the present invention is useful for shield tunnel.
Background technology
Shield tunnel method is a kind of method, and wherein shield tunnel rig is assembled the section of jurisdiction of serving as support of tunnel thing in soil being holed and shift.
More particularly, described shield tunnel method is a kind of method that comprises a series of systems, wherein carry out boring according to the rotation of the front end cutterhead of shield tunnel rig, by the helical conveyor arranging in shield tunnel rig, the soil producing due to boring is transferred to outside, and the section of jurisdiction that support of tunnel thing is served as in assembling in shifted space.
Shield tunnel rig is extensively known substantially.
In known shield tunnel rig, then the shield tunnel rig (referring to Fig. 1) disclosing in 93-006410 korean patent application case will be described in especially.
Shield tunnel rig 10 comprises cutterhead 16, shield Head Section 22, shield structure main body 12 and shield tail region 24.
Opening 86 is formed at partition wall 30 tops.In opening 86, hinged lid 88 is arranged in partition wall 30.Lid 88 is connected to the piston rod 92 of hydraulic cylinder 90, and hydraulic cylinder 90 is attached to dividing plate 32 by arm 94.
This lid 88 carrys out closing any opening 86 by hydraulic cylinder 90 conventionally.But, in the time being applied to the ground pressure of the space region between partition wall 30 and cutterhead 16 and exceeding in hydraulic cylinder 90 pressure of setting, lid is driven into lid by offseting with the pressure of hydraulic cylinder 90 one side of dividing plate 32 and opens opening 86 and soil is incorporated in particle chamber 28.
Rotor 96 and stator 98 that formation is configured to the stone breaker that crushes the relatively large rubble that has entered particle chamber 28 are arranged in particle chamber 28.Rotor 96 is attached to axis of rotation 68, and stator 98 arrives partition wall 30 in rotor 96 attached underneath.Water under high pressure is fed to particle chamber 28 by feed pipe 100, and the water of supplying is discharged into the rear of shield structure main body 12 by delivery pipe 102 along the soil in particle chamber 28.In the time that boring starts, piston rod 46 and 48 is retracted in the hydraulic cylinder 40 in the starting jack 14 of rig 10.
Under this state, rig 10 receives the driving force in shield structure main body 12 by each starting jack 14, the motor 70 of rotating mechanism 18 can rotate, the rotation of each motor 70 is delivered to surface plate 58 via reducer 72, toothed belt gear 74, gear 76 and axis of rotation 68, and and then cutterhead 16 meeting rotations.Due to the rotation of cutterhead 16, in excavating, carry out and advance.The soil excavating enters the space in partition wall 30 fronts, through the opening 86 of partition wall 30, be introduced in particle chamber 28, from particle chamber 28 through delivery pipe 102, and be discharged from together with water.Although shield structure main body 12 is advanced, section of jurisdiction 104 is arranged in the space that the rear of shield structure main body 12 forms.
In correlation technique, the problem (referring to Fig. 2) of the above-mentioned shield tunnel rig disclosing in 10-0936471 Korean Patent will be described in.
The inventor of 10-0936471 Korean Patent is identical with inventor and the applicant of the application's case with applicant.
Roundel structure support of tunnel thing 10 comprises seven sections of jurisdiction and fixes by (K) section of jurisdiction of binding.
The four edges of each section of jurisdiction has discharge structure, the waterproof agent 18 that described discharge structure comprises draining taxiway 16 and arranges at front and the rear of draining taxiway 16.Because be provided with waterproof agent, thus do not have percolating water to penetrate junction surface, and even in the time that percolating water penetrates junction surface, outside it is also discharged into by draining taxiway 16.
In 10-0936471 Korean Patent, although carry out preventing and processing percolating water by discharge structure completely in this way, but described structure has cross sectional engagement portion, wherein the junction surface, all rear ends of seven sections of jurisdiction is converged at plane place, and there is not longitudinal integrated structure (for example, line structure) that cross sectional engagement portion is connected and combined.Therefore, cross sectional engagement portion is easily because the differential pressure that ground causes is vertically shifted.The impact of earthquake than the problem of described differential pressure more greatly and more serious.Antidetonation provision is indispensable.Seismic design will reflect that the seriousness of problems is considered to enforceable.
In discharge structure in 10-0936471 Korean Patent, suppose that junction surface, section of jurisdiction is not with the arranged in form of z shape.Therefore, first, pay the utmost attention to cross sectional engagement portion is connected and combined.
Summary of the invention
[technical problem]
