CN103675659A - 断路器分合闸时行程-时间波形预处理方法与装置 - Google Patents

断路器分合闸时行程-时间波形预处理方法与装置 Download PDF

Info

Publication number
CN103675659A
CN103675659A CN201310629239.0A CN201310629239A CN103675659A CN 103675659 A CN103675659 A CN 103675659A CN 201310629239 A CN201310629239 A CN 201310629239A CN 103675659 A CN103675659 A CN 103675659A
Authority
CN
China
Prior art keywords
time
point
stroke
breaker switching
sampling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310629239.0A
Other languages
English (en)
Other versions
CN103675659B (zh
Inventor
梁经宛
路光辉
陈新美
马仪成
焦坡
雍明超
赵宝
牧继清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XJ Electric Co Ltd
State Grid Hunan Electric Power Co Ltd
Xuchang XJ Software Technology Co Ltd
Original Assignee
XJ Electric Co Ltd
Xuchang XJ Software Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XJ Electric Co Ltd, Xuchang XJ Software Technology Co Ltd filed Critical XJ Electric Co Ltd
Priority to CN201310629239.0A priority Critical patent/CN103675659B/zh
Publication of CN103675659A publication Critical patent/CN103675659A/zh
Application granted granted Critical
Publication of CN103675659B publication Critical patent/CN103675659B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及断路器分合闸时行程-时间波形预处理方法与装置,本发明提供了一种全新的对分合闸行程-时间特性曲线进行预处理的方法,对现场采集到的行程-时间特性数据至少利用一种方式进行拟合,达到剔除坏点和野点的目的,为后续利用此分合闸波形进行高压开关故障的正确判别提供准确的判断依据。

