CN103791227B - The medical liquid oxygen concentration gas supply system Construction Method - Google Patents

The medical liquid oxygen concentration gas supply system Construction Method Download PDF

Info

Publication number
CN103791227B
CN103791227B CN 201410049418 CN201410049418A CN103791227B CN 103791227 B CN103791227 B CN 103791227B CN 201410049418 CN201410049418 CN 201410049418 CN 201410049418 A CN201410049418 A CN 201410049418A CN 103791227 B CN103791227 B CN 103791227B
Authority
CN
Grant status
Grant
Patent type
Prior art keywords
pipe
construction
oxygen
pressure
tank
Prior art date
Application number
CN 201410049418
Other languages
Chinese (zh)
Other versions
CN103791227A (en )
Inventor
沈延辉
王追尚
沈静君
刘学应
Original Assignee
宁波奉天海供氧净化成套设备有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Grant date

Links

Abstract

本发明公开了医用液态氧集中供气系统施工工法,包括如下步骤:(1)施工准备,(2)贮槽吊装,(3)贮槽运输,(4)贮槽安装,(5)管道脱脂,(6)管道安装,(7)管道强度试验,(8)管道吹扫,(9)设备带安装,(10)阀门安装,(11)气密性试验,(12)管道接地,(13)站内调试,(14)竣工检验。 The present invention discloses a medical liquid oxygen concentration gas supply system construction method comprising the steps of: (1) construction preparation, (2) lifting the tank, (3) transport tank (4) installed tank, degreasing (5) pipe , (6) pipe installation, (7) strength test pipe, (8) the purge pipe, (9) with a mounting device (10) valve is installed, (11) air tightness test, (12) ground pipeline, (13 ) station commissioning, (14) tests on completion. 本发明根据医疗机构新建、改建、扩建工程中供氧中心部分的建设而实施的技术和方法,使其贮气量大,安全可靠,操作方便,能够降低成本,气品质量高,经济效益显著,且日常维持工作量小;一方面保证医院的安全用氧,另一方面为医院节省成本支出,增加效益,与传统的施工方法相比,在工期、质量、安全等方面具有明显地优势。 According to the present invention is a medical institution new construction, renovation, techniques and methods of construction of the central portion of oxygen in the embodiment of the expansion project, so that a large gas storage, safe, reliable, easy operation, cost reduction, high quality product gas, significant economic benefits, and ongoing maintenance workload is small; the one hand, to ensure the safety of the hospital with oxygen, on the other hand for the hospital to save costs, increase efficiency, compared to conventional construction methods, has obvious advantages in the schedule, quality, safety and so on.

Description

医用液态氧集中供气系统施工工法 The medical liquid oxygen concentration gas supply system Construction Method

技术领域 FIELD

[0001] 本发明涉及医疗机构领域供气施工工法,尤其是涉及医用液态氧集中供气系统施工工法。 [0001] The present invention relates to the field of medical gas construction method particularly relates to a medical liquid oxygen concentration gas supply system Construction Method.

背景技术 Background technique

[0002] 氧气具有非常广泛的用途,主要包括供给呼吸,支持燃烧和反应放热三个方面。 [0002] Oxygen has a very wide range of uses, including supplying breathing, and support combustion reaction exotherm three aspects. 合理吸氧可以改善和调节患者、孕妇、老年人的心脑血管、呼吸系统功能,缓解高血压,心脏病,慢性肺病等疾病的发生及发展,有利于消除疲劳和恢复健康,随着我国医疗卫生事业的发展和人们健康水平的提高,医院的建筑卫生设备水平也得到了有效地改善,医用集中供氧系统在医疗机构的新建、扩建中得到了推广和应用,并成为医疗机构开展诊治疾病、健康保健工作的重要措施之一。 Reasonable regulation and oxygen can improve cardiovascular patients, pregnant women, the elderly, respiratory function, relieve the occurrence and development of hypertension, heart disease, chronic lung disease and other diseases, help eliminate fatigue and restore health, along with our medical improve health development and people's health, building and sanitary equipment level of the hospital has been effectively improved, centralized medical oxygen supply system in the new medical institutions, has been expanded in the promotion and application, and become a medical institutions for treatment of diseases one of the important measures of health care.

[0003] 医用集中供氧是指利用集中供氧系统将氧气气源的高压经减压后,通过管道输送到各个用气终端,并在各个用气终端利用呼吸机、出氧管等设备供气,以满足患者的供氧需求。 [0003] The medical oxygen concentration refers to the use of high-pressure oxygen systems concentrated under reduced pressure oxygen supply is delivered to the respective terminals through the gas conduit, and each terminal using a gas ventilator, oxygen supply pipes and other equipment gas to meet the oxygen needs of patients. 目前,医院集中供氧系统基本上有三种形式:(1)气钢瓶组合,主要由气钢瓶、汇流排、 自动切换控制台、声光报警器及管道和附件组成;(2)PSA制氧系统,主要由制氧主机、无油空气压缩机、缓冲罐、干燥机和贮氧罐及管道系统组成;(3)液氧供气系统,主要由低温液体贮罐、汽化器、止回阀、安全阀、压力表、减压器及管道等组成。 Currently, hospital oxygen supply system is substantially concentrated in three forms: (1) a combination of gas cylinders, primarily by the gas cylinders, bus, auto switch consoles, sound and light alarm accessories and piping and composition; (2) PSA-oxygen system , oxygen mainly by the host, oil-free air compressor, a buffer tank, dryer, and oxygen storage tanks and the piping system; (3) oxygen gas supply system, mainly from the cryogenic liquid storage tank, carburetor, check valves, safety valves, pressure gauges, pressure reducer and pipe components.

[0004] 目前大多医疗机构采用钢瓶气态氧供应,用液氧的医院在国内所占比例并不高, 存在着管理不便,安全隐患较大,经济成本高等缺点。 [0004] At present, most medical organizations to adopt supply gaseous oxygen cylinders, liquid oxygen proportion of hospitals in the country is not high, there is inconvenience management, greater security risk, high cost economy.

发明内容 SUMMARY

[0005] 本发明的目的在于针对现有技术的缺陷,提供医用液态氧集中供气系统施工工法,以达到使用快捷方便,送气安全可靠,供氧持续稳定,设备利用率高的效果,不仅极大地提高了医疗机构的社会效益和经济效益,更提高了患者的生命安全保障系数。 [0005] The object of the present invention is for the drawbacks of the prior art, to provide a medical liquid oxygen concentration gas supply system construction method to achieve quick and easy to use, safe and reliable gas supply, oxygen supply steady, high utilization effect, only a very earth to improve the social and economic benefits of medical institutions, but also improve the safety of patient protection factor.

[0006] 为了解决上述技术问题,本发明采用如下技术方案: [0006] To solve the above problems, the present invention adopts the following technical solution:

[0007] 医用液态氧集中供气系统施工工法,其特征在于包括如下步骤: [0007] The medical liquid oxygen concentration gas supply system construction method comprising the steps of:

[0008] (1)施工准备 [0008] (1) construction preparation

[0009] 熟悉和审查施工图纸,了解医用气体工程在图纸上预留、预埋的孔洞和管线位置, 结合土建结构施工图纸,核对土建单位已留孔洞的标高、坐标,然后编制施工图预算,列出各分项工程的工作量,确定安装工程中各分项工程用料、用工和机具使用情况,并汇总成表,接着编制安装工程施工技术方案,确定采取的技术措施,编写安全和技术方面的交底记录,最后组织施工人员进行技术培训;选择和设计贮槽安装场地,对地面承载能力、充灌槽车的通行道、通风条件、排水沟和环境安全进行设计,槽车输液金属软管长度小于4米,贮槽至汽车的位置小于3米;根据贮槽充灌后的重量及当地地质状态,按土建图纸要求进行施工及养护; [0009] familiar and review construction drawings to understand the medical gas reserve in the drawings, embedded holes and pipeline location, combined with the structure of civil construction drawings, check civil engineering units have been leaving holes in elevation, coordinates, and preparation of construction drawing budget, lists the workload of each sub-project, determine the installation of the sub-projects in the use of materials, labor and equipment usage, and summarized into a table, then prepare to install construction technology program to determine the technical measures, security and technical writing tests, record-keeping, and finally tissue construction technical training; sump installation site selection and design, the bearing capacity of the ground, filling the tanker traffic channel, ventilation, gutters and environmental safety design, the soft metal infusion tankers tube length less than 4 meters, the position of the sump is less than 3 meters to the car; and local geology based on the weight of the tank filling state, by drawing civil construction and maintenance requirements;

[0010] ⑵贮槽吊装toon] 在贮槽外壳封头上设有两只吊耳,在贮槽外壳正面的左右支脚上各有一只吊耳, 用一台有两只卷扬机的吊机将贮槽由水平状态直立或由直立状态放平,在起吊前先进行试吊,检查吊起的平稳性和可靠性,再开始升高和吊移; [0010] ⑵ lifting sump Toon] in the sump is provided with two lugs head with a housing, each with a lug in the housing around the front support legs sump, using a two winch cranes have the reservoir by a horizontal or vertical groove by a flat standing state, before the first trial lifting crane, lifting the check stability and reliability, and began to rise again suspended shift;

[0012] (3)贮槽运输 [0012] (3) transport tank

[0013] 贮槽运输采用裸装,先将贮槽放在运输车托架上,并用钢带将贮槽与两个运输托架捆绑住,贮槽水平放在两个运输托架上时,贮槽的正面垂直朝上,贮槽外壳底部的管道引出不锈钢封头,把贮槽和运输托架与运输工具连接牢固,运输过程中变更运输工具时,按吊装的要求进行吊装作业; When [0013] using bare transport tank, the first tank bracket on the truck, and with the sump with two strip transport carriage tied down, placed on the sump level two transport carriage, front sump vertically upward, the bottom of the sump duct drawn stainless steel head housing, the sump and transport vehicle is firmly connected to the bracket, when the vehicle is changed during transport, lifting required hoisting operations;

[0014] ⑷贮槽安装 [0014] ⑷ sump installation

[0015] 当贮槽运到现场时,基础设施没有完成,用吊机按吊装的方法将贮槽同运输托架, 从车上吊下,放在有保护措施的地方;当贮槽运到现场,安装就位条件具备时,先将贮槽从车上吊下放到地面上,然后拆开两个运输托架与贮槽捆绑的钢带,再按吊装的要求进行贮槽升高、直立、吊移的就位作业;贮槽安装就位后,检查阀门管道系统,用压力对阀门进行气密性试验,将贮槽的使用接口与配套系统用管道进行连接; [0015] When the tank transported to the site, the infrastructure is not completed, according to the method used crane lifting the tank with shipping brackets, hanging down from the car and place it in place protective measures; when the tank transported to the site when mounted in place conditions are met, the car hanging from the first tank onto the ground, and then open the transport carriage with two binding strip sump, then lifting the requirements of the sump increase, upright, hanging shift operations in place; the sump in place, check valves, pipe systems, the valve pressure air tightness test, the sump system using an interface connected with the supporting pipe;