(a) the invention provides a kind of tunnel segment structure, wherein forming two central authorities penetrates the section of jurisdiction that path and two ends penetrate path and sequentially arranges in column, thereby contiguous in a longitudinal direction, twisted wire inserts take longitudinal section of jurisdiction as unit, prestretching and being anchored in four row, only single twisted wire is anchored in each section of jurisdiction, to make only described section of jurisdiction be anchored and fix, three residue twisted wires penetrate path and allow to carry out sequentially grappling and be fixed in the section of jurisdiction in other row by above method, form basis, the section of jurisdiction adjacency test wall that all four twisted wires all penetrate, and simultaneously by structurally stable basis in abutting connection with the easily sequentially grappling and fix the section of jurisdiction in other row of test wall three remaining twisted wires around, and in the time repeating this process, the grappling of basis, section of jurisdiction gained in other row in abutting connection with test wall is sequentially carried out together with boring with fixing, and and then can assemble efficiently and economically described section of jurisdiction.
(b) the present invention also provides a kind of tunnel segment structure, wherein shear connector is formed at each section of jurisdiction in a lateral direction, section of jurisdiction in each row is arranged in a longitudinal direction with the form of z shape, and twisted wire is arranged to form basis, section of jurisdiction in abutting connection with test wall simultaneously, and and then because of the shear stress due to shear connector with because the overlapping rigidity due to twisted wire can increase, produce so firm tunnel segment structure earthquake etc. to high-durability.
(c) in the present invention, two central authorities penetrate path and are adjacent to center line, and two ends penetrate path and be adjacent to two ends, and and then can make because of the eccentric moment minimum due to the differential pressure of soil pressure.
[technical solution]
Configuration of the present invention following (referring to Fig. 4, Fig. 5, Fig. 6 and Fig. 7).
The present invention comprises a kind of tunnel segment structure with longitudinal twisted wire and transverse shearing force key, wherein two central authorities penetrate path 10 and two ends and penetrate path 20 and meet at right angles and form with cross sectional engagement portion, penetrate in path 10 in two central authorities, form twisted wire through hole F3 and F4 and twisted wire anchorage zone G1 and G2, twisted wire anchorage zone G1 and G2 are positioned at tunnel boring direction side, penetrate in path 20 at two ends, twisted wire insertion and fixed space district E1 and E2 and twisted wire are formed through hole F1 and F2, twisted wire insertion and fixed space district E1 and E2 and twisted wire anchorage zone G1 and G2 are positioned on rightabout, form with line P and Q and there is the Qa=Pa of relation, the basic section of jurisdiction A (A1=A2=A3=A4) of the shear connector of Qb=Pb and Qc=Pc=2Qa=2Pa is formed, in A1 and A4 and lower end when tangent, on A1 A2 → B and on A4 A3 → C sequentially arrange, section of jurisdiction K is inserted between B and C, section of jurisdiction B, C is identical with basic section of jurisdiction A with K, section of jurisdiction B and section of jurisdiction C respectively the bottom Qa of online Q and the Qa place, top of line Q form than the long Qd of Qa, and the top of the section of jurisdiction K online Q corresponding with it and Qa place, bottom form than the short Qd of Qa.
In addition, the present invention comprises a kind of tunnel segment structure with longitudinal twisted wire and transverse shearing force key, wherein be formed in twisted wire anchorage zone G1 and G2 corresponding to the round taper hole of the public cone of the front end of twisted wire, and corresponding to the space region of the fixed area, rear end of twisted wire be formed at that twisted wire inserts and fixed space district E1 and E2 in.
The present invention comprises a kind of tunnel segment structure with longitudinal twisted wire and transverse shearing force key, and wherein flow groove and water swelling waterproof agent are formed at the junction surface place of the four edges of each section of jurisdiction.
As illustrated in Fig. 3, shield tunnel of the present invention has circular cross section.The number that forms the section of jurisdiction of circular cross section is odd number.Seven or five is preferred.
For convenience of description, seven sections of jurisdiction will be described.
First, will the shape of each section of jurisdiction be described.
The present invention has a kind of configuration, and described configuration packet contains basic section of jurisdiction A, the section of jurisdiction K that binds, and is adjacent to section of jurisdiction B and the C (A1=A2=A3=A4) of section of jurisdiction K.
As illustrated in Fig. 4, basic section of jurisdiction A has a kind of structure, wherein has and is related to that the shear connector of Qa=Pa, Qb=Pb and Qc=Pc=2Qa=2Pa is formed in groove and with shape formation heterogeneous with line P and Q.
As illustrated in Fig. 9, the section of jurisdiction of each row is with form assembling and the layout of z shape.
Odd column, for example first row, the 3rd row and the 5th row are arranged in same position place, and even column, and for example secondary series, secondary series and the 6th row are positioned at the centerline of section of jurisdiction A,, are positioned at 1/2 below of A that is.
Section of jurisdiction K serves as bind section of jurisdiction and the form assembling with wedge.
Section of jurisdiction K is identical with basic section of jurisdiction A, but top and the Qa place, bottom of online Q form than the short Qd of Qa.