Description

断路器分合闸时行程-时间波形预处理方法与装置
技术领域
本发明涉及一种断路器分合闸时行程-时间波形预处理方法。
背景技术
80%的高压断路器故障是由于机械特性不良造成的,且大多数故障是操动机构的问题。加强高压断路器机械特性的在线监测对保证高压断路器的安全运行具有重要的现实意义。其中,断路器分合闸时的行程-时间特性(如图1、2所示)是表征断路器机械特征的重要参数,也是计算断路器分合闸速度的依据,得到波形曲线后,就可以对波形进行分析,判断出对应时刻的断路器机构的状态是否正常。它包含很多信息,反映了电磁铁本身以及所控制的锁闩或阀门以及连锁触头在操作过程中的工作情况。因此断路器分合闸时的行程-时间特性对于高压断路器的在线监测及故障诊断具有重要的意义。
分合闸行程-时间特性是在多种干扰现场环境下在线测得的,因此所得到的波形往往含有很多因干扰而产生的“毛刺”,这对从波形中提取有用信息十分不利。因此对分合闸行程-时间特性曲线进行预处理是非常重要的,它的主要目的是剔除曲线中的毛刺和脉冲干扰,以削弱环境的干扰影响,保证既要剔除“坏点”,又要保存数据的真实性,减少波形检测的误检率。目前主要的预处理方法是采用低通滤波器、中值滤波算法和小波变换等,它们各有优劣,也在一定程度上达到了一定的预处理的效果,但是效果不够理想。
发明内容
本发明的目的是提供一种断路器分合闸时行程-时间波形预处理方法与装置,用以解决现有滤波等预处理方法效果不够理想的问题。
为实现上述目的,本发明的方案包括:
断路器分合闸时行程-时间波形预处理方法,至少包括第一次拟合的步骤:
在断路器分合闸过程中以设定采样周期进行采样,得到一系列采样点((t1,x1),(t2,x2),…,(tn,xn));
对每个周期的波形求导,得到各周期的导数值λ1,λ2,…,λn-1,对于每个采样周期,判断其后的采用点是否为坏点:对于任一采样周期k,判断|λk-(λ1+…+λm)/m|≥Δ是否成立,若成立则判断采样周期k之后的采样点((tk+1,xk+1))为坏点,并进行剔除;Δ为设定的第一阈值,n为采样点数;
用最小二乘法对上述剔除坏点之后的采样点进行第一次拟合,得到断路器第一次分合闸波形曲线。
所述断路器分合闸时行程-时间波形预处理方法还包括第二次拟合的步骤:
根据第一次分合闸波形曲线得到各采样时刻的行程拟合值,将各采样时刻的原始采样点值与对应时刻的行程拟合值进行比较,若它们之间的差值的绝对值大于设定的第二阈值,则进行第二次剔除,剔除对应采样点;
用最小二乘法对第二次剔除坏点之后的采样点进行第二次拟合,得到最终的断路器分合闸波形曲线。
断路器分合闸时行程-时间波形预处理装置,至少包括第一次拟合的模块:
在断路器分合闸过程中以设定采样周期进行采样,得到一系列采样点((t1,x1),(t2,x2),…,(tn,xn));
对每个周期的波形求导,得到各周期的导数值λ1,λ2,…,λn-1,对于每个采样周期,判断其后的采用点是否为坏点:对于任一采样周期k,判断|λk-(λ1+…+λm)/m|≥Δ是否成立,若成立则判断采样周期k之后的采样点((tk+1,xk+1))为坏点,并进行剔除;Δ为设定的第一阈值,n为采样点数;
用最小二乘法对上述剔除坏点之后的采样点进行第一次拟合,得到断路器第一次分合闸波形曲线。
所述断路器分合闸时行程-时间波形预处理方法还包括第二次拟合的模块:
根据第一次分合闸波形曲线得到各采样时刻的行程拟合值,将各采样时刻的原始采样点值与对应时刻的行程拟合值进行比较,若它们之间的差值的绝对值大于设定的第二阈值,则进行第二次剔除,剔除对应采样点;
用最小二乘法对第二次剔除坏点之后的采样点进行第二次拟合,得到最终的断路器分合闸波形曲线。
本发明提供了一种全新的对分合闸行程-时间特性曲线进行预处理的方法,对现场采集到的行程-时间特性数据至少利用一种方式进行拟合,达到剔除坏点和野点的目的,为后续利用此分合闸波形进行高压开关故障的正确判别提供准确的判断依据。
第一次拟合过程根据每个周期的导数判据剔除了相应的坏点,达到了一定的预处理效果。
进一步的,第二次拟合过程在第一拟合的基础上,通过与原始数据的比较,再次剔除一定量的坏点,使预处理效果更加显著。
附图说明
图1是断路器合闸行程-时间特性曲线图;
图2是断路器分闸行程-时间特性曲线图;
图3是断路器分合闸行程-时间特性曲线预处理流程图。
具体实施方式
下面结合附图对本发明做进一步详细的说明。
断路器分合闸时行程-时间波形预处理方法至少应包括第一次拟合过程,以下实施方式是一种优选实施例,其包括两次拟合过程,下面对整个过程进行具体描述。
如图3所示,第一步利用采集器对断路器分合闸波形进行采样,得到一系列的采样点(t1,x1),(t2,x2),…,(tn,xn)。
第二步再利用各采样点的数值和采样时刻对每个采样周期内的波形进行求导,λk=(xk+1-xk)/采样周期,得到的导数分别为(λ1,λ2,…,λn-1);如此时在第k个采样周期得到的导数值为λk,同时在第k个采样周期之前保留了m个导数值,它们分别为(λ1,λ2,…,λm),若此时|λk-(λ1+…+λm)/m|≥Δ(Δ为设定的第一阈值),则判别该采样周期内第k+1个采样点为坏点,并进行剔除,否则保留该点。在程序中,递增k值以实现对每个周期均进行上述判断过程。
第三步利用最小二乘法对第二步剔除坏点之后的采样点进行拟合,得到断路器分合闸波形曲线,从而得到各采样时刻的行程曲线值。
第四步将各采样时刻的原始采样点值与第三步中所得到对应采样时刻的行程拟合值进行比较,若他们之间差值的绝对值大于设定的第二阈值,即若|在ti时刻的拟合曲线值xi*-在ti时刻的原始采样值xi|≥设定的第二阈值,则剔除掉xi,否则保留该点;i小于等于n。在程序中,递增i值以实现对每个周期均进行上述判断过程。
第五步利用最小二乘法对两次剔除坏点之后的采样点进行重新拟合,得到处理后的断路器分合闸行程-时间曲线,完成对其的预处理。
以上给出一种具体的实施方式,但本发明不局限于所描述的实施方式。本发明的基本思路在于上述方案,对本领域普通技术人员而言,根据本发明的教导,设计出各种变形的公式、参数并不需要花费创造性劳动。在不脱离本发明的原理和精神的情况下对实施方式进行的变化、修改、替换和变型仍落入本发明的保护范围内。