[0016] (5)管道脱脂 [0016] (5) Degreasing pipe

[0017] 按设计要求进行脱脂,根据管道工作介质、管道材质、管径、管子的脏污情况制定管道的脱脂措施;将有油迹和锈蚀的管子放在槽型容器内用碱溶液进行清洗,再用清水洗净碱水,最后用有机溶剂脱脂,在脱脂液中浸泡2小时,脱脂后的管道和工件用清洁干燥的滤纸擦拭其内壁,直至纸上油脂痕迹消失,或用紫外线灯照射脱脂表面,直至紫荧光消失; 用清水冲洗内表面,冲洗干净后再通风处晾干,然后对脱脂合格的管道及工件封闭管口; (6)管道安装 [0017] degreased according to design requirements, measures to develop skim conduit pipe according to soiling of the working medium, pipe material, pipe diameter, pipe; rust and traces of oil will be placed in the groove of the pipe vessel was washed with an alkaline solution , then washed with water alkaline, and finally the organic solvent degreasing, degreasing was immersed for 2 hours, the pipe piece and the inner wall after the degreasing wiping with a clean dry filter paper, until disappearance of traces of oil on paper, or irradiation with ultraviolet light degreasing the surface, until the purple fluorescence disappeared; the inner surface of the rinsing with water, rinse and then air to dry and defatted qualified pipes and nozzle closure workpiece; (6) installation pipe

[0018] a、先根据图纸要求量取尺寸,并做标记的移植,然后用钢锯或砂轮切割机切割,切割后用锉刀锉去毛刺,切口端面倾斜偏差小于管子外径的1 %,长度小于3_ ; [0018] a, the first amount of drawings according to size, and transplants mark and cut with a hacksaw or grinder after cutting deburring file with a file, the inclined cut end deviation is less than 1% of the pipe diameter, length less than 3_;

[0019] b、采用冷弯法弯制氧气管道,用在压力大于3MPa的管道,弯曲半径大于管子外径的5倍,其他管道大于管子外径的3. 5倍,管子弯曲的角度大于90 %弯扁程度小于8% ; [0019] b, cold bending process bending oxygen pipeline, conduit with a pressure greater than 3MPa angle bending radius larger than 5 times the tube outside diameter, the other conduit is greater than 3.5 times the tube outside diameter, the tube bend is greater than 90 the degree of bending flat% less than 8%;

[0020] c、采用银基钎焊焊接连接,直管上两个对接焊缝中心之间的距离大于管子的外径,长度大于200mm,管道焊缝及其边缘200mm内密封,焊缝距离管道起点的尺寸大于100mm,管道环型焊缝距管道支架、吊架净距离大于50mm,焊接完成后进行外观质量检验,并在表面进行防腐处理; [0020] c, using silver-based brazing weld connection, the outer diameter of the straight tube distance between the center of the butt weld the two tubes greater than a length greater than 200mm, 200mm pipe weld and seal the edges of the weld from the pipeline the starting point of a size greater than 100mm, away from weld ring conduit pipe supports, hangers net distance is greater than 50mm, the quality of the appearance inspection after welding is completed, and anti-corrosion treatment on a surface;

[0021] d、熟悉图纸,了解管道的走向、分支和管道的规格材质、安装位置,进行工艺评定并编制作业指导书,按图施工,用氩弧焊焊接系统管道之间的连接,系统管道穿过墙或底板时,加PVC套管保护,管道支架均匀布置,主管路布置于管井内,吊顶内安装副管道,安装高度根据安装现场作调整,管道支架沿墙或柱子敷设,站房中间管道的吊架安装在梁的下方, 气体管道采用独立的支吊架,钢管与支吊架接触处设绝缘材料;在管道穿越建筑墙体上设置套管,管道与管道之间采用密封材料封口,并在护理站内安装压力表箱,每个床位的供氧管路均从每个病房的墙角穿过,用铝合金装饰罩罩住;按工艺流程图顺序进行施工,当现场条件受到限制,项目质量责任人根据实际情况进行调整,并报工艺责任工程师确认; [0021] d, familiar with the drawings, to understand, the branch pipe and the pipe material specifications, installation location, for process evaluation and preparation of the operating instructions, according to the drawings, the connection between the TIG welding system piping, piping system passes through a wall or floor, and PVC protective casing, the pipe holder arranged uniformly, the main line is disposed within the tube well, the sub duct ceiling installation, the installation height adjusted according to the installation site, laying pipe support along the wall or pillar, an intermediate station house hanger duct mounted below the beam, independent of the gas pipe hanger, hanger pipe and disposed in contact with the insulating material; a sleeve disposed on the pipe through building walls, using a sealing material between the duct and the duct seal , and a pressure gauge mounted in the tank nursing station, each bed through the oxygen supply pipes are each ward from the corner, an aluminum alloy trim cover covering; the construction according to the sequence flow chart, when field conditions are restricted, responsible for project quality adjusted according to actual situation and report to the confirmation process engineer responsibility;

[0022] (7)管道强度试验 [0022] (7) the pipe strength test

[0023] 管道安装完毕后,先检查系统各管道接口、节点和管道支架,然后向管道内充气, 用空气进行预实验,当压力升至试验压力的50%时,观察管道的情况,接着按试验压力的10 %逐级升压,每级稳压5分钟,直至试验压力;稳压10分钟后,再将压力降至设计压力,停压时间根据查漏工作而定; After the [0023] pipeline installation, the system first checks each pipe joint, pipe support node and then inflated into the duct, a preliminary experiment air, when the pressure was raised to 50% of the test pressure, the pipe was observed cases, followed by 10% of the test pressure boosting stepwise, each stage regulator for 5 minutes, until the test pressure; regulator after 10 minutes, and then the pressure was reduced design pressure, stop pressure leak time according to the work;

[0024] (8)管道吹扫 [0024] (8) the purge duct

[0025] 在管道强度试验合格后,编制吹洗方案,采用氮气或压缩空气作为介质进行管道吹扫,在吹扫前先检查支架,并进行加固,将孔板、法兰连接的调节阀、节流阀、安全阀和仪表拆卸,将焊接的阀门和仪表采取流经旁路或卸掉阀头及阀座加保护套,同时设置吹扫禁区,打开各吹扫排污口的房间门窗;在管道吹扫过程中用木锤敲击管道的焊缝、拐角、分支和死角处,直至铁锈、尘土水分及其它杂物消失;吹扫工作结束后,把拆下的阀门器件恢复, 并封住各吹出口,做好吹扫记录; [0025] After passing the test pipe strength, the preparation program purged using nitrogen or compressed air as a purging medium pipe, before purging check stent, and reinforcement, regulating valve orifice, flange connection, throttle valve and meter detached, and the welding instrument valve taken through the bypass or remove the valve head and valve seat wear jackets, while purging the box set, the room door open outfall of each sweep; at by purging conduit pipe weld mallet percussion, corners and dead ends at the branch, until rust, dust and other debris moisture disappeared; work after purging, the valve devices to restore removed, and seals each of the outlets, do purge records;

[0026] (9)设备带安装 [0026] (9) with mounting device

[0027] 管道吹扫完毕后,根据设计图纸要求,在中心线上安装截止阀和氧气快速插座,快速插座的安装高度使大盖合拢后快速插座顶部高出面板,设备带内管道球头与氧气快速插座中心对准,然后旋入螺母,用扳手拧紧,设备带装配完毕后进行压力试验和气密性试验; 设备带用膨胀螺栓紧固在病房墙上,安装高度符合设计图纸要求; [0027] After completion of purging the pipe, according to the design drawings, and the oxygen shut-off valve installed in the center line of the receptacle fast, fast mounting socket so that the height of the large lid closed rapid outlet above the top panel, the devices with a ball head and the pipe oxygen rapid centering socket, and then screwed into the nut, tighten with a wrench, pressure test and tightness test strip device after assembled; expansion bolt tightening device with the wall in the ward, the installation height as designed drawings;

[0028] (10)阀门安装 [0028] (10) Valves

[0029] 设备带安装完毕后,先查看阀门的合格证并核对检查,按设计图纸上标明的规格、 型号和位置安装,当图纸上没有标明位置和高度时,根据现场操作、维修方便及美观的角度设计;安装时阀门的箭头方向与介质流动的方向一致,阀杆向上或水平方向安装; [0029] After the device with installation, first check valve certification and verification checks, according to the design drawings marked specifications, type and location of the installation, when the drawing is not the time indicate position and height, according to the site operation, easy maintenance and aesthetics design angle; direction of the arrow when the valve is mounted coincides with the direction of media flow, the valve stem upward or horizontal mounting;

[0030] (11)气密性试验 [0030] (11) tightness test

[0031] 阀门安装完毕后,对进行试验的管道、容器通入气体,保压24小时,每隔2小时观察压力表的变化,然后计算出泄漏率; [0031] After the installation of the valve, the pipeline testing, the gas introduced into the container, packing 24 hours, every two hours to observe the change of the pressure gauge, and then calculates the leak rate;

[0032] (12)管道接地 [0032] (12) conduit to ground

[0033] 有静电接地要求的管道,各段管子间导电,用静电接地连接的钛管道及不锈钢管道,导线跨接或接地引线采用钛板或不锈钢板过渡,导电接触面除锈并连接,静电接地安装完毕后进行测试; [0033] The electrostatic grounding requirements pipes, tubes between the conductive segments, titanium and stainless steel pipe conduit with an electrostatic ground connection, the ground lead wire jumper or titanium or stainless steel plate using a transition, and connected to the conductive contact surface rust, electrostatic after testing the ground installation;

[0034] (13)站内调试 [0034] (13) station debugging

[0035] 管道接地完毕后,先将器械插头及氧气湿化器插头插入各使用终端,检查插卸的灵活性、互换性和气密性,在手术室和抢救室分别设置两个以上氧气终端,再用氧气湿化器上的流量计检查终端流量,每个终端流量大于l〇L/min ;然后进行报警装置测试,关闭气源,放出供氧管道中气体,当欠压报警装置发出声、光信号时,记下管道压力值,重复3次; [0035] After the completion of the ground pipeline, and the first oxygen humidification apparatus plug inserted into the plug using a terminal, check insertion unloading flexibility, compatibility and air tightness, two or more oxygen is provided in the operating room and emergency room terminals, respectively , then the terminal check the flow meter on the oxygen humidifier, a flow rate greater than each terminal l〇L / min; then a test alarm, turn off gas supply, gas discharge duct oxygen, audible alarm device when the undervoltage when an optical signal, write line pressure value is repeated three times;

[0036] (14)竣工检验 [0036] (14) Test Completion

[0037] 贮槽安装结束和站内调试完毕后,对施工完成的供气系统进行检查,并对工程前期工作、实施情况、初验与试运行情况、经济技术分析进行登记,合格后开始投入使用。 After commissioning is completed within [0037] tank installation is completed and the station, on the completion of construction of the gas supply system of checks and preliminary engineering work, implementation, registration and preliminary acceptance test run, the economic and technical analysis, put into use after passing .