Section of jurisdiction B and C are adjacent to section of jurisdiction K, and are only different from basic section of jurisdiction A at neighbouring surface place.The Qa place, bottom of the online Q of section of jurisdiction B forms than the long Qd of Qa, and the Qa place, top of the online Q of section of jurisdiction C forms than the long Qd of Qa.
The z shape assembly of section of jurisdiction is to be made up of two contiguous sections of jurisdiction at 0c and Pc place.For instance, two Qa are adjacent to Qc and assembled (referring to Fig. 9).
In this way, the structural portion of each section of jurisdiction can significantly not be different from basic section of jurisdiction A, except section of jurisdiction K and section of jurisdiction B adjacent thereto and C have slightly different structures.Therefore, easily manufacture described section of jurisdiction.
Then, the twisted wire of describing each section of jurisdiction is penetrated to path.
In each section of jurisdiction, two central authorities penetrate path 10 and two ends and penetrate path 20 and meet at right angles and form parallelly with cross sectional engagement portion.
Two central authorities penetrate path 10 and are adjacent to the center line of described section of jurisdiction, and two ends penetrate that path 20 is adjacent to end and with respect to center line symmetry.Penetrate into end and penetrate path 20 because need twisted wire to penetrate path 10 by central authorities, thus with distance apart of center line and with end distance be apart identical.
As Fig. 9 and Figure 10 illustrated, penetrate from end the twisted wire that the insertion in path 20 and fixed space district E1 and E2 start and penetrate twisted wire anchorage zone G1 and the G2 in path 10 through central authorities, and be anchored in twisted wire anchorage zone G1 and G2, it has the syndeton of z shape form.In addition, because central authorities penetrate the twisted wire anchorage zone G1 in path 10 and G2 near center line, so can make eccentric bending moment because of soil due to pressure minimum and form the robust construction of section of jurisdiction.
Insert and fixed space district E1 and E2 are formed in the side that end penetrates path 20, and twisted wire anchorage zone G1 and G2 be formed in the side that central authorities penetrate path 10, it is positioned on rightabout.
Twisted wire insertion and fixed space district E1 and E2 are the spaces that is inserted into new twisted wire.
The public cone of front end of twisted wire is anchored in the round taper hole of twisted wire anchorage zone G1 and G2, and the fixed area, rear end of twisted wire is fixed in twisted wire insertion and fixed space district E1 and E2.
In all contact surfaces tangent to each other of section of jurisdiction and section of jurisdiction, water swelling waterproof agent can be set around the flow groove of middle body.
[favourable effect]
(a) according to the present invention, forming two central authorities penetrates the section of jurisdiction that path and two ends penetrate path and sequentially arranges in column, thereby contiguous in a longitudinal direction, twisted wire inserts take longitudinal section of jurisdiction as unit, prestretching and being anchored in four row, only single twisted wire is anchored in each section of jurisdiction, to make only described section of jurisdiction be anchored and fix, three residue twisted wires penetrate path and allow to carry out sequentially grappling and be fixed in the section of jurisdiction in other row by above method, form basis, the section of jurisdiction adjacency test wall that all four twisted wires all penetrate, and simultaneously by structurally stable basis in abutting connection with the easily sequentially grappling and fix the section of jurisdiction in other row of test wall three remaining twisted wires around, and in the time repeating this process, the grappling of basis, section of jurisdiction gained in other row in abutting connection with test wall is sequentially carried out together with boring with fixing.Therefore, can assemble efficiently and economically described section of jurisdiction.
(b) according to the present invention, shear connector is formed at each section of jurisdiction in a lateral direction, section of jurisdiction in each row is arranged in a longitudinal direction with the form of z shape, and twisted wire is arranged to form basis, section of jurisdiction in abutting connection with test wall simultaneously, and and then because of the shear stress due to shear connector with because the overlapping rigidity due to twisted wire can increase, produce so firm tunnel segment structure earthquake etc. to high-durability.
(c) according to the present invention, two central authorities penetrate path and are adjacent to center line, and two ends penetrate path and be adjacent to two ends, and and then its be stable in structure, this is because make because of the eccentric moment minimum due to the differential pressure of soil pressure.
Accompanying drawing explanation
Fig. 1 is cross section state graphic of the normally used shield tunnel rig of explanation.
Fig. 2 is the phantom drawing of the shield duct piece in correlation technique.
Fig. 3 is circular cross section graphic of explanation shield duct piece of the present invention.
Fig. 4 is the phantom drawing of basic section of jurisdiction A of the present invention.
Fig. 5 is the phantom drawing of section of jurisdiction B of the present invention.
Fig. 6 is the phantom drawing of section of jurisdiction C of the present invention.
Fig. 7 is the phantom drawing of section of jurisdiction K of the present invention.
Fig. 8 is the enlarged drawing of Fig. 4.