Claims (4)

1.断路器分合闸时行程-时间波形预处理方法,其特征在于,至少包括第一次拟合的步骤:
在断路器分合闸过程中以设定采样周期进行采样,得到一系列采样点((t1,x1),(t2,x2),…,(tn,xn));
对每个周期的波形求导,得到各周期的导数值λ1,λ2,…,λn-1,对于每个采样周期,判断其后的采用点是否为坏点:对于任一采样周期k,判断|λk-(λ1+…+λm)/m|≥Δ是否成立,若成立则判断采样周期k之后的采样点((tk+1,xk+1))为坏点,并进行剔除;Δ为设定的第一阈值,n为采样点数;
用最小二乘法对上述剔除坏点之后的采样点进行第一次拟合,得到断路器第一次分合闸波形曲线。
2.根据权利要求1所述的断路器分合闸时行程-时间波形预处理方法,其特征在于,所述断路器分合闸时行程-时间波形预处理方法还包括第二次拟合的步骤:
根据第一次分合闸波形曲线得到各采样时刻的行程拟合值,将各采样时刻的原始采样点值与对应时刻的行程拟合值进行比较,若它们之间的差值的绝对值大于设定的第二阈值,则进行第二次剔除,剔除对应采样点;
用最小二乘法对第二次剔除坏点之后的采样点进行第二次拟合,得到最终的断路器分合闸波形曲线。
3.断路器分合闸时行程-时间波形预处理装置,其特征在于,至少包括第一次拟合的模块:
在断路器分合闸过程中以设定采样周期进行采样,得到一系列采样点((t1,x1),(t2,x2),…,(tn,xn));
对每个周期的波形求导,得到各周期的导数值λ1,λ2,…,λn-1,对于每个采样周期,判断其后的采用点是否为坏点:对于任一采样周期k,判断|λk-(λ1+…+λm)/m|≥Δ是否成立,若成立则判断采样周期k之后的采样点((tk+1,xk+1))为坏点,并进行剔除;Δ为设定的第一阈值,n为采样点数;
用最小二乘法对上述剔除坏点之后的采样点进行第一次拟合,得到断路器第一次分合闸波形曲线。
4.根据权利要求1所述的断路器分合闸时行程-时间波形预处理装置,其特征在于,所述断路器分合闸时行程-时间波形预处理方法还包括第二次拟合的模块:
根据第一次分合闸波形曲线得到各采样时刻的行程拟合值,将各采样时刻的原始采样点值与对应时刻的行程拟合值进行比较,若它们之间的差值的绝对值大于设定的第二阈值,则进行第二次剔除,剔除对应采样点;
用最小二乘法对第二次剔除坏点之后的采样点进行第二次拟合,得到最终的断路器分合闸波形曲线。
CN201310629239.0A 2013-11-30 2013-11-30 断路器分合闸时行程-时间波形预处理方法与装置 Active CN103675659B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310629239.0A CN103675659B (zh) 2013-11-30 2013-11-30 断路器分合闸时行程-时间波形预处理方法与装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310629239.0A CN103675659B (zh) 2013-11-30 2013-11-30 断路器分合闸时行程-时间波形预处理方法与装置

Publications (2)