[0038] 进一步,步骤(2)中的贮槽包括内筒、外筒、顶盖和底盖,顶盖的顶面上设置有至少两个吊耳,顶盖的内部设置有升压盘管,升压盘管上设置有压力阀,内筒位于外筒的内部,内筒与外筒之间设置有氧气分配器和空温式汽化器,空温式汽化器的顶面上设置有液相进口,液相进口连接升压盘管,空温式汽化器的底面上设置有气相出口,气相出口连接氧气分配器,底盖的底面上设置有支脚,支脚上设置有吊耳,外筒的侧面上设置有液面观察口、压力表和出气管,实现将液态氧转化成气态氧输出。 [0038] Further, the step of tank (2) comprises an inner cylinder, an outer cylinder, a top cover and a bottom cover, a top cover is provided with at least two lugs, disposed inside the cap with a top surface of the booster coil , the step-up coil is provided with a pressure valve, located inside the outer cylinder the inner cylinder, the oxygen dispenser and evaporator air temperature between the inner tube and the outer tube is provided, the top surface disposed carburetor air temperature are liquid inlet , the bottom surface of the liquid inlet connector boosting coil, air temperature carburetor provided with a gas outlet, a gas phase outlet connected to an oxygen dispenser, the bottom surface of the bottom cover is provided with a foot, is provided with a lug support legs, on the side of the outer cylinder viewing port is provided with a liquid level, pressure gauge and the tube, to achieve liquid oxygen into a gaseous oxygen output.

[0039] 进一步,内筒的底部设置有吸附层,可以有效将液化气体中的杂质吸附,防止杂质通过输送管进入手术室、急诊室等。 [0039] Further, the bottom of the inner cylinder is provided with an adsorption layer, the liquefied gas can be effectively adsorbed impurities, through the delivery tube to prevent impurities from entering the operating room, emergency room.

[0040] 进一步,底盖的内部设置有绝缘层,防止带电物质进入内筒而影响贮槽的安全性。 [0040] Further, inside the bottom cover is provided with an insulating layer, an antistatic material into the cylinder and affect the safety of the sump.

[0041] 本发明由于采用了上述技术方案,具有以下有益效果: [0041] The present invention adopts the above technical solution has the following advantages:

[0042] 使用快捷方便,送气安全可靠,供氧持续稳定,设备利用率高,提高了医疗机构的社会效益和经济效益,提高了患者的生命安全保障系数:本发明根据医疗机构新建、改建、 扩建工程中供氧中心部分的建设而实施的技术和方法,使其贮气量大,贮存压力低,安全可靠,操作方便,能够降低生产成本,气品质量高,比瓶氧供氧系统节省2/3左右,经济效益显著,且日常维持工作量小;一方面保证了医院的安全用氧,另一方面又为医院节省成本支出,增加效益;适用于医疗机构液氧集中供氧工程的规划、设计、施工、使用、保养、维护等各个方面,与传统的施工方法相比较,在工期、质量、安全、造价等技术经济指标方面具有明显地优势;利用流体力学和热力学原理,通过低温液体贮罐、汽化器、减压阀、稳压器等实现无动力、压差式供氧,氧气 [0042] quick and easy to use, safe and reliable gas supply, oxygen supply steady, high capacity utilization, improve the social and economic benefits of medical institutions to improve the lives and safety of patient protection factor: the invention of medical institutions construction, reconstruction, construction techniques and methods of the central portion of the oxygen in the embodiment of the expansion project, so that gas storage, low reservoir pressure, safe, reliable, easy to operate, it is possible to reduce production costs, high quality product gas, oxygen bottles 2 to save oxygen system about / 3, significant economic benefits, and ongoing maintenance workload is small; the one hand, to ensure the safety of the hospital with oxygen, on the other hand for the hospital to save costs, increase efficiency; liquid oxygen for medical institutions centralized planning oxygen supply project , design, construction, use, maintenance, maintenance and other aspects, compared with the traditional construction method has obvious advantages in the technical and economic indicators schedule, quality, safety, cost and other; fluid mechanics and thermodynamics, via cryogenic liquid tank, carburetor, valves, regulators, and other power-free, differential pressure oxygen, oxygen 达终端处均配备有截止阀,使用时只要将截止阀打开,可以不间断供氧,压力、流量稳定,使用快捷、方便;供氧压力仅为钢瓶氧压力的1/16,可避免用钢瓶出线泄漏而引起局部区域或氧浓度增高和其高压力等因素所产生的安全威胁,通过设置氧气欠压声光报警装置,实现供氧的自动或手动切换,采用氧气稳压箱双路设计,保证了供氧的连续性,提高了设备运转的安全性;液态氧通过汽化产生气态氧,减少了充气环节,提高了氧气纯度,运输费用低,占用空间小,无浪费的气源。 Up terminal are equipped with shut-off valve, when used as long as the shut-off valve is opened, uninterrupted supply of oxygen, pressure, flow stability, is quick and easy; oxygen pressure is only 1/16 of the oxygen pressure cylinder, the cylinder can be avoided by line leak caused a security threat or localized regions and their high oxygen concentration increased pressure and other factors produced by providing an oxygen-voltage sound and light alarm devices, manual or automatic switch, with oxygen in the oxygen surge tank dual design, ensure the continuity of supply of oxygen, improve the safety of operation of the device; liquid oxygen gaseous oxygen produced by vaporization, to reduce the inflatable part, to improve the oxygen purity, low transportation costs, a small footprint, waste-free gas source.

附图说明 BRIEF DESCRIPTION

[0043] 图1为本发明医用液态氧集中供气系统施工工法中贮槽的结构示意图; [0043] FIG. 1 is a schematic configuration of the medical liquid oxygen sump concentrate supply system construction method to the present invention;

[0044] 图2为本发明的施工工艺流程图; [0044] FIG. 2 is a process flow diagram for the construction of the invention;

[0045] 图3为本发明中空温式汽化器的工作原理图。 Working Principle [0045] FIG. 3 is an evaporator temperature of the hollow.

具体实施方式 detailed description

[0046] 本发明医用液态氧集中供气系统施工工法,其原理是液氧贮罐内的液态氧经空温式汽化器汽化后输入到氧气分配器,通过分配器上的各阀门分别进入各使用单位的氧气主管路上,各单位或各楼的氧气主管路由管道井通往各楼层的氧气二级稳压稳流箱,在此分别调至各层终端所需的氧气压力并由各层走廊内的横管通向各医疗区域的终端,当医疗工作需要时,将医疗器械插到墙上的氧气快速接头上即可吸入所需的纯净氧气。 [0046] The present invention focuses on the medical liquid oxygen supply system construction method principle is input after the liquid oxygen evaporator air temperature by vaporization of liquid oxygen in the oxygen tank to the dispenser, through the valve into the dispenser on each used separately oxygen charge of road units, each unit in charge of routing tube wells or oxygen leading to each floor of each building two oxygen steady flow tank, this corridor layers were adjusted to the required layers by the terminal oxygen pressure the leading end of each cross tube medical area, when the medical needs work, the medical device can be sucked into the pure oxygen required for the oxygen quick connector wall.

[0047] 本发明需要准备如下材料: [0047] The present invention need the following materials:

[0048] 1、主要材料如表1所示 [0048] 1, the main material as shown in Table 1

[0049] [0049]

Figure CN103791227BD00091

[0050] 表1主要材料表 [0050] Table 1 Main Table Material

[0051] 2、机具设备如表2所示: [0051] 2, machinery equipment as shown in Table 2:

[0052] [0052]

Figure CN103791227BD00092

[0053] [0053]

Figure CN103791227BD00101

Figure CN103791227BD00111

[0055] 表2主要生产设备 [0055] Table 2 The main production equipment

[0056] 3、本发明的相关数据如表3所示: [0056] 3, according to the present invention, data shown in Table 3:

[0057] [0057]

Figure CN103791227BD00112

[0058] 表3建筑物、构筑物之间的防火间距 Fire spacing between the [0058] Table 3 buildings, structures

[0059] 本发明的实施步骤如图2所示,包括如下步骤: [0059] Step embodiment of the present invention shown in Figure 2, comprising the steps of:

[0060] (1)施工准备 [0060] (1) construction preparation

[0061] 熟悉和审查施工图纸,了解医用气体工程在图纸上预留、预埋的孔洞和管线位置, 结合土建结构施工图纸,核对土建单位已留孔洞的标高、坐标,然后编制施工图预算,列出各分项工程的工作量,确定安装工程中各分项工程用料、用工和机具使用情况,并汇总成表,接着编制安装工程施工技术方案,确定采取的技术措施,编写安全和技术方面的交底记录,最后组织施工人员进行技术培训;选择和设计贮槽安装场地,对地面承载能力、充灌槽车的通行道、通风条件、排水沟和环境安全进行设计,槽车输液金属软管长度小于4米,贮槽至汽车的位置小于3米;根据贮槽充灌后的重量及当地地质状态,按土建图纸要求进行施工及养护; [0061] familiar and review construction drawings to understand the medical gas reserve in the drawings, embedded holes and pipeline location, combined with the structure of civil construction drawings, check civil engineering units have been leaving holes in elevation, coordinates, and preparation of construction drawing budget, lists the workload of each sub-project, determine the installation of the sub-projects in the use of materials, labor and equipment usage, and summarized into a table, then prepare to install construction technology program to determine the technical measures, security and technical writing tests, record-keeping, and finally tissue construction technical training; sump installation site selection and design, the bearing capacity of the ground, filling the tanker traffic channel, ventilation, gutters and environmental safety design, the soft metal infusion tankers tube length less than 4 meters, the position of the sump is less than 3 meters to the car; and local geology based on the weight of the tank filling state, by drawing civil construction and maintenance requirements;