Fig. 9 is the plan view of explanation section of jurisdiction of the present invention with the state of the arranged in form of z shape.
Figure 10 be schematically illustrate about the section of jurisdiction A1 in the 4th in Fig. 9 row come through and the schematic diagram of grappling twisted wire.
Figure 11 is the phantom drawing of the section of jurisdiction that uses in the bolt method in correlation technique.
Figure 12 is the cross section state that combines by bolt of joint graphic of explanation Figure 11.
[critical element label declaration]
G1, G2: twisted wire anchorage zone
E1, E2: twisted wire inserts and fixed space district
Hole, F2, F3 and F4: twisted wire is through hole
10: central authorities penetrate path
20: end penetrates path
The specific embodiment
The method of building shield tunnel with the tunnel segment structure with longitudinal twisted wire and transverse shearing force key of the present invention with reference to graphic detailed description.
First, of the present invention twisted wire is inserted and is anchored on the basic conception in the section of jurisdiction of the form assembling of z shape as follows.
The length of twisted wire is almost identical with the length of arranging four longitudinal sections of jurisdiction.This is because twisted wire connects and grappling take four longitudinal sections of jurisdiction as unit.The twisted wire of one unit is four section of jurisdiction row, as illustrated in Figure 10.Figure 10 schematically illustrates the graphic of four twisted wires about the row of the 4th in the section of jurisdiction assembly of Fig. 9 A1.
For instance, the twisted wire starting from the first row E2 of Figure 10 by prestretching and be anchored on the 4th row G1.All four twisted wires are through the A1 in the 4th row.Now, be different through starting point and the anchor point of four twisted wires of the A1 in the 4th row.The single twisted wire starting from first row is anchored in the A1 the 4th row.First this twisted wire fixes the A1 in the 4th row.In the time of the A1 fixing in this way in the 4th row, twisted wire is from secondary series, the 3rd row and the 4th leu order.In the time of the A1 not fixing in the 4th row, the twisted wire of secondary series, the 3rd row and the 4th row may be through the A1 in the 4th row.This is because the twisted wire in secondary series in fact can not be through the loose A2 in the 5th row.
The twisted wire starting from secondary series is through the A1 the 4th row, and can be anchored at the 5th row when only the twisted wire that started from first row E2 of A1 in the 4th row is fixing subsequently.This be because only the 4th row be fixed Shi Caike be anchored on the 5th row in.In addition, in order to be anchored in the 6th row since the twisted wire of the 3rd row, need to fix the 5th row and the 4th row simultaneously.
All four twisted wires are through all sections of jurisdiction, but only single section of jurisdiction is anchored in section of jurisdiction.A1 during three residue twisted wires are listed as through the 4th, and be sequentially anchored in next column subsequently.In other words, make basis, section of jurisdiction in abutting connection with test wall by the grappling of twisted wire, described basis reinforces through three twisted wires in abutting connection with test wall, and other bases are repeatedly formed on boring direction in abutting connection with test wall.
As illustrated in Figure 10, four twisted wires in the 4th row are the twisted wires that start from first row, secondary series, the 3rd row and the 4th row.That is to say, the twisted wire starting from first row E2 by prestretching and be anchored on the 4th row G1, and the twisted wire starting from secondary series E2 by prestretching and be anchored on the 5th row G1.Similarly, since the 3rd row E1 twisted wire by prestretching and be anchored on the 6th row G2 in, and since the 4th row E1 twisted wire by prestretching and be anchored on the 7th row G2 in.
In this way, four twisted wires that penetrate in path that are inserted in the 4th row are the twisted wires that start from first row, secondary series, the 3rd row and the 4th row, and are the supporting members that depends on the 4th leu order grappling and fix the 5th row, the 6th row and the 7th row simultaneously.This be the 4th row in A1 why be called as basis in abutting connection with test wall reason.
In addition, the section of jurisdiction in each row is with the arranged in form of z shape, and and then can increase because of the shear stress due to shear connector.In addition, because the only twisted wire in four twisted wires is anchored and is fixed in each row, so the overlapping rigidity of twisted wire can increase, and through assembling structure be firm for the differential pressure due to soil pressure and earthquake, and serve as for by the basis of the section of jurisdiction building continuously in abutting connection with test wall.Therefore, build and be easier to.In addition, the length of twisted wire is the length that makes loss minimum and make tensile force maximum.
Although described for convenience of description seven sections of jurisdiction, as long as the number of section of jurisdiction is odd number, identical concept is applicable to five or seven sections of jurisdiction.
But, in first row, secondary series and the 3rd row of Figure 10, basis is not set in abutting connection with test wall.This is inevitable phenomenon, because section of jurisdiction and twisted wire are to assemble with the form of z shape.