Publication Number Publication Date
CN103675659A true CN103675659A (zh) 2014-03-26
CN103675659B CN103675659B (zh) 2016-06-08

Family

ID=50313817

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310629239.0A Active CN103675659B (zh) 2013-11-30 2013-11-30 断路器分合闸时行程-时间波形预处理方法与装置

Country Status (1)

Country Link
CN (1) CN103675659B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105975737A (zh) * 2016-07-25 2016-09-28 河南森源电气股份有限公司 转折点计算模型及电机电流的断路器状态监测方法、系统
CN106291343A (zh) * 2016-07-25 2017-01-04 河南森源电气股份有限公司 利用分合闸电流进行真空断路器状态监测的方法及系统
CN106291344A (zh) * 2016-07-25 2017-01-04 河南森源电气股份有限公司 基于分闸压力曲线的断路器刚分点检测方法及系统

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012042251A (ja) * 2010-08-16 2012-03-01 Hitachi Plant Technologies Ltd Atp法における計測値の処理方法
CN102579038A (zh) * 2012-03-28 2012-07-18 深圳市理邦精密仪器股份有限公司 一种心电波形数据自动排布的方法和装置
CN102608527A (zh) * 2012-03-14 2012-07-25 南京因泰莱配电自动化设备有限公司 一种断路器动特性测试中的数据滤波处理方法
CN102706921A (zh) * 2012-06-13 2012-10-03 南京第四分析仪器有限公司 一种消除铸铁热分析曲线干扰的滤波方法
CN102767472A (zh) * 2012-07-18 2012-11-07 华北电力大学 一种风电机组功率曲线的提取方法
CN102930164A (zh) * 2012-10-31 2013-02-13 北京航天自动控制研究所 一种飞行器控制数据的转换方法
CN103155076A (zh) * 2010-08-31 2013-06-12 Abb技术有限公司 电路断路器断续器行程曲线估算

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012042251A (ja) * 2010-08-16 2012-03-01 Hitachi Plant Technologies Ltd Atp法における計測値の処理方法
CN103155076A (zh) * 2010-08-31 2013-06-12 Abb技术有限公司 电路断路器断续器行程曲线估算
CN102608527A (zh) * 2012-03-14 2012-07-25 南京因泰莱配电自动化设备有限公司 一种断路器动特性测试中的数据滤波处理方法
CN102579038A (zh) * 2012-03-28 2012-07-18 深圳市理邦精密仪器股份有限公司 一种心电波形数据自动排布的方法和装置
CN102706921A (zh) * 2012-06-13 2012-10-03 南京第四分析仪器有限公司 一种消除铸铁热分析曲线干扰的滤波方法
CN102767472A (zh) * 2012-07-18 2012-11-07 华北电力大学 一种风电机组功率曲线的提取方法
CN102930164A (zh) * 2012-10-31 2013-02-13 北京航天自动控制研究所 一种飞行器控制数据的转换方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
佚名: "10种软件滤波方法的示例程序", 《新浪博客HTTP://BLOG.SINA.COM.CN/S/BLOG_54D696F90100HMCS.HTML》 *
吴展等: "一种改进的动态过程测量数据预处理方法", 《传感器技术学报》 *
赖素建等: "信号预处理中错点剔除方法的研究", 《佳木斯大学学报(自然科学版)》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105975737A (zh) * 2016-07-25 2016-09-28 河南森源电气股份有限公司 转折点计算模型及电机电流的断路器状态监测方法、系统
CN106291343A (zh) * 2016-07-25 2017-01-04 河南森源电气股份有限公司 利用分合闸电流进行真空断路器状态监测的方法及系统
CN106291344A (zh) * 2016-07-25 2017-01-04 河南森源电气股份有限公司 基于分闸压力曲线的断路器刚分点检测方法及系统
CN106291343B (zh) * 2016-07-25 2018-11-23 河南森源电气股份有限公司 利用分合闸电流进行真空断路器状态监测的方法及系统
CN105975737B (zh) * 2016-07-25 2019-06-11 河南森源电气股份有限公司 转折点计算模型及电机电流的断路器状态监测方法、系统
CN106291344B (zh) * 2016-07-25 2020-02-11 河南森源电气股份有限公司 基于分闸压力曲线的断路器刚分点检测方法及系统