[0062] (2)贮槽吊装 [0062] (2) Lifting sump

[0063] 如图1所示,IC槽包括内筒2、外筒1、顶盖4和底盖6,顶盖4的顶面上设置有至少两个吊耳5,顶盖4的内部设置有升压盘管12,升压盘管12上设置有压力阀13,内筒2位于外筒1的内部,内筒2的底部设置有吸附层7,可以有效将液化气体中的杂质吸附,防止杂质通过输送管进入手术室、急诊室等;内筒2与外筒1之间设置有氧气分配器3和空温式汽化器14,空温式汽化器14的顶面上设置有液相进口16,液相进口16连接升压盘管12,空温式汽化器14的底面上设置有气相出口17,气相出口17连接氧气分配器3,空温式汽化器14的工作原理如图3所示,底盖6的内部设置有绝缘层8,防止带电物质进入内筒2而影响贮槽的安全性,底盖6的底面上设置有支脚9,支脚9上设置有吊耳5,外筒1的侧面上设置有液面观察口10、压力表11和出气管15,实现将液态氧转化成气态氧输出。 [0063] As shown, the IC comprises a groove inner cylinder 2, the outer tube 1, the cap 4 and the bottom cover 6, a top surface of the top cover 4 is provided with at least two lifting lugs 5, arranged inside the top cover 4 step-up coil 12, the boost coil 12 is provided with a pressure valve 13, the inner cylinder 2 located within the outer cylinder 1, the bottom of the inner tube 2 is provided with an adsorption layer 7, the liquefied gas can be effectively adsorbed impurities, through the delivery tube to prevent impurities from entering the operating room, emergency room and the like; oxygen dispenser 3 is provided with a carburetor and air temperature between the outer cylinder 2 and the inner tube 14 1, air-temperature liquid vaporizer is provided with a top surface 14 of the inlet 16 , the liquid inlet 16 is connected to the boosting coil 12, a bottom surface of the air-temperature vaporizer 14 is provided with a gas outlet 17, oxygen gas outlet 17 is connected to the dispenser 3, the working principle of air-temperature vaporizer 14 shown in Figure 3, the bottom inside the cover 6 is provided with an insulating layer 8, antistatic substances into the inner cylinder 2 and affect the safety of the sump, the bottom surface of the bottom cover 6 is provided with a leg 9 is provided with a lug 5 9 foot, the side surface of the outer cylinder 1 It is provided with a viewing port on the liquid surface 10, pressure gauge 11 and the outlet pipe 15, to achieve liquid oxygen into a gaseous oxygen output.

[0064] 在贮槽外壳封头上设有两只吊耳,在贮槽外壳正面的左右支脚上各有一只吊耳, 用一台有两只卷扬机的吊机将贮槽由水平状态直立或由直立状态放平,在起吊前先进行试吊,检查吊起的平稳性和可靠性,再开始升高和吊移。 [0064] provided in the sump housing head with two lugs, each lug around a sump housing front support legs, using a machine with two winch cranes to erect a horizontal state or sump the discharge from the upright state level prior to the first trial lifting crane, lifting the check stability and reliability, and the suspension began to rise again shifted.

[0065] 空温式汽化器是通过吸收外界环境中的热量并传递给低温介质使其汽化的设备。 [0065] carburetor air temperature by absorbing heat in the external environment, and transmitted to the device so that vaporized cryogenic medium. 由于其具备结构简单、运行成本低廉等优点广泛应用于低温液体汽化器。 Because of its simple structure, low operating cost and the like are widely used in low-temperature liquid vaporizer. 由热力学相关知识可知,汽化器管内工作介质的压力在临界压力以上,温度低于临界温度时为液体,高于临界温度时为气体;在临界压力和临界温度以下时,有一相变的气-液两相区,温度高于压力对应的饱和温度时为气体,低于饱和温度时为过冷液体。 As seen from thermodynamic knowledge, the pressure within the vaporizer tube working medium above a critical pressure and a temperature below the critical temperature of the liquid, above the critical temperature of the gas; at critical pressure and critical temperature, has a phase transition of the gas - liquid when the two-phase region, the temperature higher than the saturation temperature corresponding to the pressure of a gas, subcooled liquid is below the saturation temperature. 如果压力高于临界压力,它的换热特点是分为预热段(临界温度以下)和蒸发段(临界温度以上)两个区段,没有两相共存的汽化阶段。 If the pressure above the critical pressure, it is characterized by a heat exchanger into the preheating section (critical temperature) and the evaporating section (above the critical temperature) of the two sections, there is no vaporization stage of a two phase coexist. 因此,介质的压力和温度决定汽化器的设计方案,不同的流态传热特性有很大差别,需分别考虑、计算。 Thus, the pressure and temperature of the medium determines the design of the vaporizer, the heat transfer characteristics of different flow patterns are very different, need to be considered separately calculated.

[0066] 按照热力学第一定律,汽化器的汽化过程中吸收的总热量,有如下关系式: [0066] According to the first law of thermodynamics, the total heat absorbed in vaporization of the vaporizer, there is the following relationship:

[0067] Q = m (hout-hin) = (Q^Qg) η [0067] Q = m (hout-hin) = (Q ^ Qg) η

[0068] 式中:Q为星型翅片导热管在单位时间内的传热量--KJ/s ; [0068] wherein: Q is a star-shaped finned heat transfer tube in a heat transfer amount per unit time --KJ / s;

[0069] m为单位时间内汽化液体质量--Kg ; [0069] m is the mass of liquid vaporized per unit time --Kg;

[0070] h-为汽化器出口气体焓值--KJ/Kg ; [0070] h- gas at the outlet of the vaporizer enthalpy --KJ / Kg;

[0071] hin为汽化器进口液体焓值--KJ/Kg ; [0071] hin liquid inlet enthalpy to the evaporator --KJ / Kg;

[0072] QiS单排星型翅片导热管液相区单位时间内的传热量--KJ/s ; [0072] QiS single row star-shaped finned heat transfer tubes transfer heat --KJ / s within the liquid phase region per unit time;

[0073] 〇8为单排星型翅片导热管气相区单位时间内的传热量--KJ/s ; [0073] 〇8 a single row star-shaped finned heat transfer tube in the gas phase heat transfer area per unit time --KJ / s;

[0074] N为星型翅片导热管的排数。 [0074] N is the number of rows of finned heat transfer tubes of the star.

[0075] (3)贮槽运输 [0075] (3) transport tank

[0076] 贮槽运输采用裸装,先将贮槽放在运输车托架上,并用钢带将贮槽与两个运输托架捆绑住,贮槽水平放在两个运输托架上时,贮槽的正面垂直朝上,贮槽外壳底部的管道引出不锈钢封头,把贮槽和运输托架与运输工具连接牢固,中等速度行驶,不得激烈振动,严禁贮槽与其他任何物体碰撞,在任何时候都禁止对贮槽作滚动搬动搬运,只有当两个运输托架在植草安装就位的吊装前才能拆除;运输过程中变更运输工具时,按吊装的要求进行吊装作业; When [0076] using bare transport tank, the first tank bracket on the truck, and with the sump with two strip transport carriage tied down, placed on the sump level two transport carriage, front sump vertically upward, the bottom of the sump duct drawn stainless steel head housing, the sump and transport vehicle is firmly connected with the carriage, moderate speeds, the vibration can not be intense, non sump collision with any other objects in the prohibited at any time for rolling tanks moving handling, lifting the front only when two transport brackets in place in order to dismantle grass; when changing vehicles, according to the requirements of hoisting lifting operations carried out during transport;

[0077] (4)贮槽安装 [0077] (4) mounted sump

[0078] 当贮槽运到现场时,基础设施没有完成,用吊机按吊装的方法将贮槽同运输托架, 从车上吊下,放在有保护措施的地方;当贮槽运到现场,安装就位条件具备时,先将贮槽从车上吊下放到地面上,然后拆开两个运输托架与贮槽捆绑的钢带,再按吊装的要求进行贮槽升高、直立、吊移的就位作业;在吊装过程中,严禁碰撞摔打,并特别注意外壳顶部的安全装置、底部的真空规管和抽真空阀不得碰撞,就位时应挂垂直线,垂直度不大于2/1000 ;贮槽安装就位后,检查阀门管道系统,用压力对阀门进行气密性试验,将贮槽的使用接口与配套系统用管道进行连接; [0078] When the tank transported to the site, the infrastructure is not completed, according to the method used crane lifting the tank with shipping brackets, hanging down from the car and place it in place protective measures; when the tank transported to the site when mounted in place conditions are met, the car hanging from the first tank onto the ground, and then open the transport carriage with two binding strip sump, then lifting the requirements of the sump increase, upright, hanging shift operations in place; in the lifting process, non-collision beat, with particular attention to the safety device on top of the housing, and the vacuum gauge of the vacuum valve at the bottom can not be a collision, should hang the vertical position, perpendicular not more than 2 / 1000; in place after the tank, check valve piping system, the valve pressure air tightness test, the sump system using an interface connected with the supporting pipe;

[0079] (5)管道脱脂 [0079] (5) Degreasing pipe

[0080] 按设计要求进行脱脂,根据管道工作介质、管道材质、管径、管子的脏污情况制定管道的脱脂措施;将有油迹和锈蚀的管子放在槽型容器内用碱溶液进行清洗,再用清水洗净碱水,最后用有机溶剂脱脂,在脱脂液中浸泡2小时,脱脂后的管道和工件用清洁干燥的滤纸擦拭其内壁,直至纸上油脂痕迹消失,或用紫外线灯照射脱脂表面,直至紫荧光消失; 用清水冲洗内表面,冲洗干净后再通风处晾干,然后对脱脂合格的管道及工件封闭管口;脱脂用的有机溶剂多次使用后含油量提高需及时更换,规定如表4所示: [0080] degreased according to design requirements, measures to develop skim conduit pipe according to soiling of the working medium, pipe material, pipe diameter, pipe; rust and traces of oil will be placed in the groove of the pipe vessel was washed with an alkaline solution , then washed with water alkaline, and finally the organic solvent degreasing, degreasing was immersed for 2 hours, the pipe piece and the inner wall after the degreasing wiping with a clean dry filter paper, until disappearance of traces of oil on paper, or irradiation with ultraviolet light degreasing the surface, until the purple fluorescence disappeared; the inner surface of the rinsing with water, rinse and then dry and ventilated place, then skim conduit and the work of qualified closing the nozzle; degreased with an organic solvent a plurality of times using increasing oil content shall be changed , as specified in table 4:

[0081] [0081]

Figure CN103791227BD00131

[0082] 表4脱脂剂含油量参数 [0082] TABLE 4 Oil content parameter degreasers

[0083] (6)管道安装 [0083] (6) plumbing

[0084] a、先根据图纸要求量取尺寸,并做标记的移植,然后用钢锯或砂轮切割机切割,切割后用锉刀锉去毛刺,切口端面倾斜偏差小于管子外径的1 %,长度小于3_ ; [0084] a, the first amount of drawings according to size, and transplants mark and cut with a hacksaw or grinder after cutting deburring file with a file, the inclined cut end deviation is less than 1% of the pipe diameter, length less than 3_;

[0085] b、采用冷弯法弯制氧气管道,用在压力大于3MPa的管道,弯曲半径大于管子外径的5倍,其他管道大于管子外径的3. 5倍,管子弯曲的角度大于90 %弯扁程度小于8% ; [0085] b, cold bending process bending oxygen pipeline, conduit with a pressure greater than 3MPa angle bending radius larger than 5 times the tube outside diameter, the other conduit is greater than 3.5 times the tube outside diameter, the tube bend is greater than 90 the degree of bending flat% less than 8%;