Existing bolt method and assemble method of the present invention are carried out in first row, secondary series and the 3rd row.Because existing bolt method is known, with reference to 10-2004-0026598 korean patent application case, its concept is described briefly.
As illustrated in Figure 11, in 10-2004-0026598 korean patent application case, longitudinal bolt preformed hole 13 and cross bolts preformed hole 12 are formed in section of jurisdiction.In the method, section of jurisdiction is used cross bolts preformed hole 12 connect in a lateral direction and engage, and longitudinal bolt preformed hole 13 is omitted, and longitudinal twisted wire of the present invention penetrates path and forms in a longitudinal direction.First, cross bolts preformed hole 12 is fixed by bolt, and twisted wire uses above method and prestretching and be anchored on longitudinal twisted wire and penetrate in path subsequently.
Figure 12 is tangent to each other and the graphic of bolt 7 and the fixing state of nut 8 that be fixed of explanation cross bolts preformed hole 12.
Hereinafter, will the method for building shield tunnel with the tunnel segment structure with longitudinal twisted wire and transverse shearing force key of the present invention be described.The method of building shield tunnel with the tunnel segment structure with longitudinal twisted wire and transverse shearing force key comprises following operation.
(a) in boring tunnels space region, setting has seven sections of jurisdiction with shape identical in claim 1 and structure, in A1 and A4 and lower end when tangent, sequentially arrange and locate A1 → A2 → B and A4 → A3 → C, to form round-shaped, section of jurisdiction K is inserted and is fixed between B and C, and form the operation of first row.
(b) the each section of jurisdiction in layout and location secondary series is to make it be adjacent to first row, and form the same round-shaped with in first row, the rear end of A1 in secondary series is positioned in the center line of the A1 in first row, and the half of the A1 that first row and secondary series is arranged to be shifted subsequently, set bolt is inserted in the cross bolts preformed hole 13 of first row, and the operation of fixing secondary series and each section of jurisdiction.
(c) the each section of jurisdiction in the 3rd row is arranged and is positioned at round-shaped in, to make it be adjacent to secondary series, and there is the height identical with the corresponding section of jurisdiction of first row, by the half of secondary series and the 3rd row displacement A1, and subsequently set bolt is inserted in the cross bolts preformed hole 13 of secondary series, and fixes the operation of the 3rd row and each section of jurisdiction.
(d) twisted wire is inserted into the each section of jurisdiction A1 in first row, A2, B, K, C, the twisted wire of A3 and A4 insert and fixed space district E2 in and through the F3-G1 in E2-F2 → four row in F3-G1 → three row in secondary series, by twisted wire prestretching and be anchored on and be arranged in the 4th each section of jurisdiction A1 being listed as, A2, B, K, C, in the twisted wire anchorage zone G1 of A3 and A4, be fixed in the each section of jurisdiction in the 4th row, the twisted wire that twisted wire is inserted into the each section of jurisdiction in secondary series insert and fixed space district E2 in and through the F3-G1 in E2-F2 → five row in F3-G1 → four row in the 3rd row, by twisted wire prestretching and be anchored on and be arranged in the 5th each section of jurisdiction A1 being listed as, A2, B, K, C, in the twisted wire anchorage zone G1 of A3 and A4, and be fixed in the each section of jurisdiction in the 5th row, and use identical method, with the order of the 3rd row and the 4th row, twisted wire is inserted in the twisted wire insertion and fixed space district E1 of each section of jurisdiction, with the order of the 6th row and the 7th row, twisted wire prestretching is arranged in to the 6th row and the 7th each section of jurisdiction A1 being listed as with being anchored on, A2, B, K, C, in the twisted wire anchorage zone G2 of A3 and A4, and be fixed in the operation of each section of jurisdiction of the 6th row and the 7th in being listed as.
(e) by by twisted wire insert and be pulled in secondary series in advance in fix the 5th row in each section of jurisdiction time, by by twisted wire insert and be pulled in advance the 3rd row in fix the 6th row in each section of jurisdiction, and by by twisted wire insert and be pulled in advance the 4th row in fix the 7th row in each section of jurisdiction, because using with method identical in first row, twisted wire is inserted and is pulled in advance in the 5th row, be again fixed in the operation of the each section of jurisdiction in the 8th row.
(f) by being inserted and be pulled in advance in the 6th row, twisted wire fixes the each section of jurisdiction that is arranged in the 9th row, by being inserted and be pulled in advance in the 7th row, twisted wire fixes the each section of jurisdiction that is arranged in the tenth row, in n-3 row, fix by twisted wire is inserted and is pulled in advance the each section of jurisdiction that is arranged in n row, and and then sequentially carry out the operation of the assembling to shield tunnel.
In addition, the tunnel segment structure in use with longitudinal twisted wire and transverse shearing force key is built in the method for shield tunnel, public the front end of twisted wire cone is anchored in the round taper hole being formed in twisted wire anchorage zone G1 and G2, and the fixed area, rear end of twisted wire is fixed in twisted wire insertion and fixed space district E1 and E2.