Also Published As

Publication number Publication date
CN103675659B (zh) 2016-06-08

Similar Documents

Publication Publication Date Title
US11489490B2 (en) Arc fault detection method for photovoltaic system based on adaptive kernel function and instantaneous frequency estimation
CN109886475B (zh) 基于ai的计量自动化系统的信息安全态势感知系统
CN104390657A (zh) 一种发电机组运行参数测量传感器故障诊断方法及系统
CN108664741B (zh) 基于时间序列模型特征的变电站故障检测方法
CN103901882A (zh) 一种列车动力系统在线监控故障诊断的系统及其方法
CN103336222A (zh) 基于模糊推理脉冲神经膜系统的电力系统故障诊断方法
CN104537487A (zh) 一种输变电设备运行动态风险的评估方法
CN106779095B (zh) 基于kmp算法的智能变电站设备软压板校核的方法
CN103197177A (zh) 一种基于贝叶斯网络的变压器故障诊断分析方法
CN101430360A (zh) 供电系统中二次设备的错误数据鉴别方法
CN106526468B (zh) 基于波形特征识别的断路器状态检测方法
Zhang The railway turnout fault diagnosis algorithm based on BP neural network
CN108470084A (zh) 一种基于神经网络和案例推理的汽轮机轴系振动故障诊断方法
CN104636746B (zh) 一种基于局部区域小波变换的gis设备特征值提取方法
CN109492790A (zh) 基于神经网络与数据挖掘的风电机组健康管理方法
CN103675659A (zh) 断路器分合闸时行程-时间波形预处理方法与装置
Souhe et al. Fault detection, classification and location in power distribution smart grid using smart meters data
CN112187528A (zh) 基于sarima的工业控制系统通信流量在线监测方法
CN102981096B (zh) 一种基于wams时序分解的电网故障辨识方法
CN103389701A (zh) 基于分布式数据模型的厂级过程故障检测与诊断方法
CN112085043A (zh) 一种变电站网络安全智能监控方法及系统
CN106199251A (zh) 一种基于自适应建模分析的配电网故障预警系统及方法
CN105629144A (zh) 基于指纹库的高压开关设备局部放电诊断方法及系统
CN106569126A (zh) 一种基于双谱分析算法的断路器故障诊断的方法
CN203929118U (zh) 环网柜关键配电设备状态在线监测系统

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB02 Change of applicant information

Inventor after: Liang Jingwan

Inventor after: Yong Mingchao

Inventor after: Zhao Bao

Inventor after: Mu Jiqing

Inventor after: Lu Guanghui

Inventor after: Sun Chaowu

Inventor after: Shi Yi

Inventor after: Chen Xinmei

Inventor after: Huang Lai

Inventor after: Wu Xiaozhong

Inventor after: Ma Yicheng

Inventor after: Jiao Po

Inventor before: Liang Jingwan

Inventor before: Lu Guanghui

Inventor before: Chen Xinmei

Inventor before: Ma Yicheng

Inventor before: Jiao Po

Inventor before: Yong Mingchao

Inventor before: Zhao Bao

Inventor before: Mu Jiqing

CB03 Change of inventor or designer information
TR01 Transfer of patent right

Effective date of registration: 20161223

Address after: No. 1298 Xuchang City, Henan province 461000 XJ Avenue

Patentee after: Xuji Electric Co., Ltd.

Patentee after: Xuchang XJ Software Technology Co., Ltd.

Patentee after: State Grid Hunan Electric Power Company

Address before: No. 1298 Xuchang City, Henan province 461000 XJ Avenue

Patentee before: Xuji Electric Co., Ltd.

Patentee before: Xuchang XJ Software Technology Co., Ltd.

TR01 Transfer of patent right