[0086] c、采用银基钎焊焊接连接,直管上两个对接焊缝中心之间的距离大于管子的外径,长度大于200mm,管道焊缝及其边缘200mm内密封,焊缝距离管道起点的尺寸大于100mm,管道环型焊缝距管道支架、吊架净距离大于50mm,管道的固定焊接对接,对接接口不得强行组对焊接,其内壁错边量小于壁厚的10%,并将管道垫置牢固;焊接完成后进行外观质量检验,并在表面进行防腐处理,严禁在带压管道上进行焊接、开孔、切割等作业,必须放空管道内的介质,使压力降至零后可作业; [0086] c, using silver-based brazing weld connection, the outer diameter of the straight tube distance between the center of the butt weld the two tubes greater than a length greater than 200mm, 200mm pipe weld and seal the edges of the weld from the pipeline the starting point of a size greater than 100mm, away from weld ring conduit pipe supports, hangers net distance is greater than 50mm, the fixed butt welding of pipes, the docking interface can not be forced to set the welding, the inner wall is less than the wall thickness of the wrong side of 10%, and the underlaying pipe firmly; the appearance quality inspection after completion of welding, and the surface of the anti-corrosion treatment, is prohibited welding, drilling, cutting and other operations on a pipeline with pressure, must be vented medium within the conduit, the pressure may drop to zero after operation;

[0087] d、熟悉图纸,了解管道的走向、分支和管道的规格材质、安装位置,按图施工,用氩弧焊焊接系统管道之间的连接,系统管道穿过墙或底板时,加PVC套管保护,管道支架均匀布置,主管路布置于管井内,吊顶内安装副管道,安装高度根据安装现场作调整,副管道支架最大间距为2m,主管道支架最大间距为2. 5m ;管道支架沿墙或柱子敷设,站房中间管道的吊架安装在梁的下方,气体管道采用独立的支吊架,钢管与支吊架接触处设绝缘材料;在管道穿越建筑墙体上设置套管,管道与管道之间采用不燃性密封材料封口,并在护理站内安装压力表箱,每个床位的供氧管路均从每个病房的墙角穿过,用铝合金装饰罩罩住;按工艺流程图顺序进行施工,当现场条件受到限制,项目质量责任人根据实际情况进行调整,并报工艺责任工程师确认;管道的支架安 [0087] d, when familiar with the drawings, to understand, the branch pipe and the pipe material specifications, installation location, according to the drawings, the connection between the TIG welding system piping, conduit through a wall or floor system, and PVC protective casing, the pipe holder arranged uniformly, the main line is disposed within the tube well, the sub duct ceiling installation, the installation height adjusted according to the installation site, the sub-pipe support distances up to 2m, the maximum spacing of the main pipe bracket 2. 5m; pipe racks laying along the wall or pillar, pipe hanger station house is mounted below the intermediate beam, independent of the gas pipe hanger, hanger pipe and disposed in contact with the insulating material; a sleeve disposed on the pipe through the building wall, between the pipe and the pipe using a seal material sealing an incombustible, and tank pressure gauge mounted in the nursing station, each bed through the oxygen supply pipes are each ward from the corner, cover with aluminum decorative cover; press process the construction sequence diagram, when site conditions are restricted, responsible for project quality adjusted according to actual situation and report to the responsible engineer confirmation process; stent pipeline safety 牢固,气体干管采用三角支架共架敷设,管道与支架用管卡固定,支架之间最大距离符合表5所示,安装氧气管道过程中,需要敲击管道时用木锤或橡皮锤敲击,注意防止管道被硬物划伤,防止压弯、压扁; Firm, dry gas tube using common frame, tripod laying pipeline and a fixed support with pipe clips, the maximum distance between the support as specified in Table 5, the oxygen pipeline installation process, if desired tap tapping pipe with a wooden hammer or rubber hammer , avoid hard objects from being scratched conduit, to prevent buckling, flattening;

[0088] [0088]

Figure CN103791227BD00141

[0089] 表5医用气体管道支吊架最大间距[0090] (7)管道强度试验 [0089] Table 5 medical gas pipe hangers maximum spacing [0090] (7) the pipe strength test

[0091] 管道安装完毕后,先检查系统各管道接口、节点和管道支架,然后向管道内充气, 用空气进行预实验,当压力升至试验压力的50%时,观察管道的情况,接着按试验压力的10 %逐级升压,每级稳压5分钟,直至试验压力;稳压10分钟后,再将压力降至设计压力,停压时间根据查漏工作而定; After [0091] The pipeline installation, the system first checks each pipe joint, pipe support node and then inflated into the duct, a preliminary experiment air, when the pressure was raised to 50% of the test pressure, the pipe was observed cases, followed by 10% of the test pressure boosting stepwise, each stage regulator for 5 minutes, until the test pressure; regulator after 10 minutes, and then the pressure was reduced design pressure, stop pressure leak time according to the work;

[0092] (8)管道吹扫 [0092] (8) the purge duct

[0093] 在管道强度试验合格后,编制吹洗方案,采用氮气或压缩空气作为介质进行管道吹扫,在吹扫前先检查支架,并进行加固,将孔板、法兰连接的调节阀、节流阀、安全阀和仪表拆卸,将焊接的阀门和仪表采取流经旁路或卸掉阀头及阀座加保护套,同时设置吹扫禁区,防止吹出口把脏物、杂物吹到墙上、天花板上、各吹出口处严禁站人,防止被吹出的杂物击伤,打开各吹扫排污口的房间门窗;在管道吹扫过程中用木锤敲击管道的焊缝、拐角、分支和死角处,直至铁锈、尘土水分及其它杂物消失;吹扫工作结束后,把拆下的阀门器件恢复,并封住各吹出口,做好吹扫记录; [0093] After passing the test pipe strength, the preparation program purged using nitrogen or compressed air as a purging medium pipe, before purging check stent, and reinforcement, regulating valve orifice, flange connection, throttle valve and meter detached, and the welding instrument valve taken through the bypass or remove the valve head and valve seat wear jackets, while purging the box set, the outlet to prevent dirt, debris blown wall, ceiling, each of the air outlet is prohibited to stand, to prevent debris being blown wounded, room doors open outfall of each sweep; the process by purging conduit pipe weld mallet percussion corner , and dead ends at the branch, until rust, dust and other debris moisture disappeared; work after purging, the valve devices to restore removed, and the outlets sealed, purged good record;

[0094] (9)设备带安装 [0094] (9) with mounting device

[0095] 管道吹扫完毕后,根据设计图纸要求,在中心线上安装截止阀和氧气快速插座,快速插座的安装高度使大盖合拢后快速插座顶部高出面板,设备带内管道球头与氧气快速插座中心对准,然后旋入螺母,用扳手拧紧,设备带装配完毕后进行压力试验和气密性试验; 设备带用膨胀螺栓紧固在病房墙上,安装高度符合设计图纸要求; [0095] After completion of purging the pipe, according to the design drawings, and the oxygen shut-off valve installed in the center line of the receptacle fast, fast mounting socket so that the height of the large lid closed rapid outlet above the top panel, the devices with a ball head and the pipe oxygen rapid centering socket, and then screwed into the nut, tighten with a wrench, pressure test and tightness test strip device after assembled; expansion bolt tightening device with the wall in the ward, the installation height as designed drawings;

[0096] (10)阀门安装 [0096] (10) Valves

[0097] 设备带安装完毕后,先查看阀门的合格证并核对检查,按设计图纸上标明的规格、 型号和位置安装,当图纸上没有标明位置和高度时,根据现场操作、维修方便及美观的角度设计;安装时阀门的箭头方向与介质流动的方向一致,阀杆向上或水平方向安装; [0097] After the device with installation, first check valve certification and verification checks, according to the design drawings marked specifications, type and location of the installation, when the drawing is not the time indicate position and height, according to the site operation, easy maintenance and aesthetics design angle; direction of the arrow when the valve is mounted coincides with the direction of media flow, the valve stem upward or horizontal mounting;

[0098] (11)气密性试验 [0098] (11) tightness test

[0099] 阀门安装完毕后,对进行试验的管道、容器通入气体,保压24小时,每隔2小时观察压力表的变化,然后计算出泄漏率;泄漏率以小于0. 5%为合格。 [0099] After the installation of the valve, the pipeline testing, the gas introduced into the container, packing 24 hours, every two hours to observe the change of the pressure gauge, and then calculates the leak rate; leak rate of less than 0.5% to be acceptable . 计算公式: The formula is:

[0100] A = 100(l-P2Tl/PlT2)/t [0100] A = 100 (l-P2Tl / PlT2) / t

[0101] 式中:A--小时泄漏率,% ; [0101] wherein: A-- hours leak rate,%;

[0102] Pl--试验开始时压力,MPa ; [0102] When the start of the test pressure Pl--, MPa;

[0103] t--试验时间,h ; [0103] t-- test time, h;

[0104] P2--试验结束时压力,MPa ; [0104] P2-- end of the test pressure, MPa;

[0105] Tl--试验开始时温度,K ; [0105] Tl-- temperature at the start of the test, K;

[0106] T2--试验结束时温度,K。 [0106] T2-- end of the test the temperature, K.

[0107] 中压医用气体管道作试验,其介质为洁净水,试验压力为管道设计压力的1. 5倍; 低压医用气体管道作试验,其介质为空气或氮气,试验压力为管道设计压力的1. 15倍;医用真空管道作试验,介质为空气或氮气,试验压力为〇. 2MPa,医用气体管道压力试验维持试验压力10分钟,保持原状态为合格;管道的耐压试验压力和气密性试验压力如表6所示: [0107] medium-pressure medical gas pipeline for testing, which medium is clean water, the test pressure is the design pressure of the pipe 1.5 times; low-pressure gas pipe for medical tests, which medium is air or nitrogen gas, the test pressure is the design pressure of the pipe 1.15 times; the medical vacuum line for testing, the medium is air or nitrogen, is square test pressure 2MPa, medical gas pipeline pressure test test pressure is maintained for 10 minutes to maintain the original state is qualified; test pressure pipes and airtightness as shown in table 6 test pressure:

[0108] [0108]

Figure CN103791227BD00151

[0109] 表6气密性试验及耐压试验规定 [0109] Table 6 tightness test and a predetermined pressure test

[0110] (12)管道接地 [0110] (12) conduit to ground

[0111] 有静电接地要求的管道,各段管子间导电,用静电接地连接的钛管道及不锈钢管道,导线跨接或接地引线采用钛板或不锈钢板过渡,导电接触面除锈并连接,静电接地安装完毕后进行测试; [0111] electrostatic grounding requirements pipes, tubes between the conductive segments, titanium and stainless steel pipe conduit with an electrostatic ground connection, the ground lead wire jumper or titanium or stainless steel plate using a transition, and connected to the conductive contact surface rust, electrostatic after testing the ground installation;

[0112] (13)站内调试 [0112] (13) station debugging

[0113] 管道接地完毕后,先将器械插头及氧气湿化器插头插入各使用终端,检查插卸的灵活性、互换性和气密性,在手术室和抢救室分别设置两个以上氧气终端,再用氧气湿化器上的流量计检查终端流量,每个终端流量大于l〇L/min ;然后进行报警装置测试,关闭气源,放出供氧管道中气体,当欠压报警装置发出声、光信号时,记下管道压力值,重复3次, 按下式计算,应符合报警压力误差不大于3% : [0113] After the completion of the ground pipeline, and the first oxygen humidification apparatus plug inserted into the plug using a terminal, check insertion unloading flexibility, compatibility and air tightness, two or more oxygen is provided in the operating room and emergency room terminals, respectively , then the terminal check the flow meter on the oxygen humidifier, a flow rate greater than each terminal l〇L / min; then a test alarm, turn off gas supply, gas discharge duct oxygen, audible alarm device when the undervoltage when an optical signal, write line pressure value, repeated three times, the following formula should be consistent alarm pressure error less than 3%:

[0114] β = IOOx I pb-po I /po [0114] β = IOOx I pb-po I / po

[0115] 式中:β -一报警装置相对误差,% ; [0115] where: β - an alarm relative error,%;

[0116] pb--实际报警压力值,MPa ; [0116] pb-- actual alarm pressure, MPa;

[0117] po--预置报警压力值,MPa。 [0117] po-- preset alarm pressure, MPa.