Claims (5)

1. one kind has the tunnel segment structure of longitudinal twisted wire and transverse shearing force key, wherein two central authorities penetrate path (10) and two ends and penetrate path (20) and meet at right angles and form with cross sectional engagement portion, penetrate in path (10) in described two central authorities, form twisted wire through hole F3 and F4 and twisted wire anchorage zone G1 and G2, described twisted wire anchorage zone G1 and G2 are positioned at tunnel boring direction side, penetrate in path (20) at described two ends, twisted wire insertion and fixed space district E1 and E2 and twisted wire are formed through hole F1 and F2, described twisted wire insertion and fixed space district E1 and E2 and described twisted wire anchorage zone G1 and G2 are positioned on rightabout, form with line P and Q and there is the Qa=Pa of relation, the basic section of jurisdiction A (A1=A2=A3=A4) of the shear connector of Qb=Pb and Qc=Pc=2Qa=2Pa is formed, in A1 and A4 and lower end when tangent, on A1 A2 → B and on A4 A3 → C sequentially arrange, section of jurisdiction K is inserted between B and C, and described section of jurisdiction B, C is identical with described basic section of jurisdiction A with K, except described section of jurisdiction B and described section of jurisdiction C, the bottom Qa of online Q and the Qa place, top of described line Q form than the long Qd of Qa respectively, and the described section of jurisdiction K corresponding with it the top of described line Q and Qa place, bottom form than the short Qd of Qa outside.
2. tunnel segment structure according to claim 1,
Wherein, be formed in described twisted wire anchorage zone G1 and G2 corresponding to the round taper hole of the public cone of the front end of described twisted wire, and corresponding to the space region of the fixed area, rear end of described twisted wire be formed at that described twisted wire inserts and fixed space district E1 and E2 in.
3. tunnel segment structure according to claim 1 and 2,
Wherein flow groove and water swelling waterproof agent are formed at the junction surface place of the four edges of each section of jurisdiction.
4. use has the method that the tunnel segment structure of longitudinal twisted wire and transverse shearing force key is built shield tunnel, and described method comprises:
(a) in boring tunnels space region, setting has seven sections of jurisdiction with shape identical in claim 1 and structure, in A1 and A4 and lower end when tangent, sequentially arrange and locate A1 → A2 → B and A4 → A3 → C, to form round-shaped, section of jurisdiction K is inserted and is fixed between B and C, and form the operation of first row;
(b) the each section of jurisdiction in layout and location secondary series is to make it be adjacent to first row, and form the same round-shaped with in described first row, the rear end of A1 in described secondary series is positioned in the center line of the A1 in described first row, and the half of the A1 that described first row and described secondary series is arranged to be shifted subsequently, set bolt is inserted in the cross bolts preformed hole (13) of described first row, and the operation of fixing described secondary series and each section of jurisdiction;
(c) the each section of jurisdiction in the 3rd row is arranged and is positioned at round-shaped in, to make it be adjacent to described secondary series, and there is the height identical with the described corresponding section of jurisdiction of described first row, by the half of described secondary series and described the 3rd row displacement A1, and subsequently set bolt being inserted in the cross bolts preformed hole (13) of described secondary series, and the operation of fixing described the 3rd row and each section of jurisdiction;
(d) twisted wire is inserted into the each section of jurisdiction A1 in described first row, A2, B, K, C, the twisted wire of A3 and A4 insert and fixed space district E2 in and through the F3-G1 in the E2-F2 in the F3-G1 in described secondary series → described the 3rd row → described the 4th row, by described twisted wire prestretching and be anchored on and be arranged in the described the 4th each section of jurisdiction A1 being listed as, A2, B, K, C, in the twisted wire anchorage zone G1 of A3 and A4, be fixed in the each section of jurisdiction in described the 4th row, the described twisted wire that described twisted wire is inserted into each section of jurisdiction in described secondary series insert and fixed space district E2 in and through the F3-G1 in the E2-F2 in the F3-G1 in described the 3rd row → described the 4th row → described the 5th row, by described twisted wire prestretching and be anchored on and be arranged in the described the 5th each section of jurisdiction A1 being listed as, A2, B, K, C, in the described twisted wire anchorage zone G1 of A3 and A4, and be fixed in the each section of jurisdiction in described the 5th row, and use identical method, with the order of described the 3rd row and described the 4th row, described twisted wire is inserted in the described twisted wire insertion and fixed space district E1 of each section of jurisdiction, with the order of described the 6th row and described the 7th row, described twisted wire prestretching is arranged in to described the 6th row and the 7th each section of jurisdiction A1 being listed as with being anchored on, A2, B, K, C, in the described twisted wire anchorage zone G2 of A3 and A4, and be fixed in the operation of each section of jurisdiction of described the 6th row and the described the 7th in being listed as,
(e) by described twisted wire is inserted and be pulled in advance described secondary series in while fixing the each section of jurisdiction in described the 5th row, by being inserted and be pulled in advance, described twisted wire in described the 3rd row, fixes the each section of jurisdiction in described the 6th row, and by being inserted and be pulled in advance, described twisted wire in described the 4th row, fixes the each section of jurisdiction in described the 7th row, described twisted wire is inserted and is pulled in advance in described the 5th row because using with method identical in described first row, be again fixed in the operation of the each section of jurisdiction in the 8th row; And
(f) fix by described twisted wire being inserted and is pulled in advance in described the 6th row the each section of jurisdiction that is arranged in the 9th row, fix by described twisted wire being inserted and is pulled in advance in described the 7th row the each section of jurisdiction that is arranged in the tenth row, fix by described twisted wire is inserted and is pulled in advance in n-3 row the each section of jurisdiction that is arranged in n row, and and then sequentially carry out the operation of the assembling to shield tunnel.
5. method according to claim 4,
Wherein public the front end of described twisted wire cone is anchored in the round taper hole being formed in described twisted wire anchorage zone G1 and G2, and the fixed area, rear end of described twisted wire is fixed in described twisted wire insertion and fixed space district E1 and E2.
CN201280044802.1A 2011-09-15 2012-09-11 There is the tunnel segment structure of longitudinal twisted wire and transverse shearing force key and use the described structure method to build shield tunnel Expired - Fee Related CN103797216B (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
KR10-2011-0092822 2011-09-15
KR1020110092822A KR101470056B1 (en) 2011-09-15 2011-09-15 Segment body with the prestressed strand cables of a longitudinal direction and the shear keys of a horizontal direction
PCT/KR2012/007280 WO2013039315A2 (en) 2011-09-15 2012-09-11 Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same

