The transportation resources that monorail crane locomotive car load in gallery is allocated and transported safely and fast
Technical field
The present invention relates to underground coal mine transport field.
Background technology
At present, monorail crane locomotive has become the important transportation equipment of underground coal mine digging tunnel transported material, and after Mining Area exploitation terminates, monorail crane locomotive is also maneuvered into other exploiting field accordingly and transports material.Usually in old mine same level exploiting field between do not realize single track hanging beam circuit network due to distance, locomotive driving cabin, drive division, lifting beam and all kinds of pipeline, Circuits System all can only be taken apart and be bundled on the car of large square position, transport other exploiting field to and assemble use again.Whole dismounting, transport, assembling process, complicated loaded down with trivial details holding time is long, and the monorail crane locomotive fault re-assemblied is many, is difficult to normally run at short notice, wastes manpower and materials and time, has had a strong impact on mine normal production.
Summary of the invention
The object of the invention is, for solving the deficiencies in the prior art, to provide the transportation resources that car load in gallery is allocated and transported safely and fast of a kind of monorail crane locomotive.
For achieving the above object, technical scheme of the present invention is:
The transportation resources that monorail crane locomotive car load in gallery is allocated and transported safely and fast, it is characterized in that, concrete steps are:
The first step, first according to prepare want allocate and transport the size of monorail crane locomotive and the profile of joint number, process the transportation frame corresponding with its size and joint number, transportation frame is provided with one section of single track hanging beam; Reprocess the double track square position car that a row size is corresponding with transportation frame with joint number, and by all transportation frame placement positioning on respective square position car.
Second step, respectively save the size of pipe link again according to monorail crane locomotive, the single track hanging beam short circuit head that processing and fabricating corresponding energy level turns to, by short circuit head, the single track hanging beam on all transportation frames is movably connected, all square positions car and double track traction electric motor are coupled together, common group arranges into the whole frame transport trolley that row transport monorail crane locomotive again.
3rd step, be transported to exploit terminate rear exploiting field by organizing the whole frame transport trolley that arrange, rest in the transhipment station of monorail crane, the former single track hanging beam line end of transhipment station is adjusted downwards, adjusts to and the single track hanging beam equal height in transportation frame unwheeling, then both are docking together; Then preparing to want that the monorail crane locomotive allocated and transported drives on the hanging beam of whole frame transport trolley; Stop working after traction electric motor comes to a complete stop and execute lock, the junction of the hanging beam in the end of former single track hanging beam circuit and transportation frame unwheeling is taken apart, pipe link between respectively being saved by monorail crane locomotive is taken apart, and the whole frame transport trolley being loaded with monorail crane locomotive with traction electric machine handlebar is transported to the new exploiting field arranging single track hanging beam circuit;
4th step, the single track hanging beam circuit of new exploiting field transhipment station end to be adjusted downwards, adjust to and the single track hanging beam equal height in transportation frame unwheeling, then both are docking together; Again the pipe link between monorail crane locomotive respectively saves is connected, check errorless; Start monorail crane locomotive, monorail crane locomotive is reached the single track hanging beam circuit of transhipment station in whole frame transport trolley, has has so far allocated and transported.
Good effect of the present invention is: when when the exploiting field of down-hole same level allocation and transportation monorail crane locomotive, achieve integral transportation, avoid and locomotive driving cabin, drive division, lifting beam and all kinds of pipeline, Circuits System are all taken apart and re-assemblied process, a large amount of manpower and materials and time are saved, improve monorail crane locomotive service efficiency, ensure that mine normal safe is produced.
Accompanying drawing explanation
Fig. 1 is schematic diagram of the present invention..
In figure: 1-double track traction electric motor, 2-transportation frame, 3-single track hanging beam, 4-short circuit head, 5-square position car, 6-pipe link, 7-monorail crane locomotive, 8-single track hanging beam circuit, 9-permutation transport trolley.
Detailed description of the invention
With reference to accompanying drawing, method of the present invention is described in detail below.
As shown in Figure 1, for achieving the above object, technical scheme of the present invention is: the transportation resources that a kind of monorail crane locomotive car load in gallery is allocated and transported safely and fast, and concrete steps are:
The first step, first according to prepare want allocate and transport the size of monorail crane locomotive 7 and the profile of joint number, process the transportation frame 2 corresponding with its size and joint number, transportation frame 2 is provided with one section of single track hanging beam 3; Reprocess a row size and the joint number double track square position car 5 corresponding with transportation frame 2, and by all transportation frame 2 placement positioning on respective square position car 5.
Second step, again according to the size of each joint pipe link 6 of monorail crane locomotive 7, processing and fabricating accordingly can the single track hanging beam short circuit head 4 that turns to of level, by short circuit head 4, the single track hanging beam 3 on all transportation frames 2 is movably connected, all square positions car 5 and double track traction electric motor 1 are coupled together, common group arranges into the permutation transport trolley 9 that row transport monorail crane locomotive 7 again.
3rd step, be transported to exploit terminate rear exploiting field by organizing the permutation transport trolley 9 that arrange, rest in the transhipment station of monorail crane, former single track hanging beam circuit 8 end of transhipment station is adjusted downwards, adjusts to and single track hanging beam 3 equal height in transportation frame unwheeling, then both are docking together; Then preparing to want that the monorail crane locomotive 7 allocated and transported drives on the single track hanging beam 3 of whole frame transport trolley; Stop working after traction electric motor 1 comes to a complete stop and execute lock, the junction of the hanging beam 3 in the end of former single track hanging beam circuit 8 and transportation frame unwheeling is taken apart, pipe link 6 between respectively being saved by monorail crane locomotive is taken apart, with traction electric motor 1, the permutation transport trolley 9 being loaded with monorail crane locomotive is transported to the new exploiting field arranging single track hanging beam circuit;
4th step, the single track hanging beam circuit (in similar Fig. 1 8) of new exploiting field transhipment station end to be adjusted downwards, adjust to and single track hanging beam 3 equal height in transportation frame unwheeling, then both are docking together; Again the pipe link 6 of monorail crane locomotive 7 respectively between joint is connected, check errorless; Start monorail crane locomotive 7, monorail crane locomotive 7 is reached in permutation transport trolley 9 on the single track hanging beam circuit (similar Fig. 1 8) of transhipment station, so far allocated and transported.