[0118] (14)竣工检验 [0118] (14) Test Completion

[0119] 贮槽安装结束和站内调试完毕后,对施工完成的供气系统进行检查,并对工程前期工作、实施情况、初验与试运行情况、经济技术分析进行登记,合格后开始投入使用。 After commissioning is completed within [0119] tank installation is completed and the station, on the completion of construction of the gas supply system of checks and preliminary engineering work, implementation, registration and preliminary acceptance test run, the economic and technical analysis, put into use after passing .

[0120] 本发明质量控制措施: [0120] Quality control measures according to the present invention:

[0121] ⑴所有原材料、元器件、设备和所有外协件,均实行定点采购,供货企业的选定由公司技术人员与采购人员一起考察,所有材料必须经质检部检验合格方能入库; [0121] ⑴ all raw materials, components, equipment and spare parts and all, are the implementation of fixed procurement, supplier firms selected by the investigation with the company's technical staff and procurement staff, all materials must be in order by the QC inspection library;

[0122] (2)对于公称压力大于IMPa的阀门应逐个进行壳体压力试验和密封试验,不合格的不得入库,对公称压力小于IMPa的阀门应从每批中抽查10 %,且不得少于1个,进行壳体压力试验和密封试验; [0122] (2) should be greater than the nominal one by one to the valve housing IMPa pressure test and sealing test, not failed storage, is less than the nominal pressure of the valve should IMPa checks each batch of 10%, and no less than 1, pressure test and sealing test case;

[0123] (3)产品制造的每道工序都必须符合该道工序的加工图纸和工艺文件的技术、质量要求,否则不得转入下道工序; [0123] (3) Manufacturing of each process must meet the technical and technological drawing processing procedure of the document, the quality requirements, or not into the next process;

[0124] (4)对从事医用中心供氧、中心吸引系统工程安装的人员,公司实行定期培训制度,使他们了解、熟悉相应的安装技术及有关知识,并经考核合格,才能从事相应工程的安装; [0124] (4) engaged in medical oxygen supply, central suction system engineering, installation personnel, the company implemented regular training system so that they understand and are familiar corresponding installation technology and knowledge, and after passing an examination in order to engage in the corresponding project installation;

[0125] (5)工程安装必须按图纸要求进行,技术部在工程队出发前对施工人员进行施工技术交底; [0125] (5) installation must be carried out by drawing, the construction technology department technical tests of construction workers in the engineering team before departure;

[0126] (6)每一层或一个部分的管路安装完毕后必须做压力试验和气密性试验,气密性试验压力取管路的设计压力,保压24小时,氧气系统小时泄漏率不大于0. 2% ; [0126] (6) after each layer or portion of a pipe installation must be done pressure test and tightness test, air tightness test pressure taking the line pressure design, packing 24 hours, the oxygen leak rate not hour system greater than 0.2%;

[0127] (7)氧气系统管路与元件禁止与各类油脂接触,严禁带有油污的手套进行操作; [0127] (7) Oxygen system piping and components in contact with various oils prohibited, forbidden to operate the glove with oil;

[0128] (8)管道焊接必须由持证焊工进行施焊,焊接工艺必须经企业焊接工艺评定合格的焊接工艺。 [0128] (8) for welding pipe welding must be performed by a licensed welders, the welding process must be approved by the qualified company welding procedure the welding process.

[0129] 本发明安全控制措施: [0129] The present invention controls security measures:

[0130] (1)坚持安全交底制度,每天上班前,项目负责人除进行施工交底外还需向全体施工人员做安全措施交底; [0130] (1) adhere to safety tests, system, every day before work, project leader for construction tests, in addition to outside needs to be done to all tests, construction workers safety measures;

[0131] (2)严格遵守生产安全和消防安全制度,落实各项安全措施,进入施工现场要戴好安全帽、高空作业时要佩戴安全带、施工现场禁止吸烟等; [0131] (2) strict adherence to production safety and fire safety systems, and implement safety measures, the construction site should wear a helmet to wear a seat belt, the construction site prohibit smoking when high-altitude operations;

[0132] (3)施工用脚手架的搭设必须遵守有关安全技术规程规范、质量标准及工程安全管理规定,搭设要整齐统一,符合安全生产和施工需要; [0132] (3) must comply with the erection of scaffolding construction safety-related technical standards and regulations, quality standards and safety regulations engineering, erection neatly unified, consistent with safe production and construction needs;

[0133] (4)施工现场的安全警示标志必须齐全、醒目,临边、孔洞、人员进出口等部位安全防护措施必须完善,在车辆、行人通行的地方和上下层交叉立体施工时,应当设置沟井坎穴覆盖物和施工标志,夜间施工要保证作业场所和相关通道有足够的照明; [0133] (4) Construction site safety warning signs must be complete, eye-catching, limb, holes, and other parts of the import and export personnel security measures must be perfect, three-dimensional construction in the vehicle when crossing, where pedestrians and upper and lower layers, should be set pits, wells, ridges and holes coverings and construction signs, nighttime construction to ensure that the workplace and the associated channel has sufficient lighting;

[0134] (5)施工机具应当按照施工总平面布置图规定的位置和线路设置,不得任意侵占场内道路,施工机具进场前必须经过安全检查,经检查合格方能使用; [0134] (5) construction equipment should be arranged in accordance with the general plane of the construction and the predetermined position of FIG line settings can not occupy any site road, before entering the construction equipment must be security checks, inspection and approval before using;

[0135] (6)施工机械操作人员必须建立机组责任制并依照有关规定持证上岗,禁止无证人员操作和未经批准擅自动用他人操作的设备; [0135] (6) construction machinery operators and accountability must be established in accordance with the relevant provisions of the unit certificates, ban unlicensed personnel to operate the equipment and the unauthorized use of another person operation;

[0136] (7)手提电动工具使用前应检查是否有漏电现象,施工用配电箱应装漏电保护器, 在潮湿区域施工时必须穿绝缘鞋,下班后应及时拉掉电闸,拔掉插头。 [0136] (7) before the hand-held power tool should check for leakage, the construction should be mounted with the distribution box leakage protection, insulation must wear the shoe construction in wet areas, should be pulled off after work gates, unplug .

[0137] 本发明环保措施: [0137] The present invention environmental initiatives:

[0138] (1)施工现场库房内的原材料、元器件、设备、工具应分类摆放整齐,仓库应保持清洁、干燥; [0138] (1) raw materials, components, equipment, tools within the construction site should be classified neatly warehouse, the warehouse should be kept clean and dry;

[0139] (2)现场临时设施搭设要本着需要、实用,力求统一、美观的原则进行。 [0139] (2) on-site erection of temporary facilities must be based on need, practical, and strive to unify, the beauty of principle. 搭设要符合有关规定,尤其是要满足安全生产和防火的要求。 To comply with the relevant provisions of erection, especially to meet the requirements of production safety and fire protection. 办公、生活、后勤设施更要做到室内外与周围环境的统一,整洁、卫生、美观、节约应统筹兼顾; Office, living, logistics facilities and more to do with the indoor and outdoor surroundings unity, clean, health, beauty, conservation should be balanced;

[0140] (3)项目施工、管理人员工作期间应穿工作服,使用个人劳动防护用品,根据作业特点和人员岗位不同,分色着装,并使用胸卡上岗; [0140] (3) construction project, should wear work clothes during the administration of personnel, use of personal protective equipment labor, depending on the operating characteristics and staff positions, separation of dress, and using the badge posts;

[0141] (4)项目办公室、仓库、车间、宿舍等场所要保持清洁卫生,划分卫生包干区,定期打扫。 [0141] (4) project offices, warehouses, workshops, dormitories and other places to keep clean, lump sum District Health division, cleaned regularly. 职工食堂、饮食店、小卖部等要符合国家卫生法规的规定,保持相应的室内和周围环境的清洁卫生,注重防鼠、防蝇、防尘、定期消毒; Cafeteria, restaurant, canteen, etc. should comply with national hygiene regulations, maintain the appropriate room and clean surroundings, pay attention to rodents, flies, dust, regular disinfection;

[0142] (5)项目施工应认真遵守国家和当地政府明确的关于环境保护的有关规定,妥善处置建筑垃圾、废水、废渣、废气和施工噪音、夜间施工、粉尘等,要积极采取措施进行综合治理,达到排放标准和处置要求; [0142] (5) construction project should be carefully comply with national and local governments clear provisions on environmental protection, proper disposal of construction waste, waste water, waste, emissions and construction noise, night construction, dust, etc., should actively adopt comprehensive measures governance, meet emission standards and disposal requirements;

[0143] (6)结合项目施工的具体特点和要求制订相应的文明施工管理办法并认真付诸实施;明确责任,划分区域,实行分片包干管理; [0143] (6) in conjunction with the construction of the project to develop the specific characteristics and requirements of the corresponding civilization construction management approach and seriously implemented; a clear responsibility to the divided region, the implementation of Fenpianbaogan management;

[0144] (7)阶段性工作完后,拆除施工临时设施,撤退施工机械设备并清理场地,修复承包人损坏的场内交通道路,撤离无关施工人员。 [0144] (7) stage after work, removal of temporary construction facilities, construction machinery and equipment retreat and clean up the site, the contractor repairing damaged roads venue, the withdrawal has nothing to do construction workers.