Publications (2)

Publication Number Publication Date
CN103797216A true CN103797216A (en) 2014-05-14
CN103797216B CN103797216B (en) 2016-06-29

Family

ID=47883875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201280044802.1A Expired - Fee Related CN103797216B (en) 2011-09-15 2012-09-11 There is the tunnel segment structure of longitudinal twisted wire and transverse shearing force key and use the described structure method to build shield tunnel

Country Status (3)

Country Link
KR (1) KR101470056B1 (en)
CN (1) CN103797216B (en)
WO (1) WO2013039315A2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105257321A (en) * 2015-09-28 2016-01-20 上海市基础工程集团有限公司 Shield tunnel initial-stage construction duct piece pulling connection device and construction method
CN105401957A (en) * 2015-10-23 2016-03-16 济南轨道交通集团有限公司 Shield tunnel duct piece both-way prestress strengthening device and construction method
CN117145522A (en) * 2023-10-27 2023-12-01 北京建工土木工程有限公司 Underwater bottom sealing method for mechanical vertical excavation of tunnel pump house

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20160075901A (en) 2014-12-19 2016-06-30 한국건설기술연구원 Segment structure having shear key of island type and longitudinal strand for shield tunnel
CN107023306B (en) * 2017-06-09 2023-06-20 中南大学 Spiral assembled tunnel structure and construction method thereof
CN108915723B (en) * 2018-07-27 2023-06-27 中铁第四勘察设计院集团有限公司 Shield tunnel segment structure crossing vertical dislocation movable fault