[0145] 以上仅为本发明的具体实施例,但本发明的技术特征并不局限于此。 Merely specific embodiments of the present invention, [0145] above, the technical features of the present invention is not limited thereto. 任何以本发明为基础,为实现基本相同的技术效果,所作出地简单变化、等同替换或者修饰等,皆涵盖于本发明的保护范围之中。 In the present invention, any basis, to achieve substantially the same technical effect, make the simple change, equivalent replacement or modification, etc., it is contemplated within the scope of the present invention.

Claims (4)

  1. 1.医用液态氧集中供气系统施工工法,其特征在于包括如下步骤: (1) 施工准备熟悉和审查施工图纸,了解医用气体工程在图纸上预留、预埋的孔洞和管线位置,结合土建结构施工图纸,核对土建单位已留孔洞的标高、坐标,然后编制施工图预算,列出各分项工程的工作量,确定安装工程中各分项工程用料、用工和机具使用情况,并汇总成表,接着编制安装工程施工技术方案,确定采取的技术措施,编写安全和技术方面的交底记录,最后组织施工人员进行技术培训;选择和设计贮槽安装场地,对地面承载能力、充灌槽车的通行道、通风条件、排水沟和环境安全进行设计,槽车输液金属软管长度小于4米,贮槽至汽车的位置小于3米;根据贮槽充灌后的重量及当地地质状态,按土建图纸要求进行施工及养护; (2) 贮槽吊装在贮槽外壳封头上设有两只吊耳 1. The medical liquid oxygen concentration gas supply system construction method comprising the steps of: (1) construction preparation and examination familiar construction drawings, to understand medical gas reserve in the drawings, the holes and embedded pipeline location, binding civil structure construction drawings, check civil engineering units have been leaving holes in elevation, coordinates, and preparation of construction drawing budget, listing the amount of work each sub-project, determine the installation of the sub-projects in the use of materials, labor and equipment, and summary into a table, followed by the preparation of the installation construction technology program to determine the technical measures, writing tests, safety and technical aspects of recording, the last organized technical training construction workers; the installation site selection and design of the tank, the carrying capacity of the ground, filling slots vehicle traffic channel, ventilation, gutters and environmental safety design, tankers infusion metal hose length less than 4 meters, the position of the sump is less than 3 meters to the car; and local geology based on the weight of the tank filling state, for construction and maintenance required by civil drawings; (2) provided with two lifting lugs tank sump housing head with 在贮槽外壳正面的左右支脚上各有一只吊耳,用一台有两只卷扬机的吊机将贮槽由水平状态直立或由直立状态放平,在起吊前先进行试吊, 检查吊起的平稳性和可靠性,再开始升高和吊移; (3) 贮槽运输贮槽运输采用裸装,先将贮槽放在运输车托架上,并用钢带将贮槽与两个运输托架捆绑住,贮槽水平放在两个运输托架上时,贮槽的正面垂直朝上,贮槽外壳底部的管道引出不锈钢封头,把贮槽和运输托架与运输工具连接牢固,运输过程中变更运输工具时,按吊装的要求进行吊装作业; (4) 贮槽安装当贮槽运到现场时,基础设施没有完成,用吊机按吊装的方法将贮槽同运输托架,从车上吊下,放在有保护措施的地方;当贮槽运到现场,安装就位条件具备时,先将贮槽从车上吊下放到地面上,然后拆开两个运输托架与贮槽捆绑的钢带,再按吊装的要求 Each lug around a sump housing front support legs, using a hoist crane has two upstanding from the sump to the horizontal state or the upright state by the flat, prior to the first trial lifting crane, lifting check the stability and reliability, and the suspension began to rise again shift; (3) using transport tank sump bare transport, on the first tank truck carriage, and with the tank and two strip transport tied down the carriage, on two horizontal transport sump brackets, front sump vertically upward, the bottom of the sump duct drawn stainless steel head housing, the sump and transport vehicle firmly connected with the carriage, when changing vehicles, according to the requirements of hoisting lifting operations carried out during transport; (4) the tank when the tank is installed transported to the site, the infrastructure is not completed, according to the method used crane lifting the tank with the transport carriage, hanging down from the car, put protective measures in place; when the tank transported to the site, installation place conditions are met, the first tank hanging down from the car onto the ground, and then open bracket and two transport tanks bundled strip, then lifting requirements 行贮槽升高、直立、吊移的就位作业;贮槽安装就位后,检查阀门管道系统,用压力对阀门进行气密性试验,将贮槽的使用接口与配套系统用管道进行连接; (5) 管道脱脂按设计要求进行脱脂,根据管道工作介质、管道材质、管径、管子的脏污情况制定管道的脱脂措施;将有油迹和锈蚀的管子放在槽型容器内用碱溶液进行清洗,再用清水洗净碱水,最后用有机溶剂脱脂,在脱脂液中浸泡2小时,脱脂后的管道和工件用清洁干燥的滤纸擦拭其内壁,直至纸上油脂痕迹消失,或用紫外线灯照射脱脂表面,直至紫荧光消失;用清水冲洗内表面,冲洗干净后再通风处晾干,然后对脱脂合格的管道及工件封闭管口; (6) 管道安装a、 先根据图纸要求量取尺寸,并做标记的移植,然后用钢锯或砂轮切割机切割,切割后用锉刀锉去毛刺,切口端面倾斜偏差小于管子 OK sump rises, vertical, hanging position shift operations; in place after the tank, check valves, pipe systems, the valve pressure air tightness test, and supporting the sump system using an interface connected to conduit ; degreasing (5) is degreased duct according to design requirements, measures to develop skim conduit pipe according to soiling of the working medium, pipe material, pipe diameter, pipe; rust and traces of oil will be placed in the groove of the tube container base cleaning solution, then rinse alkaline, and finally the organic solvent degreasing, degreasing was immersed in 2 hours, and the duct work after the degreasing wipe clean the inner wall with a dry filter paper, until disappearance of traces of oil on paper, or by irradiating ultraviolet lamp degreased surface, until the purple fluorescence disappeared; rinse the inner surface, then rinse ventilated place to dry, then skim conduit and the work of qualified spout closed; (6) installation pipe a, according to the amount of drawings take size, and transplants mark and cut with a hacksaw or grinder after cutting deburring file with a file, cut end of the tube is smaller than the inclination deviation 径的1 %,长度小于3_ ; b、 采用冷弯法弯制氧气管道,用在压力大于3MPa的管道,弯曲半径大于管子外径的5 倍,其他管道大于管子外径的3. 5倍,管子弯曲的角度大于90 %弯扁程度小于8% ; c、 采用银基钎焊焊接连接,直管上两个对接焊缝中心之间的距离大于管子的外径,长度大于200mm,管道焊缝及其边缘200mm内密封,焊缝距离管道起点的尺寸大于100mm,管道环型焊缝距管道支架、吊架净距离大于50mm ;焊接完成后进行外观质量检验,并在表面进行防腐处理; d、熟悉图纸,了解管道的走向、分支和管道的规格材质、安装位置,进行工艺评定并编制作业指导书,按图施工,用氩弧焊焊接系统管道之间的连接,系统管道穿过墙或底板时, 加PVC套管保护,管道支架均匀布置,主管路布置于管井内,吊顶内安装副管道,安装高度根据安装现场作调整,管道支架沿 1% of the diameter, length less than 3_; b, cold bending process bending oxygen pipeline, the pipeline for use in a pressure greater than 3MPa bending radius larger than 5 times the tube outside diameter, the other conduit is greater than 3.5 times the tube outside diameter, the bending angle of the pipe bend is greater than 90% less than the extent of flat 8%; c, using silver-based brazing weld connection, the distance between the straight pipe butt weld two centers is greater than the outer diameter of the tube, a length greater than 200mm, pipeline welds 200mm and inner edge seal, pipe welds starting from a size greater than 100mm, away from weld ring conduit pipe supports, hangers clear distance is greater than 50mm; the quality of the appearance inspection after welding is completed, and the surface of the anti-corrosion treatment; D, familiar with the drawings, to understand, the branch pipe and the pipe material specifications, installation location, for process evaluation and preparation of the operating instructions, according to the drawings, the connection between the TIG welding system piping, conduit through a wall or floor system when, and PVC protective casing, the pipe holder arranged uniformly, the main line is disposed within the tube well, the sub duct ceiling installation, the installation height adjusted according to the installation site, the stent along the pipe 或柱子敷设,站房中间管道的吊架安装在梁的下方,气体管道采用独立的支吊架,钢管与支吊架接触处设绝缘材料;在管道穿越建筑墙体上设置套管,管道与管道之间采用密封材料封口,并在护理站内安装压力表箱,每个床位的供氧管路均从每个病房的墙角穿过,用铝合金装饰罩罩住;按工艺流程图顺序进行施工,当现场条件受到限制,项目质量责任人根据实际情况进行调整,并报工艺责任工程师确认; (7) 管道强度试验管道安装完毕后,先检查系统各管道接口、节点和管道支架,然后向管道内充气,用空气进行预实验,当压力升至试验压力的50 %时,观察管道的情况,接着按试验压力的10% 逐级升压,每级稳压5分钟,直至试验压力;稳压10分钟后,再将压力降至设计压力,停压时间根据查漏工作而定; (8) 管道吹扫在管道强度试验合格后,编制吹 Laying or pillar, pipe hanger station house is mounted below the intermediate beam, independent of the gas pipe hanger, hanger pipe and disposed in contact with the insulating material; a sleeve disposed on the pipe through building walls, pipes and using a sealing material sealing between the duct and the tank pressure gauge mounted in the nursing station, each bed through the oxygen supply pipes are each ward from the corner, cover with aluminum decorative cover; the construction according to the sequence flow chart , when the conditions are restricted site, responsible project quality adjustment according to the actual situation, process and report acknowledgment responsible engineer; (7) the pipe conduit installed strength test, each of the first pipe joint inspection system, and pipe support node, and then to the conduit inflatable, air pre-experiment, the test pressure when the pressure was raised to 50%, when viewed pipeline, followed by 10% of the test pressure boosting stepwise, each stage regulator for 5 minutes, until the test pressure; Regulators after 10 minutes, the pressure was reduced to the design pressure, to stop the leak pressure time according to a given work; (8) after purging pipe conduit passing strength test, the preparation of blown 方案,采用氮气或压缩空气作为介质进行管道吹扫, 在吹扫前先检查支架,并进行加固,将孔板、法兰连接的调节阀、节流阀、安全阀和仪表拆卸,将焊接的阀门和仪表采取流经旁路或卸掉阀头及阀座加保护套,同时设置吹扫禁区,打开各吹扫排污口的房间门窗;在管道吹扫过程中用木锤敲击管道的焊缝、拐角、分支和死角处,直至铁锈、尘土水分及其它杂物消失;吹扫工作结束后,把拆下的阀门器件恢复,并封住各吹出口,做好吹扫记录; (9) 设备带安装管道吹扫完毕后,根据设计图纸要求,在中心线上安装截止阀和氧气快速插座,快速插座的安装高度使大盖合拢后快速插座顶部高出面板,设备带内管道球头与氧气快速插座中心对准,然后旋入螺母,用扳手拧紧,设备带装配完毕后进行压力试验和气密性试验;设备带用膨胀螺栓紧固在病房墙上 Program, using nitrogen or compressed air as a purging medium pipe, before purging check stent, and reinforcement, the orifice plate flange regulating valve, throttle valve and meter disassembled, the weld taken through the bypass valve and instrument or remove the valve head and valve seat wear jackets, while purging the box set, open the doors and windows of rooms of each purge outfall; tapping pipe with the pipe weld purging process mallet joints, corners and dead ends at the branch, until rust, dust and other debris moisture disappeared; work after purging, the valve devices to restore removed, and the outlets sealed, purged good record; (9) after the apparatus was purged with complete installation of pipes, according to the design drawings, and the oxygen shut-off valve installed in the center line of the receptacle fast, fast mounting socket so that the height of the large lid closed rapid outlet above the top panel, the devices with a ball head and the pipe oxygen rapid centering socket, and then screwed into the nut, tighten with a wrench, pressure test and tightness test strip device after assembled; apparatus with expansion bolt in the wall ward ,安装高度符合设计图纸要求; (10) 阀门安装设备带安装完毕后,先查看阀门的合格证并核对检查,按设计图纸上标明的规格、型号和位置安装,当图纸上没有标明位置和高度时,根据现场操作、维修方便及美观的角度设计;安装时阀门的箭头方向与介质流动的方向一致,阀杆向上或水平方向安装; (11) 气密性试验阀门安装完毕后,对进行试验的管道、容器通入气体,保压24小时,每隔2小时观察压力表的变化,然后计算出泄漏率; (12) 管道接地有静电接地要求的管道,各段管子间导电,用静电接地连接的钛管道及不锈钢管道,导线跨接或接地引线采用钛板或不锈钢板过渡,导电接触面除锈并连接,静电接地安装完毕后进行测试; (13) 站内调试管道接地完毕后,先将器械插头及氧气湿化器插头插入各使用终端,检查插卸的灵活性、互换性和气密性, Installation height meet the design requirements of the drawings; the (10) valve installed equipment with installation, first check valve certification and verification checks, according to the design drawings marked specifications, type and location of the installation, when the drawings did not indicate the location and height when, according to the site operation, easy maintenance and aesthetic design point of view; direction of the arrow when the valve is mounted coincides with the direction of media flow, the valve stem upward or horizontal mounting; (11) airtightness test valve after installation of the test pipe, gas is introduced into the container, packing 24 hours, every two hours to observe the change of the pressure gauge, and then calculates the leak rate; (12) a duct pipe grounded electrostatic grounding requirements, the conductive tubes between the segments, with static grounding titanium and stainless steel conduit pipe connections, a ground lead wire jumper or titanium or stainless steel plate using a transition, and connected to the conductive contact surface rust, the static ground test installation; commissioning duct (13) after completion of a ground station, first and oxygen humidification apparatus plug inserted into the plug using a terminal, check insertion unloading flexibility, compatibility and air tightness, 手术室和抢救室分别设置两个以上氧气终端,再用氧气湿化器上的流量计检查终端流量,每个终端流量大于l〇L/min ;然后进行报警装置测试,关闭气源,放出供氧管道中气体,当欠压报警装置发出声、光信号时,记下管道压力值,重复3次; (14)竣工检验贮槽安装结束和站内调试完毕后,对施工完成的供气系统进行检查,并对工程前期工作、实施情况、初验与试运行情况、经济技术分析进行登记,合格后开始投入使用。 Operating rooms and emergency room terminals are provided two or more oxygen, then the terminal check the flow meter on the oxygen humidifier, a flow rate greater than each terminal l〇L / min; then a test alarm, turn off gas supply, for discharge gaseous oxygen, when the voltage alarm device emits sound, light signals, note the pipeline pressure, was repeated three times; after debugging the inner (14) and the end of the installation completion check station sump, the construction of the gas supply system will be completed check the preliminary work and engineering, implementation, registration and preliminary acceptance test run, the economic and technical analysis, put into use after passing.
  2. 2. 根据权利要求1所述的医用液态氧集中供气系统施工工法,其特征在于:步骤(2) 中的所述贮槽包括内筒、外筒、顶盖和底盖,所述顶盖的顶面上设置有至少两个所述吊耳, 所述顶盖的内部设置有升压盘管,所述升压盘管上设置有压力阀,所述内筒位于所述外筒的内部,所述内筒与所述外筒之间设置有氧气分配器和空温式汽化器,所述空温式汽化器的顶面上设置有液相进口,所述液相进口连接所述升压盘管,所述空温式汽化器的底面上设置有气相出口,所述气相出口连接所述氧气分配器,所述底盖的底面上设置有支脚,所述支脚上设置有所述吊耳,所述外筒的侧面上设置有液面观察口、压力表和出气管。 The medical liquid oxygen concentration gas supply system Construction Method according to claim 1, wherein: the step of the tank (2) comprises an inner cylinder, an outer cylinder, top and bottom covers, the top cover the top surface is provided with at least two of said lug, said inner cover is provided with a step-up coil, the coil is provided with a boost pressure valve, the inner tube is located inside the outer cylinder , there is provided an oxygen dispenser and evaporator air temperature between the inner tube and the outer tube, the top surface of the air-temperature liquid vaporizer inlet is provided, connected to said liquid inlet of said booster disk tube, the air temperature of the evaporator is provided with a bottom surface of the gas outlet, the gas outlet is connected to the oxygen dispenser, the bottom surface of the legs is provided with a bottom cover, said support leg provided with said lug, the It is provided on the side surface of said outer cylinder with a level viewing port, a pressure gauge and the trachea.
  3. 3. 根据权利要求2所述的医用液态氧集中供气系统施工工法,其特征在于:所述内筒的底部设置有吸附层。 3. The medical liquid oxygen concentration gas supply system of claim 2 Construction method as claimed in claim, wherein: said inner tube is provided with a bottom layer adsorption.
  4. 4. 根据权利要求2所述的医用液态氧集中供气系统施工工法,其特征在于:所述底盖的内部设置有绝缘层。 The medical liquid oxygen concentration gas supply system of claim 2 Construction method as claimed in claim, wherein: the inside of the bottom cover is provided with an insulating layer.
CN 201410049418 2014-02-13 2014-02-13 The medical liquid oxygen concentration gas supply system Construction Method CN103791227B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201410049418 CN103791227B (en) 2014-02-13 2014-02-13 The medical liquid oxygen concentration gas supply system Construction Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201410049418 CN103791227B (en) 2014-02-13 2014-02-13 The medical liquid oxygen concentration gas supply system Construction Method