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07252996A (en) * 1994-03-11 1995-10-03 Nippon Steel Corp Steel segment
CN201301715Y (en) * 2008-11-20 2009-09-02 中铁十六局集团有限公司 Shear pin of molding segment
CN201650307U (en) * 2010-04-16 2010-11-24 北京工业大学 Connecting structure of longitudinal separation seams of segments of plastic pipeline for being assembled in soil
CN201705365U (en) * 2010-04-07 2011-01-12 中国石油天然气集团公司 Duct piece structure of shield tunnel through mouth
JP4707308B2 (en) * 2002-07-26 2011-06-22 東京地下鉄株式会社 Precast member wall structure and its joint

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007270473A (en) * 2006-03-31 2007-10-18 Ishikawajima Constr Materials Co Ltd Composite segment and composite segment joint structure
KR100936471B1 (en) * 2007-03-09 2010-01-13 한국건설기술연구원 A circular structure supported by the segment with A drainage structure and method constructing the shield tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07252996A (en) * 1994-03-11 1995-10-03 Nippon Steel Corp Steel segment
JP4707308B2 (en) * 2002-07-26 2011-06-22 東京地下鉄株式会社 Precast member wall structure and its joint
CN201301715Y (en) * 2008-11-20 2009-09-02 中铁十六局集团有限公司 Shear pin of molding segment
CN201705365U (en) * 2010-04-07 2011-01-12 中国石油天然气集团公司 Duct piece structure of shield tunnel through mouth
CN201650307U (en) * 2010-04-16 2010-11-24 北京工业大学 Connecting structure of longitudinal separation seams of segments of plastic pipeline for being assembled in soil

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105257321A (en) * 2015-09-28 2016-01-20 上海市基础工程集团有限公司 Shield tunnel initial-stage construction duct piece pulling connection device and construction method
CN105401957A (en) * 2015-10-23 2016-03-16 济南轨道交通集团有限公司 Shield tunnel duct piece both-way prestress strengthening device and construction method
CN117145522A (en) * 2023-10-27 2023-12-01 北京建工土木工程有限公司 Underwater bottom sealing method for mechanical vertical excavation of tunnel pump house
CN117145522B (en) * 2023-10-27 2024-01-26 北京建工土木工程有限公司 Underwater bottom sealing method for mechanical vertical excavation of tunnel pump house

Also Published As

Publication number Publication date
KR20130029524A (en) 2013-03-25
WO2013039315A3 (en) 2013-05-10
KR101470056B1 (en) 2014-12-05
CN103797216B (en) 2016-06-29
WO2013039315A2 (en) 2013-03-21

Similar Documents

Publication Publication Date Title
CN103797216A (en) Segment structure having vertical strands and horizontal shear keys and method for constructing shield tunnel using same
CN107725068A (en) A kind of assembled supporting construction and its construction method based on outside steel arch-shelf and inner side concrete slab
CN110656951A (en) Disaster safety control method for full-face tunnel boring machine excavation extrusion deformation card machine
CN102900449B (en) Support method for underground goaf roof of coal mine
CN102562093B (en) Full-length anchoring supporting method with intensive resin anchor rod and anchor-shotcrete net
KR101483763B1 (en) Method constructing the shield tunnel using segments with the prestressed strand cables of a longitudinal direction and the shear keys of a horizontal direction
CN106592824A (en) Precast cavity type middle-thin wall concrete shear wall
CN110566226A (en) shallow-consolidation deep-injection supporting method for rapid excavation of broken roof large-section roadway
CN109578032A (en) A kind of high stress breaking surrounding rock chamber reinforcement means
CN112832778A (en) Construction structure and construction method of medium-hardness and hard surrounding rock super-large section tunnel
CN211174126U (en) Open cut tunnel structure
JP2006219914A5 (en)
CN102418400B (en) Pretensioning prestressed reinforced concrete precast beam
CN109736807A (en) The double stope moat ditch formula mining methods of long route
JP5246426B2 (en) Construction method of underground structure
CN112112669B (en) Method for laying wall steel frame in multi-arch tunnel
CN106703878B (en) A kind of block method of the prefabricated block self locking solid wall of new concrete
JP4760548B2 (en) Side-by-side tunnel structure and its construction method
CN102852539A (en) Resin bolting ejector anchor net roadway support method
JPH1054197A (en) Segment for shield lining, and method for constructing shield tunnel
JPH03202598A (en) Reinforced structure of eye-glass shaped tunnel
CN201794216U (en) Reinforced concrete prefabricated beam pre-stressed by pre-tensioning method
KR101599295B1 (en) Moudle unit and moudle unit for under-ground structure and under-ground structure construction method therewith
CN114922063B (en) Suspension bridge tunnel type anchorage
JP2899661B2 (en) Large section tunnel and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160629

Termination date: 20210911