Publications (2)

Publication Number Publication Date
CN103791227A true CN103791227A (en) 2014-05-14
CN103791227B true CN103791227B (en) 2015-09-30

Family

ID=50667152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201410049418 CN103791227B (en) 2014-02-13 2014-02-13 The medical liquid oxygen concentration gas supply system Construction Method

Country Status (1)

Country Link
CN (1) CN103791227B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104014562B (en) * 2014-05-20 2016-02-10 天津市管道工程集团有限公司 High-purity gas pipeline wall length overall cleaning process
CN104634016B (en) * 2015-01-30 2017-02-22 中国科学院力学研究所 One kind of CO <sub> 2 liquid refrigerant filling apparatus and method for </ sub> experimental system
CN106148982A (en) * 2015-04-02 2016-11-23 上海航天设备制造总厂 Degreasing method for booster module liquid oxygen pipeline system of new generation carrier rocket
CN106044235B (en) * 2016-06-12 2018-01-09 青岛海川建设集团有限公司 The medical pneumatic tube construction process stream transmission system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0877195A1 (en) * 1997-05-09 1998-11-11 Praxair Technology, Inc. Process and apparatus for backing-up or supplementing a gas supply system
CN201764246U (en) * 2010-07-02 2011-03-16 武汉钢铁(集团)公司 Novel poor krypton xenon liquid oxygen storage tank
CN103090188A (en) * 2011-11-01 2013-05-08 中煤能源黑龙江煤化工有限公司 Liquid oxygen system

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2706192A1 (en) * 1977-02-14 1978-08-17 Siemens Ag Anaesthetic respirator with pressurised container - has throttle in liq. container between oxygen supply and bellows to control mixt.
JP4051366B2 (en) * 2004-08-23 2008-02-20 岩谷瓦斯株式会社 Liquefied gas filling method of the liquefied gas tank and tank

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0877195A1 (en) * 1997-05-09 1998-11-11 Praxair Technology, Inc. Process and apparatus for backing-up or supplementing a gas supply system
CN201764246U (en) * 2010-07-02 2011-03-16 武汉钢铁(集团)公司 Novel poor krypton xenon liquid oxygen storage tank
CN103090188A (en) * 2011-11-01 2013-05-08 中煤能源黑龙江煤化工有限公司 Liquid oxygen system

Also Published As

Publication number Publication date Type
CN103791227A (en) 2014-05-14 application

Similar Documents

Publication Publication Date Title
US4452499A (en) Service stand for work area
CN102305761A (en) Acid medium transmission pipeline welded joint and parent metal corrosion simulation testing device and method
CN103590416A (en) Pre-buried construction method for high-precision foundation bolts
US7347204B1 (en) Breathing air system for a facility
CN102819623A (en) Method for detecting collision positions through building information modeling (BIM)
CN202902487U (en) Circulating air air-conditioner for car paint spraying line water paint spraying room
CN101294860A (en) Quality detecting method for inner lining old pipe
CN201313619Y (en) Prefabricated modularization integrated cabin unit room
CN203944254U (en) Water spray system of tower crane
CN2398500Y (en) Prize-installation gas station
US6484740B2 (en) Blower assembly for gas wells
CN204901084U (en) Prefabricated integration assembled sectional shelf -unit based on BIM
CN104975839A (en) Composite multi-stage fracturing acidification and nitrogen foam fast flow back process
CN101046102A (en) No-negative pressure water supplier for both domestic use and fire fighting
CN204613202U (en) Simulate secret coal exploitation overlying strata migration and routed sand experimental apparatus of gushing water
CN203288151U (en) Small practical oil drilling teaching drilling rig
Global Property Loss Prevention Data Sheets 2-8
Baird et al. Large-scale repository design
CN2435295Y (en) LPG feeding means for vehicle
CN2763244Y (en) Bottom charging/discharging liquid apparatus for vehicle tanker
Fernandez et al. Cost-effective methane emissions reductions for small and midsize natural gas producers
CN204127563U (en) Sealed double-sided reinforcement plate end cap device for PCCP pressing pipe
CN103575064A (en) Device and method for oxygen and nitrogen separation through air and rapid increase of pressure nitrogen loads
CN204456189U (en) Subway station top pipe gallery structure
Ramabhushanam et al. Structural assessment of bomb damage for World Trade Center